Professional Documents
Culture Documents
A PROJECT REPORT
OF
“PLANNING AND DESIGN OF NET ZERO ENERGY
RESIDENTAL BUILDING”
UNDER THE GUIDENCE OF
Mr.A.B.Ghadge
SUBMITTED BY:-
1
Certificate
Principal
2
ACKNOWLEDGMENT
It is being a result of patients, hard work and mutual understanding; it is our great
pleasure to represent this project on “Ayurvedic Medicine & its Uses”
Everything needs some where to fallback upon sometimes. And we are not an
exception. The completion of this project is the result of immense, heartfelt advice
and suggestions from various people in various fields no matter how small they
might seem to be. We would first like to thank our guide Mr.A.B.Ghadge
without whom the completion of this project would be nothing but a mere dream.
Their suggestions, advice and wonderful ideas had never failed to add some color
to this project.
The patience, advice and encouragement of our classmates and our friends
in general had been too helpful to be neglected. Wondering what would
happen without them. We heartily like to express our gratitude to them too.
Well charity can also last at home sometimes. We would also like to thank
one another in our project group for this advice, hardworking patience and off
course precious idea.
3
BONAFIDE CERTIFICATE
Certified that this project report titled “PLANNING AND DESIGN OF NET
the work reported herein does not form part of any other project report or
DATE:
4
ABSTRACT
5
ACKNOWLEDGEMENT
The author is grateful and records his sincere thanks to Dr. T. P. GANESAN
Pro Vice Chancellor (P&D) and Dr. C. MUTHAMIZHCHELVAN, Director, (E&T), SRM
UNIVERSITY for providing all the necessary facilities for carrying out this work.
The author expresses his sincere thanks and Gratitude to HOD Dr. R. ANNADURAI,
Department of Civil Engineering, for his valuable suggestions and advice in carrying out this
thesis work.
The author hereby acknowledges with deep sense of gratitude the valuable guidance
given by the Guide Mrs.VASANTHI P, Assistant Professor, Department of Civil Engineering,
for initiative and motivation during the course of this work.
The author is extremely grateful to the valuble advices given by the class incharge
Mr.K.PRASANNA, Assistant professor,Department of Civil Engineering, for constant support.
The author is grandly indebted to all the Faculty Members of Department of Civil
Engineering, for their valuable help rendered during the course of study.
Finally, the author expresses his hearty thanks to Friends for their kind help and
encouragement throughout the course of this thesis work.
6
TABLE OF CONTENTS
7
2.4.1 Fire Safety, Detection And Extinguishing
System 10
2.4.2 Security Deposits 10
8
4.3.3.1 Solar Panels 55
4.3.3.2 Solar Regulator 55
4.3.3.3 Power Inverter 56
4.3.3.4 Solar Batteries 56
4.3.4 Designing of Solar Panel 57
4.4 RATE ANALYSIS OF SOLAR PANELS 59
4.5 INFRARED THERMOMETER 60
4.6 HOLLOW BRICK 62
4.6.1 Parameters of Hollow Brick 62
4.6.2 Advantages of Hollow Bricks 64
4.7 ESTIMATION 65
4.7.1 Abstract Estimate of Conventional Building 65
4.7.2 Abstract Estimate of NZERB 67
4.7.3 Rate Analysis 70
5 CONCLUSION 72
5.1 CONCLUSION 72
5.2 FUTURE SCOPE 72
REFERENCES 73
9
LIST OF TABLES
10
LIST OF FIGURES
11
ABBREVIATIONS
12
Mu,max - Maximum ultimate moment
Ast( reqd) - Area of steel required
Ast (min) - Area of minimum steel required
ast - Area of 1 bar
D.L - Dead Load
L.L - Live Load
Φ - Angle of internal friction
NC , NY, Nq - Bearing capacity factors
CMDA - Chennai metropolitian development authority
PWD - Public works department
NBC - National Building Code
KKNP - Kudankulam Nuclear Power Plant
W.h - Watt hour
A.h - Ampere hour
13
CHAPTER 1
OVERVIEW
1.1 OBJECTIVE
1.2 NECESSITY
1.3 SCOPE
14
ii. Design of load bearing structure using hollow bricks
iii. Design of solar panels
iv. Comparison of room temperature between NZERB and conventional building
v. Comparison of energy consumption between NZERB and conventional building.
1.4 METHODOLOGY
This entire project is an planning and design in nature and the methodology followed in
this project is listed as below.
i. Selection of site where renewable energy is available
ii. Study the climate conditions of area
iii. Aligning the building to utilize maximum amount of renewable resources
iv. Planning and design of proposed NZERB building
v. Comparison of the NZERB building with other conventional building
Design experience in the following areas has been gained during the course of the
project
i. Design of slabs
i. Economic: Building shall be designed such that the entire energy requirements are met
by solar energy only due to shortage of conventional energy.
ii. Sustainability Constraints: The design shall be such that the requirement of cooling
do not fluctuate throughout the year.
15
iii. Economic Constraint: The materials adopted for construction are economical
compared to conventional materials.
The codes for design of buildings and structures, Design co-efficient, Limit state design
method and Fixing of dimensions are shown in Table 1.1
The codes for Computer aided building drawing, layout and planning and
Byelaws, Setbacks, Open space, Floor area ratio are shown in Table 1.2
Table 1.2 Application of earlier course work
Course Code and Name Context
CE 0104- Computer aided building Computer aided building drawing
16
drawing
CE0102- Elements of building science
layout and planning
and Architecture
Byelaws, Setbacks, Open space, Floor
CE0209- Building technology
area ratio
CE0303-Structural Design II R.C.C Design
CE0304-Structural Design III R.C.C Design
i. Auto CAD
ii. MS EXCEL
iii. MS WORD
1.11 CONCLUSION
The two types of buildings are analyzed with respect to cost, time, availability of
skilled labour and ease in construction.
