No.

Jenis Pekerjaan Harga dasar Sat Keterangan

I Upah Pekerjaan Tanah


Pekerja Rp. 71,500.00 oh tanjungrejo
Tukang Rp. 71,500.00 oh
Kepala Tukang Rp. 88,000.00 oh
Mandor Rp. 88,000.00 oh
Sewa Mesin Stamper Rp. 100,000.00 hr
Sewa Vibro hr

II Upah Pekerjaan Pasangan


Aanstamping Rp. 41,625.00 m3
Onderlagh Rp. 10,125.00 m2
Basecourse Rp. 7,565.00 m2
Pondasi batu belah Rp. 140,625.00 m3
Beraben pondasi Rp. 7,500.00 m2
Pasang bata Rp. 27,000.00 m2
Pasang bata Rp. 180,000.00 m3
Plesteran bata Rp. 21,375.00 m2
Plesteran beton Rp. 24,750.00 m2 52750-PPN
Plesteran alur horisontal Rp. 90,000.00 m2
Acian dinding Rp. 13,500.00 m2
Acian lantai Rp. 10,125.00 m2
Sponengan Rp. 7,875.00 m'
Buis U 20 Rp. 10,125.00 m'
Buis U 30 Rp. 17,000.00 m'
Buis Ø 50 Rp. 39,375.00 m'
Buis Ø 60 Rp. 50,625.00 m'
U alluminium 10 mm Rp. 5,750.00 m'
Upah Cor beton : Pioneer
Site mix ( sloof / kolom praktis ) Rp. 168,750.00 m3
Site mix ( kolom/balok/plat ) Rp. 225,000.00 m3
Site mix ( tangga / lisplank ) Rp. 180,000.00 m3
Ready mix Rp. 157,500.00 m3
Upah Pembesian : Pioneer
Pembesian sloof / kolom praktis Rp. 2,250.00 kg
Pembesian balok & kolom Rp. 2,250.00 kg
Pembesian plat Rp. 2,250.00 kg
Wiremesh Rp. 7,312.50 m2
Upah Begesting : Pioneer
Begesting Foot plat / Poer Rp. 22,500.00 m2
Begesting sloof / kolom praktis Rp. 22,500.00 m2
Begesting kolom struktur Rp. 84,375.00 m2
Begesting balok struktur Rp. 84,375.00 m2
Begesting Plat Rp. 84,375.00 m2
Begesting Tangga Rp. 101,250.00 m2
Begesting lisplank Rp. 101,250.00 m2
Begesting dinding Rp. 50,625.00 m2
Perancah balok/plat/tangga Rp. 29,700.00 m2
Perancah dinding Rp. 16,875.00 m2
Scaffolding Rp. 12,500.00 m2
III Upah Pekerjaan lantai & dinding
Screed 3 cm Rp. 20,812.50 m2
Trowel lantai Rp. 6,750.00 m2
walles Rp. 1,380.00 m2
Lantai kerja Rp. 168,750.00 m3 580000-PPN
Lantai keramik 20 x 20 Rp. 28,125.00 m2
Lantai keramik 30 x 30 ; 60 x 60 Rp. 24,750.00 m2
Dinding keramik 20 x 20 Rp. 34,875.00 m2
Lantai batu alam Rp. 34,875.00 m2
Dinding batu alam Rp. 75,937.50 m2
Paving block + pemadatan Rp. 16,875.00 m2
Kanstein Rp. 11,500.00 m'
Waterstop Rp. 6,187.50 m'
Kawat duri Rp. 3,937.50 m'
Rooster 15 x 30 Rp. 75,375.00 m2
Rooster 20 x 20 Rp. 37,500.00 m2
Cat tembok baru Rp. 6,000.00 m2 cat + 5%
Cat tembok ulang Rp. 4,500.00 m2 cat + 5%
Cat kanstein Rp. 8,000.00 m2 cat + 5%
Cat genteng Rp. 8,000.00 m2 cat + 5%
III Upah Bongkar
Kanstein Rp. 9,450.00 m'
Paving block Rp. 6,750.00 m2
Sesek tanah Rp. 5,625.00 m2
Pembersihan rumput Rp. 5,400.00 m2
Perataan & pemadatan Rp. 5,625.00 m2
Buang keluar lokasi Rp. 54,000.00 m3
Buang dalam lokasi Rp. 35,000.00 m3
Pondasi batu belah Rp. 264,375.00 m3
Beton Rp. 337,500.00 m3
Lantai keramik 30 x 30 Rp. 13,500.00 m2
Lantai keramik 20 x 20 Rp. 16,875.00 m2
Dinding keramik 20 x 25 Rp. 20,250.00 m2
Dinding bata Rp. 10,125.00 m2
Glassblock Rp. 50,000.00 m2
Closet duduk Rp. 56,250.00 bh
Closet jongkok Rp. 48,375.00 bh
Washtafel Rp. 48,375.00 bh
Washbak Rp. 15,000.00 bh
Floor drain Rp. 5,000.00 bh
Atap genteng Rp. 5,625.00 m2
Nok genteng Rp. 7,500.00 m'
Atap seng Rp. 4,218.75 m2
Usuk & reng Rp. 10,125.00 m2
Gording kayu Rp. 11,250.00 m'
Usuk kayu Rp. 5,625.00 m'
Kupas Plesteran dinding Rp. 7,312.50 m2
Kupas Rabat lantai Rp. 7,500.00 m2
Sesek cat lama Rp. 2,812.50 m2
Bongkar plafond + rangka Rp. 10,687.50 m2
Bongkar partisi + rangka Rp. 13,500.00 m2
Bongkar lisplank + rangka Rp. 15,000.00 m'
Bongkar asbes gelombang + rangka Rp. 9,375.00 m2
Bongkar atap transparant + rangka Rp. 6,093.75 m2
Ketrik dinding Rp. 2,812.50 m2
Talang seng Rp. 8,437.50 m'
Torong seng / PVC Rp. 4,500.00 m'
No. Jenis Bahan/ Material Harga

I PASIR,BATU DAN PC
1 Tanah urug Rp. 85,000.00
1 Tanah padas Rp. 62,500.00
2 Pasir Muntilan Rp. 400,000.00
3 Split / Kriss Rp. 250,000.00
4 Batu belah Rp. 185,000.00
5 Batu pecah 5/7 Rp. 125,000.00
6 Batu Merah Rp. 800.00
7 Semen TIGA RODA Type I Rp. 54,000.00
8 AM 30 ( Perekat keramik dinding ) Rp. 18,750.00
9 AM 55 ( Nat / Tile grout ) Rp. 64,600.00
9 AM 50 ( Nat / Tile grout ) Rp. 14,500.00

II KAYU DAN PLYWOOD


1 Bambu apus Rp. 15,000.00
2 Kayu Meranti 4/6 ; 5/7 - 400 Rp. 5,200,000.00
3 Papan Randu 2/20 - 200 Rp. 15,000.00
4 Papan Meranti 2/20 - 400 Rp. 5,850,000.00
5 Papan Bangkirai 3/20 ~ 3/30 - 400 Rp. 12,000,000.00
5 Balok 6/12 Bangkirai Rp. 12,500,000.00
6 Kaso 5/7 Bangkirai Rp. 8,500,000.00
7 Reng 2/3 Bangkirai Rp. 7,500,000.00
7 Multiplex 12 mm Rp. 205,000.00

