CONSTRUCTION OF ELEVATED PATHWAY (PHASEII)

Barangay Simbuco, Kolambugan, Lanao del Norte

BILL OF MATERIALS AND COST ESTIMATES

I. CONCRETE MASONRY WORKS:

A. Materials;

38 Bags Portland cement P 275.00 P 10,450.00


5 Cum Washed sand 1,200.00 6,000.00
5 Cum Washed gravel 1,200.00 6,000.00
6 cum 6" Boulders 1,100.00 6,600.00
2 Bundles 1"x2"x8' Moro Lumber 280.00 560.00
1 kls Assorted CW Nails 85.00 85.00
29,695.00

B. Labor; 30% 8,908.50

TOTAL P 38,603.50

C. Unit Cost 40,000.00 2,105.26/l.m.


19 Linear Meter

SUMMARY

A. MATERIALS - -- - -- - - - - - - - - - - - - - - - - - - P 29,695.00

B. LAB O R ; 8,908.50

C. CONTINGENCY 1,396.50

TOTAL ESTIMATED PROJECT COST P 40,000.00