AVAILABILITY
COST ELECTRICITY OF
RESOURSES
17
NORMAL
It requires an Easily Available
CONVENTIONAL Low
active source
BUILDING
18
CHAPTER 2
INTRODUCTION
2.1 GENERAL
Fast rate of urbanization and increase in the consumption of electricity has become a
major problem in Tamil Nadu. Due to increase in consumption of electricity the Tamil Nadu
electricity board is unable to fulfill the requirements of the public and industrial sectors .In Tamil
Nadu, This is the major problem faced. Officials were banking on a number of projects, which
would generate 14,000 MW of power, from thermal, nuclear and other power projects. Most of
these should have been completed by 2012. But the projects have got delayed, with the KKNP
turning out to be a big challenge .Hence requirement has brought in new building technologies
by utilizing the renewable energy resources.
This project envisages the preparation of a Residential layout by incorporating the Tamil
Nadu Government rules and the preparation of a plan for a residential building in a plot by using
software AutoCAD. Finally this project will end up with the preparation of an estimation of the
prepared plan (Ref 1).
19
2.2 LITERATURE REVIEW
Anna Joanna,
Aalborg University, Department of Civil Engineering,
According to ANNA, “With energy conservation arrangements, such as high-insulated
constructions, solar heating system. Extra Energy supply for the electric installations in the house
is taken from the municipal mains” (Ref 2).
Saitoh, (1988) (JAPAN)
According to SAITOH, “… a multi-purpose natural energy autonomous
house will meet almost all the energy demands for solar panel and cooling as well as supply of
hot water. For this purpose, solar energy, the natural underground coldness and sky radiation
cooling are utilized.”
i. Solar panels are designed to harness.
ii. Solar energy in buildings include systems that capture heat (such as Solar water heating
systems and passive heating).
iii. It converts solar energy into electrical energy, its done with the help of photovoltic (PV)
systems (Ref 3).
In this primary residential use zone, buildings shall be permitted only for the following
purposes and accessory uses.
(a) Professional consulting offices of the residents and incidental uses there to occupy a floor
area not exceeding 40 square meters.
20
(b) Petty shops dealing with daily essentials including retail sale of provisions, soft drinks,
cigarettes, newspapers, tea stalls, mutton stall and milk kiosks, cycle repair shops and tailoring
shops.
Rear setback according to Chennai Metro Development Authority (CMDA) code is shown in
Table 2.2.
Table 2.2 Rear Set Back
Depth of Plot Rear Set Back
Up to 15m 1.5m
Between 15m to 30m 3.0m
Above 30m 4.5m
21
More than 9m 1.5m on either side
Every multi-storied development erected shall be provided with (i) Lifts as prescribed in
National Building Code; (ii) a stand-by electric generator of adequate capacity for running lift
and water pump, and a room to accommodate the generator; (iii) a room of not less than 6 meters
by 4.5 meters in area with a minimum head room of 3 meters to accommodate electric
transformer in the ground floor; and (iv) at least one meter room of size 2.4 meters by 2.4 meters
for every 10 consumers or three floor whichever is less. The meter room shall be provided in the
ground floor.
All building in their design and construction shall be such as to contribute to and
ensure individually and collectively and the safety of life from fire, smoke, fumes and also panic
arising from these or similar other causes.
In building of such size, arrangement or occupancy than a fire may not itself
provide adequate warning to occupants automatic fire detecting and alarming facilities shall be
provided where necessary to warn occupants or the existence of fires, so that they may escape, or
to facilitate the orderly conduct of fire exit drills. Fire protecting and extinguishing system shall
conform to accepted standards and shall be installed in accordance with good practice a
recommended in the National Building Code of India, and for the satisfaction of the Director of
22
Fire Services by obtaining a no objection certificate from him (Ref.4).
The applicant shall deposit a sum at the rate of Rs.100 per square meters of floor
area as a refundable non-interest earning security and earnest deposit. The deposit shall be
refunded on completion of development as per the approved plan as certified by CMDA, if not, it
would be forfeited.
23
CHAPTER 3
3.1 OBJECTIVE
Solar panels is one of the technologies used to achieve net-zero status. To eliminate the
necessity of active energy loads solar techniques are used which include the use of photovoltaic
panels and solar thermal collectors to harness the energy.
iii. Comparing the net zero energy building with conventional building.
3.3 METHODOLOGY
This entire project is an planning and design in nature and the methodology
followed in this project is listed as below.
CHAPTER 4
4.1 PLANNING
The key plan of the residential building is drawn by considering the alignment of the
building with respect to the CMDA.
25
The key plan of the site is shown in Figure 4.1
The ground floor of the building consist of one hall, two bedrooms, one dinning, one
kitchen. The allocations of the rooms in the plan has been done with due consideration of sun
diagram as per the requirement of zero energy building. The plan has been prepared using Auto
CAD software.
The Ground Floor plan is shown in Figure 4.2
26
Fig.4.2 Ground Floor Plan
The first floor of the building consist of one hall, two bedrooms, one dinning, one
kitchen. The allocations of the rooms in the plan has been done with due consideration of sun
diagram as per the requirement of zero energy building. The plan has been prepared using Auto
CAD software.
The First Floor plan is shown in Figure 4.3
27
Fig.4.3 First Floor plan
28
kN
Live Load = 2 (Ref 7)
m2
1. Effective Span
Lx = 3.26 m
Ly = 5.1 m
Ly 5.1
Aspect ratio = Lx = 3.26 = 1.56<2
Refer Table 26
29
Short Span αx = 0.068
Long Span αy = 0.037
[Note that Lx only to be taken, where it is long span or short span only coefficient
varies].
Mu = Wu × Co-efficient × Lx2 (4.1)
Mu is calculated by equation 4.1
Where,
(or)
= 0.138fckb d2
30
fck R
Ast(+) Short = b d 2fy[1 - √1-4.598 f ] (4.3) Ast(+)
ck
= 184.27 mm2
Minimum Steel = 0.12% × D × B
0.12
Ast,min = ( 100 )× 130 × 1000 = 156 mm2
= 0.4057
20 0.4057
Ast(+)Long = 1000 × 95 × ( 2 )× 415 [1 – √4.598 × ]
20
31
= 109.37 mm2
Ast(+)Long<Ast,min
7. Spacing for all Steel
i. 3d = 3 × 95 = 285 mm
ii. 300
Spacing = 285 mm
8. Check for Deflection
Short Span Lx = 3260 mm
Ast(+) Short = 116.37 mm2
Basic Value = 20
184.27 N
Fs = 0.58 × 415×184.27 =240.2 mm2
Ast(+)Short 184.27 × 100
Pt= = ( 1000 × 105 )
bd
= 0.175%
Modification Factor = 1.62
Modified Basic Value = 20 × 1.62 = 32.8
Span 3260
= = 31.047
d 105
1. Effective Span
Lx = 3 m
Ly = 3.5 m
Ly 0.23
Aspect ratio = = 3.5 + + 0.23 = 1.154 < 2Hence Two Way Slab
Lx 3
2. Load Calculation
Lx 3230
Assuming Slab Thickness d = 32 = 32
= 100 mm
kN
∴Weight of Floor Finish = 0.04 X 24 = 0.96 m2
kN
∴Imposed Load =2 m2
kN
Total Load = 6.08 m2
kN
Factored Load (Wu) = 1.5× 6.96 = 9.127 m2
Ly
= 1.154 ( already found out )
Lx
Refer Table 26
Short Span αx = 0.043
Long Span αy = 0.035
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies
].