III BESI DAN KAWAT


1 Besi Beton Rp. 10,000.00
2 Bendrat Rp. 15,000.00
3 Paku Rp. 12,000.00
Besi 6 mmBesi 6 mm SNI Rp. 25,000.00
4 Besi 8 mmBesi 8 mm SNI Rp. 33,000.00
5 Besi 10 mmBesi 10 mm SNI Rp. 55,000.00

IV LANTAI DAN DINDING


1 Keramik lantai 60x60 Platinum Rp. 75,000.00
2 Keramik lantai 40x40 Platinum Rp. 75,000.00
3 Keramik lantai 40x40 Platinum ( Selasar / teras ) Rp. 75,000.00
4 Keramik lantai 33,3x33,3 ( open space / Gua maria ) Rp. 75,000.00
5 Keramik lantai 33,3x33,3 ( open space / Gua maria ) Rp. 75,000.00
6 Keramik lantai 33,3x33,3 ( Trap cagar budaya ) Rp. 75,000.00
7 Keramik Lantai 30x30 Inserto Rp. 75,000.00
8 Keramik Lantai 30x30 Listel Rp. 75,000.00
9 Keramik Lantai 30x30 Corner Rp. 75,000.00
10 Keramik lantai 30x60 Rp. 75,000.00
11 Keramik lantai 20x20 Asia Tile Roxy Black ( KM ) Rp. 55,000.00
12 Keramik lantai 20x20 Asia Tile Roxy Grey ( KM ) Rp. 55,000.00
13 Keramik dinding 30x30 Morano Asia Rp. 45,000.00
14 Keramik dinding 20x25 Asia Tile Metro Basic ( KM ) Rp. 55,000.00
15 Keramik dinding 20x25 Asia Tile Zola basic ( KM ) Rp. 55,000.00
15 Keramik dinding 20x20 Putih Rp. 75,000.00
16 Keramik dinding 20x20 KIA putih Rp. 65,000.00
17 Keramik dinding 30x30 KIA Rp. 70,000.00
17 Batu Andesit Bakar 20x20 lantai KM/WC Rp. 210,000.00
18 Batu lempeng tak beraturan Rp. 155,000.00
18 Nossing tangga 6 x 20 Rp. 25,000.00
19 Glass Block 20x20 Rp. 26,000.00
20 Rooster beton 20x20 Rp. 9,000.00
21 Paving block 6 cm Hexagonal natural Rp. 130,000.00
22 Kanstin Std 10/12.5 x 30 x 50 Rp. 40,000.00
23 Bata Ringan Rp. 850,000.00
24 Perekat Bata Ringan Rp. 150,000.00
25 Alat Bantu Rp. 5,000.00

V PENUTUP PLAFOND , PARTISI DAN ATAP


1 Partisi GRC 5 mm 2 sisi rk hollow 4/4 + 2/4 ~ 0.7 meni + cat finish Rp. -
2 Partisi Gypsum 9 mm 2 sisi rk hollow 4/4 + 2/4 ~ 0.7 meni + cat finish Rp. -
Partisi Gypsum 9 mm rk Hollow 40/40 + 20/40 ~ 0.6 galvanis +Glasswool + cat finish Rp. 285,000.00
3 Plafond Gypsum 9 mm rk Hollow 40/40 + 20/40 ~ 0.6 galvanis + cat finish Rp. -
4 Plafond Gypsum 9 mm ( WET ) rk Hollow 40/40 + 20/40 ~ 0.6 galvanis + cat Finish Rp. -
4 Plafond GRC 100x100 cm rk Hollow 40/40 + 20/40 ~ 0.6 galvanis + cat Finish Rp. -
5 Compond dag Rp. -
6 List tepi alm U 10 mm / Shaddow Line Rp. -
7 Genteng Kodok ex. SOKKA Rp. 6,000.00
8 NOK Genteng Kodok ex. SOKKA Rp. 15,000.00
9 Baja ringan SNI Rp. -

VI PENGECATAN
1 Ambril Rp. 3,000.00
2 Thinner Rp. 27,500.00
3 Alkali Resisting Primer Waterbase MOWILEX ( undercoat ) Rp. 40,000.00
4 Waterbase MOWILEX ( wallsealer ) Rp. 30,000.00
5 Cat Tembok dalam MOWILEX Lakestone W108 Intrique Rp. 51,000.00
6 Cat Tembok dalam MOWILEX VS 1801 Excellent White Rp. 75,000.00
7 Cat Tembok Luar MOWILEX Weathercoat Lakestone W 0959 Rp. 75,000.00
8 Cat Tembok Luar MOWILEX Weathercoat Morning Dew W 1518 Rp. 75,000.00
9 Cat Tembok Luar MOWILEX Weathercoat Blue lazio W 1433 Rp. 75,000.00
10 Cat Tembok Luar MOWILEX Weathercoat Cool grey W 0982 Rp. 75,000.00
11 Cat Genteng MOWILEX -45 tile Golden Rp. 60,000.00
12 Cat kayu Bee brand Rp. 70,000.00
12 Cat kayu Mowilex Woodstain WS 503 Walnut Rp. 58,000.00

