Professional Documents
Culture Documents
EXHIBIT “D”
SCOPE OF WORKS AND TECHNICAL SPECIFICATIONS
PART 1
SCOPE OF WORKS
1.1.1 Khalifa Port is located at Taweelah, in the Emirate of Abu Dhabi, UAE approximately 80km
North-East of Abu Dhabi city. Khalifa Port has been operational since September 2012. The
power required for Khalifa Port operations from 2012 to date is being provided via the existing
33/11kV substations KPZPRY-1, KPZPRY-2 and KPZPRY-13 shown in figure 1.
1.1.2 Furthermore, Abu Dhabi Ports have recently received approval for further increase in
container/cargo handling capacity by undertaking the following works at Khalifa Port, namely
Shamal development CT3 as shown in figure 2.
1.1.3 The power requirements to support the operations of these new developments cannot be
met from the existing 33/11kV substations. Therefore, construction of a new 33kV substation
is needed in order to meet this additional power demand. The tentative location of the new
33/11kV substation is identified in figure 2 which will be developed by Abu Dhabi Ports
(hereinafter referred to as “Employer”).
1.1.4 The project can broadly be categorized into following three packages as below,
33/11 kV Substation works including all the Civil, Architectural, Structural and MEP
works
Four 20MVA transformers and all associated switchgear for the capacity of 60MVA (n-
1)
Access road and all utilities up to the tie-in connections
Cabling works including all associated elements from Taweelah Grid station or KIZAD
KP4 Grid station / South Quay / Building 55 (refer to Optional scope for details)
The detailed Scope of Works is described in Section 3.0 of this document
1.2.1 Khalifa Port infrastructure have been built over the years under various Contracts. Contractor
shall refer to Exhibit F [Information] for the details of the existing roads and utilities.
1.2.2 Reclamation works are currently ongoing for the expansion areas and Contractor shall refer
to Exhibit D Part 2 [Specifications] for the reclamation specifications.
1.3.1 This Project is developed to provide the power for the Shamal development developed for the
Container Terminal CT3 Expansion which is planned for the quay wall (800 m length) with the
future expansion planned for the quay wall (400 m length). This will serve also future
expansion areas planned foYr the bulk cargo handling.
1.4.1 All the Works under this Contract shall be delivered in one phase.
1.5.1 Contractor shall follow all relevant local and/or international codes & guidelines for the
Project as provided in the Specifications and standards listed in Exhibit D Part 2
[Specifications].
1.5.2 All design and sizing calculation shall be carried out accordance to ADDC/TAQA/RSB
specification and standards
1.5.3 Contractor shall check and comply with all regulations, acts, orders or codes which apply to
any part of the contract as well as all relevant plant by-laws, plant regulations, etc.
1.5.4 In the event of any inconsistency or discrepancy between the documents, the most stringent
requirements shall be followed to complete the Scope of Works.
1.5.5 All materials, testing, design and execution shall be in conformity with these codes and
standards, unless otherwise stated in the Contract.
2.1.1 Contractor shall be responsible for providing all required project management resources and
management structure necessary in order to achieve the requirements of the contract and to
liaise and interface with Employer counterparts.
2.1.2 Contractor shall, within fourteen (14) calendar days of the effective date of the Contract,
submit its project management team structure for review and approval by Employer. The
submittal shall include:
2.1.3 Employer will review and, at its sole discretion, may select some or all of the proposed
candidates for the positions for interview. Employer will have the right to reject any of the
proposed candidates and, upon such rejection, Contractor shall submit alternative candidates
for consideration.
2.1.4 As part of the review process, Employer will identify the positions it determines to be critical
for the project and Contractor shall not demobilize or remove the approved candidates for
these positions without Employer’s written approval. Approved candidates shall be allocated
full time for the Works (i.e. not shared resources with other projects) unless expressly agreed
by Employer in advance.
2.2.2 All deliverables produced on the project shall be in strict accordance with the requirements
of both Employer and any applicable Government Authority. In the event of a conflict between
the requirements of either Employer or any applicable Government Authority, Contractor
shall notify Employer of such conflict and request direction on the appropriate option to
proceed.
2.2.3 Contractor shall be required to submit each deliverable through Employer’s Electronic
Document Management System (EDMS). Submittals shall be in pdf and native formats.
2.2.4 As stated in the various sections below, Employer shall only be obliged to review and respond
to the deliverables which Employer selected for review and comment. While Contractor shall
submit all documentation and deliverables produced during the execution of the Works,
Employer shall not be obliged to review and comment on them but hereby reserves the right
to review and respond even if the deliverable has not been identified previously for review.
However, such review shall not affect Contractor’s performance of the Works, subject to
Contractor’s compliance with the Contract.
2.2.5 Employer’s review and comment or non-review of any document or deliverable produced by
Contractor shall not relieve Contractor of any obligation or requirement of this Contract.
2.3.1 Within fourteen (14) calendar days of the Commencement Date, the Contractor shall submit
a ninety (90) Day schedule showing all initial activities for the first ninety (90) Days. The ninety
(90) Day schedule shall include summary activities depicting the general sequence of work
leading to the completion milestones identified in Exhibit B, Attachment 6. An accompanying
narrative describing the critical path and the key resources required to perform the work shall
be included.
2.3.2 Within twenty-eight (28) Calendar days after the Commencement Date, Contractor shall
submit, to Employer for its Approval, a schedule for the Works. The schedule shall be
submitted in native electronic format together and include a detailed narrative report
describing the Contractor’s plan for performing the Works.
2.3.3 The Baseline Schedule shall consist of a precedence network diagram using the critical path
method (“CPM”) using Primavera software version 6.0 to clearly show each individual
essential activity in sequence to meet every Key Dates Schedule milestone identified in Exhibit
B, Attachment 6 [Key Dates Schedule] and the Time for Completion of the Works or Section.
Float in the Baseline Schedule shall not be considered to be for the exclusive benefit of either
Employer or Contractor.
2.3.4 Extensions of time for performance required under other Contract clauses, including
extension of the required dates of completion of the milestones, shall be shown only where
contractual entitlement has been notified by the Employer in accordance with the Contract.
Exhibit “D”, Part 1 Page 7 of 42 2101-278
Scope of Works, Rev. A
Extensions of time shall be made only to the extent that agreed-upon extensions for affected
activities exceed the current total float available along those activities paths.
2.3.5 The Contractor shall ensure its major Subcontractors actively participate in developing and
updating the schedule and that all schedules submitted to the Employer are consistent with
its Subcontractors' schedules approved by the Contractor. The Contractor shall include in the
schedule activities of the Employer and any other party that could impact the Works. The
Contractor shall ensure that the schedule is an accurate representation of the plan for the
execution of the Works and that the Contractor uses such schedule to execute the Works in
accordance with the Contract.
2.3.6 The Contractor shall develop and maintain, as required from time to time, including when
directed by the Employer, recovery schedules and time impact analyses.
2.3.7 The Contractor shall submit in hard copy and its native electronic format, a weekly and
monthly updated schedule that accurately reflects all Works performed and the plan for
completing the Works. In providing this update the Contractor shall not adjust the Time for
Completion for the Works or Section unless expressly permitted in accordance with the
Contract. The most current updated schedule shall be used by Contractor, in conjunction with
other means, for planning, organizing, and directing the Works. All schedule submittals
including all updates and/or changes by the Contractor shall include but not be limited to the
following Clauses.