(or)
33
Mu,lim = 0.138 fckbd2
Same as equation 4.2
fck R
Ast(+) Short = b d 2fy[1 - √1-4.598 f ]
ck
Mu 1
R = bd2 = 4.1 ×106 1002× 1000 = 0.41
20 0.41
Ast(+) Short = 1000 × 100 × × 415 [1 - √1-4.598 × 20 ]
2
2
= 116.37 mm
Minimum Steel = 0.12% × D × B
0.12
Ast,min = × 125 × 1000 = 150 mm2
100
d= 125 – 20 – 10/2 - 10
d= 90 mm
6. Calculation of Ast for Long Span
fck R
Ast(+)Long= b d 2fy[1 - √1- 4.598f ]
ck
34
Mu
R = bd2
106
= 3.33 ×1000×1002
= 0.33
20 0.33
Ast(+)Long = 1000 × 100 × 2 × 415 [1 – 4.598 × ]
20
= 93.2 mm2
Ast(+)Long<Ast,min
7. Spacing for Steel
π
Ast= 4 ×102 = 78.5 mm2
78.5
Ast(+)Short = 116.37× 1000 = 674.5 mm
78.5
Ast(+)Long = 93.2× 1000 = 842.27 mm
Span 3230
= = 32.3
d 100
32.3 < 34
∴Hence its ok
35
1. Effective Span
Lx = 3.85 m
Ly = 3.95 m
Ly 3.95
Aspect ratio = Lx = 3.85 = 1.027<2
kN
∴Weight of Floor Finish = 0.04 × 24 = 0.96 m2
kN
Imposed Load = 2 m2
kN
∴Total Load = 6.75 m2
kN
Factored Load (Wu) = 1.5 × 6.75 = 10.125 m2
Refer Table 26
Short Span αx = 0.048
Long Span αy = 0.047
36
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies
].
Mu = Wu× Co-efficient × Lx2
Same as equation 4.1
Mu(+) Short = 0.048 × 10.125 × 3.852 = 7.203 kN.m
Mu(+) Long = 0.047 × 10.125 × 3.852 = 7.063 kN.m
Take the Highest Moment and check for adequacy of the section.
0.36 × Xu max 1− 0.42 × Xu max
Mu,lim= [ ] fck b d2
d d
(or)
= 0.138fckb d2
Same as equation 4.2
= 0.138 × 20 × 1000 × 1252
= 43.125 kN.m
(Mu Limit) > (Mu Short)
∴ Hence its ok
4. Calculation of Steel
fck R
Ast(+) Short = b d 2fy[1 - √1-4.598 f ]
ck
= 164.08 mm2
Minimum Steel = 0.12% × D × B
0.12
Ast,min = ( 100 )× 150 × 1000
= 180 mm2
Ast(+) Short <Ast,min
5. Check for maximum Spacing
i. 3d = 3 × 125 = 375 mm
ii. 300
Max Spacing = 300 mm
37
∴ d for long span bars
d
d= D – Clear Cover – 2 - ∅
10
d= 150 – 20 – - 10
2
d= 115 mm
6. Calculation of Ast for Long Span
fck R
Ast(+)Long = b d 2fy[1 - √1- 4.598f ]
ck
= 0.553
20 0.553
Ast(+)Long = 1000 × 115 × ( 2 ) × 415 [1 – √4.598 × ]
20
= 181.11 mm2
Ast(+)Long<Ast,min
7. Spacing for all Steel
i. 3d = 3 × 115 = 345 mm
ii. 300
Spacing = 300 mm
8. Check for Deflection
Short Span Lx = 3850 mm
Ast(+)Short = 181.11 mm2
Basic Value = 20
181.11 N
Fs = 0.58 × 415 ×181.11 =240.2 mm2
Ast(+)Short 181.11 × 100
Pt= = (1000 × 125)
bd
= 0.157%
Modification Factor = 1.8
Modified Basic Value = 20 × 1.8 = 36
Span 3850
= = 30.8
d 125
38
4.2.4 Design of Bathroom
Using M20 Concrete
Fe415 steel
kN
Live Load = 2 m2
1. Effective Span
Lx = 2.38 m
Ly = 4.28 m
Ly 4.28
Aspect ratio = Lx = 2.38 = 1.798<2
kN
∴Weight of Floor Finish = 0.04 × 24 = 0.96 m2
kN
Imposed Load = 2 m2
kN
∴Total Load = 5.75 m2
kN
Factored Load (Wu) = 1.5 × 5.75 = 8.625 m2
39
Refer Table 26, Page No.91 of IS456
Two adjacent edges are discontinuous
Ly
= 1.798 (already found out)
Lx
Refer Table 26
Short Span αx = 0.085
Long Span αy = 0.047
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies
].
Mu = Wu× Co-efficient × Lx2
Same as equation 4.1
Mu(+) Short = 0.085 × 8.625 × 2.382 = 4.127 kN.m
Mu(+) Long = 0.047 × 8.625 × 2.382 = 2.29 kN.m
Take the Highest Moment and check for adequacy of the section.