VII SANITASI & PEMIPAAN


1 Buis beton Ø 90 ex. Lokal Rp. 300,000.00
2 Buis beton Ø 80 ex. Lokal Rp. 220,000.00
3 Buis beton Ø 60 ex. Lokal Rp. 160,000.00
5 Buis beton U 30 ex. Lokal Rp. 35,000.00
6 Buis beton U 20 ex. Lokal Rp. 27,000.00
6 Buis beton Ø 20 ex. Lokal Rp. 40,000.00
7 Grass block ( paving lubang untuk rumput ) Rp. 85,850.00
Sanitair :
Closet Jongkok Amstad Rp. 310,250.00
Closet Jongkok Rp. 508,300.00
Closet Duduk Amstad Rp. 2,550,000.00
Jet Shower Rp. 232,900.00
Jet Shower Rp. 195,000.00
Jet Shower Rp. 404,600.00
Shower mixer Rp. 1,022,000.00
Shower Head Rp. 1,230,000.00
Washtafel Rp. 1,212,950.00
Washtafel Rp. 1,456,900.00
Kran Washtafel Rp. 101,250.00
Washtafel Rp. 990,250.00
Kran Washtafel Rp. 618,800.00
Towel Ring Rp. 225,250.00
Kran dinding Rp. 251,600.00
Tissue holder Rp. 96,050.00
Tissue holder Rp. 608,000.00
Floor drain Rp. 142,500.00
Floor drain Rp. 84,000.00
Floor drain Rp. 388,450.00
Urinoir Rp. 2,072,000.00
Sekat Urinoir Rp. 1,144,780.00
Cermin 5 mm 80 x 140 cm Rp. 450,000.00
Washbak Royal Helena ST 3 Rp. 314,250.00
Kran Onda 1/2 Rp. 76,000.00
Kran Onda 1/2 CLS 01 ( Taman ) Rp. 49,500.00
Kran Onda 1/2 CLS 04 Rp. 43,000.00
Kran Onda 1/2 CLS 05 ( u/ dapur ) Rp. 74,500.00
Kran Onda 1/2 Dapur Rp. 125,000.00
Floor drain Rp. 12,500.00
Stop kran KITZ 3/4" Rp. 250,000.00
Stop kran KITZ 2 " Rp. 675,000.00
Roof drain stainless Ø 3" Rp. 165,900.00
Stop Kran Onda 3/4" Long neck Rp. 230,000.00
Stop Kran Onda Ø 2" Rp. 395,000.00
Pemipaan :
Pipa PVC Maspion AW Ø 3/4" abu-abu Rp. 26,500.00
Pipa PVC Maspion AW Ø 1/2" abu-abu Rp. 24,000.00
Pipa PVC Maspion AW Ø 1" abu-abu Rp. 33,000.00
Pipa PVC Maspion AW Ø 1 1/2" abu-abu Rp. 60,500.00
Pipa PVC Maspion AW Ø 2" abu-abu Rp. 90,000.00
Pipa PVC Maspion AW Ø 3" abu-abu Rp. 150,000.00
Pipa PVC Maspion D Ø 3/4" abu-abu Rp. 23,000.00
Pipa PVC Maspion D Ø 1 1/2" abu-abu Rp. 33,000.00
Pipa PVC Maspion D Ø 2" abu-abu Rp. 43,000.00
Pipa PVC Maspion D Ø 3" abu-abu Rp. 92,500.00
Pipa PVC Maspion D Ø 4" abu-abu Rp. 130,000.00
Pipa PVC Maspion D Ø 5" abu-abu Rp. 220,000.00
Pipa PVC Maspion D Ø 6" abu-abu Rp. 213,000.00
Pipa PVC Maspion C Ø 2" abu-abu Rp. 35,500.00
Pipa PVC Rucika AW Ø 2" abu-abu Rp. 150,000.00
Pipa PVC Rucika AW Ø 3" abu-abu Rp. 325,000.00
Pipa PVC Rucika AW Ø 4" abu-abu Rp. 420,000.00
Pipa PVC Rucika AW Ø 6" abu-abu Rp. 784,000.00
Pipa PVC Rucika AW Ø 8" abu-abu Rp. 1,226,900.00
VIII Aluminium + Kaca
1 Aluminium 3' Alexindo (Silver) Rp. 55,000.00
2 Aluminium 4' Alexindo (Silver) Rp. 75,000.00
3 Aluminium 3' Superex (Silver) Rp. 90,000.00
4 Aluminium 4' Superex (Silver) Rp. 100,000.00
5 Aluminium 3' YKK (Silver) Rp. 100,000.00
6 Aluminium 4' YKK (Silver) Rp. 120,000.00
7 Kaca 5 mm (Polos) Rp. 85,000.00
8 Kaca 5 mm (Rayban) Rp. 120,000.00
9 Kaca 5 mm (Dark Blue) Rp. 180,000.00
10 Kaca 5 mm (Dark Green) Rp. 180,000.00
11 Kaca 6 mm (Polos) Rp. 120,000.00
12 Kaca 6 mm (Rayban) Rp. 220,000.00
13 Kaca 6 mm (Dark Blue) Rp. 220,000.00
14 Kaca 6 mm (Dark Green) Rp. 220,000.00
15 Kaca 8 mm (Polos) Rp. 250,000.00
16 Kaca 8 mm (Rayban) Rp. 350,000.00
17 Kaca 8 mm (Dark Blue) Rp. 450,000.00
18 Kaca 8 mm (Dark Green) Rp. 450,000.00
19 Kaca 10 mm (Polos) Rp. 300,000.00
20 Kaca 10 mm (Dark Blue) Rp. 470,000.00
21 Kaca 10 mm (Dark Green) Rp. 470,000.00
22 Kaca 12 mm (Polos) Rp. 350,000.00
23 Kaca 12 mm (Dark Blue) Rp. 500,000.00
24 Kaca 12 mm (Dark Green) Rp. 500,000.00
25 Perlengkapan alat-alat & aksesories pembantu : Rp. 10,000.00

VIII LAIN-LAIN
1 Upah Tenaga lantai 1 1
Upah Tenaga lantai 2 / rata-rata 1.2
2 Waterproofing coating Rp. 75,000.00
3 Waterstop L = 25 cm Rp. 100,000.00
4 Grouting Sika Grout 215 Rp. 12,000,000.00
5 Rubber sealant 1 x 1 cm Sikaflex + cutting Rp. 49,000.00
6 Selang Plastik Ø 3/4" ( pembungkus dowel ) Rp. 6,500.00
5 Ijuk Rp. 400,000.00
### Ready Mix K-250 Rp. 800,000.00
### Ready Mix K-300 Rp. 825,000.00
### Sewa Pompa Rp. 55,000.00
9 Penguin TB200 Rp. 2,500,000.00

Pintu kayu & Aksesories :


Pintu double teakwood 450,000.00
Pintu panil 600,000.00
Pintu panil + kaca 550,000.00
Acc :
Kunci 2 slag 450,000.00
Engsel pintu 45,000.00
Engsel Jendela 35,000.00
Expagnolate 175,000.00
Rel pintu garasi 2,750,000.00
Finish Wood stin Mowilex 155,000.00
75,000.00
Kosen 6/15 Bkr 150,000.00
Satuan Keterangan

/ m3
/ m3
/ m3
/ m3
/ m3
/ m3
/ bh
/ zak 2.34
/ kg
/ kg
/ kg

/ batang
/ m3
/ lbr
/ m3
/ m3
/ m3
/ m3
/ m3
/ lembar

/ kg
/ kg
/ kg
/ btg
/ btg
/ btg

/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ bh
/ bh
/ bh
/ m2
/ bh
/ m3
/ bh
/ Ls

/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m'
/ bh
/ bh
/ m2

/ lmbr
/ ltr
/ ltr
/ ltr
/ ltr
/ ltr
/ ltr
/ ltr
/ ltr
/ ltr
/ ltr
/ ltr
/ ltr

/ m1
/ m1
/ m1
/ m1
/ m1
/ m1
/ m2

/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh
/ Bh

/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg
/ btg

/m'
/m'
/m'
/m'
/m'
/m'
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
/ m2
Ls

kali
kali
/ m2 aquaproof
/m'
/ m3
/ m' Saputro
/ m' Miliard / maspion
/ m3
/ m3
/ m3
/ hr
bh

/m2
/m2
/m2
set
bh
bh
set
set
/m2
/m'
/m'
No. Uraian Pekerjaan Bahan/T.Kerja Analisa Sat

1 Pengukuran dan Pemasangan bouplank Kayu 5/7 x 2m 0.001 M3


Paku biasa 2" - 5" 0.020 Kg
Papan Meranti 2/20 - 400 0.001 M3
Pekerja 0.100 Oh
Tukang kayu 0.100 Oh
Kepala Tukang 0.010 Oh
Mandor 0.005 Oh

2 1 M2 Pembuatan Kantor dan Gudang Sementara Dolken Kayu Ø 8-10/ 400 cm 1.250 Btg
Kayu albasia 0.180 M3
Paku Biasa 0.850 Kg
Semen Portland 35.000 Kg
Pasir Pasang 0.150 M3
Seng Gelombang 0.250 Lbr
Playwood 3 mm 1.000 Lbr
Pekerja 0.200 Oh
Tukang Kayu 0.200 Oh
Kepala Tukang 0.020 Oh
Mandor 0.002 Oh

3 1 M2 Membersihkan Lapangan dan Perawatan Pekerja 0.100 Btg


Mandor 0.050 M3

4 1 M3 Bongkaran Beton Pekerja 6.667 Oh


Mandor 0.333 Oh

5 1 M² Bongkaran Dinding Pekerja 0.330 Oh


Mandor 0.033 Oh
Sat.Harga Harga Sat
Total Harga
Bahan/T.Kerja Pekerjaan

5,200,000.00 3,466.67
12,000.00 240.00
5,850,000.00 7,605.00
71,500.00 7,150.00
71,500.00 7,150.00
88,000.00 880.00
88,000.00 440.00
Jumlah 26,931.67
-
-
-
-
-
-
-
-
-
-
-
Jumlah -
71,500.00 7,150.00
88,000.00 4,400.00
Jumlah 11,550.00
-
-
Jumlah -
-
-
Jumlah -
No. Uraian Pekerjaan Bahan/T.Kerja Analisa Sat

