qp Aura (SON- indexler) Start Date 08-Apr-19

Report Date 24-May-19 03:51 Finish Date 09-Sep-19

SR-02 Schedule Report Comparison to Target

WBS
Project Phase Activity ID Activity Name At Completion BL Activity % Start Finish
Duration Duration Complete

qp0625 qp A.Ş
qp06 qp Constructure
thesis.last qp Aura (SON- indexler)
thesis.last.D&E Design and Engineering
A1000 Start Dormitory Building Construction 0 0 100% 08-Apr-19 A
A1008 Review and Approve Design 1 3 100% 03-May-19 A 03-May-19 A
A1002 Assemble Technical Data and Equipment 3 2 100% 09-Apr-19 A 11-Apr-19 A
A1003 Review Technical Data and Equipment 1 1 100% 11-Apr-19 A 11-Apr-19 A
A1001 Investigation of Field 1 1 100% 08-Apr-19 A 08-Apr-19 A
A1004 Architectural Drawings 9 7 100% 12-Apr-19 A 24-Apr-19 A
A1005 Structural Calculations 4 4 100% 23-Apr-19 A 26-Apr-19 A
A1006 Electrical Project Drawing 2 2 100% 29-Apr-19 A 30-Apr-19 A
A1007 Mechanical Project Drawing 2 2 100% 01-May-19 A 02-May-19 A

Subtotal 20 22 08-Apr-19 A 03-May-19 A

thesis.last.FOUNDT
Foundation
A1050 Begining of Building Construction 0 0 100% 08-May-19 A
A1060 Site Preparation 2 3 100% 08-May-19 A 09-May-19 A
A1070 Excavation 2 2 100% 13-May-19 A 14-May-19 A
A1080 Installment Underground Water Pipes 1 1 100% 20-May-19 A 20-May-19 A
A1090 Installment Underground Electric Conduits 1 1 100% 20-May-19 A 20-May-19 A
A1100 Formwork Concrete Mat Footing 3 2 100% 04-Jun-19 A 07-Jun-19 A
A1110 Pour Concrete Mat Footing 1 1 100% 06-Jun-19 A 07-Jun-19 A
A1091 Leveling (lean) Concrete 1 1 100% 21-May-19 A 21-May-19 A
A1140 Foundation Phase Complete 0 0 100% 06-Jun-19 A
A1073 Evaluation of Axes 1 1 100% 17-May-19 A 17-May-19 A
A1092 Membraine Installment 1 1 100% 22-May-19 A 22-May-19 A
A1093 Lean Concrete 1 1 100% 23-May-19 A 23-May-19 A
A1094 Reinforcement for Mat Footing 4 7 100% 24-May-19 A 29-May-19 A
A1071 Jet-Grout 3 2 100% 15-May-19 A 17-May-19 A

Subtotal 22 22 08-May-19 A 07-Jun-19 A

thesis.last.STRCT
Structure
A1150 Begin Structure Phase 0 0 100% 07-Jun-19 A
A1160 Ground-floor Formwork 5 6 100% 07-Jun-19 A 13-Jun-19 A
A1170 Ground-floor Reinforcements 4 4 100% 07-Jun-19 A 12-Jun-19 A
A1180 Groundfloor Concrete Casting 1 1 100% 17-Jun-19 A 17-Jun-19 A
A1190 First-floor Formwork Scaffolding 3 1 50% 28-Jun-19 A 02-Jul-19
A1200 First-floor Formwork 4 3 33.33% 01-Jul-19 A 04-Jul-19
A1210 First-floor Reinforcements 4 5 20% 03-Jul-19 A 08-Jul-19
A1220 First-floor Concrete Casting 1 1 0% 09-Jul-19 09-Jul-19
A1230 Second-floor Formwork Scaffolding 1 1 0% 19-Jul-19 19-Jul-19
A1250 Second-floor Formwork 3 3 0% 22-Jul-19 24-Jul-19
A1260 Second-floor Reinforcements 5 5 0% 22-Jul-19 26-Jul-19
A1270 Second-floor Concrete Casting 1 1 0% 29-Jul-19 29-Jul-19
A1280 Structue Phase Complete 0 0 0% 05-Aug-19 05-Aug-19
A1181 Demolding Ground-floor Formwork 1 1 100% 18-Jun-19 A 18-Jun-19 A
A1222 Demolding First-floor Formwork 1 1 0% 15-Jul-19 15-Jul-19
A1182 Ground-floor Curing 7 7 100% 19-Jun-19 A 27-Jun-19 A
A1221 First-floor Curing 7 7 0% 10-Jul-19 18-Jul-19
A1273 Demolding Second-floor Formwork 1 1 0% 02-Aug-19 02-Aug-19
A1272 Second -flooring Curing 7 7 0% 30-Jul-19 07-Aug-19

Subtotal 44 43 07-Jun-19 A 07-Aug-19

thesis.last.MECHAN
Mechanical / Electrical Systems
thesis.last.MECHAN.PLUMP&ELEC
Plumbing and Electrical

Page 1 of 3
qp Aura (SON- indexler) Start Date 08-Apr-19
Report Date 24-May-19 03:51 Finish Date 09-Sep-19

SR-02 Schedule Report Comparison to Target

WBS
Project Phase Activity ID Activity Name At Completion BL Activity % Start Finish
Duration Duration Complete