0.36 × Xu max 1− 0.42 × Xu max
Mu,lim= [ ] fck b d2
d d
(or)
= 0.138fckb d2
Same as equation 4.2
= 0.138 × 20 × 1000 × 852
=19.94 kN.m
(Mu Limit) > (Mu Short)
∴ Hence its ok
4. Calculation of Steel
fck R
Ast(+) Short = b d 2fy[1 - √1-4.598 f ]
ck
= 139.92 mm2
Minimum Steel = 0.12% × D × B
40
0.12
Ast,min= ( 100 ) × 110 × 1000 = 132 mm2
d= 75 mm
6. Calculation of Ast for Long Span
fck R
Ast(+)Long= b d 2fy[1 - √1- 4.598f ]
ck
= 0.4082
20 0.4082
Ast(+) Long = 1000 × 75 × ( 2 ) × 415 [1 – √4.598 × ]= 86.88 mm2
20
41
= 0.1646%
Modification Factor = 1.9
Modified Basic Value = 20 × 1.9 = 38
Span 2380
= = 28
d 85
28 < 38
∴ Hence its ok
1. Effective Span
Lx = 3.78 m
Ly = 6.93 m
Ly 6.93
Aspect ratio = Lx = 3.78 = 1.83<2
kN
∴Weight of Floor Finish = 0.04 × 24 = 0.96 m2
kN
Imposed Load = 2 m2
42
kN
∴Total Load = 6.75 m2
kN
Factored Load (Wu) = 1.5 × 6.75 = 10.125 m2
Ly
= 1.83 (already found out)
Lx
Refer Table 26
Short Span αx = 0.087
Long Span αy = 0.047
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies
].
Mu = Wu× Co-efficient × Lx2
Same as equation 4.1
Mu(+) Short = 0.087 × 10.125 × 3.782 = 12.58 kN.m
Mu(+) Long = 0.047 × 10.125 × 3.782 = 6.79 kN.m
Take the Highest Moment and check for adequacy of the section.
0.36 × Xu max 1− 0.42 × Xu max
Mu,lim= [ ] fck b d2
d d
(or)
= 0.138fckb d2
Same as equation 4.2
= 0.138 × 20 × 1000 × 1252
= 43.125 kN.m
(Mu Limit) > (Mu Short)
∴ Hence its ok
4. Calculation of Steel
fck R
Ast(+) Short = b d 2fy[1 - √1-4.598 f ]
ck
43
Same as equation 4.3
Mu 12.58 ×106
R = bd2 = 1252 × 1000 = 0.805
20 0.8
Ast(+) Short = 1000 × 125 ×2 × 415 [1 - √1-4.598 × 20 ]
= 184.27 mm2
Minimum Steel = 0.12% × D × B
0.12
Ast,min = ( 100 )× 130 × 1000
= 156 mm2
Ast(+) Short <Ast,min
5. Check for maximum Spacing
i. 3d = 3 ×105 = 315 mm
ii. 300
Max Spacing = 300 mm
∴d for long span bars
d
d= D – Clear Cover – 2 - ∅
d= 130 – 20 – 10/2 - 10
d= 95 mm
6. Calculation of Ast for Long Span
fck R
Ast(+)Long= b d 2fy[1 - √1- 4.598f ]
ck
= 0.4057
20 0.4057
Ast(+)Long = 1000 × 95 × ( 2 )× 415 [1 – √4.598 × ]
20
= 109.37 mm2
Ast(+)Long<Ast,min
7. Spacing for all Steel
i. 3d = 3 × 95 = 285 mm
ii. 300
44
Spacing = 285 mm
8. Check for Deflection
Short Span Lx = 3260 mm
Ast(+) Short = 116.37 mm2
Basic Value = 20
184.27 N
Fs = 0.58 × 415×184.27 = 240.2 mm2
Ast(+)Short 184.27 × 100
Pt= = (1000 × 105)
bd
= 0.175%
Modification Factor = 1.62
Modified Basic Value = 20 × 1.62
=32
Span 3260
= = 31.047
d 105
1. Effective Span
Lx = 2.23 m
Ly = 3.73 m
Ly 0.23
Aspect ratio = Lx = 3.73 + 2.23 + 0.23 = 1.67 < 2
45
∴ Actual Depth (d) = 90-5-20 = 65 mm
D 90
Self Weight of a Slab = 1000 × 25 = 1000 × 25
kN
= 2.25 m2
kN
Weight of Floor Finish = 0.04 × 24 = 0.96 m2
kN
∴Imposed Load = 2 m2
kN
∴Total Load = 5.25 m2
kN
Factored Load (Wu) = 1.5 × 5.25 = 7.875
m2
Ly
= 1.67 (already found out)
Lx
Refer Table 26
Short Span αx = 0.06
Long Span αy = 0.035
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies
].
Mu = Wu× Co-efficient × Lx2
Same as equation 4.1
Mu(+) Short = 0.06 × 7.88 × 2.232 = 2.35 kN.m
Mu(+) Long = 0.035 × 7.88 × 2.232 = 1.373 kN.m
Take the Highest Moment and check for adequacy of the section.
0.36 × Xu max 1− 0.42 × Xu max
Mu,lim= [ ] fck b d2
d d
(or)
Mu,lim = 0.138 fckb d2
46
Same as equation 4.2
= 0.138 × 20 × 1000 × 652
=11.66 kN.m
(Mu Limit) > (Mu Short)
∴ Hence its ok
3. Calculation of Steel
fck R
Ast(+) Short = b d 2fy[1 - √1-4.598 f ]
ck
= 103.56 mm2
Minimum Steel = 0.12% × D × B
0.12
Ast,min= × 90 × 1000
100
= 108 mm2
Ast(+) Short <Ast,min
4. Check for maximum Spacing
i. 3d = 3 × 65 = 195 mm
ii. 300
Max Spacing = 195 mm
∴d for long span bars
d
d= D – Clear Cover – 2 - ∅
10
d= 90 – 20 – - 10
2
d= 55 mm
5. Calculation of Ast for Long Span
fck R
Ast(+)Long= b d 2fy[1 - √1- 4.598f ]
ck
= 0.115
47
20 0.115
Ast(+) Long =1000 × 55 × 2 × 415 [1 – 4.598 × ]
20
= 71.05 mm2
Ast(+) Long <Ast,min
6. Spacing for all Steel
𝜋
Ast = × 102 = 78.5 mm2
4
78.5
Ast(+) Short = 103.56× 1000 = 758.01 mm
78.5
Ast(+) Long = 71.05× 1000 = 1104.8 mm
= 0.16%
34.3 < 36
∴ Hence its ok
1. Effective Span
Lx = 2.6 m
Ly = 3.73 m
Ly 0.23
Aspect ratio = Lx = 3.73 + + 0.23 = 1.43 < 2
2.6
48
Hence Two Way Slab
2. Load Calculation
Assuming Slab Thickness
Lx 2600
d = 32 = = 80 mm
32
kN
∴Weight of Floor Finish = 0.04 × 24 = 0.96 m2
kN
Imposed Load =2 m2
kN
∴Total Load = 5.62 m2
kN
Factored Load (Wu) = 1.5 × 5.62 = 8.43 m2
Ly
= 1.43 (already found out)
Lx
Refer Table 26
Short Span αx = 0.049
Long Span αy = 0.028
[ Note that Lx only to be taken, where it is long span or short span only coefficient varies
].