1 Menggali 1 M3 Tanah Biasa sedalam 1 meter Pekerja 0.750 oh


Mandor 0.025 oh

2 Menggali 1 M3 Tanah Biasa sedalam 2 meter Pekerja 0.900 oh


Mandor 0.045 oh

3 Menggali 1 M3 Tanah Biasa sedalam 3 meter Pekerja oh


Mandor oh

4 Menggali 1 M3 Tanah Keras sedalam 1 meter Pekerja oh


Mandor oh

5 Menggali 1 M3 Tanah Cadas sedalam 1 meter Pekerja oh


Mandor oh

6 Menggali 1 M3 Tanah Lumpur sedalam 1 meter Pekerja oh


Mandor oh

7 Mengerjakan 1 M2 Stripping tebing setinggi 1 meter Pekerja oh


Mandor oh

8 Membuang 1 M3 Tanah sejauh 15 meter Pekerja oh


Mandor oh

9 Mengurug Kembali 1 M3 Galian tanah biasa sedalam Pekerja 0.250 oh


1 meter Mandor 0.008 oh

Mengurug Kembali 1 M3 Galian tanah biasa sdlm 2


10 Pekerja oh
meter
Mandor oh

Mengurug Kembali 1 M3 Galian tanah biasa sdlm 3


11 Pekerja oh
meter
Mandor oh

Mengurug Kembali 1 M3 Galian tanah Keras sdlm 1


12 Pekerja oh
meter
Mandor oh

Mengurug Kembali 1 M3 Galian tanah Cadas sdlm 1


13 Pekerja oh
meter
Mandor oh

Mengurug Kembali 1 M3 Galian tanah Lumpur sdlm 1


14 Pekerja oh
meter
Mandor oh

15 Memadatkan 1 M3 Tanah ( Per 20 cm ) Pekerja 0.500 oh


Mandor 0.050 oh

16 Mengurug 1 M3 Pasir Urug Pasir Urug 1.200 m3


Pekerja 0.300 oh
Mandor 0.010 oh
17 Mengurug 1 M3 tanah urug mendatangkan Tanah Urug 1.200 m3
dipadatkan Pekerja 0.300 oh
Mandor 0.010 oh

17 Mengurug 1 M3 tanah padas mendatangkan Tanah Padas 1.200 m3


dipadatkan Pekerja 0.300 oh
Mandor 0.010 oh

18 Memasang 1 M3 Lapisan Pudel Camp:1KP:3PP:7TL


untuk stabilisasi tanah
19 Memasang 1 M3 Lapisan Pudel Camp:1KP:3TL untuk
stabilisasi tanah
20 Tk.Gali 0.0275 ht
Pemadatan Tanah Pondasi/m2 (dgn Mesin Stamper)
Kep.Tukang 0.0055 ht
Mandor 0.0018333 ht
Mesin Stamper 0.02 bh
Sat.Harga Harga Sat
Total Harga
Bahan/T.Kerja Pekerjaan

71,500.00 53,625.00
88,000.00 2,200.00
Jumlah 55,825.00
-
-
Jumlah -
-
-
Jumlah -

Jumlah

Jumlah

Jumlah

Jumlah

Jumlah
71,500.00 17,875.00
88,000.00 730.40
Jumlah 18,605.40

Jumlah

Jumlah

Jumlah

Jumlah

Jumlah
71,500.00 35,750.00
88,000.00 4,400.00
Jumlah 40,150.00
400,000.00 480,000.00
71,500.00 21,450.00
88,000.00 880.00
Jumlah 502,330.00
Jumlah
62,500.00 75,000.00
71,500.00 21,450.00
88,000.00 880.00
Jumlah 97,330.00

71,500.00 1,966.25
88,000.00 484.00
88,000.00 161.33
100,000.00 2,000.00
Jumlah 4,611.58
No. Uraian Pekerjaan Bahan/T.Kerja Analisa

1 Memasang 1 M3 Pondasi Batu Kosong (Aanstamping) Batu Belah 15/20 cm 1.200


Pekerja 0.780
Tukang Batu 0.390
Kepala Tukang 0.039
Mandor 0.039

2 Memasang 1 M3 Pondasi Batu Belah, camp 1PC : 3 PP


3 Memasang 1 M3 Pondasi Batu Belah, camp 1PC : 4 PP
4 Memasang 1 M3 Pondasi Batu Belah, camp 1PC : 5 PP
5 Memasang 1 M3 Pondasi Batu Belah, camp 1PC : 6 PP Batu Belah 15/20 cm 1.200
Semen Portland 2.340
Pasir Pasang 0.561
Pekerja 1.500
Tukang Batu 0.600
Kepala Tukang 0.060
Mandor 0.075

6 Memasang 1 M3 Pondasi Batu Belah, camp 1PC : 8 PP


Memasang 1 M3 Pondasi Siklop, 60% beton
7
camp:1PC:2PB:3KR dan 40% Batu Belah
8 Memasang 1 M3 Pondasi Sumuran, diameter 100 cm
Sat.Harga Harga Sat
Sat Total Harga
Bahan/T.Kerja Pekerjaan

m3 185,000.00 222,000.00
Oh 71,500.00 55,770.00
Oh 71,500.00 27,885.00
Oh 88,000.00 3,432.00
Oh 88,000.00 3,432.00
Jumlah 312,519.00

m3 185,000.00 222,000.00
zak 54,000.00 126,360.00
m3 400,000.00 224,400.00
Oh 71,500.00 107,250.00
Oh 71,500.00 42,900.00
Oh 88,000.00 5,280.00
Oh 88,000.00 6,600.00
Jumlah 734,790.00
I. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANTAI
Analisa Harga Satuan Pekerjaan Penutup Lantai
Sesuai SNI 7395:2008

NO URAIAN SATUAN VOLUME HARGA SATUAN (Rp)

I-01 Memasang 1 M2 Lantai Ubin Granito ukuran 40 x 40 cm


Granito 40 x 40 cm buah 6.63 #REF!
Semen Portland kg 9.80 1804.00
Pasir Pasang M3 0.05 227641.34
Semen Warna Kg 1.30 15003.63
Pekerja Oh 0.25 70593.60
Tukang Batu Oh 0.13 98831.04
Kepala Tukang Oh 0.01 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-02 Memasang 1 M2 Lantai Ubin Granito ukuran 30 x 30 cm


Granito 30 x 30 cm buah 11.87 102438.60
Semen Portland kg 10.00 1804.00
Pasir Pasang M3 0.05 227641.34
Semen Warna Kg 1.50 15003.63
Pekerja Oh 0.26 70593.60
Tukang Batu Oh 0.13 98831.04
Kepala Tukang Oh 0.01 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-03 Memasang 1 M' Plint Ubin Granito ukuran 10 x 40 cm


Plint granito 10 x 40 cm buah 2.65 16492.61
Semen Portland kg 1.14 1804.00
Pasir Pasang M3 0.00 227641.34
semen Warna Kg 0.10 15003.63
Pekerja Oh 0.09 70593.60
Tukang Batu Oh 0.09 98831.04
Kepala Tukang Oh 0.01 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-04 Memasang 1 M' Plint Ubin Granito ukuran 10 x30 cm