2.4.1 An activity diagram shall include but not limited to the following information for each activity:
Identification by activity ID
Description of the task or event
Duration
Dependency
Personnel by discipline and man-hours
Earliest start and finish dates
Latest start and finish dates
Total float and free-float time
Critical Path
2.4.2 Activity descriptions shall be brief but shall convey the scope of work described. Unusual
abbreviations shall be explained in a legend or in the narrative report. In general, activity
durations shall not exceed thirty (30) work days, except where appropriate to reflect the
Works, e.g. procurement or level of effort activities.
2.4.3 All activities shall be logically driven with mostly finish to start relationships and minimal
constraints, unless accepted by Employer.
2.5.1 A detailed narrative report shall describe the Contractor’s plan for performing the Works as
shown on the activity diagram. The narrative description shall summarize personnel
requirements by discipline and the other resources included in the resource loaded schedule.
The Narrative Report shall also include the Contractor’s proposal for the basis for recording
progress including any graphs, histograms, charts, and other graphical depictions of data.
2.5.2 As a minimum the Narrative report shall briefly explain the following headings with supporting
documents:
2.6.1 During the performance of the Works, the Contractor shall submit to Employer reports in
accordance with the Contract including but not limited to daily and weekly reports on the
actual progress. Such progress reports shall include but not be limited to the following reports
described in this section. Templates for these reports will be provided by the Employer at the
Kickoff meeting and be reissued from time to time by the Employer and be adopted by the
Contractor to be part of the Contract.
2.7.1 Contractor shall submit a Weekly Construction Status Report before 10:00hr on the following
Business Day after the end of each workweek. This should include a summary of the Works
accomplished during the preceding week and planned for the next three (3) weeks, and any
key changes to the status of the Works. The report shall show all Contractor’s Personnel,
Contractor’s Equipment, and Goods together with all Contractor’s supervision required to
manage the elements of the Works shown.
Exhibit “D”, Part 1 Page 9 of 42 2101-278
Scope of Works, Rev. A
2.7.2 The report shall be comprised of, but not be limited to, the following sections:
2.8.1 Contractor shall submit a Daily Construction Status Report before 10:00h on the following
Business Day that shall include but not be limited to details of:
Health, Safety and Environment incidents / accidents / near misses, and any HSE
training provided
Contractor’s Equipment used at the Site, both planned and actual. Such
information shall also be provided for each Subcontractor.
Contractor’s Personnel engaged in execution of the Works at the Site, both
planned and actual. The total shall be stated separately for manual and non-
manual. Such information shall also be provided for each Subcontractor.
Description of the works performed
Listing of tests performed, and detailing any failures
Description of any special events / delay and downtime
Quantum of work performed
2.9.1 Contractor shall be required to arrange Weekly Progress Meetings (WPMs) with Employer’s
representatives during the execution of the Works. During the WPMs, Contractor shall report
Exhibit “D”, Part 1 Page 10 of 42 2101-278
Scope of Works, Rev. A
on overall progress achieved during the previous period and follow-up on any actions assigned
to either Contractor or Employer.
2.9.2 Contractor shall be responsible for preparing detailed minutes of meeting capturing the
various discussions and agreed actions as an outcome of the Weekly Progress Meetings
(WPMs) and submit the same for Employer review, input and approval. Contractor shall
ensure that the minutes of meeting are circulated to Employer for review and approval not
more than one (1) day after the date of the WPM.
2.10.1 Contractor shall ensure that, at all times, work is carried out in accordance with the laws, rules,
regulations and in strict accordance with the requirements of the Abu Dhabi Occupational,
Safety, Health (OSHAD) System.
2.10.2 Additionally, Contractor shall ensure fully comply with and follow HSE requirements of
Employer. Depending on the classification type (A, B, C or D) which are based on the HSE risks
associated with the nature of the work / services under the Contract, the HSE requirements
of Employer may vary. Contractor shall refer to the Abu Dhabi Ports HSE requirements at
https://www.adports.ae/port-users/general-information/guidelines/ .
2.10.3 Contractor shall, within twenty (20) calendar days of the effective date of the Contract submit
its Environmental, Health and Safety Management Plan for review and approval by Employer.
The submittal shall include but not be limited to:
2.10.6 In respect to Health and Safety incidents Employer shall be entitled to effect deductions/
withholdings as specified herein below:
2.10.9 Employer may in any Payment Certificate make any correction or modification that should
properly be made to any previous Payment Certificate. A Payment Certificate shall not be
deemed to indicate the Employer’s acceptance, approval, consent or satisfaction.
2.10.10 Employer shall be entitled, at Contractor’s cost, to appoint a third party to undertake tasks to
remedy any findings from the incident which are the obligation of Contractor in event of
Contractor’s failure to do so.
2.11.1 The Contractor’s Design shall be in accordance with the Employer’s Design requirements and
specifications as provided in Exhibit D - Part 2 [Specifications], Exhibit E [Drawings] and
Exhibit F [Information] of the Contract. Any further, additional design / engineering Works
which are required to design, construct and handover fully operational infrastructure facilities
in accordance with Employer’s requirements shall be considered as included in the Contractor
Scope of Works and shall be carried out by the Consultant and/or supervision Consultant
appointed by the Contractor.
2.11.2 Any design drawings or activity which is not explicitly stated in this Scope of Works document
or included in Employer’s documents and drawings provided in Exhibit D – Part 2
[Specifications] or Exhibit E [Drawings] or Exhibit F [Information], but is either implied or
necessary in order to be able to execute the Works, shall be the responsibility of the
Contractor.
2.11.3 Employer’s obligations with regard to engineering and design activities shall be strictly limited
to the documents provided in Exhibit E [Drawings] and Exhibit F [Information]. All engineering
and design activities necessary in order to execute the Works shall be provided by the
Contractor, including any further site investigations required to determine the conditions
required to inform and validate elements of the Works to be designed by the Contractor.
2.11.4 Employer shall not carry any liability with regards to additional information provided in Exhibit
E [Drawings] or Exhibit F [Information].
2.11.5 The Contractor has been identified as being responsible for the Design of the Works. The
Contractor shall be responsible for reviewing, validating and modifying the details provided in
Exhibit E [Drawings] or Exhibit F [Information] to ensure applicability to the location of the
physical infrastructure to be built under this Contract as part of the Works. As part of
Contractor’s review, validation and modification, Contractor shall accept any and all design
liability for these elements of the Works.
2.11.6 Contractor shall provide all engineering and design activities necessary in order to execute the
Works, including any further site/geotechnical investigations required to determine the
conditions which is required to review, validate, add and modify Employer provided design.
All the design works shall be carried out by the approved design consultant, supervision
Exhibit “D”, Part 1 Page 13 of 42 2101-278
Scope of Works, Rev. A
consultant and sub-consultants/subcontractors as per the local Authorities legislations,
regulations and guidelines.
2.11.7 The Contractor’s engineering and design activities shall be in accordance with and be able to
demonstrate compliance with all Abu Dhabi Government Authority requirements and
regulations for the Works involved. Contractor shall be solely responsible for obtaining any
required approvals from Abu Dhabi Government Authorities for any Contractor engineering
and design activities.
2.11.8 Contractor shall responsible for effective coordination between the Authorities and
Stakeholders during the project phase and arrange the necessary meetings, workshops and
proposals if any comments/discussions/review required during the project duration with the
Authorities and Stakeholders.
2.11.9 Contractor shall be required to submit and obtain approvals and/or permits from all the
relevant authorities for the works, in accordance with the requirements of the respective
authority. For clarity, Contractor shall be required to obtain the approval of Employer prior to
submitting any deliverables to any authorities.
