Department of Public Works and Highways

Contract ID No. : 23HO0272


Contract Name : Organizational Outcome 2: Protect Lives and Properties
Against Major Floods, Flood Management Program,
Construction/ Maintenance of Flood Mitigation
Structures and Drainage Systems, Construction of
Riverbank Protection along Talaba River (Sitio Cansibog
- Sitio Upper Talayong), Barangay Tupas, Ronda, Cebu
(Phase 2)
Location of the Contract : Ronda, Cebu

Contract ID No. : 23HO0273


Contract Name : Organizational Outcome 2: Protect Lives and Properties
Against Major Floods, Flood Management Program,
Construction/ Maintenance of Flood Mitigation
Structures and Drainage Systems, Construction of
Revetment Wall along Ylaya River (Purok Manga
Section), Brgy. Ylaya, Ronda, Cebu (Package 2)
Location of the Contract : Ronda, Cebu

Contract ID No. : 23HO0274


Contract Name : Organizational Outcome 2: Protect Lives and Properties
Against Major Floods, Flood Management Program,
Construction/ Maintenance of Flood Mitigation
Structures and Drainage Systems, Construction of
Revetment Wall at Brgy. Libo-o (Left Side), Ronda,
Cebu
Location of the Contract : Ronda, Cebu

Contract ID No. : 23HO0275


Contract Name : Organizational Outcome 2: Protect Lives and Properties
Against Major Floods, Flood Management Program,
Construction/ Maintenance of Flood Mitigation
Structures and Drainage Systems, Construction of
Revetment Wall at Brgy. Uno - Brgy. Sto. Niño,
Malabuyoc, Cebu
Location of the Contract : Malabuyoc, Cebu

Contract ID No. : 23HO0276


Contract Name : Organizational Outcome 2: Protect Lives and Properties
Against Major Floods, Flood Management Program,
Construction/ Maintenance of Flood Mitigation
Structures and Drainage Systems, Construction of
Revetment Wall at Brgy. Pawa (Package 2), Dumanjug,
Cebu
Location of the Contract : Dumanjug, Cebu

Contract ID No. : 23HO0277


Contract Name : Organizational Outcome 2: Protect Lives and
Properties Against Major Floods, Flood Management
Program, Construction/ Maintenance of Flood
Mitigation Structures and Drainage Systems,
Construction of Revetment Wall along Barangay Vive

Supplemental Bulletin No. S23-C7-030 Page 1 of 4


River Flood Control, Ronda, Cebu (Phase 2)

Supplemental Bulletin No. S23-C7-030 Page 2 of 4


Location of the Contract : Ronda, Cebu

Contract ID No. : 23HO0278


Contract Name : Organizational Outcome 2: Protect Lives and Properties
Against Major Floods, Flood Management Program,
Construction/ Maintenance of Flood Mitigation
Structures and Drainage Systems, Construction of
Revetment Wall at Brgy. Liboo - Brgy. Poblacion,
Ronda, Cebu
Location of the Contract : Ronda, Cebu

Contract ID No. : 23HO0279


Contract Name : Organizational Outcome 2: Protect Lives and Properties
Against Major Floods, Flood Management Program,
Construction/ Maintenance of Flood Mitigation
Structures and Drainage Systems, Construction of Dike
at Valencia River (Downstream Right Side), Alegria,
Cebu (Phase 2)
Location of the Contract : Alegria, Cebu

Contract ID No. : 23HO0281


Contract Name : Organizational Outcome 2: Protect Lives and Properties
Against Major Floods, Flood Management Program,
Construction/ Maintenance of Flood Mitigation
Structures and Drainage Systems, Construction of
Revetment Wall at Brgy. Sto. Niño, Malabuyoc, Cebu
Location of the Contract : Malabuyoc, Cebu

-----------------------------------------------------------------------------------------------

DPWH - CEBU 7TH DISTRICT ENGINEERING OFFICE


Cogon, Dumanjug, Cebu

SUPPLEMENTAL BULLETIN NO. S23-C7-030


October 10, 2023

This Supplemental Bulletin No. S23-C7-030 is issued to to amend provisions in the Bidding
Documents (BDs) for hereunder projects as follows:

