You are on page 1of 10

Askari-1- road CIVIL WORK PROGRESS

S.No Address Excavated Duct Layed(57mm)


Completed Length (m) Start Date End Date Completed Length (m)
1 Dc#4 to block 21 25 25/03/2019 25/03/2019 60
2 block#22 to D#4 0
3 block#22 to D#4 0
4 Block #5 to Block #6 23 0
Grand Total 48 60
Duct Layed(25mm) Back Filled
Start Date End Date Completed Length (m) Start Date End Date Completed Length (m)
26/03/2019 26/03/2019 0 25
25 28/03/2019 28/03/2019
35 28/03/2019 28/03/2019
28/03/2019 28/03/2019 50 23
110 48
HHs DCs SPURs
Start Date End Date Planned Installed Planned Installed Length Completed
26/03/20126/03/201 2 2 1 1 5 5

2
2 1 1 5
Remarks

From Dc #4 to block 21 for 48F Duct cable


From Dc #4 to block 22 for 48F Duct cable
From Dc #4 to Electrick pol for 12F Feeder
From Dc #4 to block 05 for 48F Duct cable
DATE VENDOR NAME Project Block OFC TYPE Pulled(MetREMARKS
25/03/2019 Magnam Star Askari-1 22 to 25 12F CLT 100 FOC Pulling Done
25/03/2019 Magnam Star Askari-1 22 to 27 12F CLT 180 FOC Pulling Done
25/03/2019 Magnam Star Askari-1 22 to 22 12F CLT 60 FOC Pulling Done
25/03/2019 Magnam Star Askari-1 22 to 16 12F CLT 135 FOC Pulling Done
25/03/2019 Magnam Star Askari-1 21 to 23 12F CLT 65 FOC Pulling Done
25/03/2019 Magnam Star Askari-1 21 to 17 12F CLT 110 FOC Pulling Done
26/03/2019 Magnam Star Askari-1 21 to 13 12F CLT 170 FOC Pulling Done
26/03/2019 Magnam Star Askari-1 21 to 14 12F CLT 220 FOC Pulling Done
26/03/2019 Magnam Star Askari-1 6 to 4 12F CLT 65 FOC Pulling Done
26/03/2019 Magnam Star Askari-1 6 to 8 12F CLT 65 FOC Pulling Done
26/03/2019 Magnam Star Askari-1 6 to 10 12F CLT 120 FOC Pulling Done
26/03/2019 Magnam Star Askari-1 5 to 3 12F CLT 65 FOC Pulling Done
26/03/2019 Magnam Star Askari-1 5 to 9 12F CLT 120 FOC Pulling Done
26/03/2019 Magnam Star Askari-1 4F feeder 12F CLT 170 FOC Pulling Done
TOTAL 1645

f
f
DATE VENDOR NAME Project Block OFC TYPE Pulled(Meter) REMARKS
25/03/2019 Magnam Star Askari-1 Dc #4 to 22 48F Duct 83 FOC Pulling Done
25/03/2019 Magnam Star Askari-1 Dc#4 to 21 48F Duct 70 FOC Pulling Done
25/03/2019 Magnam Star Askari-1 Dc#4 to 5 48F Duct 140 FOC Pulling Done
25/03/2019 Magnam Star Askari-1 Dc#4 to 6 48F Duct 110 FOC Pulling Done
TOTAL 403
S.no Items UOM
1 HDPE Pipe 57MM
Issue From Wherehouse on 11/3/2019 HDPE Pipe M 100
Total Consumed M 60
Remeaning M 40

2 HDPE Pipe 25MM


Issue From Wherehouse on 21/3/2019 HDPE Pipe M 150
Total Consumed M 110
Remeaning M 40

3 12F CLT UOM


Issue From Wherehouse on 21/3/2019 M 4100
Total Consumed M 1645
Remeaning M 2455

4 48F Duct UOM


Issue From Wherehouse on 21/3/2019 M 606
Total Consumed M 403
Remeaning M 203

5 DC cabnet UOM
Issue From Wherehouse on 21/3/2019 N/A 1
Total Consumed 1
Remeaning 0

6 48F joint clouser UOM


Issue From Wherehouse on 21/3/2019 N/A 4
Total Consumed 4
Remeaning 0

7 1*64 Splitter with BOX UOM


Issue From Wherehouse on 21/3/2019 N/A 1
Total Consumed 1
Remeaning 0

8 Angle iron Round Clamp UOM


Issue From Wherehouse on 21/3/2019 N/A 60
Total Consumed 49
Remeaning 11