2.11.10 Contractor shall, within twenty-eight(28) calendar Days of the effective date of the Contract,
submit to Employer for review and approval a list of all design and engineering documents
that Contractor envisages will be required to be produced for the execution of the work along
with the planned date for the submittal. During such review, Employer will identify the
engineering and design documents which Contractor shall be required to submit for approval
prior to proceeding with the work.
2.11.11 For any design and engineering documents identified by Employer to require Employer review
and approval, Employer will review and respond to such submittals within fourteen (14)
calendar days of receipt. Employer’s response shall take the form of;
2.11.12 Employer’s commitment to review design and engineering deliverables within fourteen (14)
calendar days considers the below-listed items. Failure to meet these items will lead to a delay
in Employer’s review, for which Employer shall not be held responsible.
2.11.13 Further to above clause, at the discretion of Employer, should Contractor fail to submit quality
controlled and verified design/engineering deliverables, Employer reserves the right to
instruct Contractor to appoint a third-party checking engineer to review engineering
deliverables prior to submission to Employer. If required, such reviews are considered
included in Contractor’s scope of work.
2.11.14 For preliminary and detailed design documents returned to Contractor with code 2 or code 3,
Contractor shall be responsible for addressing the comments and resubmitting the document
for review and approval within seven (7) calendar days until a code 1 status is achieved prior
to proceed with the next status of the design.
2.11.15 For all construction and as built engineering submission returned to Contractor with code 2
or code 3, Contractor shall be responsible for addressing the comments and resubmitting the
document for review and approval within fourteen (14) calendar days until a code 1 status is
achieved.
2.11.16 Contractor shall be solely responsible for ensuring that the incorporation of comments and
resubmittal do not impact the execution of the Works in accordance with the requirements
of the Contract.
2.11.17 Should Contractor elect to propose any functional changes to Employer’s Design to facilitate
the execution of the work or to value engineer the design, Contractor shall present such
changes with suitable justification for changes for Employer review and approval. However,
Employer shall not be obliged to accept any proposed changes to Employer’s design and shall
at all times retain the right to reject such proposals and direct Contractor to execute the works
in accordance with Employer’s Schematic design.
2.11.18 Contractor shall comply with the Employers Document and Drawings formats for the
deliverable’s submission to Employer. Also, Contractor shall comply with the Employer’s
drafting standards. Details will be provided to Contractor after the Contract award.
2.11.19 Any delays in the approval process from Authorities does not relieve the Contractor from the
responsibilities under the Contract.
2.11.20 Contractor shall be responsible for a timely appointment of any third-party consultants
required for the design carried out by the Contractor.
2.11.21 Contractor shall carryout all the Works through Contractor appointed Consultant and/or
Supervision Consultant who are authorized to carry out the similar works in Abu Dhabi. Also,
Contractor’s Consultant and/or Supervision Consultant shall ensure that all the necessary
approvals obtained from the governing authorities. Design deliverables shall include the
below but not limited to;
2.11.22 Contractor shall obtain all NOCs and permits required from all applicable stakeholders,
organizations, government bodies and utility companies for the Works including, but not
limited to, the following;
2.11.23 Contractor shall be aware that the requirements and timescales for obtaining NOCs and
permits are determined by the relevant awarding body and may vary from time to time.
Contractor shall determine the requirements and timescales for obtaining each NOC and
permit and include such in the Programme.
2.12 Procurement
2.12.2 Within twenty-eight (28) calendar days of the effective date of the Contract, the Contractor
will submit for Employer review and approval a project procurement plan identifying all
procurement activities required for the execution of the Works. Such project procurement
plan shall include but not be limited to the following:
2.12.4 Throughout the execution of the work, Contractor shall maintain and update such project
procurement plan with regard to actual dates and any changes.
2.13.1 In order to clear Equipment and Plant from Abu Dhabi customs authorities without payment
of customs duty, Contractor shall request Employer to issue a Consignment Clearance
Authorisation (CCA) / Duty Exemption Letter addressed to Abu Dhabi Customs Authorities,
along with the following details as a minimum:
2.13.3 The CCA letter issued by Employer will allow Contractor to avoid customs duty on Equipment
and Plant. However, any handling, storage and other miscellaneous costs charged by Abu
Dhabi customs authority shall be borne by the Contractor.
2.13.4 Contractor is required to submit Suppliers Custom Purposes Invoice, based on CIF (as per
latest INCOTERMS) value. However, as transit insurance will be arranged and paid by
Employer, Suppliers Custom Purposes Invoices shall include transit insurance charges as
actually paid by Employer. Employer will advise to the Contractor the percentage transit
insurance charges payable for the project during execution phase.
2.13.5 Wherever applicable, Contractor along with CCA application letter will also be required to
submit Chemical, Radioactive & Hazardous Material Release Permit from environmental
agencies such as Environmental Research & Wildlife Development Agency, Abu Dhabi or
Environmental Agency, Abu Dhabi, etc. as applicable.
2.13.6 Contractor shall, where applicable, forward copies of complete and full shipping documents
to Employer within one week after shipping. In the event of air freight, the documents shall
be forwarded by fast courier service such that these are received by Employer prior to arrival
of the consignment in the Emirate of Abu Dhabi. Responsibility for delays, loss or damage of
shipping documents shall rest with the Contractor.
2.13.7 The shipping documents provided by Contractor are for information purposes only and in no
way release Contractor of its obligation to ship, deliver and install the Equipment and Plant at
the Site in accordance with the terms of this Contract.
2.14 Mobilization
2.14.1 Contractor shall be solely responsible for undertaking any actions necessary in order to
mobilize the resources to execute the Works in accordance with the requirements of the
Contract. This shall include but not be limited to:
2.14.4 Prior to any mobilization activities taking place, Contractor and Employer shall conduct a joint
survey of the temporary facilities area(s) to document the condition of the area(s), including
as a minimum photographic records of the area(s). Such joint survey(s) will then be utilized
for verification of the completion of demobilization activities.
2.14.5 Contractor shall be responsible for obtaining all required gate passes, permits to work and any
other permissions and permits necessary to mobilize resources within the Site. The processes
for obtaining Gate Passes and permits to work can be found at https://www.adports.ae/port-
users/general-information/forms/hse-security-department/
2.15.1 Contractor shall be responsible for the provision, operation, maintenance and removal of all
temporary facilities required for the execution of the Works in areas designated by Employer.
This shall include but not be limited to:
2.16.1 Prior to commencing any element of the Works, Contractor shall be required to undertake a
detailed photographic pre-commencement survey of the work area in order to determine the
precise nature and condition of the area.
2.16.2 Such survey shall be conducted with Employer’s personnel in attendance and witnessing the
survey activities. Once each pre-commencement survey is completed, Contractor shall submit
to Employer a pre-commencement survey report documenting the results of the survey. Each
survey report shall be submitted as a hard copy document accompanied with the native files
for each element of the survey.
2.17 Survey
2.17.1 Contractor shall perform all necessary surveys necessary for the design and construction of
the Works. The Contractor shall perform pre-construction, progress, post-construction
topographic surveys, as applicable, witnessed and approved by the Employer. The survey
reports and data in both ASCII and DWG format shall be submitted to the Employer for review
and approval.
2.17.2 Contractor shall perform all the necessary trail pits and site investigations to identify the
existing services in coordination with Employer and Authorities.