Mu = Wu× Co-efficient × Lx2
Same as equation 4.1
49
Mu(+) Short = 0.049 × 8.43× 2.62 = 2.79 kN.m
Mu(+) Long = 0.028 × 8.43 × 2.62 = 1.595 kN.m
Take the Highest Moment and check for adequacy of the section.
0.36 × Xu max 1− 0.42 × Xu max
Mu,lim= [ ] fck b d2
d d
(or)
Mu,lim = 0.138fckb d2
Same as equation 4.2
Mu,lim = 0.138 × 20 × 1000 × 802
Mu,lim =17.66 kN.m
(Mu Limit) > (Mu Short)
∴ Hence its ok
4. Calculation of Steel
fck R
Ast(+) Short = b d 2fy[1 - √1-4.598 fck]
= 126 mm2
Ast(+) Short <Ast,min
5. Check for maximum Spacing
i. 3d = 3 × 80 = 240 mm
ii. 300
50
d= 70 mm
6. Calculation of Ast for Long Span
fck R
Ast(+)Long= b d 2fy[1 - √1- 4.598f ]
ck
= 0.325
20 0.325
Ast(+) Long =1000 ×70 × × 415 [1 – 4.598 × ]
2 20
= 64.34 mm2
Ast(+) Long <Ast,min
7. Spacing for Steel
𝜋
Ast = × 102 = 78.5 mm2
4
78.5
Ast(+) Short = 99.15 × 1000 = 791.7 mm
78.5
Ast(+) Long = 64.34× 1000 = 1200.08 mm
= 0.14%
Modification Factor = 1.8
Modified Basic Value = 20 × 1.8 = 36
Span 2600
= = 32.5
d 80
32.5 < 36
∴ Hence its ok
51
4.2.8 Design of Wall
Design of a wall
1.Calculation of Loads
Maximum short span = 3.60 m
Width of corridor = 1.50 m
Height of the storey =3m
kN
Live load =2 m2
2. Assumptions
Height of the Plinth from ground = 0.5 m
Height of the Plinth above Footing = 1 m
Height of the Parapet Wall =1m
Thickness of Roof Slab =110 mm
Brick Size = 230 × 115 × 75
3. Slenderness Ratio and Stress Factor
Ground Floor + First Floor
H = 3+0.115+0.5+3+0.115+1 = 7.73 m
Effective Height (h) = 0.75H = 0.75 × 7.73 = 5.797 m
h 5.8
Slenderness Ratio = = 0.23 = 25.21
t
52
Fc = Ks × Ka × Kp× Basic compressible stress (4.4)
Fc is calculated by equation 4.4
Where,
Ks= Stress reduction factor
Ka= Area reduction factor
Kp= Shape modification factor
Fc = 0.44 × 0.48 × 1 × 1
N
= 0.21 m²
8. Safe Load
𝑓𝑐 6𝑒
Q=(1 + )𝐴
𝑡
0.21 × 1000 × 300
= 1
kN
= 63 m
9. Wall Area
Outer wall = Total Perimeter x 3(floor height)
= ((11.31×2) + (8.93×2))×3
= 40.83 m3
Inner wall = (4.87×3) + (4.87×3) + (3.5×2×3)
= 29.22 + 21 = 50.22 m3
Total wall volume = 91.05 m3
10. Deductions:
Outer Deductions = 1.098+1.089+2.226+1.089+1.4884+1.4884+1.4884+
1.4884+1.4884+1.098
= 14.042 m3
Inner Deductions = 1.89+1.89+2.496+1.746+1.746
= 9.768 m3
Total Deduction =23.81 m3
Total wall volume – Total Deductions = 91.05 -23.81 = 67.25 m3
23.81
% Opening = 67.25 × 100
= 35.4 %
53
∴Thickness = 1 Brick thick wall (using nomograms)
11. For Hall :
Wlx lx
Wu= × {3- [( ly)]2} (4.5)
6
54
kN
10% for the weight of the Building = 63+6.3 = 70 m
Load
1. Area of Footing = SBC
kN
Assume SBC = 150 m2
70
A = 150 = 0.47 m2
Step 2: Assumptions
Height of the Plinth from ground = 0.5 m
55
Height of the Plinth above Footing =1m
Height of the Parapet Wall =1m
Thickness of Roof Slab = 0.120 m
Hollow Brick Size = 0.40 × 0.20 ×0. 20 m
56
Step 4: Shape modification factor
N
Crushing Strength of Hollow Brick= 4.1 mm2
H = 20
=1
W 20
= H = 20 =
1
W 20
57
Step 9: Stress Reduction Factor
ks = 0.81
The values of slenderness ratio for effective length and height of the building is given in
Table 4.1
58
K 3.15 2.976 14.88 2.55 2.976 12.75
L 3.15 1.935 9.7 2.55 1.935 9.675
M 3.15 5.07 15.75 2.55 5.07 12.75
The values of stress reduction factor for slenderness ratio of the building is given in Table
4.2
59
The values of safe allowable load for the building is given in Table 4.4
Table 4.4 Safe allowable load
Load from wall (critical wall M) +10% for the weight of the Building + weight of slab
(hall, bed room & dining) + floor finish
kN
=100 m
kN
Factored load= 1.25 × 100=125 m
Load 125
1. Area of Footing = = = 0.833 m2
SBC 50
kN
Assume SBC = 150 m2
60
= (2 x 200+300) = 700 mm
Provide Width of P.C.C = 700 mm
It is customary to provide 150 to 300 mm P.C.C thickness
Provide = 300 mm
The Projection of P.C.C beyond the brick work should not be more than ½ of the
thickness of P.C.C
300
= = 150 mm
2
61
kN
Live load = 2 m2
Rise = 150 mm
Thread = 250 mm
Using M20 Concrete and Fe415
D = 200 mm
D √R2 +T2 kN
Self weight = 1000 × × 2 = 5.83 m2 (4.6)
T
Step3: Calculation of Mu
17.55×16
Mu = = 35 kN.m
8
0.36 × Xu max 1− 0.42 × Xu max
Mu,lim = [ ] fck b d2
d d
62
35 × 106 = 0.36 × 0.48(1-0.42 × 0.48) × 1000 × d2 × 20
d=113 mm
Assume Clear cover 20 mm
Diameter of bar = 20 mm
D= 113+20+10 = 143 mm
D= 150mm (approximately)
d= 150-20-10 = 120 mm
dactual = 120 mm
63
4.3 DESIGN OF SOLAR PANEL AND ITS COMPONENTS
4.3.1 Solar Power System Components
Brief revision of the major components found in a basic solar power system.