Supplemental Bulletin No. S23-C7-030 Page 3 of 4


Contract Current Provision of BDs Amended Provision of BDs
ID No. (including Previous under this Supplemental
Amendments) Bulletin

23HO0272 Scope of Work - Construction of Scope of Work - Construction of


223.00 l.m. Dike with Steel Sheet 230.00 l.m. Dike with Steel Sheet
Pile Foundation Pile Foundation
ABC – 96,495,366.63 ABC – 96,495,256.55
Revised Bill of Quantities (BOQ)
23HO0273 Scope of Work - Construction of Scope of Work - Construction of
155.00 l.m. Dike with Steel Sheet 164.00 l.m. Dike with Steel Sheet
Pile Foundation Pile Foundation
ABC – 96,496,414.07 ABC – 96,495,338.58
Revised Bill of Quantities (BOQ)
23HO0274 Scope of Work - Construction of Scope of Work - Construction of
221.00 l.m. Dike with Steel Sheet 167.00 l.m. Dike with Steel Sheet
Pile Foundation Pile Foundation
ABC – 77,196,688.57 ABC – 77,196,632.05
Revised Bill of Quantities (BOQ)
23HO0275 Scope of Work - Construction of Scope of Work - Construction of
136.00 l.m. Dike with Steel Sheet 133.00 l.m. Dike with Steel Sheet
Pile Foundation Pile Foundation
ABC – 72,372,066.39 ABC – 72,371,564.61
Revised Bill of Quantities (BOQ)
23HO0276 Scope of Work - Construction of Scope of Work - Construction of
110.00 l.m. Dike with Concrete 142.00 l.m. Dike with Steel Sheet
Sheet Pile Foundation Pile Foundation
ABC – 72,371,717.18 ABC – 72,371,563.82
Revised Bill of Quantities (BOQ)
23HO0277 Scope of Work - Construction of Scope of Work - Construction of
103.00 l.m. Dike with Steel Sheet 104.00 l.m. Dike with Steel Sheet
Pile Foundation Pile Foundation
ABC – 72,372,069.97 ABC – 72,371,963.98
Revised Bill of Quantities (BOQ)
23HO0278 Scope of Work - Construction of Scope of Work - Construction of
137.00 l.m. Dike with Steel Sheet 115.00 l.m. Dike with Steel Sheet
Pile Foundation Pile Foundation
ABC – 67,546,119.60 ABC – 67,546,119.25
Revised Bill of Quantities (BOQ)
23HO0279 Scope of Work - Construction of Scope of Work - Construction of
189.00 l.m. Dike with Steel Sheet 209.00 l.m. Dike with Steel Sheet
Pile Foundation Pile Foundation

Supplemental Bulletin No. S23-C7-030 Page 4 of 4


ABC – 67,546,718.96 ABC – 67,546,715.58
Revised Bill of Quantities (BOQ)
23HO0281 Scope of Work - Construction of Scope of Work - Construction of
77.00 l.m. Dike with Steel Sheet Pile 88.00 l.m. Dike with Steel Sheet Pile
Foundation Foundation
ABC – 48,996,119.13 ABC – 48,996,116.16
Revised Bill of Quantities (BOQ)

This Supplemental Bulletin shall form an integral part of the said Bidding Documents.

For the guidance and information of all concerned.

ALTIUS A. ENRIQUEZ
Chief, Quality Assurance Section
BAC Chairman

Supplemental Bulletin No. S23-C7-030 Page 5 of 4


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Cebu 7th District Engineering Office
Cogon, Dumanjug, Cebu

Contract ID No.: 23HO0279


Contract Name: Organizational Outcome 2: Protect Lives and Properties Against Major Floods, Flood
Management Program, Construction/ Maintenance of Flood Mitigation Structures and Drainage
Systems, Construction of Dike at Valencia River (Downstream Right Side), Alegria, Cebu (Phase 2)

Location of Contract: Alegria, Cebu


BILL OF QUANTITIES
Pay Item
Description Unit Quantity Unit Price (Pesos) Amount (Pesos)
No.
(1) (2) (3) (4) (5) (6)
Organizational Outcome 2: Protect Lives and Properties Against Major Floods, Flood Management Program, ABC
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems, Construction of Dike at 67,546,715.58
Valencia River (Downstream Right Side), Alegria, Cebu (Phase 2)
PART A FACILITIES FOR THE ENGINEER
Provision of Combined Field Office, mos. 8.53 In Words: Pesos In Words: Pesos
Laboratory and Living Quarters
A.1.1 (6)
Building for the Engineer (Rental
Basis) In Figures: Php In Figures: Php

