V & J Engineering Services

Purok 2, Quezon Avenue Extension, Palao, Iligan City


Branches: Alfonso Homes I, Barangay Labas, Sta. Rosa City, Laguna / 573 Marcos Ave., San Benito Sur, Aringay, La Union
0917-523-4166 / 0966-415-9496 / 0917-804-6752 / 0945-820-1946

Proposal

To : McConnel Dowell Date: December 20, 2022

Project : Cementitious Fire Proofing for Steel Structure Pipe Bridge at BLNG Project First Gen., Brgy. Bolbok,
Batangas City

DESCRIPTION Unit of Total


Measure

Mortar Based (Cementitious) Spray-On Fireproofing as per API 2218 for the
Pipe Bridge 01 (Area 3) and Pipe Bridge 02 (Area 5) at BLNG project

Offer includes:

1. Sikacrete Spray on Fire Protection Mortar, 1 lot


2. 3mm Ø High Tensile Wire Mesh (3.5 x 30mm), 1 lot
3. 4 mm Ø High Tensile Wire Studs, 1 lot
1 Lot PHP 4,789,938.60
4. Manpower, Labor and Application
5. Mobilization / Demobilization
6. Project Management, QC and Admin
7. Scaffolding and Platforms
8. Equipment, Tools and Consumables
9. PPE, Covid-19 requirements and Medical
10. Service Vehicles and Accommodation

General Application:

1. Applied using the wet method, with a worm gear / spraycrete


machine. To be able to carry out the application, a wire mesh will be
installed around the steel.
2. Check that the surface is free of oil, grease, dust or any other
substance that could prevent the correct adherence of the system.
3. Mortar will be sprayed in one or more layers, not exceeding 12.5
mm for the first layer. The time between layers should be between 
1-2 hours and should not exceed 24 hours.
4. Proposal does not include the primer coating and blasting of the steel
structure.

Value Added Tax (12%) PHP 574,792.63


Total Amount Due PHP 5,364,731.23

1
V & J Engineering Services
Purok 2, Quezon Avenue Extension, Palao, Iligan City
Branches: Alfonso Homes I, Barangay Labas, Sta. Rosa City, Laguna / 573 Marcos Ave., San Benito Sur, Aringay, La Union
0917-523-4166 / 0966-415-9496 / 0917-804-6752 / 0945-820-1946

a. Proposal is in Philippine Peso and Inclusive of VAT.


b. Completion of works: Within 45 to 60 days form receipt of P.O. and 30% Down Payment.
Availability of items may depend on stocks of manufacturer / suppliers.
c. Payment Terms: 30% Down Payment and Progress Billing of 60%, 90% and 10% after completion of works.
d. Price Validity: Thirty (30) Days

Thank you for allowing us to quote on your requirement. Please feel free to contact us if you have any
clarification and questions.