You are on page 1of 4

28 February 2019

MAN Automotive Concessionaires Corporation


EDSA cor. Seminary Road, Bahay Toro,
Quezon City 1106
Metro Manila
Email: info@matruckandbus.ph

Attention: Mr. HENRY CULAWAY


Liason Officer

Mr. MARVIN J. LAPUZ


Purchaser

Subject: Proposal for the Construction of Oil Separator


at MACC Novaliches Plant

Dear Mr. Culaway & Mr. Lapuz,

We are pleased to offer herewith our proposal for the above-mentioned subject for the required
Construction Services to carry out the project to wit:

I. PROJECT DESCRIPTION

Requiring the services of PVBS Construction Services & Consultancy as a Contractor


for the above-mentioned subject of the following project information below:

A. Location : MACC Plant, Novaliches, Quezon City, Manila

B. Description of the Project : Construction of Oil Separator Structure

C. Dimension : 3.0mL x 1.2mW x 2.0mH

D. Owner : MAC Automotive Concessionaires Corporation

II. SCOPE OF WORKS

A. Supply and installation of Concrete Trench Canal with Steel Grille Cover

B. Supply and installation of Concrete Oil Interceptor with Steel Plate Cover

C. Tapping of 2-Existing area drain to the Oil Interceptor

D. Tapping of Oil Interceptor to the Existing Sidewalk Drainage

PVBS CONSTRUCTION SERVICES & CONSULTANCY


Blk 29 Lot 5 Herb St., cor. Pardinas St., Purok 13
Zone 6 Bgy. South Signal
Taguig City, Metro Manila, 1630 Philippines
M: +639184252769 / +639152418181
T: (+632) 959 4365
E: pvbs.construction.services2013@gmail.com
TIN : 926 – 665 - 404
1| P a g e
III. PROPOSED WORK SCHEDULE

The proposed work schedule to carry-out the work and construction will start provided
that the Client conform on the proposal and issue the “Notice to Proceed” to commence
the work , to wit:

WEEK
ITEM PHASE DAYS
1 2 3 4 5 6 7
I GENERAL REQUIREMENTS 15
II CONCRETE TRENCH CANAL 10
III OIL INTERCEPTOR 25
IV PROJECT TURN-OVER 5

40 Days (6 Weeks)

Note: WORK SCHEDULE IS SUBJECT TO CHANGES DEPENDS ON ACTUAL SITE CONDITIONS.

IV. SUMMARY OF PROPOSAL

PVBS Construction Services & Consultancy is expected to provide the summary of cost
including indirect cost and tax for providing Construction Services as follows:

Item Description Qty Unit Amount


I GENERAL REQUIREMENTS 1 LOT 316,250.00
II CONCRETE TRENCH CANAL 1 LOT 222,525.00
III OIL INTERCEPTOR 1 LOT 845,365.00
Sub-Total 1,384,140.00
VAT (12%) 166,096.80
Contingencies (3%) 46,507.10
Overall Estimated Cost 1,596,743.90

The total General Construction Works for the above-mentioned project shall be in
Philippine Peso:

One Million Five Hundred Ninety Six Thousand Seven Hundred Forty Three Pesos
& 90/100 centavos

PVBS CONSTRUCTION SERVICES & CONSULTANCY


Blk 29 Lot 5 Herb St., cor. Pardinas St., Purok 13
Zone 6 Bgy. South Signal
Taguig City, Metro Manila, 1630 Philippines
M: +639184252769 / +639152418181
T: (+632) 959 4365
E: pvbs.construction.services2013@gmail.com
TIN : 926 – 665 - 404
2| P a g e
V. BILL OF QUANTITIES (BOQ)

Item Description Qty Unit Unit Rate Total Amount


1 General Requirements 316,250.00
Mobilization / Demobilization 1 lot 92,000.00
Permits and Clearances 1 lot By Owner
Hauling of Debris 1 lot 138,000.00
Deliveries/Transportation 1 lot 86,250.00
2 Concrete Trench Canal 222,525.00
Excavation 6 cu.m. 15,525.00
Concrete trench canal 15 lm 51,750.00
Steel Grating 15 lm 77,625.00
Steel framing 15 lm 77,625.00
3 Oil Interceptor 845,365.00
Excavation 1 lot 28,750.00
Chipping of existing pavement 1 lot 6,468.75
Concreting 1 lot 219,937.50
Steel Reinforcement 1 lot 81,937.50
Formworks 1 lot 62,790.00
PVC Pipe 1 lot 86,250.00
CHB 4" 1 lot 107,812.50
Plastering Works 1 lot 27,168.75
Checkered plate cover 3 set 86,250.00
Consumables/accessories 1 lot 138,000.00
Sub-Total 1,384,140.00

VI. WORK DURATION

Time table to carry out all works shall be minimum of Forty (40) days or more or less
Six Months upon approval /conforming this proposal and shall be extended depends on
circumstances thereof.

VII. TERMS OF PAYMENT

The following terms of payment shall be as follows:

50% : Down payment

50% : Upon Completion of Work

VIII. MISCELLANEOUS / EXTRA WORKS

Any additional works requested by the owner after approval of this proposal not included
on the program of works shall be charged as Extra Work Order with separate cost per
item.
PVBS CONSTRUCTION SERVICES & CONSULTANCY
Blk 29 Lot 5 Herb St., cor. Pardinas St., Purok 13
Zone 6 Bgy. South Signal
Taguig City, Metro Manila, 1630 Philippines
M: +639184252769 / +639152418181
T: (+632) 959 4365
E: pvbs.construction.services2013@gmail.com
TIN : 926 – 665 - 404
3| P a g e
We hope that you find the above in order and we look forward to working with on this
project.

Should our proposal merit your favorable consideration, please confirm by signing on the space
provided below.

Very truly yours,

PAUL VINCENT B. SETIAS


General Manager
PVBS Construction Services & Consultancy

Conforme:

_________________________

PVBS CONSTRUCTION SERVICES & CONSULTANCY


Blk 29 Lot 5 Herb St., cor. Pardinas St., Purok 13
Zone 6 Bgy. South Signal
Taguig City, Metro Manila, 1630 Philippines
M: +639184252769 / +639152418181
T: (+632) 959 4365
E: pvbs.construction.services2013@gmail.com
TIN : 926 – 665 - 404
4| P a g e