2.18 Construction
2.18.1 Contractor shall be responsible for all construction activities necessary for the execution of
the Works under the Contract. This shall include but not be limited to;
2.18.3 The use of storage lagoons for temporary dewatering of excavations and other areas shall not
be permitted. Contractor shall be permitted to use the existing storm water drainage system
based on explicit permission of Employer and any other relevant stakeholders. This shall be
subject to acceptance of Contractor’s proposal for use of the system.
2.18.4 Contractor shall be solely responsible for the operation and maintenance of all storm water
drainage system that Contractor discharges into, inclusive of all downstream connected
networks. Contractor shall maintain, to Employer’s approval, a regular preventative
maintenance programme on the section of network under Contractor responsibility, including
network including open channel, gravity pipes and forced main pumping stations, oil
separators, settlement basins and outfall.
2.18.5 Contractor shall provide additional pumps, rising mains, settlement tanks and any other
enhancements to the existing storm drainage system as to meet the requirements of
Contractor’s discharge and any other discharge into the network. This may include additional
rising mains to the sea outfall. Contractor shall be responsible for obtaining the relevant
approvals for additional outfalls, if required.
2.18.7 All basins, tanks and mechanical and electrical equipment shall be fully serviced and
warranties on the service shall be provided to Employer for their use.
2.18.8 Contractor shall, within twenty-eight (28) calendar days from the effective date of the
Contract, submit to Employer a construction management plan for the Works. Such plan shall
include but not be limited to:
2.18.9 Upon receipt of the construction execution plan, Employer will review such plan and provide
a written response within ten (10) calendar days. Employer’s review will identify which of the
construction execution management documents Contractor shall submit for Employer’s
review and approval prior to proceeding with the Works.
2.18.10 Contractor construction deliverables shall include but not be limited to:
2.19.1 Contractor shall be responsible for carrying out all inspection and testing activities required
to demonstrate that all of the Works is fully compliant with the requirements of the Contract
and shall include but not be limited to:
Quality assurance and quality control audits to confirm compliance with all
approved plans, procedures and processes
Material testing
In-situ testing of constructed elements
Visual inspections
Surveillance
Surveying
Development of as-built engineering documentation (drawings, specifications,
etc.)
2.19.2 All testing conducted shall be performed by an independent 3rd party testing services provider
employed by Contractor. The nominated independent 3rd party testing services provider and
the testing process to be implemented shall be submitted to Employer for review and approval
prior to commencing work. Contractor shall ensure that the sufficient qualified and no of
personnel dedicated testing engineer employed to handle the testing works.
2.19.3 Contractor shall be responsible for ensuring that all inspection and testing activities are
documented contemporaneously with the physical execution of the work.
2.19.4 Contractor shall, within twenty-eight (28) calendar days from the effective date of the
Contract, submit to Employer an inspection and testing plan for the Works. Such plan shall
include but not be limited to:
2.20 Handover
2.20.2 Contractor shall, within twenty-eight (28) calendar days from the effective date of the
Contract, submit to Employer an inspection and testing plan for the Works. Such plan shall
include but not be limited to:
2.20.6 Within three (3) calendar days of receipt of Employer’s response confirming Employer’s
agreement that handover can take place, Contractor shall deliver each handover pack with
the original documentation to Employer and will provide the copy that had been maintained
within Employer’s facilities to Contractor.
2.20.7 The Contractor shall provide all necessary documentation and assistance to the Employer for
the handover of all of the Works to the stakeholder asset owner, including but not limited to:
2.20.9 Contractor shall be responsible for undertaking all inspections and testing required by
Employer and/or stakeholders.
2.20.10 Where applicable, the Contractor shall prepare Bills of Quantities and as built GIS files for all
constructed Works based on as-built information in a format acceptable to the relevant
utility/road owners and obtain relevant stakeholder asset owners’ approval of the Bills of
Quantities and as built data.
2.20.11 Contractor shall be responsible for the timely close out of all punch list items. Contractor shall
provide a weekly report on the status of the close out of all punch list items. If Contractor fails
to close out all punch list items within a reasonable period, Employer reserves their right to
complete the remaining punch list items through another party at Contractor’s cost and risk.
2.21 Demobilization
2.21.1 Contractor shall be responsible for all actions required for the demobilization of their facilities
and resources from the Site. Contractor shall be responsible for restoring the temporary
facilities area(s) to the same condition in which they were prior to Contractor’s mobilization
and use. The joint pre-mobilization survey previously conducted shall be referred to ascertain
the original condition of the area.
3.1.1 Contractor shall be responsible for any and all activities, unless specifically excluded
from this scope of work, as required in order to be able to execute the Works in
accordance with the requirements of the Contract.
3.1.2 The sections below provide specific detail of the work that is included in each element
of the Works. Any activity required to execute the Works which is not be explicitly
stated below but is either implied or necessary in order to be able to execute the
Works, Contractor shall be responsible for its execution.
3.1.3 The scope detailed in the following subsections shall be read in conjunction with the
performance specifications provided in Exhibit “D”, Part 2 [Specifications], the
drawings provided in Exhibit “E” [Drawings] and the information provided in Exhibit “F”
[Information].
3.1.4 All Works shall be fully compliant with ADDC/TAQA applicable Standards,
Specifications and requirements acceptable to ADDC.
3.1.5 Contractor shall be aware that in this contract and all documents included are based in
the Abu Dhabi Datum (ADD). If any existing level is expressed in meters Contractor shall
use the following figures to convert between the datum systems: 0.0m ADD equals -
0.053 NADD. The main datum system for this contract shall be m ADD. Contractor is
responsible to verify the levels as per site conditions as required.
3.1.6 Contractor shall also submit for approval operation and maintenance manuals of the
permanent works completed, in sufficient detail to enable Employer to operate,
maintain, dismantle, reassemble and adjust the permanent works. The Works shall not
be considered completed for the purpose of taking over until such operation and
maintenance manuals have been submitted and approved by Employer.
3.1.11 Contractor shall be responsible to coordinate with Authorities for the connection fees
and tariff meters. Connection fees and tariff meter costs will be borne by Employer.
3.2.1 Employer has provided a layout of the asphalt roads in Exhibit “E” [Drawings]. The
performance requirements for the proposed roads are provided in Exhibit “D”, Part 2
[Specifications]. All works shall comply with
ADM/ADDC/TRANSCO/TAQA/RSB/DOT/AD QCC and all other Authorities
specifications.
3.2.2 Contractor shall undertake all works associated with the design, procurement,
construction, installation, testing and commission of the 33/11 kV substation and it’s
infrastructure. Contractor’s scope includes, but is not limited to, the following:
Site clearance
Earthworks including all the embankment, cutting and grading
Subgrade works
All electrical Plant for the complete system
Four (4) nos. 20MVA transformers together with associated 33kV switchgears,
11kV switch gears, LV switchgear, MV and LV and FO cabling works
SCMS system with integrations works for ADDC DMS center via FO and GPRS
communication
33/11kv substations control and protection panels including complete SCMS
system
All subsystem required for 33/11kV substation as per ADDC standards and
specification
Tariff meters
Protection systems
11kv Capacitor bank and Reactor Control
Redundant 110V DC system with redundant charger
Any other requirements as required by the site conditions, ADM, ADDC,
TRANSCO, TAQA, RSB, DOT, AD QCC and all relevant Authorities specifications and
standards
3.2.3 33/11kV SCMS works shall be carried out as per ADDC standards and specification.
3.2.4 As per ADDC guidance SCADA integration to be performed with ADDC DMS control
Center with FO communication and GPRS communication if require.
