Professional Documents
Culture Documents
Traffic Management Plan PDF
Traffic Management Plan PDF
PIU-1, Jhapa
in Panchthar District
2019
Submitted By: Swachchhanda-Kankai JV
Sifal, Kathmandu, Nepal
1. Introduction
1.1 Purpose
1.2 Scope
1.3 Objectives
1.4 Operating Policies For Traffic Management Plan
1.5 Preparation of Traffic Management Plan
2. Project Introduction
2.1 Introduction and Salient Features
3. Traffic Management Objectives
4. Organizational Chart
4.1 Roles & Responsibilities
4.2 Responsibilities of personnel
5. Planning
5.1.1 Risk Identification and Assessment
5.1.2 Traffic Assessment(Pedestrian and Vehicular Traffic)
5.1.3 Heavy and Oversize vehicles
5.1.4 Special Traffic Situations And Other Leaseholders
5.1.5 Cyclists and Pedestrians & Crossing
6. Implementation
1. Introduction
Traffic Management Plans (TMPs) provide planning and implementation for all site users to be
safely and efficiently guided through a site and ensure the operational performance of the site and adjoining
roads is not impacted. TMPs are prepared in advance of sites being commissioned and generally subject to
auditing before and after implementation.
Traffic Management is the management of occupational safety and site performance risks associated with
work activities undertaken in a traffic environment. The Traffic Management Plan is a key workplace
document that has legal standing. As such it is critical that the structure and content of the Plan is sufficient
to explain the potential hazards, the assessed risks and the proposed treatments for the proposed work
activities and work site.
1.1 Purpose
The purpose of Traffic Management Plan is to ensure the safety and health of work personnel, the public
and those who will be impacted by the work and to ensure that site road users are not inconvenienced and
that site operations be kept at a satisfactory level of performance.
1.2 Scope
Applies to all members of Upgrading and Performance based maintenance of Phidim- Nagin- Sidin-
Prangbung – Falot Road ( Phidim – Ludintar Sector ) Road _1 &
And Samdin- Chokmangu – Nawamidada – Faktep Ghurbisepanchami Road (Samdin-
Nawamidada Sector) Road _2 in Panchthar District
1.3 Objectives
The primary objectives of this Traffic Management Plan are to:
To provide protection to all people related to project and the general public from traffic
hazards that may arise as a result during the road construction phase.
To manage potential adverse impacts on traffic flows and pedestrian movements to ensure
road and pedestrian network performance is maintained at an acceptable level.
To minimise adverse impacts on users of the road reserve and adjacent properties and
facilities.
2. Project Introduction
2.1 Introduction & Salient Features
Contract Completion
Contractual Cost date April19, 2023
Rs. 928,335,587.20 With VAT
4. Organization Chart
Organization chart of the Swachchhanda-Kankai JV, CONTRACT NO.:
DoLIDAR/RCIP/Works/NCB-02/2074/075
5. Planning
5.1.1 Risk Identification and Assessment
To clearly identify the risks associated with the site operations and then outline the way
risks will be managed, the Traffic Management Plan (TMP) shall include an assessment of all risks
associated with site operations and determine the operational measures that minimize the risk.
The identification and assessment process must be undertaken and the likelihood and
consequences rates before the application of risk treatments (Primary Risk) and after (Residual
Risk) the determined controls.
The Site Manager shall, so far as practicable, control or reduce identified risks in accordance with
the hierarchy of control. The Site manager will reassess, authorize and manage its risk control
measures in accordance with the level of risk.
6. Implementation
6.1 Hazard Identification, Risk Assessment and Control
While the TMP outlines foreseeable hazards as part of the traffic management planning
process, given the evolving nature area, the TMP should detail the mechanism that will be
utilised to identify and assess future hazards as they arise throughout the life of the site.
The procedure for evaluating proposed risk treatments and confirming that they are
effective (including signoff of by responsible parties) will be included in the TMP. The
traffic management plan will be evaluated by qualified personnel following its initial
implementation.