A1340 Electrical Wiring Preparation 19 1 0% 10-Jul-19 A 05-Aug-19


A1350 Electrical Wiring Installment 5 5 0% 06-Aug-19 12-Aug-19
A1380 Fire Warning System Installment 5 5 0% 05-Aug-19 09-Aug-19
A1400 Sound/HeatingInsulation preparation 1 1 0% 08-Aug-19 08-Aug-19
A1770 Installment Security System 3 3 0% 05-Aug-19 07-Aug-19
thesis.last.MECHAN.PLUMP&ELEC.CMMNCTN
Communicaton Network
A1740 Installment of Infrastructure of Telephone Network 5 5 0% 05-Aug-19 09-Aug-19
A1750 Installment of Infrastructure of Internet Network 5 5 0% 08-Aug-19 14-Aug-19

Subtotal 8 8 05-Aug-19 14-Aug-19

Subtotal 26 25 10-Jul-19 A 14-Aug-19

Subtotal 26 25 10-Jul-19 A 14-Aug-19

thesis.last.EXT.WORK
Exterior Works
thesis.last.EXT.WORK.BRICKS
Bricks
A1420 Brick Procurement 1 1 0% 08-Aug-19 08-Aug-19
A1430 Brick Works 5 5 0% 09-Aug-19 15-Aug-19

Subtotal 6 6 08-Aug-19 15-Aug-19

thesis.last.EXT.WORK.ROOF
Roof
A1440 Roof-floor Slab İsolation 1 1 0% 05-Aug-19 05-Aug-19
A1450 Roof-floor Formwork Scaffolding 2 2 0% 06-Aug-19 07-Aug-19
A1460 Roof Membraine installment 1 1 0% 07-Aug-19 08-Aug-19
A1470 Roof Tiling Works 3 3 0% 08-Aug-19 13-Aug-19

Subtotal 7 7 05-Aug-19 13-Aug-19

thesis.last.EXT.WORK.DOOR
Doors and Windows
WNDWS
A1490 Installment of Door(Exterior-Metal) and Windows 12 12 0% 16-Aug-19 03-Sep-19
A1489 Procuremnt of Door(Exterior-Metal) and Windows 1 1 0% 16-Aug-19 16-Aug-19

Subtotal 13 13 16-Aug-19 03-Sep-19

thesis.last.EXT.WORK.FCD
Facade Works
A1500 Scaffolding 1 1 0% 05-Aug-19 05-Aug-19
A1510 Plastering 5 5 0% 13-Aug-19 19-Aug-19
A1520 Paint 4 4 0% 20-Aug-19 23-Aug-19
A1501 Isolation Installment 5 5 0% 06-Aug-19 12-Aug-19

Subtotal 15 15 05-Aug-19 23-Aug-19

Subtotal 22 22 05-Aug-19 03-Sep-19

thesis.last.INT Interior Works


WORKS
thesis.last.INT
Plumbing and Lighting Fixture
WORKS.PLMB&LIGHT
A1530 Preparation of Lightening System 1 1 0% 26-Aug-19 26-Aug-19
A1540 Installment of Lightening System 6 6 0% 27-Aug-19 03-Sep-19
A1550 Preparation of Interior Plumbing System 1 1 0% 26-Aug-19 26-Aug-19
A1560 Installment of Interior Plumbing System 8 8 0% 27-Aug-19 05-Sep-19

Subtotal 9 9 26-Aug-19 05-Sep-19

thesis.last.INT
Finish Floor and Carpeting
WORKS.FLOOR
CARPET

Page 2 of 3
qp Aura (SON- indexler) Start Date 08-Apr-19
Report Date 24-May-19 03:51 Finish Date 09-Sep-19

SR-02 Schedule Report Comparison to Target

WBS
Project Phase Activity ID Activity Name At Completion BL Activity % Start Finish
Duration Duration Complete

A1570 Screed Concrete 4 4 0% 13-Aug-19 19-Aug-19


A1580 Ceramic Tile 3 3 0% 19-Aug-19 22-Aug-19
A1569 Installment Interior Heating System Pipes 9 9 0% 26-Aug-19 05-Sep-19

Subtotal 17 24 13-Aug-19 05-Sep-19

thesis.last.INT
Paint
WORKS.PAINT
A1590 Interior Plastering 8 8 0% 05-Aug-19 14-Aug-19
A1600 Interior Wall Paint 5 5 0% 15-Aug-19 21-Aug-19

Subtotal 13 13 05-Aug-19 21-Aug-19

thesis.last.INT
Carpentry
WORKS.CRPTY
A1610 Kitchen Cupboard Prepare 1 1 0% 22-Aug-19 22-Aug-19
A1620 Kitchen Cupboard Installment 2 2 0% 23-Aug-19 26-Aug-19
A1760 Installement of Interior Doors 6 6 0% 22-Aug-19 29-Aug-19

Subtotal 6 6 22-Aug-19 29-Aug-19

Subtotal 24 24 05-Aug-19 05-Sep-19

thesis.last.ENVRMT
Environmental Arrangement
A1630 Removal of Construction Wastes 3 3 0% 22-Aug-19 26-Aug-19
A1640 Procurement of Environmental Materials 10 10 0% 27-Aug-19 09-Sep-19

Subtotal 13 13 22-Aug-19 09-Sep-19

Subtotal 111 110 08-Apr-19 A 09-Sep-19

Subtotal 111 110 08-Apr-19 A 09-Sep-19

Subtotal 111 110 08-Apr-19 A 09-Sep-19

Total 111 110 08-Apr-19 A 09-Sep-19