3.2.5 In addition to SCMS works redundant historian servers shall be provided with
engineering station and workstations for historical data archives,
3.2.7 All 33kV incomer feeder metering CT/VT accuracy shall comply with ADDC and RSB
Standards, Specifications and requirements, hence 33kV incomer panel shall have
dedicated CT/VT core for Main and Check meter. In comer Tariff CT accuracy shall be
0.2S and VT shall be 0.2
3.2.8 All 11kV outgoing CT shall be 0.5 Class accuracy for tenant metering purpose, similarly
all other 33kv, 11kv CT/VT local metering, protection accuracy and burden shall meet
the ADDC specs.
3.2.9 Incomer 33kv VT shall be stand alone with dedicated panel for easy maintenance, plug
type VTs are not acceptable.
3.2.11 Substation accessories shall be provided as per ADDC standards and specification for
example SCMS accessories, SF6 Gas handling unit (Complete set), Dummy plugs and
testing cables, CB trolleys, test plugs etc., For battery room require accessories to be
provided.
3.2.12 All design calculation shall be carried out as such Short circuit, Load flow, Earthing,
Lightning, Harmonic analysis, relay coordination and setting adoption.
3.2.13 Contractor shall follow ADDC procedures for commissioning and energization. During
the testing and commissioning OEM engineer must be available at site relevant ADDC
competency certificate for each category of testing.
3.2.14 33kv and 11kv Switch gear testing shall be carried out after successful commissioning
of 110V DC system for control power supply. Hence contractor will be responsible for
DG power source for 110V DC commissioning until substation energization.
3.2.15 Contractor shall be responsible to address the correct numbering of the new 33/11kV
substation and the exact location as part of its design scope.
3.2.16 Load Demand Notification submission to ADDC further all necessary coordination to be
completed i.e., STEP1 to STEP 5 procedure until energization shall be Contractor scope
of work.
3.2.17 Since the source of power shall be coordinated with ADDC/Transco, Contractor shall
be responsible to coordinate with Authorities as part of the design development to
identify the proposed routing and obtain all the necessary approval for the 33 kV cables
and FO cables with the corridor routing and crossings. Upon obtaining the approval,
Employer will provide instruction to proceed with the Optional scope of works as
3.2.18 Contractor shall carryout all the necessary trail pits, site surveys and coordination as
part of this works and this is to be carried out as a base scope of works.
ADPORTS-PM-DZ-SKCH-01458_00A
ADPORTS-PM-DZ-SKCH-01459_00A
ADPORTS-PM-DZ-SKCH-01460_00A
3.2.20 Contractor shall be responsible for testing and commissioning (startup), power on /
energization, and turnover of the Works. This includes but is not limited to:
All coordination with ADDC and relevant authorities to ensure on time, safe and
compliant energization
Contractor shall follow ADDC procedures for commissioning and energization.
During the testing and commissioning OEM engineer must be available at site
relevant ADDC competency certificate for each category of testing.
33kv and 11kv Switch gear testing shall be carried out after successful
commissioning of 110V DC system. Hence contractor will be responsible for DG
power source for 110V DC commissioning until substation energization.
Testing and Commissioning (start-up) Plan (including training program for end-
users / maintainer)
Construction testing (statutory tests)
Pre-commissioning or pre-operational testing (component tests)
Commissioning tests (system cleaning and initial system operations)
Start-up and integrated system operations testing
Performance testing (verification of specifications)
Training of end-users / maintainers
Operations and Maintenance manuals that include, but are not limited to, all
records of tests performed
Contractor shall follow ADDC procedures for commissioning and energization.
During the testing and commissioning OEM engineer must be available at site
relevant ADDC competency certificate for each category of testing.
33kV and 11kV Switch gear testing shall be carried out after successful
commissioning of 110V DC system. Hence contractor will be responsible for DG
power source for 110V DC commissioning until substation energization.
3.2.21 Contractor shall maintain the Permanent Works in accordance with the Contract,
including the provision of Operation and Maintenance manuals, up to the date of issue
of the Taking-Over Certificate for the whole of the Works. Contractor's Personnel for
the maintenance element of the Works shall include a continuation of sufficient
personnel who were present during execution of the Permanent Works with detailed
knowledge of the associated elements of the Permanent Works.
3.2.23 Contractor shall be responsible to survey the existing levels, roads at tie in location and
as per the proposed road/building levels. Any modifications, removal and relocations
required to the existing roads, road furnishes, and utilities shall be carried out by
Contractor.
3.2.24 Details of the existing and proposed tie-in locations are indicative only and shall be
verified and developed by Contractor to the approval of Employer during the design
development phase.
3.2.25 Employer will provide the Affection Plans from ADM, for which purpose, Contractor
shall produce plans showing the Electrical substation compound and cable route
corridors locations with coordinates of the boundaries. Employer will advise on
appropriate building numbering.
3.2.26 Contractor shall liaise with Employer and relevant stakeholders and record meetings
to enable Contractor to confirm the following:
Interfaces between this Contract and other contracts for shared access to the
utility corridors
Interfaces between this Contract and Ports Operations for shared access to
public roads and other Port areas
Interface with the Taweelah Power Plant and/or KIZAD KP4 Grid station for laying
of 33 kV cables, their routing inside the Taweelah Power Plant and/or KP4 Grid
station and terminations to the connection points inside the Taweelah Power
Plant
Interface with any other relevant stakeholders for any other aspects related to
the Works subject to this Contract
3.2.27 Design and Construction supervision consultant must have ADDC approval for 33/11kV
primary substation installation, testing and commissioning works with previous track
record. Supervision consultant shall be available full time at site with each discipline
engineers till completion of the construction period and commissioning engineer shall
be available until successful energization of the substation.
3.2.28 Design and construction supervision consultant shall be responsible for ADDC
coordination regarding any design discrepancies, non-compliances, deviations and
etc., for obtain all approvals.
3.2.29 Design and supervision consultant shall be responsible for testing witness of FAT, SAT
and any other witness require as per ADDC standards and specification.
3.2.30 Contractor shall be responsible for the design of the MV (33 kV cables)/FO cabling
network including all the Authority approvals as part of the base scope of works.
3.2.32 All the rectification/replacement works of the existing cables are not part of the
Contractor scope of works which shall be dealt separately in accordance with the
Contract after the completion of the investigation works.
3.2.33 For the existing cables, Contractor shall be responsible for carrying out all site surveys,
trail pits, cable detection, testing, verification, condition checks, identification of the
routes to ensure that the existing cables locations and its conditions. All shall be
coordinated with the Transco/ADDC for the necessary work permits and approvals.
3.3.1 The scope of these Works shall include soil investigation, compilation, organization,
and evaluation of data from field investigations and laboratory testing. It shall include
geotechnical analyses and evaluations pertaining to foundation recommendations and
design criteria. CONTRACTOR shall prepare and submit the below to EMPLOYER for
review and approval:
Geophysical Survey reports (in accordance with all relevant Authority requirements)
3.3.2 CONTRACTOR shall be responsible for obtaining all necessary authority
approvals/NOCs for undertaking the Ground Investigations (GI). CONTRACTOR shall be
responsible to ensure that all the GI works are undertaken in accordance with the
requirements of Abu Dhabi Municipality (ADM) and any other relevant Authorities.
3.3.3 CONTRACTOR shall appoint a GI subcontractor for performing the works and obtaining
the required permits and approvals. CONTRACTOR shall be responsible for managing
all the activities associated with the permitting process of the GI works leading up to,
and including, the approval of GI reports.
3.4 Earthworks
3.4.1 Contractor shall construct the earthworks, cable berm, surcharge fill and importation
of engineering fill material as necessary to achieve electrical substation compound and
cable route surface levels.
