You are on page 1of 2

Case History: High-Pressure/High-Temperature

Underbalanced Drillstem Testing

T his paper describes the


method developed to achieve
underbalanced drillstem testing (DST)
in a deepwater field offshore India. DST
x x
tools rated to 450°F and 15,000-psi
differential pressure were configured
to maintain integrity and successfully
evaluate the well potential. By use of a
multicycle DST tool string, the reservoir
potential was tested safely and
effectively with an underbalanced test
fluid in two deepwater wells, achieving
the desired test objectives.

Introduction
An operator in India needed to con-
duct high-pressure/high-temperature
x x 9⅝-in. casing
(HP/HT) drillstem testing on a deep-
water well with low-density clear brine 7-in. liner
in the annulus. Performing DST was nec- x x
essary to assess hydrocarbon poten- 5-in. liner
tial in the deepwater block for further
field-development plans. The DST tools
Fig. 1—Well schematic.
performed satisfactorily for approxi-
mately 18 days during the test on a semi-
submersible rig. Before lowering the DST tools, a well- and solid settlement could have result-
The well was completed in a 6-in. hole, integrity test was performed by conduct- ed in the retrievable packer sticking and
which resulted in a 5-in. casing program, ing an inflow test for a 5-in.-liner shoe, a could have presented challenges for an-
thereby creating a significant challenge. 5-in.-liner-hanger top, and a 7-in.-liner- nulus pressure transmission to operate
The retrievable packer suitable for the hanger top. Hermetic tests were per- DST tools. The kill-mud weight required
7-in. casing was set above the 5-in.-liner- formed to ensure that casings sustained was in the range of 15.8 to 16.8 lbm/gal,
hanger top, resulting in a tail pipe of ap- the required annulus pressure for opera- compared with the available brine weight
proximately 350 m. Well killing at the tion of the DST tools. of 11.4 to 13.8 lbm/gal. The bottomhole
end of the DST with such a long tail pipe temperature was in the range of 365
was a challenge. Need for HP/HT to 370°F.
The method of operating DST tools Underbalanced Testing
in both underbalanced brine and kill- The anticipated pore pressure was sig- Slimhole DST Tools
weight mud was developed along with a nificantly higher than the available brine The option of deploying slimhole
meticulously designed well-test program weight. The use of kill-weight mud for the DST tools suitable for a 5-in. liner was
and a well-kill procedure with a long tail DST operation was considered, but high- planned but was not possible because
pipe below the 7-in. retrievable packer. temperature conditions, barite sagging, of the available time frame. Slimhole
DST tools would have limited opera-
tions such as wireline correlation and
This article, written by JPT Technology Editor Chris Carpenter, contains highlights slickline sampling.
of paper SPE 178089, “Case History: HP/HT Underbalanced Drillstem Testing,
Deepwater KG Offshore,” by Mahesh Sarode and Milind Khati, Halliburton, Planning and Execution
prepared for the 2015 SPE Oil and Gas India Conference and Exhibition, Mumbai, The objectives and challenges of this DST
24–26 November. The paper has not been peer reviewed. job were defined as follows:

For a limited time, the complete paper is free to SPE members at www.spe.org/jpt.

