BACK UP DATA

KOLAM RETENSI KALI KOMAK

* GALIAN

SKETSA VOLUME

60.00

45.00

LUAS LUAS rata-rata P Volume


No. L1 (m) L2 (m) L3 (m) H1 (m) H2 (m) H3 (m) Keterangan
(M2) (M2) ( M1 ) (M3)

I. Galian Penampang
1 0+000 45.00 - - 2.50 - - 112.50
112.50 60.00 6,750.00
2 0+060 45.00 - - 2.50 - - 112.50

II. Galian Pondasi Pas. Dinding


1 0+000 3.50 - - 3.00 - - 10.50
10.50 210.00 2,205.00
2 0+210 3.50 - - 3.00 - - 10.50
TOTAL GALIAN 8,955.00

III. Galian Normalisasi kali


1 0+000 6.00 - - 1.50 - - 9.00
9.00 50.00 450.00
2 0+050 6.00 - - 1.50 - - 9.00

TOTAL GALIAN 450.00


BACK UP DATA

KOLAM RETENSI KALI KOMAK

Pagar
* DINDING KOLAM

SKETSA VOLUME Urugan P


Dinding
Urugan
Paving Block
Pagar pengaman
1.00 3.00 1.00

Rabat Beton
Urugan Pilihan Dinding Pas. Batu
3.50
Dinding Beton
2.00 Urugan Biasa

3.00
2.00

1.50
2.00 3.00 2.00

LUAS LUAS rata-rata P Volume


No. L1 (m) L2 (m) L3 (m) H1 (m) H2 (m) H3 (m) Keterangan
(M2) (M2) ( M1 ) (M3)

I. BETON DINDING BAGIAN DALAM


1 0+000 1.00 2.00 1.50 3.50 3.00 2.00 12.75
12.38 170.00 2,103.75
2 0+170 1.00 2.00 - 4.00 3.00 - 12.00

2,103.75

II. PAS. BATU DINDING BAGIAN LUAR


1 0+000 1.00 2.00 - 3.50 3.00 - 11.25
11.25 210.00 2,362.50
2 0+210 1.00 2.00 - 3.50 3.00 - 11.25

TOTAL PASANGAN 2,362.50

III. Pasangan KANAL


1 0+000 0.50 1.00 4.00 1.50 1.00 0.30 3.33
3.33 50.00 166.25
2 0+050 0.50 1.00 4.00 1.50 1.00 0.30 3.33

TOTAL PASANGAN 166.25


BACK UP DATA

KOLAM RETENSI KALI KOMAK

* BANGUNAN PELENGKAP

SKETSA VOLUME
60.00
Paving Block
Pagar pengaman
1.00 3.00 1.00

Rabat Beton
Urugan Pilihan Dinding Pas. Batu
3.50
Dinding Beton
2.00 Urugan Biasa

45.00 2.00
3.00

1.50
2.00 3.00 2.00

LUAS LUAS rata-rata P Volume


No. L1 (m) L2 (m) L3 (m) H1 (m) H2 (m) H3 (m) Keterangan
(M2) (M2) ( M1 ) (M3)

I. Pasangan Baya-baya
1 0+000 3.00 5.00 - 4.00 3.00 - 31.00
31.00 4.00 124.00
2 0+004 3.00 5.00 - 4.00 3.00 - 31.00

TOTAL PASANGAN 124.00

II. Pasangan Mercu


1 0+000 0.75 2.00 - 2.00 3.00 - 8.75
8.75 12.00 105.00
2 0+012 0.75 2.00 - 2.00 3.00 - 8.75

TOTAL PASANGAN 105.00

III. PEKERJAAN BETON BERTULANG


A. Plat Kontrol Pintu
1 0+000 6.00 - - 0.30 - - 1.80
1.80 6.00 10.80
2 0+006 6.00 - - 0.30 - - 1.80

TOTAL BETON 10.80

B. LAPIS AUS MERCU


1 0+000 4.50 - - 0.30 - - 1.35
1.35 12.00 16.20
2 0+012 4.50 - - 0.30 - - 1.35

TOTAL BETON 16.20


2.00 3.00 2.00

LUAS LUAS rata-rata P Volume


No. L1 (m) L2 (m) L3 (m) H1 (m) H2 (m) H3 (m) 2 2 1 3 Keterangan
(M ) (M ) (M ) (M )

C. ENDSILL
1 0+000 5.00 - - 0.35 - - 1.75
1.75 24.00 42.00
2 0+024 5.00 - - 0.35 - - 1.75

TOTAL BETON 42.00

IV. PEKERJAAN RABAT BETON (JL. INSPEKSI)


1 0+000 3.00 - - 0.30 - - 0.90
0.90 190.00 171.00
2 0+190 3.00 - - 0.30 - - 0.90

TOTAL BETON 171.00

V. PEKERJAAN LANTAI PAVING BLOCK


1 0+000 3.00 - - - - - 3.00
3.00 190.00 570.00
2 0+190 3.00 - - - - - 3.00

TOTAL PAVING BLOCK 570.00

VI. BRONJONG
A. Bronjong Dinding
1 0+000 1.00 3.00 - 1.00 2.00 - 7.00
7.00 190.00 1,330.00
2 0+190 1.00 3.00 - 1.00 2.00 - 7.00

TOTAL BRONJONG 1,330.00

B. Bronjong Endsill
1 0+000 5.00 - - 1.00 - - 5.00
5.00 30.00 150.00
2 0+030 5.00 - - 1.00 - - 5.00

TOTAL BRONJONG 150.00