3.4.3 Excess or unsuitable ground material shall be removed, transported and placed /
disposed of as follows:
Material that complies with Employer's requirements for acceptable fill shall be
either reused in the Permanent Works or transported to locations specified by
Employer. Such material shall be stockpiled to levels agreed with Employer.
Material that does not meet these requirements may be used by Contractor in
Temporary Works or shall be disposed of offsite by Contractor to areas approved
by Employer including ADM-licensed disposal sites where required.
3.4.4 Retention and protection of any surcharge or associated settlement monitoring
equipment by previous contracts if Employer requires the continuation of such works
subsequent to Employer granting Contractor access to the Site. Contractor shall seek
and gain Employer's agreement before any monitoring equipment is removed.
3.5.1 Contractor shall design, construct, supply and install all elements of the 33/11kV
electrical substation compound, in accordance with the ADDC applicable Standards,
Specifications and requirements including, but not limited to:
3.5.3 Contractor shall supply and apply all road markings and place al road signage, traffic
calming and wayfinding, in accordance with the design and in compliance with
Authority requirements.
3.5.4 Contractor shall refer to Exhibit D Part 2 for the specifications for the Access road and
paving works in the substation compound. Pavement layer section shall be as below,
3.6.1 Contractor shall design, construct, supply and install all elements of the 33/11kV
electrical substation building, in accordance with the ADDC/TAQA applicable
Standards, Specifications and requirements, including, but not limited to:
33kV switch gear room, 11kV switchgear room, LV switch gear room, SCMS/
Control room
LVAC switchgear room, Battery room, HVAC room, DMS room,
Firefighting pump room and associated tank works
Potable water pump room and associated tank works
Transformer bays and 11kv Capacitor bank and Reactor shed etc.
All Utility rooms including cable cellar room
Internal road work, Street light poles
Exhibit “D”, Part 1 Page 33 of 42 2101-278
Scope of Works, Rev. A
Compound wall fencing and gates
Geotechnical investigations and ground improvement
Foundations and substructure
Superstructure (raft)/main frame
External cladding, glazing and roofing
Internal fit out and decoration
Fire compartmentalization, fire walls and fire protection
Fixtures and fittings
Access systems for maintenance of exterior
3.6.2 The building shall be deemed ‘weather tight’ when it is secured against the climatic
elements, i.e. wind, rain, temperature. Contractor shall confirm that installation of
equipment and plant / fit out of the building can occur without risk of damage to
equipment.
3.6.3 Contractor shall be responsible to obtain all the NOC’s, approvals, Building permit and
Building Completion Certificates for the proposed building and utilities. All the
necessary approvals for the utility corridors for the cable routing shall also require to
be obtained by the Contractor.
3.6.4 Contractor shall note that pile is not required for the proposed structure. Contractor
shall consider all the necessary ground improvements to design with the raft structure.
3.6.5 Contractor shall note that the proposed substation finished paving level (driveway
areas) inside the substation compound shall be min +4.428 ADD (+5.515 LAT).
Proposed reclamation level for the substation area is +4.078 ADD (+5.165 LAT).
Contractor shall develop the road layout and levels based on this and subject to
ADM/ADD/DOT approval.
3.6.6 Contractor shall develop the drawings and details for the Detailed Planning Approval
such as layouts, elevation and utility demand for the KIZAD approval prior to proceed
with the Building Permit approvals.
3.7.1 Contractor design, construct, supply and install all utilities, mechanical, electrical and
plumbing (MEP) systems and all other associated Services, Protection and Containment
Works within the 33/11kV electrical substation, but not limited to:
3.7.3 Contractor shall ensure that all telecom materials and/or equipment complies with the
current technical specifications of ETISALAT.
3.7.4 All Works shall comply with the applicable ETISALAT and AD QCC specification
requirements, unless otherwise stated in the relevant sections of this document.
4.1.2 All works shall be in accordance with the ADDC/TAQA applicable Standards,
Specifications and requirements, including, but not limited to:
4.1.3 For clarity, the above requirements shall be executed lump sum works for MV cable
and FO cable for each item based on the location of the connections (from and to).
4.1.4 Contractor shall provide unit rates for MV cables and FO cables for the increase or
decrease of the cable length for this scope of works.
4.2 OPTIONAL SCOPE 2 – MV and FO Cabling Works from KIZAD KP4 Grid Station
4.2.1 Contractor shall supply and install the MV cabling and FO cabling from the proposed
33/11 kV Substation to the existing KIZAD KP4 Grid Station.
4.2.2 All works shall be in accordance with the ADDC/TAQA applicable Standards,
Specifications and requirements, including, but not limited to:
4.2.4 Contractor shall provide unit rates for MV cables and FO cables for the increase or
decrease of the cable length for this scope of works.
4.2.5 For clarity, Contractor shall be responsible for the design of the MV/FO cabling network
including all the Authority approvals as part of the base scope of works.
4.3 OPTIONAL SCOPE 3 – MV and FO Cabling ducts (Cut and Cover method)
4.3.1 Contractor shall note that the cut and cover method might be required in some of the
road sections where there are no existing/sufficient ducts are available. Contractor
shall be required to provided unit rates as below for the cut and cover works expected
for the external cabling works.
4.4.1 Contractor shall note that the HDD method might be required in some of the road
sections where there are no existing/sufficient ducts are available. Contractor shall be
required to provided unit rates as below for the cut and cover works expected for the
external cabling works.
Sleeves for the cables (sleeves for 5 MV power cable and 2 FO cables with
additional 120% ducts spare ducts for future cables)
o HDD sleeves – 300 m length (3-4 crossing locations as tentative)
4.4.2 All HDD works shall be in accordance with the ADM/ADDC/TAQA applicable Standards,
Specifications and requirements, including, but not limited to:
5.0 INTERFACES
5.1.1 The primary parties which Contractor shall interface directly with Authorities, Asset
Management and Health, Safety, Environment and Security teams to provide
information and updates on Contractor’s operations and works within the area of
Khalifa Port. Contractor shall ensure such access and egress do not negatively affect
any of Khalifa Port and Operators.
5.1.2 Such interfacing shall also include the provision of forecasted requirements permits to
work, temporary works affecting the existing Khalifa Port infrastructure and general
coordination.
5.1.3 Contractor shall be required to interface directly with the Authorities for the necessary
permits, approvals to carry out the works. This shall include but not limited to ADM,
TPD, ADDC, ADWEA, ADCD, ETISALAT, TRANSCO etc.
5.1.4 As part of the execution of the works, Contractor shall be required to directly interface
with the following existing Contractor and Plot investors
6.1.2 Contractor shall be responsible for cleaning and servicing the office location and
Employer’s personnel shall be able to use the common facilities in Contractor’s office
(kitchen, toilets, printing facilities, etc.)
Not required.
7.1.1 Employer will provide timely documented transfer of responsibility for the work areas
to Contractor to enable the execution of the Works. Such transfer of responsibility may
occur in its entirety or in separate transfers depending on Contractor’s and Employer’s
requirements.
7.1.2 Contractor shall be responsible for ensuring that its activities are contained at all times
within the work areas, with the exception of agreed access and egress routes.
Contractor shall also be responsible for securing the work areas to prevent
unauthorized access by others.
7.1.3 Transfer of responsibility back to Employer shall also be documented. In the case of
completed work, such transfer shall be documented via Employer’s Taking Over
Certificates. In the case of incomplete areas required to be transferred back to
Employer for operational requirements, such transfer shall be documented accordingly
without any acceptance of the incomplete work.