A basic solar powered system is shown in Figure 4.5
64
Fig.4.5 Working of solar panels
The solar panel consists of solar regulator it is connected to DC storage battery and then
DC is converted to AC by an inverter. AC can be directly used for the appliances.
66
PARTICULA USAGE VOLTA CONSUM INVER
ITEMS UNITS
RS IN HRS GE W PTION TORS
CFL (Ref
HALL 4 5 20 400 80
13)
FAN 2 5 50 500 100
T.V 1 5 80 400 80
BED ROOM 1 CFL 2 3 15 90 30
FAN 1 10 50 500 50
BED ROOM 2 CFL 2 3 15 90 30
FAN 1 10 50 500 50
KITCHEN OVEN 1 1 900 900 900
CFL 3 4 15 180 45
EXHAUS
1 4 50 200 50
T
Mixer 1 1 450 450 450
DINING AUTO-
1 18 150 2700 195
ROOM FRIDGE
CFL 3 4 15 180 45
FAN 1 3 50 150 50
TOILET 1 CFL 1 1 15 15 15
TOILET 2 HEATER 1 1 150 150 150
CFL 1 2 15 30 15
WATER
1 1 750 750 750
PUMP
WASHING
1 2 90 180 90
MACHINE
8365 3175
67
Power Invertor Sizing
Appliance total power draw = 3175 W
To provide a small buffer or margin your minimum size inverter choice should be
around 3500W.
A modified sine wave inverter with a 3500W continuous power rating will therefore
be your obvious choice in this specific solar system design.
Determining the Size And Number Of Solar Panels
Divide the total daily power requirement by the number of charge hours for that
geographic region eg. (8365×1.2)\6=1673 WATTS
250 Watt Solar Panel
1673
Total watt/ 250 watt solar panel = 250
=7 PANELS
= 7 x 250 W panels.
Number of Batteries
250W panels produce 4.8Amps, thus 14x 4.8 A = 67.2A x 6 Hrs
= 403.2.Ah
105Ah batteries, should be discharged to no more than 50%, thus we divide total
amps by 105A x 50% = 50A.h
404
= 8.08 x 105Ah batteries.
50𝐴
For ease of possible 24V or 48V configuration, this would mean 3 in series of 3
batteries.
Size of Regulators
Let’s say we had 20A regulators at our disposal.
One 250W panel produces around 4.8Amps.
The regulators are put in series
14 x 4.8A=67.2
So 14 solar panels would need 4 x 20 A solar regulators
.
The total cost of the solar panel is Rs. One lakh forty two thousand six hundred for
our residential building .In these solar panel cost is based on the solar panels, regulator,
batteries and inverter. The output of solar panel can be expected to vary by 0.25% for every 5
degrees variation in temperature.
In NZERB, decrease in temperature for using of hollow bricks and solar panels
produces the electricity. When compared to conventional building, the intial cost is high but
in future the electricity cost is reduced.
ii
Fig.4.6 Infrared Thermometer
The instrument Infrared Thermometer is shown in Figure 4.6
I. An infrared thermometer is a thermometer which infers temperature from a
portion of the thermal radiation sometimes called blackbody radiation emitted
by the object being measured.
II. They are sometimes called laser thermometers if a laser is used to help aim the
thermometer, or non-contact thermometers or temperature guns, to describe
the device's ability to measure temperature from a distance refer Figure.4.6
III. By knowing the amount of infrared energy emitted by the object and
its emissivity, the object's temperature can often be determined.
IV. Infrared thermometers are a subset of devices known as "thermal radiation
thermometers".
V. The most basic design consists of a lens to focus the infrared thermal radiation
on to a detector, which converts the radiant power to an electrical signal that
can be displayed in units of temperature after being compensated for ambient
iii
temperature. This configuration facilitates temperature measurement from
a distance without contact with the object to be measured.
VI. Infrared thermometers can be used to serve a wide variety of temperature
monitoring functions. A few examples provided to this article include:
VII. Detecting clouds for remote telescope operation
VIII. Checking mechanical equipment or electrical circuit breaker boxes or outlets
for hot spots
IX. Checking heater or oven temperature, for calibration and control purposes
X. Detecting hot spots / performing diagnostics in electrical circuit board
manufacturing
XI. Checking for hot spots in fire fighting situations
XII. Monitoring materials in process of heating and cooling, for research and
development or manufacturing quality control situations
XIII. The distance-to-spot ratio (D:S) is the ratio of the distance to the object and
the diameter of the temperature measurement area. For instance if the D:S
ratio is 12:1, measurement of an object 12 inches (30 cm) away will average
the temperature over a 1-inch-diameter (25 mm) area. The sensor may have an
adjustable emissivity setting, which can be set to measure the temperature of
reflective (shiny) and non-reflective surfaces.