Plint granito 10 x 30 cm buah 3.53 14819.45
Semen Portland kg 1.14 1804.00
Pasir Pasang M3 0.00 227641.34
semen Warna Kg 0.10 15003.63
Pekerja Oh 0.09 70593.60
Tukang Batu Oh 0.09 98831.04
Kepala Tukang Oh 0.01 112949.76
Mandor Oh 0.01 120009.12

Lantai - Hal 24
Jumlah

I-05 Memasang 1 M2 Lantai Keramik artistik 10 x 20 cm


Keramik artistik buah 53.00 1056.00
Semen Portland Kg 8.19 1804.00
Pasir Pasang M3 0.05 227641.34
semen Warna Kg 2.75 15003.63
Pekerja Oh 0.70 70593.60
Tukang Batu Oh 0.35 98831.04
Kepala Tukang Oh 0.04 112949.76
Mandor Oh 0.04 120009.12
Jumlah

I-06 Memasang 1 M2 Lantai Keramik artistik 10 x 10 cm atau (5 x 20) cm


Keramik artistik buah 106.00 1860.00
Semen Portland Kg 8.19 1804.00
Pasir Pasang M3 0.05 227641.34
semen Warna Kg 3.20 15003.63
Pekerja Oh 0.35 70593.60
Tukang Batu Oh 0.35 98831.04
Kepala Tukang Oh 0.04 112949.76
Mandor Oh 0.04 120009.12
Jumlah

I-07 Memasang 1 M2 Lantai Keramik corak 20 x 20 cm setara Mulia


Keramik corak 20 x 20 cm buah 26.50 4252.75
Semen Portland Kg 10.40 1804.00
Pasir Pasang M3 0.05 227641.34
semen Warna Kg 1.62 15003.63
Pekerja Oh 0.35 70593.60
Tukang Batu Oh 0.04 98831.04
Kepala Tukang Oh 0.06 112949.76
Mandor Oh 0.03 120009.12
Jumlah

I-08 Memasang 1 M2 Lantai Keramik polos 30 x 30 cm setara Mulia


Keramik polos 30 x 30 cm buah 11.87 6420.05
Semen Portland Kg 10.00 1804.00
Pasir Pasang M3 0.05 227641.34
semen Warna Kg 1.50 15003.63
Pekerja Oh 0.35 70593.60
Tukang Batu Oh 0.04 98831.04
Kepala Tukang Oh 0.06 112949.76
Mandor Oh 0.03 120009.12
Jumlah

I-09 Memasang 1 M2 Lantai Keramik corak 30 x 30 cm setara Mulia

Lantai - Hal 25
Keramik corak 30 x 30 cm buah 11.87 8324.90
Semen Portland Kg 10.00 1804.00
Pasir Pasang M3 0.05 227641.34
semen Warna Kg 1.50 15003.63
Pekerja Oh 0.35 70593.60
Tukang Batu Oh 0.04 98831.04
Kepala Tukang Oh 0.06 112949.76
Mandor Oh 0.03 120009.12
Jumlah

I-10 Memasang 1 m2 Lantai keramik ukuran (33 x 33) cm


Ubin keramik buah 10.00 4950.00
Semen Portland Kg 8.19 1804.00
Pasir Pasang M3 0.05 227641.34
semen Warna Kg 1.62 15003.63
Pekerja Oh 0.70 70593.60
Tukang Batu Oh 0.35 98831.04
Kepala Tukang Oh 0.04 112949.76
Mandor Oh 0.04 120009.12
Jumlah

I-11 Memasang 1 M2 Lantai Keramik ukuran (10 x 33) cm, variasi/border


keramik buah 33.00 1540.00
Semen Portland Kg 9.80 1804.00
Pasir Pasang M3 0.05 227641.34
semen Warna Kg 4.37 15003.63
Pekerja Oh 1.05 70593.60
Tukang Batu Oh 0.53 98831.04
Kepala Tukang Oh 0.05 112949.76
Mandor Oh 0.05 120009.12
Jumlah

I-12 Memasang 1 M2 Lantai mosaik ukuran (30 x 30) cm, campuran spesi 1pc : 3ps
Mosaik buah 11.87 33000.00
Semen Portland Kg 14.15 1804.00
Pasir Pasang M3 0.04 227641.34
semen Warna Kg 2.00 15003.63
Pekerja Oh 0.70 70593.60
Tukang Batu Oh 0.35 98831.04
Kepala Tukang Oh 0.04 112949.76
Mandor Oh 0.04 120009.12
Jumlah

I-13 Memasang 1 M2 Lantai Keramik corak 10 x 20 cm setara Roman


Keramik corak 10 x 20 cm buah 11.87 3585.35
Semen Portland Kg 14.15 1804.00
Pasir Pasang M3 0.04 227641.34

Lantai - Hal 26
semen Warna Kg 2.00 15003.63
Pekerja Oh 0.70 70593.60
Tukang batu Oh 0.35 98831.04
Kepala Tukang Oh 0.04 112949.76
Mandor Oh 0.04 120009.12
Jumlah

I-14 Memasang 1 m2 Lantai ubin Taraso ukuran (30 x 30) cm


ubin taraso buah 11.87 5882.80
Semen Portland Kg 10.00 1804.00
Pasir Pasang M3 0.05 227641.34
semen Warna Kg 1.50 15003.63
Pekerja Oh 0.26 70593.60
Tukang batu Oh 0.13 98831.04
Kepala Tukang Oh 0.01 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-15 Memasang 1 M2 Lantai Karpet


Karpet m2 1.05 562139.58
Lem Kg 0.35 97782.30
Pekerja Oh 0.17 70593.60
Tukang Oh 0.17 98831.04
Kepala Tukang Oh 0.02 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-16 Memasang 1 M2 Underlayer/Pelapis bawah karpet


Underlayer/rubber corrugated m2 1.05 93500.00
Lem Kg 0.35 97782.30
Pekerja Oh 0.17 70593.60
Tukang Oh 0.17 98831.04
Kepala Tukang Oh 0.02 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-17 Memasang 1 M2 Lantai Marmer


Marmer m2 1.06 726072.38
Semen Portland kg 8.19 1804.00
Pasir Pasang m3 0.05 227641.34
semen Warna kg 0.65 15003.63
Pekerja OH 0.70 70593.60
Tukang batu OH 0.35 98831.04
Kepala Tukang OH 0.04 112949.76
Mandor OH 0.04 120009.12
Jumlah

Lantai - Hal 27
I-18 1 M2 Lantai Parquet Jati
Parquet Jati M2 1.05 514975.92
Lem vinyl zak 0.60 31042.00
Pekerja Oh 0.70 70593.60
Tukang Kayu Oh 0.35 105890.40
Kepala Tukang Oh 0.04 112949.76
Mandor Oh 0.04 120009.12
Jumlah

I-19 Memasang 1 m2 Lantai Kayu (gymfloor)


Gymfloor m2 1.05 137500.00
Lem kg 0.60 45010.90
Pekerja Oh 0.70 70593.60
Tukang Kayu Oh 0.35 105890.40
Kepala tukang Oh 0.04 112949.76
Mandor Oh 0.04 120009.12
Jumlah

I-20 Memasang 1 m2 Lantai Vinyl ukuran (30 x 30) cm KL.1


Vinyl buah 11.87 18700.00
Lem vinyl kg 0.35 31042.00
Pekerja Oh 0.15 70593.60
Tukang Oh 0.15 105890.40
Kepala tukang Oh 0.02 112949.76
Mandor Oh 0.08 120009.12
Jumlah

I-21 1 M' Plint Keramik ukuran (10 x 40) cm


Plint Keramik buah 2.65 6573.14
Semen Portland zak 0.02 1804.00
Pasir Pasang M3 0.00 227641.34
semen Warna Kg 0.10 15003.63
Pekerja Oh 0.06 70593.60
Tukang Batu Oh 0.03 98831.04
Kepala Tukang Oh 0.00 112949.76
Mandor Oh 0.00 120009.12
Jumlah

I-22 1 M' Plint Keramik ukuran (10 x 30) cm


Plint Keramik (10 x 30) cm buah 4.30 20177.30
Semen Portland zak 0.05 1804.00
Pasir Pasang M3 0.00 227641.34
semen Warna Kg 0.30 15003.63
Pekerja Oh 0.06 70593.60
Tukang Batu Oh 0.03 98831.04
Kepala Tukang Oh 0.00 112949.76
Mandor Oh 0.00 120009.12

Lantai - Hal 28
Jumlah

I-23 1 M' Plint Keramik ukuran (10 x 20) cm


Plint Keramik buah 5.30 20177.30
Semen Portland kg 1.14 1804.00
Pasir Pasang m3 0.00 227641.34
semen Warna Kg 0.03 15003.63
Pekerja Oh 0.09 70593.60
Tukang Batu Oh 0.09 98831.04
Kepala Tukang Oh 0.01 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-24 Memasang 1 m' plint keramik ukuran (10 x 10) cm


Plint keramik artistik buah 10.60 11000.00
Semen Portland kg 1.14 1804.00
Pasir Pasang m3 0.00 227641.34
semen Warna Kg 0.05 15003.63
Pekerja Oh 0.09 70593.60
Tukang Batu Oh 0.09 98831.04
Kepala Tukang Oh 0.01 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-25 Memasang 1 m' Plint keramik ukuran (5 x 20) cm


Plint keramik buah 5.30 5500.00
Semen Portland kg 0.57 1804.00
Pasir Pasang m3 0.00 227641.34
semen Warna kg 0.01 15003.63
Pekerja Oh 0.09 70593.60
Tukang Batu Oh 0.09 98831.04
Kepala Tukang Oh 0.01 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-26 Memasang 1 m' plint ubin teraso ukuran (10 x 30) cm


plint ubin teraso buah 3.53 3828.00
Semen Portland kg 1.14 1804.00
Pasir Pasang m3 0.00 227641.34
semen Warna kg 0.10 15003.63
Pekerja Oh 0.09 70593.60
Tukang Batu Oh 0.09 98831.04
Kepala Tukang Oh 0.01 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-27 Memasang 1 m' plint vinyl karet ukuran (15 x 30) cm dengan perekat

Lantai - Hal 29
Vinyl karet buah 1.76 60500.00
Lem vinyl kg 0.08 31042.00
pekerja Oh 0.08 70593.60
Tukang Oh 0.08 98831.04
Kepala tukang Oh 0.01 112949.76
Mandor Oh 0.00 120009.12
Jumlah

I-28 Memasang 1 m2 floor hardener


Floor hardener kg 5.00 30800.00
pekerja Oh 0.12 70593.60
tukang Oh 0.12 98831.04
kepala tukang Oh 0.12 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-29 Memasang 1 M' Plint Kayu kelas II tebal 2 cm, lebar 10 cm


Papan Kayu Kelas II M3 0.00 2860000.00
Paku/sekrup 5 cm Kg 0.05 14300.00
Pekerja Oh 0.12 70593.60
Tukang Batu Oh 0.12 98831.04
Kepala Tukang Oh 0.01 112949.76
Mandor Oh 0.01 120009.12
Jumlah

I-30 Memasang 1 m' plint internal cove artistik ukuran (5 x 5 x 20) cm


Internal cove buah 5.30 7150.00
Semen Portland Kg 1.14 1804.00
Pasir Pasang m3 0.00 227641.34
semen Warna kg 0.10 15003.63
Pekerja Oh 0.75 70593.60
Tukang Batu Oh 0.75 98831.04
Kepala Tukang Oh 0.08 112949.76
Mandor Oh 0.04 120009.12

Jumlah

I-31 Memasang 1 M2 Paving Block Natural 8 cm


Paving block natural M2 1.01 126133.99
Pasir pasang Kg 0.10 227641.34
Pekerja Oh 0.25 70593.60
Tukang batu Oh 0.50 15003.63
Kepala Tukang Oh 0.03 112949.76
Mandor Oh 0.00 120009.12
Jumlah

I-32 Memasang 1 M2 Paving Block Warna 8 cm

Lantai - Hal 30
Paving block warna M2 1.01 147811.66
Pasir pasang Kg 0.10 227641.34
Pekerja Oh 0.25 70593.60
Tukang batu Oh 0.50 15003.63
Kepala Tukang Oh 0.03 112949.76
Mandor Oh 0.00 120009.12
Jumlah

I-33 Memasang 1 M2 Paving Block Natural 6 cm


Paving block natural M2 1.01 107353.58
Pasir pasang Kg 0.10 227641.34
Pekerja Oh 0.25 70593.60
Tukang batu Oh 0.50 15003.63
Kepala Tukang Oh 0.03 112949.76
Mandor Oh 0.00 120009.12
Jumlah

I-34 Memasang 1 M2 Paving Block Warna 6 cm


Paving block warna M2 1.01 123391.95
Pasir pasang Kg 0.10 227641.34
Pekerja Oh 0.25 70593.60
Tukang batu Oh 0.50 15003.63
Kepala Tukang Oh 0.03 112949.76
Mandor Oh 0.00 120009.12
Jumlah

I-35 Memasang 1 M2 Glass Block 20 x 20


Grass block buah 25.00 23643.66
Pasir pasang Kg 0.10 227641.34
Pekerja Oh 0.25 70593.60
Tukang batu Oh 0.50 15003.63
Kepala Tukang Oh 0.03 112949.76
Mandor Oh 0.00 120009.12
Jumlah

I-36 Memasang 1 M2 Glass Block 30 x 30


Grass block buah 18.00 27472.17
Pasir pasang Kg 0.10 227641.34
Pekerja Oh 0.25 70593.60
Tukang batu Oh 0.50 15003.63
Kepala Tukang Oh 0.03 112949.76
Mandor Oh 0.00 120009.12
Jumlah

I-37 Pekerjaan bekisting untuk Lantai

Lantai - Hal 31
Plat bondex m2 1.03 385.00
Kayu Kelas II m3 0.04 2860000.00
Paku 5 - 12 cm kg 0.10 18625.20
Minyak Bekisting liter 0.05 19401.25
Plywood tebal 9 mm Lbr 0.09 194012.50
Dolken kayu galam (8-10) cm, pjng 4 m btg 1.50 439259.82
Pekerja Oh 0.17 70593.60
Tukang Kayu Oh 0.08 105890.40
Kepala Tukang Oh 0.01 112949.76
Mandor Oh 0.01 120009.12
Jumlah
I-01 Memasang 1 M2 Lantai keramik setara mulia ukuran 40 x 40 cm
keramik 40 x 40 cm buah 7.00 12675.49
Semen Portland kg 11.38 1980.00
Pasir Pasang M3 0.04 227641.34
Semen Warna Kg 1.50 15003.63
Pekerja Oh 0.35 70593.60
Tukang Batu Oh 0.04 98831.04
Kepala Tukang Oh 0.06 112949.76
Mandor Oh 0.03 120009.12
Jumlah

Lantai - Hal 32
HARGA (Rp)

#REF!
17679.20
10243.86
19504.72
17648.40
12353.88
1468.35
1560.12
#REF!

1215946.18
18040.00
10243.86
22505.45
18354.34
12848.04
1468.35
1560.12
1300966.33

43705.43
2056.56
682.92
1500.36
6353.42
8894.79
1016.55
600.05
64810.09

52312.66
2056.56
682.92
1500.36
6353.42
8894.79
1016.55
600.05

Lantai - Hal 33
73417.32

55968.00
14774.76
10243.86
41259.99
49415.52
34590.86
3953.24
4200.32
214406.56

197160.00
14774.76
10243.86
48011.63
24707.76
34590.86
3953.24
4200.32
337642.43

112697.98
18761.60
10243.86
24305.89
24707.76
3459.09
7002.89
3720.28
204899.34

76206.01
18040.00
10243.86
22505.45
24707.76
3459.09
7002.89
3720.28
165885.33

Lantai - Hal 34
98816.55
18040.00
10243.86
22505.45
24707.76
3459.09
7002.89
3720.28
188495.88

49500.00
14774.76
10243.86
24305.89
49415.52
34590.86
3953.24
4200.32
190984.45

50820.00
17679.20
10243.86
65565.88
74123.28
51886.30
5986.34
6360.48
282665.33

391710.00
25526.60
8878.01
30007.27
49415.52
34590.86
3953.24
4200.32
548281.82

42558.12
25526.60
8878.01

Lantai - Hal 35
30007.27
49415.52
34590.86
3953.24
4200.32
199129.94

69828.84
18040.00
10243.86
22505.45
18354.34
12848.04
1468.35
1560.12
154848.98

590246.56
34223.81
12000.91
16801.28
1920.15
1080.08
656272.78

98175.00
34223.81
12000.91
16801.28
1920.15
1080.08
164201.22

769636.72
14774.76
10243.86
9752.36
49415.52
34590.86
3953.24
4200.32
896567.65

Lantai - Hal 36
540724.71
18625.20
49415.52
37061.64
3953.24
4200.32
653980.63

144375.00
27006.54
49415.52
37061.64
3953.24
4200.32
266012.26

221969.00
10864.70
10589.04
15883.56
1694.25
9600.73
270601.28

17418.83
36.08
682.92
1500.36
4235.62
2964.93
338.85
360.03
27537.62

86762.39
90.20
728.45
4501.09
4235.62
2964.93
338.85
360.03

Lantai - Hal 37
99981.56

106939.69
2056.56
682.92
375.09
6353.42
8894.79
1016.55
600.05
126919.08

116600.00
2056.56
682.92
750.18
6353.42
8894.79
1016.55
600.05
136954.48

29150.00
1028.28
341.46
195.05
6353.42
8894.79
1016.55
600.05
47579.60

13512.84
2056.56
682.92
1500.36
6353.42
8894.79
1016.55
600.05
34617.50

Lantai - Hal 38
106480.00
2483.36
5647.49
7906.48
903.60
480.04
123900.97

154000.00
8471.23
11859.72
13553.97
720.05
188604.98

8580.00
715.00
8471.23
11859.72
1355.40
720.05
30981.35

37895.00
2056.56
682.92
1500.36
52945.20
74123.28
8471.23
4560.35

182234.91

127395.33
22764.13
17648.40
7501.82
2823.74
300.02
178133.43

Lantai - Hal 39
149289.77
22764.13
17648.40
7501.82
2823.74
300.02
200027.87

108427.12
22764.13
17648.40
7501.82
2823.74
300.02
159165.21

124625.87
22764.13
17648.40
7501.82
2823.74
300.02
175363.96

591091.42
22764.13
17648.40
7501.82
2823.74
300.02
641829.51

494499.06
22764.13
17648.40
7501.82
2823.74
300.02
545237.15

Lantai - Hal 40
396.55
114400.00
1862.52
970.06
17461.13
658889.73
12000.91
8471.23
1129.50
1200.09
816781.72

88728.41
22532.40
9560.94
22505.45
24707.76
3459.09
7002.89
3720.28
182217.21

Lantai - Hal 41
No. Uraian Pekerjaan Bahan/T.Kerja Analisa Sat

1 1 M2 Pekerjaan pasangan dinding bata ringan Bata Ringan 0.075 m3


tebal 7,5 cm Perekat Bata Ringan 0.079 sak
Alat Bantu 1.000 Ls

Pekerja 0.300 OH
Tukang Batu 0.100 OH
Kepala Tukang 0.010 OH
Mandor 0.010 OH

2 1 M2 Pekerjaan pasangan dinding bata ringan Bata Ringan 0.100 m3


tebal 10 cm Perekat Bata Ringan 0.105 sak
Alat Bantu 1.000 Ls

Pekerja 0.300 OH
Tukang Batu 0.100 OH
Kepala Tukang 0.010 OH
Mandor 0.010 OH

3 1 M2 Pekerjaan pasangan dinding bata ringan Bata Ringan 0.125 m3


tebal 12,5 cm Perekat Bata Ringan 0.131 sak
Alat Bantu 1.000 Ls

Pekerja 0.300 OH
Tukang Batu 0.100 OH
Kepala Tukang 0.010 OH
Mandor 0.010 OH

4 1 M2 Pekerjaan pasangan dinding bata ringan Bata Ringan 0.150 m3


tebal 15 cm Perekat Bata Ringan 0.158 sak
Alat Bantu 1.000 Ls

Pekerja 0.300 OH
Tukang Batu 0.100 OH
Kepala Tukang 0.010 OH
Mandor 0.010 OH

5 1M2 Pasang Dinding Hebel 10 cm + space PM 110 Block hebel 0.100 m3


Thin bed Pm 110 0.100 Zak
Ongkos pasang 1.000 m2
Peralatan 1.000 lot
1M2 Pasang Dinding Hebel 7.5 cm + space PM
6 Block hebel 0.089 m3
110
Thin bed Pm 110 0.079 Zak
Ongkos pasang 1.000 m2
Peralatan 1.000 lot

7 1 M2 Plesteran Ex Pmortar - 210 tebal 1 cm 1 sisi PMortar - 210 0.400 Zak


Upa+alat 1.000 m2
Peralatan 1.000 Lot

8 1 M2 Acian Ex Pmortar - 310 tebal 2 - 3 mm 1 sisi PMortar -310 0.100 Zak


Upa+alat 1.000 m2

9 1M' Sponengan Semen portland 0.0125 zak


Steiger 1.0000 ls
Ongkos sponengan sudut lantai Dasar 1.0000 m'
Sat.Harga Harga Sat
Total Harga
Bahan/T.Kerja Pekerjaan