7.2.2 Transfer of responsibility for the temporary facilities area to Contractor shall be
documented via Employer’s approval of the pre-mobilization survey.
7.2.3 Contractor shall be responsible for any activities required in order to make the
Temporary Facilities area usable including arrangement of temporary utilities for the
temporary facilities.
8.1.1 Employer’s general “No Objection” to the work is provided in the form of this Contract
and further NOC request from Employer for the work shall not be required.
8.1.2 Employer provided the NOC’s and approvals in the Exhibit F [Information].
8.1.3 For all elements of the Works to be executed by Contractor, Contractor shall arrange
the necessary approvals and NOC’s from the Authorities. For clarity, Employer will not
appoint any Consultant for the approvals required to be obtained by the Contractor.
8.2.1 Contractor shall be responsible for undertaking all activities necessary in order to
obtain any required approvals, permits and NOC’s in order to be able to execute the
Works through Authority approved Consultant and/or Supervision Consultant.
8.2.2 Contractor shall appoint a stakeholder approved design and supervision consultant(s)
who will approve all Contractor design and construction documents that require
Stakeholder approvals. The Supervision Consultant shall be approved by the Employer
and the relevant Stakeholder and be fully authorized to supervise the Works or any
part thereof.
8.2.3 Contractor shall carry out any aspect of the design to be verified by an Independent
Checking Engineer (ICE) In the event of any Authority or Stakeholder requirement.
Contractor shall appoint the third party for the structural design, electrical system
studies, road safety audits and reports.
8.2.4 Contractor’s supervision consultant shall require attending the Factory Inspection
Tests (including outside UAE) which is considered as part of the Contractor’s scope of
works. All the costs associated with these inspections are considered as part of the
Contractor Scope of Works.
8.2.5 Employer and Authorities will attend the Factory Inspection Tests for all the material
(associated with the Electrical systems and cables etc.). All the associated costs for the
same are included in the Contractor Scope of Works.
8.2.6 Any equipment’s and elements which are waived by the Authorities for the Factory
Inspection Tests (outside the UAE) shall be witnessed and approved by the third party
appointed by the Contractor as part of the Contractor scope of works . Third party
entities shall be approved by the respective Authorities and shall be approved by
Employer.
Progress measurement shall be based upon the physical progress against each of the
activities / sub-activities and deliverables according to a set of weighted values, allocated
according to the effort required to complete. For working out the weightage of various
activities within each area and within each phase of the Contract, the following basis will be
used:
Relative weightings for developing the overall S-Curves against the above three phases and
for each area shall generally be in line with the weightage set out in this Attachment. The
same may however be modified if required, in consultation with Employer, based on the
actual workloads.
Activity or deliverable weight factors will be computed based on the estimated man-
hours/cost as a fraction of the total man-hours/cost for each Area / Phase / Discipline etc.
and for the whole Contract.
The weight factors thus computed will be rolled upto the higher levels by Area / Phase /
Discipline etc. in line with the agreed Work Breakdown Structure (WBS).
Issue of any deliverable at an intermediate milestone stage does not automatically mean
achievement of the said milestone progress. Contractor’s Progress Measurement System
shall make necessary allowance for deduction of weighted progress if deliverables are
rejected by Employer as not being of the required standard.
Overall progress of the Contract shall be calculated by integrating the progress against each
Contract Area / Phase / Discipline etc. as described above.
Any change to the progress weightings on account of a Change to the Scope of Works or
the Contract will be agreed at the time of executing the Change Order and incorporated into
the Contract.
1.5 GENERAL
Following activities will not be assigned a separate weightage. This would mean that the
man-hour requirements against the following activities will not be considered for progress
computation:
a) General Items (Insurances, Permits & Fees and Bank Guarantees)
b) Home Office Services
c) Project Controls.
d) QA/QC
e) Mobilization / Demobilization of Construction Plant and Equipment.
1.6 ATTACHMENTS
Attachment A: Progress Measurement System
Exhibit “D”, Scope of Work Part 1, Attachment 1, Progress Measurement Procedure Contract No. 2101-278
Attachment A, Progress Measurement Sheet
Page 1 of 8
Ref DESCRIPTION Level 1 Level 2 Level 3 Level 4
B.1.1 Temporary Facilities Note 2
B.1.2 Construction Plant and Equipment Note 2
B.1.3 Maintenance of Temporary Facilities Note 2
C CONSTRUCTION
Exhibit “D”, Scope of Work Part 1, Attachment 1, Progress Measurement Procedure Contract No. 2101-278
Attachment A, Progress Measurement Sheet
Page 2 of 8
Ref DESCRIPTION Level 1 Level 2 Level 3 Level 4
C.1.4.2 Testing and Commissioning 2.00%
C.1.4.3 Snag 1.00%
C.1.4.4 As Built 1.00%
C.1.4.5 Handing Over 1.00%
C.1.5 Compound Wall Works and External Building Works Note 2
C.1.5.1 Construction 95.00%
C.1.5.2 Testing and Commissioning 2.00%
C.1.5.3 Snag 1.00%
C.1.5.4 As Built 1.00%
C.1.5.5 Handing Over 1.00%
C.1.6 Building MEP Works Note 2
C.1.6.1 Construction 95.00%
C.1.6.2 Testing and Commissioning 2.00%
C.1.6.3 Snag 1.00%
C.1.6.4 As Built 1.00%
C.1.6.5 Handing Over 1.00%
C.2 33/11 kV Primary Substation Electrical Plant & Equipments Note 1
Exhibit “D”, Scope of Work Part 1, Attachment 1, Progress Measurement Procedure Contract No. 2101-278
Attachment A, Progress Measurement Sheet
Page 3 of 8
Ref DESCRIPTION Level 1 Level 2 Level 3 Level 4
C.2.1.2.3 Snag 2.00%
C.2.1.2.4 As Built 2.00%
C.2.1.2.5 Handing Over 1.00%
C.2.2 33kV switchgears Note 2
C.2.2.1 Supply (Major Equipments) 20.00%
C.2.2.1.1 Preparation and Submission of submittals 5.00%
