You are on page 1of 1

GTH Builders & Developers

28 M. Calixto St. Zamboanga City


Contact Number: (062) 991-2658

CONTRACTOR GENERAL BUILDING GENERAL ENGINEERING

To: Haipa Abdurahim- Salain, Ed. D.


College President, Basilan State College

From: Maria Teresa Y. Go


Contractor

Subject: Proposed Change Order No. 1


THE PROPOSED REHABILITATION OF THE STUDENT CENTER
Basilan State College Extension Campus, Sta. Clara, Lamitan City, Basilan

ContractorGTH Builders and Developers

Background/Introduction:

The Notice tp Proceed (NTP) received last January 30, 2019 with subcontract expiration date last.
THE PROPOSED REHABILITATION OF THE STUDENT CENTER. The project is on-going now.

Base on the Original Plan, the Embankment and Plumbing Works of the Proposed Building was not
included on the BOQ that may additional item needed.

Thus, new plan was approved base on the existing condition of the building.
Shown below is the tabulation of additive item base on the new approved plan.

Additive
Description Remarks
QTY Unit Unit Cost Amount
I. Embankment 216.00 m³ 531.47 114,796.50
II. Plumbing Works 1.00 Lot 74,319.92 74,319.92
189,116.42 Additional Cost for VO

Recommendation:

Base on the table presented above the proposed variation for the supply and delivery of Item is
recommended to sustain the subcontractor's activity and to fully execute the plan. The estimated
cost for the said variation is Php189,116.42. Immediate response to the said recommendation is
necessary to complete the project base on the plan and to avoid further delays.

Contract Details:

Original Contract Amount: Php 2,994,066.74


Revised Contract Amount: Php 3,183,183.16
Original Duration: 95 Calendar Days
Original Complettion Date:
Accomplishment (Actual):

Submitted by;
MARIA TERESA Y. GO
Owner/Manager

Date: 20-May-19