XIV. The most common infrared thermometers is the:
XV. Spot Infrared Thermometer or Infrared Pyrometer, which measures the
temperature at a spot on a surface (actually a relatively small area determined
by the D:S ratio).
iv
4.6 CHARACTERISTICS OF HOLLOW BRICKS
4.6.1 Parameters of Hollow Brick Used In Net Zero Energy Residential Building
I. LENGTH : 400 mm
II. WIDTH : 200 mm
III. HEIGHT: 200 mm
IV. WEIGHT: 11.1 kg
V. DENSITY: 694 kg/m³
𝑁
VI. COMPRESSIVE STRENGTH : 4.1 𝑚𝑚2
Available Sizes
Hollow Brick
Bigger Size
I. Hollow brick is same in size as that of concrete blocks
II. 1 Hollow brick = 9 Clay Bricks
III. Less mortar joints, hence less plumb & alignment
IV. Faster construction
Light Weight
I. Ease of handling, Transportation
II. Saves labour
III. Less dead load, Savings in Structural Cost
IV. (Steel & Concrete) by 10 to 15%
v
Thermal Insulation
I. Savings on mortar
II. Low ‘U’ Values – 1.0 W/m²
III. Better Thermal Insulation = less energy loss through walls
IV. Savings on Energy consumption ,Comfortable inside temperature
U-value determines thermal Insulation.Lesser the Value higher the Insulation and vice
versa. U-values are mentioned in Figure 4.7
Fig.4.7 U-VALUES
vi
iii. Fire Resistant
iv. Provide thermal and sound insulation: The air in hollow of the brick,
does not allow outside heat or cold in the house. So it keeps house cool
in summer and warm in winter.
v. Environment Friendly, fly ash used as one of the raw materials.
Constructional Advantages
4.7 ESTIMATION
4.7.1 Abstract estimate of conventional building
The quantities of the various materials in conventional building are calculated as
shown in the Table 4.6
The abstract estimate of conventional building is given in Table 4.6
Table 4.6 Abstract estimate of conventional building
Length Breadth Depth Quantity
S.No Description Nos
(m) (m) (m) (m3)
1 Excavation
Exterior wall 1 39.48 0.76 0.53 15.9
Interior wall 1 22.51 0.76 0.53 9.06
24.96
vii
2 P.C.C
Exterior wall 1 39.48 0.76 0.3 9
Interior wall 1 22.51 0.76 0.3 5.13
14.13
3 Brick work
1st Footing
Exterior wall 1 39.48 0.46 0.115 2.08
Interior wall 1 22.51 0.46 0.115 1.19
2nd Footing
Exterior wall 1 39.48 0.31 0.115 1.4
Interior wall 1 22.51 0.31 0.115 0.8
3 Wall
Exterior wall 1 39.48 0.23 7.5 68.1
Interior wall 1 22.51 0.23 7.5 38.82
112.39
Deductions
Window W 1×2 1.22 0.23 0.9 0.51
Window W1 1×5 1.22 0.23 1.22 1.71
Window W2 1×2 0.9 0.23 1.21 0.5
Door D 1×2 0.84 0.23 2.1 0.81
Door D1 1×3 0.75 0.23 2 1.035
Door D2 1 0.9 0.23 2.1 1.035
Spacing S1 1 1.2 0.23 2.08 0.57
Spacing S2 1 0.9 0.23 2.1 0.43
6.6
4 Earth Filling
Hall 1 3.03 4.87 0.5 7.378
Water closet 1 3.62 2.15 0.5 3.89
Bed Room1 1 3.62 3.72 0.5 6.73
Bed Room2 1 3.5 3 0.5 5.25
Dinning 1 3.5 2.37 0.5 4.147
Kitchen 1 3.5 2.6 0.5 4.55
31.649
5 Flooring Concrete
Hall 1 3.03 4.87 0.1 1.48
Water closet 1 3.62 2.15 0.1 0.778
Bed Room1 1 3.62 3.72 0.1 1.346
Bed Room2 1 3.5 3 0.1 1.05
Dinning 1 3.5 2.37 0.1 0.829
Kitchen 1 3.5 2.6 0.1 0.91
5.473
6 R.C.C
Lintel & Sun shades
Door D 1×2 1.4 0.23 0.15 0.078
viii
Door D1 1×3 1.05 0.23 0.15 0.108
Door D2 1 1.2 0.23 0.15 0.04
Sun Shade 1 1.2 0.45 0.075 0.04
Window W 1×2 1.52 0.23 0.15 0.104
Sun Shade 1×2 1.52 0.45 0.075 0.103
Window W1 1×5 1.52 0.23 0.15 0.2622
Sun Shade 1×5 1.52 0.45 0.075 0.26
Window W2 1×2 1.2 0.23 0.15 0.083
Sun Shade 1×2 1.2 0.45 0.075 0.081
1.1592
Roof Slab
Hall, Water Closet, Bed Room1 1 6.65 4.87 0.1 3.24
Bed Room2,Dinning,Kitchen 1 3.5 7.97 0.1 2.79
6.8496
7 Plastering
Exterior wall 1 39.48 - 7.5 296.1
Interior wall 1 22.51 - 7.5 168.8
464.92
Deductions
Window W1 1×2 1.22 - 0.9 2.196
Window W2 1×5 1.22 - 1.22 7.442
Window W3 1×2 0.9 - 1.21 2.178
Door D 1×2 0.84 - 2.1 3.528
Door D1 1×3 0.75 - 2 4.5
Door D2 1 0.9 - 2.1 1.89
Spacing S 1 1.2 - 2.08 2.496
Spacing S1 1 0.9 - 2.1 1.89
26.12
8 White Washing - - - - 438.8
9 Colour Washing - - - - 438.8
ix
3 Brick work
1st Footing
Exterior wall 1 39.24 0.4 0.2 3.13
Interior wall 1 22.51 0.4 0.2 1.8
2nd Footing
Exterior wall 1 39.24 0.25 0.2 1.96
Interior wall 1 22.51 0.25 0.2 1.12
3 Wall
Exterior wall 1 39.24 0.2 7.5 58.86
Interior wall 1 22.51 0.2 7.5 33.76
Deductions
Window W 1×2 1.22 0.2 0.9 0.4392
Window W1 1×5 1.22 0.2 1.22 1.4884
Window W2 1×2 0.9 0.2 1.21 0.432
Door D 1×2 0.84 0.2 2.1 0.705
Door D1 1×3 0.75 0.2 2 0.9
Door D2 1 0.9 0.2 2.1 0.378
Spacing S1 1 1.2 0.2 2.08 0.504
Spacing S2 1 0.9 0.2 2.1 0.378
95.02
4 Earth Filling
Hall 1 3.03 4.87 0.5 7.378
Water closet 1 3.62 2.15 0.5 3.89
Bed Room1 1 3.62 3.72 0.5 6.73
Bed Room2 1 3.5 3 0.5 5.25