JPT • FEBRUARY 2017 67


◗ Determine the initial reservoir leaks, leaks in the riser, string diagrams, were activated hydraulically while
pressure and temperature. operating‑pressure calculations, risk the downhole tester valve was kept
◗ Gather the bottomhole fluid sample. analysis, roles and responsibilities, and in fail‑safe open mode.
◗ Verify well integrity. lines of communication. 12. A reservoir study program was
◗ Perform underbalanced DST with completed. Pressure, volume, and
reservoir pressure of 15.8 lbm/ Well Preparation and Testing temperature samples were also
gal and temperature of 370°F at Operation: Detailed Steps captured, and a gradient survey
4300‑m depth. The detailed steps performed after com‑ was performed.
◗ Conduct underbalanced DST of pleting drilling, lowering a 5‑in. liner, and 13. The well‑kill operation
reservoir objects behind a 5‑in. liner cementing are listed here. Fig. 1 provides commenced. The circulating valve
using a 7‑in. retrievable packer and the well schematic. The steps to complete was cycled to circulating position
DST tools with a long tail pipe. the well preparation are provided in the to displace annulus brine by kill‑
◗ Execute the well‑kill plan. complete paper. weight mud.
Completing all the steps in well prep‑ 14. After completing the kill‑weight‑
Equipment Preparation aration is critical before beginning mud displacement, the circulating
After completing the logging activities, an underbalanced tubing‑conveyed‑ valve was cycled to the well‑test
reservoir data such as bottomhole pres‑ perforation (TCP) and DST bottomhole‑ position. At this stage, the well
sure and temperature were received. This assembly deployment. volume above the circulating valve
information is very important for equip‑ The following steps were taken to per‑ had kill‑weight brine in annulus
ment preparation. Because the DST tools form the underbalanced DST: and tubing.
operate with a dual‑fluid system at 370°F, 1. Make up and run in hole the TCP 15. The next step in the operation
all the tools were stripped and were reas‑ assembly. was to bullhead kill mud to the
sembled with special HP/HT redress kits. 2. Make up and run in hole the 2⅞‑in. formation. Bullheading gas
Equipment reassembling, function test‑ tubing to serve as tail pipe in the trapped below the 7‑in. packer
ing, and pressure testing were carried out 5‑in.‑liner section. was challenging, so, in the string
by a highly experienced DST team. 3. Make up and run in hole the 7‑in. diagram, one circulating sub was
Multicycle circulating valves and multi‑ retrievable packer and HP/HT DST strategically placed immediately
cycle downhole tester valves require ni‑ tools. below the 7‑in. packer.
trogen precharge. Because the tools were 4. Make up and run in hole the 16. The placement of the circulating
expected to operate in both underbal‑ 3½‑in. tubing up to seabed. The sub enabled bullheading below the
anced brine and kill‑weight mud, a ni‑ tubing was hydraulically pressure 7‑in. packer into the formation.
trogen precharge suitable to both fluid tested at very high pressures while 17. The contingency plan in case
systems was performed. The single‑shot running in hole considering the the formation did not allow
rupture‑disk‑operated tools were also TCP hydraulic firing‑head pressure bullheading was also prepared,
designed to operate in both fluid sys‑ and reservoir pressure. which required increasing the kill‑
tems. The function test of equipment is 5. The fluted hanger assembly was weight mud above 16.5 lbm/gal at
important because the tools are required made up on string and run in hole the depth of the circulating valve
to operate in the wellbore in HP/HT con‑ on drillpipe as a landing string. (approximately 3800 m) to balance
ditions. The equipment‑function test and 6. Wireline correlation was the hydrostatic head against the
pressure test were witnessed by an on‑ conducted to space out guns formation pressure at a depth of
site DST engineer and the operator’s on‑ on depth. 4300 m, which was approximately
site well‑test engineer. 7. The fluted hanger with drillpipe 18.0 lbm/gal.
was pulled out of hole and laid 18. A flow check was conducted,
Well-Test-Program Preparation down. and the packer was unseated
and Contingency Plan 8. The subsea safety system was afterward.
A detailed well‑test program and DST‑ made up; the latch/unlatch 19. The TCP‑DST string was pulled out
tool operating‑pressure calculation were mechanism was function tested of hole after the successful job.
prepared by the service company’s well‑ and run in hole.
test engineer and were reviewed with the 9. The flowhead was connected after Conclusion
operator’s well‑test engineer. A detailed running in hole all the assemblies. By use of the multicycle DST tool string,
discussion and review were held with all 10. The retrievable packer was set by the operator was able to test the reser‑
involved teams to explain the detailed rotation, the rupture‑disk/pipe‑ voir potential safely and effectively with
well‑test program. The well‑test program tester valve was activated, and the an underbalanced test fluid in two deep‑
served as the reference document for circulating valve was cycled for water wells, achieving the desired test
every step. It covered aspects of the op‑ cushion spotting. objectives. This project set a record for a
eration such as well information, approv‑ 11. After cushion spotting, the service company performing HP/HT un‑
al for expenditure, sequence of opera‑ circulating valve was cycled to the derbalanced DST in a deepwater environ‑
tions, contingency plans in case of tubing well‑test position, and TCP guns ment in India. JPT

68 JPT • FEBRUARY 2017

You might also like