Professional Documents
Culture Documents
VARIATION ORDER For Site Dev 2020
VARIATION ORDER For Site Dev 2020
You are hereby directed to do the specified VARIATION/CHANGE ORDER on the following
item of works.
A. Scope of works (Itemized quantities and cost on separate sheet attached)
ITEM NO. DESCRIPTION AMOUNT
1.0 FOR DELETION WORKS
3.1 Roofing
4.5mm thick polycarbonate roofing sheets PHP 3,044,414.40
3.2 Roof framing and gutter PHP 596,893.30
TOTAL DELETION PHP 3,641,307.70
2.0 ADDITIONAL WORKS
PHP
2.1 Additional height of pedestal, concrete road gutter , paving blocks, landscaping 1,803,682.70
Conforme:
ABDULRAUF MANALASAL
TAMONTAKA BUILDERS
Date: _______________________
Republic of the Philippines
DEPARTMENT OF SCIENCE AND TECHNOLOGY
PHILIPPINE SCIENCE HIGH SCHOOL- SOCCSKSARGEN REGION CAMPUS
Project Management Office
December 28, 2018
You are hereby directed to do the specified VARIATION/EXTRA WORK ORDER on the following
item of works.
A. Scope of works (Itemized quantities and cost on separate sheet attached)
ITEM NO. DESCRIPTION AMOUNT
1.0 Roof framing works/roofing/flashing/at ACAD II covered walk PHP 399,152.25
2.0 Tile works PHP 77,559.00
TOTAL EXTRA WORK COST PHP 476,711.25
ORIGINAL CONTRACT AMOUNT PHP 6,323,288.75
ADJUSTED CONTRACT COST PHP 6,800,000.00
Approved by:
Conforme:
CHUCHI P. GARGANERA, Ph.D.
Director III ABDULRAUF MANALASAL
TAMONTAKA BUILDERS
Date: _______________________
Republic of the Philippines
DEPARTMENT OF SCIENCE AND TECHNOLOGY
PHILIPPINE SCIENCE HIGH SCHOOL- SOCCSKSARGEN REGION CAMPUS
Project Management Office
December 28, 2018
You are hereby directed to do the specified VARIATION/CHANGE ORDER on the following
item of works.
A. Scope of works (Itemized quantities and cost on separate sheet attached)
ITEM NO. DESCRIPTION AMOUNT
1 For deletion works PHP 1,394,852.44
2 For addition on works
2.1 Concrete flooring for ACAD II covered walk PHP 153,228.36
2.2 Canal cover PHP 16,387.10
2.3 Decorated slab/stampcrete PHP 204,263.93
2.4 4 spans of covered walk going to dorm 1 and dorm 2 PHP 134,280.64
2.5 Mouldings for columns PHP 32,000.00
2.6 Painting for pedestal and mouldings PHP 8,544.00
2.7 Additional concrete for filled gaps PHP 19,200.00
2.8 Rental for jack hammer for demolition works PHP 5,000.00
2.9 Roof framing for ACAD III covered walk PHP 284,502.75
3 ACAD IV/Dorm IV covered walk PHP 435,401.20
3.1 Additional Electrical Installation and fixtures PHP 102,044.46
TOTAL ADDITION ON WORK COST PHP 1,394,852.44
NET COST ADJUSTMENT PHP 0
Approved by:
Conforme:
CHUCHI P. GARGANERA, Ph.D.