Dinning 1 3.5 2.37 0.5 4.147
Kitchen 1 3.5 2.6 0.5 4.55
31.649
5 Flooring Concrete
Hall 1 3.03 4.87 0.1 1.48
Water closet 1 3.62 2.15 0.1 0.778
Bed Room1 1 3.62 3.72 0.1 1.346
Bed Room2 1 3.5 3 0.1 1.05
Dinning 1 3.5 2.37 0.1 0.829
Kitchen 1 3.5 2.6 0.1 0.91
5.473
6 R.C.C
Lintel & Sun shades
Door D 1×2 1.4 0.23 0.15 0.0684
Door D1 1×3 1.05 0.23 0.15 0.0945
Door D2 1 1.2 0.23 0.15 0.036
Sun Shade 1 1.2 0.45 0.075 0.0405
Window W 1×2 1.52 0.23 0.15 0.07512
x
Sun Shade 1×2 1.52 0.45 0.075 0.1026
Window W1 1×5 1.52 0.23 0.15 0.228
Sun Shade 1×5 1.52 0.45 0.075 0.0256
Window W2 1×2 1.2 0.23 0.15 0.072
Sun Shade 1×2 1.2 0.45 0.075 0.081
0.8237
Roof Slab
Hall, Water Closet, Bed Room1 1 6.65 4.87 0.1 3.24
Bed Room2,Dinning,Kitchen 1 3.5 7.97 0.1 2.79
6.8496
7 Plastering
Exterior wall 1 39.24 - 7.5 294.3
Interior wall 1 22.51 - 7.5 168.82
463.12
Deductions
Window W1 1×2 1.22 - 0.9 2.196
Window W2 1×5 1.22 - 1.22 7.442
Window W3 1×2 0.9 - 1.21 2.178
Door D 1×2 0.84 - 2.1 3.528
Door D1 1×3 0.75 - 2 4.5
Door D2 1 0.9 - 2.1 1.89
Spacing S 1 1.2 - 2.08 2.496
Spacing S1 1 0.9 - 2.1 1.89
26.12
8 White Washing - - - - 437
9 Colour Washing - - - - 437
xi
4.7.3 Rate Analysis
The rate analysis for various description of work are calculated based on the PWD.
The rate analysis proposed for conventional building is given in the Table 4.8
Table 4.8 Rates Proposed Conventional Building
QTY in QTY in
S.NO DESCRIPTION OF WORK RATE PER AMOUNT
m³ cft
1 Earth Work Excavation 24.96 882.33 9.50 Cft 8382.00
2 Sand Filling with good river sand 31.65 1118.82 35.00 Cft 39158.00
5 Flooring Work
PCC 1:4:8 5.50 194.23 90.00 Cft 17480.00
xii
The rate analysis proposed for NZERB building is given in the Table 4.9
Table 4.9 Proposed NZERB Building
QTY in
S.NO DESCRIPTION OF WORK QTY in cft RATE PER AMOUNT
m³
1 Earth Work Excavation 21.60 763.56 9.50 Cft 7253.82
5 Flooring Work
PCC 1:4:8 5.50 194.23 90.00 Cft 17480.50
R.C.C (LINTEL,SUNSHADES
6
& ROOF SLAB) 6.84 241.55 350.00 Cft 84542.50
9
Colour washing 437.00 15448.00 5.00 Sft 77240.00
10
Steel 501.00 60.00 kg 30060.00
11
Solar Panel System 142600.00
TOTAL 1399046.82
CHAPTER 5
xiii
CONCLUSION
5.1 CONCLUSION
In this project we has completed the design of the Conventional building by using
modular bricks and Net Zero Energy Residential Building by using Hollow Brick .The plan
of the building was prepared by Auto-Cad software. IS 456:2000 code book was used to
design Slab and Footing. Design of wall was done by using IS 1905:1987.
The Comparison of the Conventional Building and NZERB was completed by using
the parameters such as the temperature by using instrument infrared thermometer which was
found to be 4oC less in NZERB compared to conventional building under same condition.
Hence by using the renewable resources the impact on the active energy loads can be
reduced, Thus we can conserve electricity locally and globally.
The building designed as a NET ZERO ENERGY BUILDING produces its own
electricity, thus it can save a huge amount in electricity bill. These kind of buildings are
environmental friendly reducing the environmental hazards (eg. It would release zero carbon
content that would help in controlling global warming).The design for the building should be
such that the requirement of temperature regulation does not fluctuate throughout the year.
REFERENCES
1. http://en.wikipedia.org/wiki/Zero-energy_building
2. http://energy.gov/energysaver/articles/annajohanna
3. http://zeb.buildinggreen.com/saitoh
xiv
4. National Building Code of India (NBC) and Chennai Metropolitan
Development Authority (CMDA).
5. S.P. Arora and S.P Bindra .(2010), Building Construction , Fifth edition,
Dhanpat Rai publishing company limited, New Delhi.
6. IS: 456 : 2000, Indian Standard Code of practice for plain and reinforced
concrete (Fourth Revision ), Bureau if Indian Standards, New Delhi
7. IS: 1905 (1987), Code of Practice for Structural use of unreinforced masonry.
8. IS 875 : Part 2 : 1987 Code of practice for design loads (other than
earthquake) for buildings and structures: Part 2 Imposed loads
9. IS 875 : Part 1 : 1987 Code of practice for design loads (other than
earthquake)for buildings and structures Part 1 Dead loads - Unit weights of
building material and stored materials (Incorporating IS:1911-1967)
10. SP 20 (S & T):1991 Handbook on masonry design and construction.
11. IS 2572:1963(R 1997) Code of practice for design of Hollow bricks
12. http://www.solarpanel.co.za/solar-power-calculator.htm
xv