Provision of Furnitures/Fixtures, L.S. 1.00 In Words: Pesos In Words: Pesos


Equipment & Appliances for the Field
A.1.1 (11)
Office for the Engineer
In Figures: Php In Figures: Php
Operation & Maintenance of mos. 8.53 In Words: Pesos In Words: Pesos
Temporary Field Office, Laboratory
A.1.1 (15)
and Living Quarters Building for
the Engineer In Figures: Php In Figures: Php

Provision of Progress Photographs mos. 8.53 In Words: Pesos In Words: Pesos

A.1.4 (1)
In Figures: Php In Figures: Php
PART B OTHER GENERAL REQUIREMENTS
Miscellaneous Survey and Staking L.S. 1.00 In Words: Pesos In Words: Pesos

B.4(10)
In Figures: Php In Figures: Php
Project Billboard/Signboard each 2.00 In Words: Pesos In Words: Pesos

B.5(1)
In Figures: Php In Figures: Php
Occupational Safety and Health mos. 8.53 In Words: Pesos In Words: Pesos
Program
B.7(1)
In Figures: Php In Figures: Php
Mobilization / Demobilization L.S. 1.00 In Words: Pesos In Words: Pesos

B.9(1)
In Figures: Php In Figures: Php
Craneway L.S. 1.00 In Words: Pesos In Words: Pesos

B.18(2)
In Figures: Php In Figures: Php
PART C EARTHWORKS
Subgrade Preparation, Common sq.m. 522.50 In Words: Pesos In Words: Pesos
Material
105(1)a
In Figures: Php In Figures: Php
PART E SURFACE COURSES
Portland Cement Concrete Pavement sq.m. 522.50 In Words: Pesos In Words: Pesos
(Unreinforced) - 0.20 m thick, 14 days
311(1)b1
In Figures: Php In Figures: Php
PART L FLOOD AND RIVER CONTROL AND DRAINAGE
L-A EARTHWORKS
Clearing and Grubbing sq.m. 1,359.00 In Words: Pesos In Words: Pesos

1700(1)
In Figures: Php In Figures: Php
Individual Removal of Trees, 150 - each 2.00 In Words: Pesos In Words: Pesos
300 mm dia.
1700(3)a1
In Figures: Php In Figures: Php
Structure Excavation, Common Soil cu.m. 1,616.00 In Words: Pesos In Words: Pesos

1702(1)a
In Figures: Php In Figures: Php
Embankment, From borrow cu.m. 773.00 In Words: Pesos In Words: Pesos

1704(1)b
In Figures: Php In Figures: Php
Aggregate Subbase Course cu.m. 104.50 In Words: Pesos In Words: Pesos

1707(1)
In Figures: Php In Figures: Php
L-B BANK AND SLOPE PROTECTION WORKS
Stone Masonry cu.m. 1,917.00 In Words: Pesos In Words: Pesos

1711(1)
In Figures: Php In Figures: Php
Crushed Aggregate Base Course cu.m. 9.00 In Words: Pesos In Words: Pesos

1709(1)
In Figures: Php In Figures: Php
Concrete, Slope Protection cu.m. 264.00 In Words: Pesos In Words: Pesos

1712(1)
In Figures: Php In Figures: Php
Structural Steel Sheet Piles, m. 3,144.00 In Words: Pesos In Words: Pesos
Furnished
1716(6)
In Figures: Php In Figures: Php
Structural Steel Sheet Piles, Driven m. 3,144.00 In Words: Pesos In Words: Pesos

1716(12)
In Figures: Php In Figures: Php
Sheet Piles, Steel, Cofferdamming m. 1,638.00 In Words: Pesos In Words: Pesos

1717(2)a2
In Figures: Php In Figures: Php
Railings l.m. 209.00 In Words: Pesos In Words: Pesos

1722(3)
In Figures: Php In Figures: Php
In Words: Pesos In Figures: Php

TOTAL