ID Task Task Name Duration Start Finish Predecessors

October 2018 November 2018 December 2018 January 2019 February 2019
Mode 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17
1 Remaining Major Work 104 days 11/1/18 2/13/19
2 LMR 2 1 day 11/27/18 11/27/18
3 Pengangkatan dg TC 1 66 days 11/1/18 1/6/19
4 Utilitas Equipment LMR 2 & 3 4 days 11/28/18 12/1/18
5 Trafo 3 unit @6,8 Tons (by Hamanroko) 2 days 11/28/18 11/29/18 2
6 Mesin Lift 8 unit @ 4 tons (SF1, SF2, HZ) 2 days 11/30/18 12/1/18 5
7 Helipad 35 days 12/2/18 1/6/19
8 Pasang F/W 12 days 12/2/18 12/13/18 6
9 Cor Tahap 1 1 day 12/14/18 12/14/18 8
10 Cor Tahap 2 1 day 12/18/18 12/18/18 9FS+3 days
11 Bongkar F/W 14 days 12/23/18 1/6/19 9FS+8 days
12 Baja Crown 40 days 11/1/18 12/10/18
13 Tangga Baja Roof-Helipad (2 Unit) 30 days 11/19/18 12/18/18
14 Cover Tangga Baja (by Srimurni Sby) 16 days 12/19/18 1/4/19 13
15 Façade Crown (by Srimurni Sby) 20 days 12/15/18 1/4/19 12FS+4 days
16 Outdoor Ac (3 unit pakai TC1 utk 52 & 53) 1 day 12/12/18 12/12/18
17 Jack Down TC1 14 days 12/30/18 1/13/19 15FS-5 days
18 Gondola 20 days 12/22/18 1/11/19 12FS+4 days
19 Waterproofing Gutter Roof 2 days 12/30/18 12/31/18 11FS-7 days
20 Pasang Ourdoor AC Roof (164 unit) 14 days 12/30/18 1/13/19 11FS-7 days
21 Waterproofing Roof 10 days 1/14/19 1/23/19 20
22 Bongkar TC2 15 days 11/18/18 12/2/18
23 Façade TC2 (27 - Roof) 10 days 11/28/18 12/7/18 22FS-5 days
24 Façade TC2 (2 - 26) 10 days 12/5/18 12/14/18 22FS+2 days
25 Façade TC1 (27 - Roof) 14 days 1/8/19 1/21/19 17FS-6 days
26 Façade TC1 (2 - 27) 14 days 1/16/19 1/29/19 17FS+2 days
27 Demob Concrete Pump 2 days 12/19/18 12/20/18 10
28 S-1 (Komando Raya) 44 days 11/23/18 1/6/19
29 Casted Back TC2 8 days 12/3/18 12/10/18
30 Casted back GF 8 days 12/3/18 12/10/18
31 Bongkar Gardu PLN Temporary 1 day 11/23/18 11/23/18
32 Pekerjaan MEP Bawah Jalan 16 days 12/9/18 12/24/18 31FF
33 Pekerjaan Jalan sampai Rigid 12 days 12/25/18 1/6/19 32
34 Bomb Check 19 days 11/30/18 12/18/18
35 Steel Structure+Finishing 14 days 11/30/18 12/13/18
36 Pasang Kaca 5 days 12/14/18 12/18/18 35
37 Outdoor Ac 43 days 11/23/18 1/5/19
38 Pondasi Outdoor AC + Grill 12 days 11/23/18 12/4/18 31SS
39 Pasang Outdoor Ac + Instalasi 20 days 12/9/18 12/28/18 38FS-6 days
40 Grill (Pabrikasi+Install) 25 days 12/3/18 12/27/18 38SS
41 Andesit (by Hamparan) 8 days 12/28/18 1/5/19 40

Task Project Summary Manual Task Start-only Deadline

Project: External Work Schedule Split Inactive Task Duration-only Finish-only Progress
Date: 11/21/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Predecessors
October 2018 November 2018 December 2018 January 2019 February 2019
Mode 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17
42 Tempat Sampah, Pos Jaga, dll. 30 days 11/23/18 12/22/18 37SS
43 Taman (by Amtara) 21 days 12/13/18 1/3/19 42FS-10 days
44 S-5 (Topas) 69 days 11/26/18 2/3/19
45 Saluran (800x800) ~ (1800x2000) 30 days 11/26/18 12/25/18
46 Urugan 7 days 12/26/18 1/1/19 45
47 Andesit (by Hamparan) 18 days 1/2/19 1/19/19 46
48 Taman (by Amtara) 8 days 1/20/19 1/27/19 47
49 Cast Back TC1 GF 8 days 1/27/19 2/3/19 20
50 S-2 58 days 11/26/18 1/23/19
51 Cor Pondasi AC 21 days 11/26/18 12/16/18
52 Urugan 7 days 1/2/19 1/8/19 46
53 Pos Jaga, Toilet, Box DW 15 days 1/6/19 1/20/19 42SS
54 Grill (Pabrikasi+Install) 25 days 12/1/18 12/25/18 51SS+5 days
55 Andesit (by Hamparan) 8 days 12/26/18 1/3/19 54
56 Taman (by Amtara) 15 days 1/9/19 1/23/19 52
57 S-3 80 days 11/25/18 2/13/19
58 Pumping Station 54 days 11/25/18 1/18/19
59 Galian 3 days 11/25/18 11/27/18
60 Struktur+Finishing 30 days 11/28/18 12/27/18 59
61 MEP 21 days 12/28/18 1/18/19 60
62 Outdoor Ac 64 days 12/11/18 2/13/19
63 Lift PS 1 24 days 12/11/18 1/4/19
64 Bongkar PH 10 days 1/12/19 1/21/19 63FS+7 days
65 Pondasi Outdoor AC + Grill 6 days 1/22/19 1/27/19 64
66 Pasang Outdoor Ac + Instalasi 10 days 1/28/19 2/6/19 65
67 Grill (Pabrikasi+Install) 16 days 1/22/19 2/6/19 65SS
68 Andesit (by Hamparan) * 7 days 2/7/19 2/13/19 67
69 Taman (by Amtara) * 7 days 2/7/19 2/13/19 68SS
70 S-6 36 days 12/1/18 1/6/19
71 Fuel Tank 36 days 12/1/18 1/6/19
72 Galian 14 days 12/1/18 12/14/18
73 Struktur Lantai & Dinding 12 days 12/15/18 12/26/18 72
74 Setting Tangki 2 days 12/27/18 12/28/18 73
75 Struktur Tutup Fuel Tank 8 days 12/29/18 1/6/19 74
76 Saluran Gorong-gorong 8 days 12/1/18 12/8/18 72SS
77 Rigid 7 days 12/9/18 12/15/18 76

Task Project Summary Manual Task Start-only Deadline

Project: External Work Schedule Split Inactive Task Duration-only Finish-only Progress
Date: 11/21/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone