A. Scope of Works
1.0 Supply 1 unit 10W 32ft x 8ft truck.
2.0 The above rate include one (1) driver, one (2) helpers, toll fee(s) (if
any), and fuel.
3.0 Loading of Pv2 materials ( Flexible hose, wires, cable trays, railing,
brackets, solar panels) from Wilcon Dasma to Wilcon Sta Rosa drop
to Wilcon Calamba and to Wilcon San Pablo.
B. Manner of Payment
1.0 50% Downpayment, balance thru billing .
C. Project Schedule
D. Price Validity
1.0 15 days from proposal date
E. Others
1.0 Permits, clearances and licenses from any government and
private agencies are excluded from this proposal.
i I CONSTRUCTORS AND DEVELOPERS, INC.
ENGINEERS * ARCHITECTS * CONSTRUCTORS * DEVELOPERS-BUILDERS
ADDRESS: B18-L27 MAHOGANY VILLAGE 1, BRGY. PULO, CABUYAO LAGUNA
We thank you for this rare opportunity of quoting for your construction
requirements. Should you have any query, please do not hesitate to call our
attention and we shall discuss the matter with you, but should you find this proposal
acceptable to your goodselves, kindly sign conformity at the space provided below
and we shall consider this as our contract agreement.
Conforme: