Professional Documents
Culture Documents
COST Monitoring and Control Earned Value Method
COST Monitoring and Control Earned Value Method
Jay..
Calculating Earned Value and Estimate to Complete
Questions?
Jay..
Jay..
What is Earned Value?
Combines Measurements of
Scope
Schedule
Current Plan
Cost
Jay..
Primavera Variables
Planned Value
is the authorized budget assigned to scheduled work.
Actual Value
is the realized cost incurred for the work performed on an activity during a specific time
period.
Earned Value
It is the budget associated with the authorized work that has been completed.
Jay..
Jay..
Jay..
Jay..
Jay..
Jay..
Jay..
Jay..
Jay..
Jay..
Jay..
Forecasting
Estimate At Completion & Estimate To Complete
Jay..
Estimate At Completion
EAC EAC
𝑩𝑨𝑪
AC + (BAC – EV)
𝑪𝑷𝑰
CPI is expected to be the same for the remainder of the project Future work will be accomplished at the planned rate
EAC EAC
(𝑩𝑨𝑪 −𝑬𝑽)
AC + AC + Bottom up ETC
(𝑪𝑷𝑰 𝒙 𝑺𝑷𝑰)
CPI and SPI influence the remaining work Initial plan is no longer valid
Jay..
Estimate To Complete
ETC ETC
EAC – AC Re-Estimate
Assumes work is proceeding on plan. Re-estimate the remaining work from the bottom up.
Jay..
Variance At Completion
VAC
BAC – EAC
The estimated difference in cost at the completion of the project.
Jay..
BAC AC EV EAC ETC Variance
Jay..
Performance measurement data element
Jay..