Director III ABDULRAUF MANALASAL
TAMONTAKA BUILDERS
Date: _______________________
DEPARTMENT OF SCIENCE AND TECHNOLOGY
PHILIPPINE SCIENCE HIGH SCHOOL- SOCCSKSARGEN REGION CAMPUS
Project Management Office
12 Backfilling works
12.1.1 Foundation 3 cu.m. 650 1,950.00
TOTAL 1,125,778.17
FOR DELETION ON WORKS
1 Stampcrete elevated park(3500 psi. 15cm thick)
1.1 Concrete Works
1.1 Portland cement type 1 640 bags 381.88 244,403.20
1.2 Gravel MSA 1" 66 cu.m. 1787.5 117,975.00
1.3 Washed and screened sand 33 cu.m. 975 32,175.00
1.4 10mm dia x9m deformed bars grade33 120 cu.m. 316.88 38,025.60
1.5 Mixer rental with FOG 640 bags 66.63 42,643.20
1.6 forms 10 units 292.5 2,925.00
1.7 Paint for stamp crete include front parking 20 units 5200 104,000.00
SUB TOTAL 582,147.00
2 Covered Pathways( Res Hub to Gym)
2.1 CONCRETE /steel works/roofing/roof framing
2.1.1 12mm dia.x 6m Deformed bars grade 40 8 pcs 341.25 2,730.00
2.1.2 10mm dia.x9m Deformed bars grade 33 28 pcs 219.38 6,142.64
2.1.3 0.4mm ribbed roofing sheets (BIEGE) 50 sq.m. 633.75 31,687.50
2.1.4 1.5mmx 2 x 4 rectangular tubing x6m 14 pcs 2080 29,120.00
2.1.5 1.5mmx 2 x 6 rectangular tubing (GIRT) 10 pcs 2795 27,950.00
2.1.6 Welding rod 10 pcs 487 4,870.00
2.1.7 6" X6" X 6M X6MM Square Tube 4.00 pcs 19500 78,000.00
2.1.8 Accessories 1.000 lot 15625 15,625.00
SUB TOTAL 196,125.14
3 Covered Pathways (towards Acad2, Dorm II and Dorm III, stem park)
3.1 CONCRETE /steel works/roofing/roof framing
3.1.1 12mm dia.x 6m Deformed bars grade 40 8 pcs 341.25 2,730.00
3.1.2 10mm dia.x9m Deformed bars grade 33 28 pcs 219.38 6,142.64
3.1.3 0.4mm ribbed roofing sheets (BIEGE) 50 sq.m. 633.75 31,687.50
3.1.4 1.5mmx 2 x 4 rectangular tubing x6m 14 pcs 2080 29,120.00
3.1.5 1.5mmx 2 x 6 rectangular tubing (GIRT) 10 pcs 2795 27,950.00
3.1.6 Welding rod 10 pcs 211.3 2,113.00
3.1.7 6" X6" X 6M X6MM Square Tube 4.00 pcs 15600 62,400.00
3.1.8 Accessories 1.000 lot 15625 15,625.00
177,768.14
3 GRAVELLING OF GROUND SURFACE 1 lot 1787.5 71,500.00
4 Landscaping and provision of landscaping plants 40.303 sq.m. 2437.5 98,237.89
You are hereby directed to do the specified VARIATION ORDER on the following
item of works.
A. Scope of works (Itemized quantities and cost on separate sheet attached)
ITEM NUMBER DESCRIPTION AMOUNT
ADDITION ON WORKS
1.0 Waiting area 441,343.07
2.0 Steel doors 19,790.00
3.0 Lavatory/Sanitizing area 74,973.29
4.0 Dress changing area/cubicles 91,735.04
5.0 Parking ( front fence) area 286,202.70
6.0 Steelworks/railings 21,036.50
7.0 Painting works 29,168.75
8.0 Plumbing works 34,771.82
9.0 Tileworks 104,551.36
10.0 Cconcrete Bumper 2,055.64
11.0 Excavation works 18,200.00
12.0 Backfilling 1,950.00
TOTAL ADDITION ON WORKS 1,125,778.17
DELETED WORKS
1 Stamp crete works 582,147.00
2 Covered pathways(Res hub to gym) 196,125.14
3 Covered pathways (towards AcadII, Dorm III, Stem park) 177,768.14
4 Gravelling of ground surface 71,500.00
5 Landscaping and provision of landscaping plants 98,237.89
TOTAL DELETED WORKS 1,125,778.17
NET VARIATION COST PHP 0
Conformed:
1125778.17