Professional Documents
Culture Documents
TABLE OF CONTENTS
13.1 INTRODUCTION.....................................................................................................13-1
LIST OF TABLES
Table 1: Design floods for Permanent Access Bridge............................................................................13-1
LIST OF FIGURES
Figure-1: Clearance Diagram for the transportation of the Main Transformer.......................................13-2
Pakistan Water and Power Development Authority, Islamic Republic of Pakistan
Diamer Basha Dam Project
Bidding Documents (Contract MW-1) Part ll: Particular Technical Specifications
Volume 3A - Technical Specifications For Main Dam and Appurtenant Structures 1
13. PERMANENT ACCESS BRIDGE
13.1 INTRODUCTION
Permanent access bridge shall accommodate access to the right bank of the Indus River, during
construction for facilitating transport of equipment for hydro-mechanical and electrical
equipment. After impounding of reservoir, the bridge shall provide access to the settlements
located on the right bank.
The Contractor shall design, supply, fabricate and construct permanent access bridge across
Indus River in accordance with the requirements stipulated in this Chapter and as approved by
the Engineer.
This chapter provides the minimum requirements for bridge roadway and facility widths, vertical
under-clearances and design live loads. All elevations, water levels, dimensions etc. shown on
the drawings are tentative which may vary as per project requirements.
Unless specifically noted in the provisions, the geometric design standards provided in this
section shall refer to the AASHTO - A Policy for Geometric Design of Highways and Streets
(Latest). The bridge and allied components shall be designed for a design speed of 60 km/hr.
13.2.1 Waterways
To assure a safe passage for a 100 year design flood (Q100) and debris an adequate hydraulic
opening must be provided. In addition a minimum freeboard of 5000 mm for the 10,000-year
flood (normal operation condition for the spillway) shall be considered as satisfying normal
hydraulic clearance requirements. The tentative design water levels are given in the following
TABLE-1. Design based on actual water levels shall be carried out by the Contractor for
approval by the Consultants.
Table 1: Design floods for Permanent Access Bridge
Inside clear width of bridge roadway shall be min. 7.9m plus shoulders and inside clear width of
walkways (on either side of the bridge) shall be 0.750m and 0.4m wide New Jersey NJ barrier.
Please refer drawing number CW50-102 for details.
Minimum vertical clearances requirements help accommodate the movement of large vehicles
for maintenance operations, utility work, and construction, electrical and mechanical equipment.
To facilitate the movement of general vehicles a minimum vertical clearance of 5.5m should be
kept. However, for the transportation of the main transformers the tentative clearance of the
following Clearance Diagram in FIGURE-1 is provided. Exact clearance values shall be used for
the bridge design as per requirements of equipment manufacturer/vendor.
Pakistan Water and Power Development Authority, Islamic Republic of Pakistan
Diamer Basha Dam Project
Bidding Documents (Contract MW-1) Part ll: Particular Technical Specifications
Volume 3A - Technical Specifications For Main Dam and Appurtenant Structures 2
13.2.3 Span
The maximum main span length is given by the following requirements and constrains:
Clearance for water crossing
Altitude of right and left bank access road
Due to the expected river bed degradation and the high sediment load of the river
Indus, a foundation in the river bed should be avoided
As result of these constrains the minimum tentative length of the main span (centre to centre of
the expansion joints) shall be approximately 200 m.
The geological/geotechnical conditions mentioned above are guidelines for the Contractor. The
Contractor, however, shall acquire all necessary information about the site and soil
conditions. The engineering design and construction of the bridge abutments, piers, footing
and anchors shall be performed accordingly.
The Permanent Access Bridge must be designed according to AASHTO LRFD Bridge Design
Specifications (Latest Edition). The design methodology shall be "Load and Resistance Factor
Design (LRFD)".
The bridge shall be designed to carry not less than the AASHTO live load and the Main
Transformer Transport Vehicle (tentative load approx. 150 ton). However, design shall be based
on actual loads which may vary as per project requirements.