Variations to the risk treatment shall be recorded and the following things will be carried
out:
Public awareness and notifications
The awareness campaign and the prior notification for the public will be a continuous
activity which the project will carry out to compensate for the above delays and minimize public
claims as result of these problems. These activities will take place sufficiently in advance of the
time when the roadblocks or traffic diversions take place at the particular roads. The reason for this
is to allow sufficient time for the public and residents to understand the changes to their travel
plans. The project will notify the public about the roadblocks and traffic diversion through print,
TV, and radio media. In addition, the project, in collaboration with the utility management
coordinator, will also seek the assistance of the ward office, local clubs, and others to post the
public notice regarding street closure and traffic diversions in the future.
The utility management coordinator will also conduct an awareness campaign to educate the public
about the following issues:
o traffic control devices in place at the work zones (signs, traffic cones, barriers)
o defensive driving behaviour along the work zones; and
o Reduced speeds enforced at the work zones and traffic diversions.
It may be necessary to employ a road safety education specialist to design an appropriate program
for road safety, and to conduct the awareness programs.
Different awareness program will be conducted to all types of target groups i.e. children, adults, and
drivers.
Indicate the office hours of relevant offices.
Educate the public about the various traffic control devices and safety measures adopted at the
work zones.
Educate the public about the safe road user behaviour to emulate at the work zones.
Project information Board will be allocated at the beginning and end of road_1 & road _2.
The purpose of installing traffic control devices at the work zones is to delineate these areas to
warn, inform, and direct the road users about a hazard ahead, and to protect them as well as the
workers. As proper delineation is a key to achieve the above objective, it is important to install
good traffic signs at the work zones.
The work zone should take into consideration the space required for a buffer zone between the
workers and the traffic (lateral and longitudinal) and the transition space required for delineation,
as applicable. For the works, a 30-cm clearance between the traffic and the temporary STOP and
GO signs should be provided. In addition, at least 60 cm is necessary to install the temporary traffic
signs and cones. Figure 5 clarifies that the "ROAD NARROWS" warning-sign is only necessary at
the works zones where high traffic speeds are likely during the off-peak hours and at night. All the
temporary traffic signs should be reflectorized, especially for the works to be conducted during
nighttimes, as per the DOR Traffic Sign Manual 1997.
All the traffic diversions will be properly delineated through proper "DIVERSION AHEAD" and
"ROADWORK AHEAD" signs. In addition, the temporary warning sign for sharp bends used at
the temporary diversion should be in place after the start of the taper of the traffic cones. Flashing
beacons should be installed at the entry to the work zone and traffic diversion for night
construction, or if backfilling of the sewer trench does not take place after the completion of a day
shift. One person is necessary at each entry to the diversion from both directions. These personnel
should be equipped with reflective jackets at all times and have traffic control batons (preferably
the LED type) for regulating the traffic during night time. In addition to the delineation devices, all
the construction workers should wear fluorescent safety vests and helmets in order to be visible to
the motorists at all times. There should be provision for lighting beacons and illumination for night
constructions. In light of the ongoing load-shedding problem in Nepal, it is practical to use solar-
powered LED lights, which are energy efficient, wherever feasible.
Provides details and location of all road furniture proposed to be used at the site for all situations.
These will be shown on a Traffic Control Diagram that will form an attachment to the TMP along
with an itemised list of all required road furniture. The Traffic Flow Diagram comprises detailed
drawings depicting the layout and type of traffic control devices to be used for all situations likely
to be encountered during the operations. Traffic Flow Diagrams are site specific.
All signs, line markings (including retroflective pavement markers and arrow markings) and
delineation (including traffic cones, bollards, barricades and guardrails) used will conform to the
designs and dimensions. All signs will reflective material.
Regularly, all signs, line markings and delineation will be checked to ensure that they are in good
condition. The TMP will detail inspection and maintenance procedures to ensure signs, line
markings and delineation are in sound condition, they are clean and not faded, retro-reflectivity is
adequate and where applicable power supply is fully operational.
Signs, line markings and delineation will be positioned and erected in accordance with the locations
and spacing.
They do not obscure other devices from the driver's line of sight.
Where there is a potential for conflict of information between existing signage and temporary
signage erected for the purpose of traffic control, the existing signs shall be covered. The material
covering the sign must not be adhered directly onto the sign or the painted surface of the post. The
legend on the sign should not be seen under all conditions i.e. day, night and wet weather.