C.2.2.1.2 Review and Approval of submittals by Employer 5.00%
C.2.2.1.3 Placing of Purchase Order by Contractor 20.00%
C.2.2.1.4 Manufacturing/Fabrication 30.00%
C.2.2.1.5 Delivery at Site 40.00%
C.2.2.2 Installation (Construction Execution) 80.00%
C.2.2.2.1 Construction 90.00%
C.2.2.2.2 Testing and Commissioning 5.00%
C.2.2.2.3 Snag 2.00%
C.2.2.2.4 As Built 2.00%
C.2.2.2.5 Handing Over 1.00%
C.2.3 11kV switch gears Note 2
C.2.3.1 Supply (Major Equipments) 20.00%
C.2.3.1.1 Preparation and Submission of submittals 5.00%
C.2.3.1.2 Review and Approval of submittals by Employer 5.00%
C.2.3.1.3 Placing of Purchase Order by Contractor 20.00%
C.2.3.1.4 Manufacturing/Fabrication 30.00%
C.2.3.1.5 Delivery at Site 40.00%
C.2.3.2 Installation (Construction Execution) 80.00%
C.2.3.2.1 Construction 90.00%
C.2.3.2.2 Testing and Commissioning 5.00%
C.2.3.2.3 Snag 2.00%
C.2.3.2.4 As Built 2.00%
Exhibit “D”, Scope of Work Part 1, Attachment 1, Progress Measurement Procedure Contract No. 2101-278
Attachment A, Progress Measurement Sheet
Page 4 of 8
Ref DESCRIPTION Level 1 Level 2 Level 3 Level 4
C.2.3.2.5 Handing Over 1.00%
C.2.4 LV switchgear Note 2
C.2.4.1 Supply (Major Equipments) 20.00%
C.2.4.1.1 Preparation and Submission of submittals 5.00%
C.2.4.1.2 Review and Approval of submittals by Employer 5.00%
C.2.4.1.3 Placing of Purchase Order by Contractor 20.00%
C.2.4.1.4 Manufacturing/Fabrication 30.00%
C.2.4.1.5 Delivery at Site 40.00%
C.2.4.2 Installation (Construction Execution) 80.00%
C.2.4.2.1 Construction 90.00%
C.2.4.2.2 Testing and Commissioning 5.00%
C.2.4.2.3 Snag 2.00%
C.2.4.2.4 As Built 2.00%
C.2.4.2.5 Handing Over 1.00%
C.2.5 SCMS system Note 2
C.2.5.1 Supply (Major Equipments) 20.00%
C.2.5.1.1 Preparation and Submission of submittals 5.00%
C.2.5.1.2 Review and Approval of submittals by Employer 5.00%
C.2.5.1.3 Placing of Purchase Order by Contractor 20.00%
C.2.5.1.4 Manufacturing/Fabrication 30.00%
C.2.5.1.5 Delivery at Site 40.00%
C.2.5.2 Installation (Construction Execution) 80.00%
C.2.5.2.1 Construction 90.00%
C.2.5.2.2 Testing and Commissioning 5.00%
C.2.5.2.3 Snag 2.00%
C.2.5.2.4 As Built 2.00%
C.2.5.2.5 Handing Over 1.00%
C.2.6 33/11kv substations control and protection panels Note 2
Exhibit “D”, Scope of Work Part 1, Attachment 1, Progress Measurement Procedure Contract No. 2101-278
Attachment A, Progress Measurement Sheet
Page 5 of 8
Ref DESCRIPTION Level 1 Level 2 Level 3 Level 4
C.2.6.1 Supply (Major Equipment) 20.00%
C.2.6.1.1 Preparation and Submission of submittals 5.00%
C.2.6.1.2 Review and Approval of submittals by Employer 5.00%
C.2.6.1.3 Placing of Purchase Order by Contractor 20.00%
C.2.6.1.4 Manufacturing/Fabrication 30.00%
C.2.6.1.5 Delivery at Site 40.00%
C.2.6.2 Installation (Construction Execution) 80.00%
C.2.6.2.1 Construction 90.00%
C.2.6.2.2 Testing and Commissioning 5.00%
C.2.6.2.3 Snag 2.00%
C.2.6.2.4 As Built 2.00%
C.2.6.2.5 Handing Over 1.00%
C.2.7 Tariff meters Note 2
C.2.7.1 Supply (Major Equipment) 20.00%
C.2.7.1.1 Preparation and Submission of submittals 5.00%
C.2.7.1.2 Review and Approval of submittals by Employer 5.00%
C.2.7.1.3 Placing of Purchase Order by Contractor 20.00%
C.2.7.1.4 Manufacturing/Fabrication 30.00%
C.2.7.1.5 Delivery at Site 40.00%
C.2.7.2 Installation (Construction Execution) 80.00%
C.2.7.2.1 Construction 90.00%
C.2.7.2.2 Testing and Commissioning 5.00%
C.2.7.2.3 Snag 2.00%
C.2.7.2.4 As Built 2.00%
C.2.7.2.5 Handing Over 1.00%
C.2.8 Protection systems Note 2
C.2.8.1 Supply (Major Equipment) 20.00%
C.2.8.1.1 Preparation and Submission of submittals 5.00%
Exhibit “D”, Scope of Work Part 1, Attachment 1, Progress Measurement Procedure Contract No. 2101-278
Attachment A, Progress Measurement Sheet
Page 6 of 8
Ref DESCRIPTION Level 1 Level 2 Level 3 Level 4
C.2.8.1.2 Review and Approval of submittals by Employer 5.00%
C.2.8.1.3 Placing of Purchase Order by Contractor 20.00%
C.2.8.1.4 Manufacturing/Fabrication 30.00%
C.2.8.1.5 Delivery at Site 40.00%
C.2.8.2 Installation (Construction Execution) 80.00%
C.2.8.2.1 Construction 90.00%
C.2.8.2.2 Testing and Commissioning 5.00%
C.2.8.2.3 Snag 2.00%
C.2.8.2.4 As Built 2.00%
C.2.8.2.5 Handing Over 1.00%
C.2.9 33/11kv Capacitor bank and Reactor Control Note 2
C.2.9.1 Supply (Major Equipments) 20.00%
C.2.9.1.1 Preparation and Submission of submittals 5.00%
C.2.9.1.2 Review and Approval of submittals by Employer 5.00%
C.2.9.1.3 Placing of Purchase Order by Contractor 20.00%
C.2.9.1.4 Manufacturing/Fabrication 30.00%
C.2.9.1.5 Delivery at Site 40.00%
C.2.9.2 Installation (Construction Execution) 80.00%
C.2.9.2.1 Construction 90.00%
C.2.9.2.2 Testing and Commissioning 5.00%
C.2.9.2.3 Snag 2.00%
C.2.9.2.4 As Built 2.00%
C.2.9.2.5 Handing Over 1.00%
C.2.10 Redundant 110V DC system with redundant charger Note 2
C.2.10.1 Supply (Major Equipments) 20.00%
C.2.10.1.1 Preparation and Submission of submittals 5.00%
C.2.10.1.2 Review and Approval of submittals by Employer 5.00%
C.2.10.1.3 Placing of Purchase Order by Contractor 20.00%
Exhibit “D”, Scope of Work Part 1, Attachment 1, Progress Measurement Procedure Contract No. 2101-278
Attachment A, Progress Measurement Sheet
Page 7 of 8
Ref DESCRIPTION Level 1 Level 2 Level 3 Level 4
C.2.10.1.4 Manufacturing/Fabrication 30.00%
C.2.10.1.5 Delivery at Site 40.00%
C.2.10.2 Installation (Construction Execution) 80.00%
C.2.10.2.1 Construction 90.00%
C.2.10.2.2 Testing and Commissioning 5.00%
C.2.10.2.3 Snag 2.00%
C.2.10.2.4 As Built 2.00%
C.2.10.2.5 Handing Over 1.00%
C.2.11 MV and LV and FO cabling works Note 2
C.2.11.1 Construction 95.00%
C.2.11.2 Testing and Commissioning 2.00%
C.2.11.3 Snag 1.00%
C.2.11.4 As Built 1.00%
C.2.11.5 Handing Over 1.00%
C.2.12 Termination of Cables at both ends including all accessories Note 2
C.2.6.1 Construction 95.00%
C.2.6.2 Testing and Commissioning 2.00%
C.2.6.3 Snag 1.00%
C.2.6.4 As Built 1.00%
C.2.6.5 Handing Over 1.00%
100%
Notes:
Note 1 - "Level 1" percentage to be agreed based on the agreed Programme of Works
Note 2 - "Level 2" percentage shall be based on Pay-line item in Form A-1 against Total Value of Level 1
Exhibit “D”, Scope of Work Part 1, Attachment 1, Progress Measurement Procedure Contract No. 2101-278
Attachment A, Progress Measurement Sheet
Page 8 of 8