The structural calculations shall incorporate but not be limited to the following loads:
Dead loads and Superimposed dead loads
Pedestrian Live loads
Vehicular Live Load
Ice loads
Wind loads (3 second gust wind speed= 100mph)
Force effects due to creep, shrinkage, Settlement, temperature gradient, uniform
temperature etc.
Forces from post-tensioning
Hydrostatic and hydrodynamic loads
Earth surcharge loads
Earth pressure loads
Pakistan Water and Power Development Authority, Islamic Republic of Pakistan
Diamer Basha Dam Project
Bidding Documents (Contract MW-1) Part ll: Particular Technical Specifications
Volume 3A - Technical Specifications For Main Dam and Appurtenant Structures 4
Seismic loads
Seismic inertia force
Earthquake dynamic earth pressure
Dynamic earthquake load
The vertical deflection and lateral deflection of the bridge under dead loads, live loads and
lateral loads should be within the permissible limits specified in the relevant codes and
standards.
Also vibration requirements of the relevant codes and standards shall be fulfilled. Vibrations
shall not cause damage to the structure and shall not cause discomfort or concern to users of
the bridge.
Load combinations will be considered as per AASHTO LRFD code and design will be carried
out for the worst load combination.
The contractor shall submit his construction methodology in accordance with AASHTO
specifications for design and construction of segmental concrete bridge prior to undertaking
any construction activity at site.
Sufficiently in advance of the start of field construction operation, so as to allow the engineer
not less than 45 calendar day review period, the contractor shall submit according to
schedule , complete details and information concerning the method materials, equipment,
and procedure the contractor propose to use in constructing that portion of super structure
for which the information is furnished. The submittal shall include a step by step erection
procedure. The contractor submittal for approval shall consists of Computer model (on CSi
Bridge 2015), all the design calculations, drawings, geotechnical report, and geometric,
geological/geotechnical, hydrological/hydraulic and all kind of relevant information.
BIM-based (Autodesk Revit etc.) Bridge model for optimization of design, construction
sequences, construction scheduling, construction management, construction process
monitoring, as-built conditions, facility management, future repair/maintenance/retrofit etc.
The contractor shall submit deflection and /or camber data calculations for each stage of
construction as required to construct structure to its final grade. The procedure used for
calculation shall account for the effect of immediate prestress losses, time dependent
prestress losses, and creep which will occur during the construction phase. The data for the
entire bridge, based on the contractor’s proposed erection sequence, method and schedule,
shall be submitted to the engineer for review prior to commencing construction.
The camber of the structure will be monitored by the contractor at each stage and corrective
actions as approved by the engineer shall be performed by the contractor to assure proper
erection of the structure to its final grade.
The contractor shall submit the geometric control plan for regular monitoring of the super
structure deflection beginning with the addition of first cantilever segment and concluding
with the last cantilever segment. The plan shall include the adjusting procedure to be utilized
for the cantilever as erected deviate from the predicted alignment by more than 25mm.
Pakistan Water and Power Development Authority, Islamic Republic of Pakistan
Diamer Basha Dam Project
Bidding Documents (Contract MW-1) Part ll: Particular Technical Specifications
Volume 3A - Technical Specifications For Main Dam and Appurtenant Structures 5
The bridge shall be constructed by the cantilever method using travelling gantries and
closure equipment.
The weight of travelling gantries including all form work shall not exceed 600KN.
Weight of the closure equipment including forms shall not exceed 400KN.
The construction stages of the bridge are outlined below:
1. Construction of Abutment block on each side and anchoring of prestressed tendons.
2. Construction of segments on both sides of each abutment simultaneously complete
in all respect.
3. Gantries to be removed after casting/prestressing of segments S21 on each side.
4. Closure equipment shall be moved in place on segment no. S21, the 200m span will
be completed by pouring the closure segment and stressing the bottom prestressing
for continuity.
5. Construction of sidewalks, barriers shall be done, asphalt overlay shall be applied.
13.3.5 Submissions
The Contractor shall submit to the Engineer two copies of each of the following:
Shop drawings, details and calculations in accordance with Clause 13.3.4; incorporating all
alterations and amendments such that they accurately reflect the details as constructed.
Complete detailed technical specifications of the bridge for approval from the Engineer
Main report including, but not limited to, sections on standards utilized, design criteria,
meteorological data related to wind speeds and snow loads, structural system description,
geotechnical report (including soil type, all design parameters like bearing pressure, active
pressure, passive pressure, sliding coefficients, seismic parameters, and slope stability /
landslide analysis, etc.).
As-Built drawings in PDF and CAD including all topography, elevations, structural
information (geometry, cable profile, size, quantity, material grades, and manufacturer
designations), and details required to illustrate the as-built conditions etc.
BIM-based (Autodesk Revit etc.) Bridge model for optimization of design, construction
sequences, construction scheduling, construction management, construction process
monitoring, as-built conditions, facility management, future repair/maintenance/retrofit etc.
If in the opinion of the Engineer the Contractor's submissions do not meet the requirements
of the Contract, the Engineer will notify the Contractor who shall make appropriate
amendments to the submissions and, shall forward three further copies within 30 days of the
Engineer's notification. The procedure described above shall apply to all resubmissions.
The Contractor shall supply to the Engineer four copies and one reproducible of the
drawings approved by the Engineer and four copies of the specifications and other
information approved by the Engineer.
HSE (Health, Safety & Environment) management Plan / Program
Detailed portfolio/profile of the Designer selected by the Contractor for the Design of bridge
along with requisite experience of similar or larger span bridges.
Pakistan Water and Power Development Authority, Islamic Republic of Pakistan
Diamer Basha Dam Project
Bidding Documents (Contract MW-1) Part ll: Particular Technical Specifications
Volume 3A - Technical Specifications For Main Dam and Appurtenant Structures 6
13.4 OPERATION AND MAINTENANCE
The Contractor will be responsible for Operation and Maintenance of Permanent Access Bridge
from the date that the said facility is available for use at site till the completion of Contract MW-1
including routine visual inspection, maintenance, repair etc. of all its members while ensuring
uninterrupted flow of traffic during the construction/maintenance period and during its use by
other Contractors. All labour, staffing, equipment, consumable parts, material and related parts,
repair/ replacement costs etc. required for operation and maintenance of the Bridge shall be
included in the cost of bridge.
13.5 WARRANTY
The Contractor shall provide a warranty against defects in bridge and workmanship for a period
of ten years beyond the defects notification period.
The cost of designing and constructing the permanent access bridge across the Indus River
including operation and maintenance shall be paid as a lump sum item. Payment for this item
will be made as per the milestones submitted by the Contractor and approved by the Engineer
in accordance with the Clause 57.2 of Conditions of Contract.
13.7.1 Substructure
13.7.1.6 Grouting
High strength grouting shall be done according to standard specifications
Pakistan Water and Power Development Authority, Islamic Republic of Pakistan
Diamer Basha Dam Project
Bidding Documents (Contract MW-1) Part ll: Particular Technical Specifications
Volume 3A - Technical Specifications For Main Dam and Appurtenant Structures 7
13.7.2 Superstructure
In this proposal, Cast in Place (CIP) post-tensioned variable depth box Girder Bridge (single
cell) with a span of 200m with parabolic profile and balanced by the Anchor solid anchor block
and prestressed tendons at abutments on both sides.
The bridge cross section has been proportioned based on AASHTO LRFD guidelines. For the
ease construction, single cell cast in places prestressed box girder with vertical webs shall be
considered. The length of each segment shall be considered between 3-6 meters.
Construction methodology is mentioned on the drawing number CW50-103.
13.7.2.6 Lighting
Lighting according to the Chapter on Road and Pavement Works of this Specification and as
shown in the drawings.