850,000.00 63,750.00
150,000.00 11,850.00
5,000.00 5,000.00
Jumlah 80,600.00
70,000.00 21,000.00
100,000.00 10,000.00
120,000.00 1,200.00
150,000.00 1,500.00
Jumlah 33,700.00
Subtotal 114,300.00
Dibulatkan 114,300.00
850,000.00 85,000.00
150,000.00 15,750.00
5,000.00 5,000.00
Jumlah 105,750.00
71,500.00 21,450.00
71,500.00 7,150.00
88,000.00 880.00
88,000.00 880.00
Jumlah 30,360.00
Subtotal 136,110.00
Dibulatkan 136,100.00
850,000.00 106,250.00
150,000.00 19,650.00
5,000.00 5,000.00
Jumlah 130,900.00
70,000.00 21,000.00
100,000.00 10,000.00
120,000.00 1,200.00
150,000.00 1,500.00
Jumlah 33,700.00
Subtotal 164,600.00
Dibulatkan 164,600.00
850,000.00 127,500.00
150,000.00 23,625.00
5,000.00 5,000.00
Jumlah 156,125.00
70,000.00 21,000.00
100,000.00 10,000.00
120,000.00 1,200.00
150,000.00 1,500.00
Jumlah 33,700.00
Subtotal 189,825.00
Dibulatkan 189,800.00
963,000.00 96,300.00
71,820.00 7,182.00
13,500.00 13,500.00
1,500.00 1,500.00
118,482.00
963,000.00 85,707.00
71,820.00 5,673.78
13,500.00 13,500.00
1,500.00 1,500.00
Jumlah 106,380.78
64,500.00 25,800.00
15,500.00 15,500.00
2,000.00 2,000.00
Jumlah 43,300.00
75,000.00 7,500.00
11,500.00 11,500.00
19,000.00
Rp. 56,983 712.29
Rp. 9,720 9,720.00
Rp. 7,857 7,857.00
Jumlah 18,289.29
No. Uraian Pekerjaan Bahan/T.Kerja Analisa Sat

1 BETON K-250 LANTAI / DAG / BALOK Ready Mix 1.000 M3


Beton Ready Mix K-250 Sewa Pompa 1.000 M3
Upah Cor 1.200 M3

2 1 m3 Beton Sloof, Kolom, Kolom Praktis Bahan


Papan 2/20 0.270 M³
Paku Biasa 2"-5" 2.000 Kg
Besi Beton D-6 0.333 btg
Besi Beton D-8 0.372 btg
Bendrat 0.423 kg
Besi Beton polos 200.000 Kg
Kawat Beton 3.000 Kg
Semen Portland 323.000 Kg
Pasir Beton 0.520 M³
Koral Beton 0.780 M³
Tenaga
Pekerja 4.850 Oh
Tukang Batu 0.350 Oh
Tukang Kayu 1.560 Oh
Tukang Besi 1.400 Oh
Kepala Tukang 0.331 Oh
Mandor 0.170 Oh

LANTAI KERJA
1 BETON 1:3:5 Semen 4.536 Zak
Kris 0.910 m3
Pasir Muntilan 0.540 m3
Pekerja 1.200 Oh
Tukang Batu 0.200 Oh
Kepala Tukang 0.020 Oh
Mandor 0.060 Oh

BETON READY MIX K-300


2 Beton Ready Mix K-300 Ready Mix 1.000 M3
Sewa Pompa 1.000 hr
Pekerja 1.200 Oh
Tukang Batu 0.200 Oh
Kepala Tukang 0.020 Oh
Mandor 0.060 Oh

3 1 M3 Beton
a Beton 1:2:3 SM ( Pondasi,sloof & Btn praktis ) Semen 6.800 Zak
Kris 0.820 M3
Pasir Muntilan 0.540 M3
Pekerja 5.650 Oh
Tukang Besi 1.400 Oh
Kepala Tukang 0.323 Oh
Mandor 0.283 Oh
b Besi Beton Besi Beton 1.100 Kg
Bendrat 0.020 Kg
Tukang Besi 1.400 Oh
Kepala Tukang 0.331 Oh
Mandor 0.170 Oh

4 BETON SLOOF 15x25 1:2:3 SITE MIX


1m3 Sloof 15/25 Besi 8 Tulangan 6 semen 0.224 zak
pasir 0.021 m3
kerikil 0.021 m3
Besi Beton D-6 0.333 btg
Besi Beton D-8 0.372 btg
Bendrat 0.423 kg
Papan 2/20 0.850 lbr
Paku 2"- 5" 0.150 kg
pekerja 0.283 oh
tukang 0.267 oh
kepala Tukang 1.263 oh
mandor 0.465 oh

5 1 m3 Beton Sloof 15x25


Cor beton K-175 1.000 m3
Besi Beton pokok, Ø 8" - 4 bh, cincin Ø 6" - 20 bh 180.890 kg
Bekisting papan 21.336 m2

Beton Ready mix K 300 lantai Dasar / M3 Beton readymix K 300 1.0000 m3
Ongkos cor beton readymix lantai Dasar 1.0000 m3

18 1 m2 Rabat Beton Expose + Acian Beton 1:2:3 8 cm 0.0800 m3


Acian 1.0000 m2
Tali air 1.0000 m'

19 Carport Pas.Paving Blok T.6cm/m2 Galian Tanah 0.250 m3


Pemadatan Tanah dgn Stamper 1.000 m2
Urugan Sirtu T.20cm 0.200 m3
Pemadatan Sirtu dgn Stamper 1.000 m2
Urugan Pasir Extra Beton T.10cm 0.150 m3
Paving Blok T.6cm 1.100 m2
Pasir Pengisi Pasir Urug 0.015 m3
Pemadatan Paving dgn Stamper 1.000 m2

4 BETON SLOOF 15x25 1:2:3 SITE MIX


1m3 Sloof 15/25 Besi 8 Tulangan 6 semen 5.938 zak
pasir 0.499 m3
kerikil 0.535 m3
besi d8 0.334 btg
besi d6 0.325 btg
papan 0.854 lbr
paku 0.150 kg
bendrat 0.243 kg
pekerja 0.339 oh
tukang 0.142 oh
kepala tukang 0.014 oh
mandor 0.017 oh

4 BETON KOLOM PRAKTIS 15x15 1:2:3 SITE MIX


1m3 Kolom15/15 Besi 8 Tulangan 6 semen 5.903 zak
pasir 0.499 m3
kerikil 0.535 m3
besi d8 0.336 btg
besi d6 0.238 btg
papan 1.023 lbr
paku 0.180 kg
bendrat 0.221 kg
pekerja 0.365 oh
tukang 0.164 oh
kepala tukang 0.016 oh
mandor 0.018 oh

4 BETON TIEBALK 15x15 1:2:3 SITE MIX


1m3 TieBalk 15/15 Besi 8 Tulangan 6 semen 5.934 zak
pasir 0.499 m3
kerikil 0.535 m3
besi d8 0.334 btg
besi d6 0.239 btg
papan 0.510 lbr
paku 0.090 kg
bendrat 0.221 kg
pekerja 0.209 oh
tukang 0.086 oh
kepala tukang 0.009 oh
mandor 0.011 oh

4 BETON RINGBALK 15x20 1:2:3 SITE MIX


1m3 RingBalk 15/20 Besi 8 Tulangan 6 semen 5.934 zak
pasir 0.499 m3
kerikil 0.535 m3
besi d8 0.334 btg
besi d6 0.283 btg
papan 0.683 lbr
paku 0.120 kg
bendrat 0.232 kg
pekerja 0.261 oh
tukang 0.112 oh
kepala tukang 0.011 oh
mandor 0.013 oh
Sat.Harga Harga Sat
Total Harga
Bahan/T.Kerja Pekerjaan

775,000.00 775,000.00
60,000.00 60,000.00
157,500.00 189,000.00
Jumlah 1,024,000.00

15,000.00 4,050.00
12,000.00 24,000.00
25,000.00 8,333.33
33,000.00 12,283.33
15,000.00 6,346.50
12,000.00 2,400,000.00
13,000.00 39,000.00
1,050.00 339,150.00
125,000.00 65,000.00
135,000.00 105,300.00

36,000.00 174,600.00
42,500.00 14,875.00
47,500.00 74,100.00
45,000.00 63,000.00
45,000.00 14,895.00
40,000.00 6,800.00
Jumlah 3,351,733.17

54,000.00 244944.00
250,000.00 227500.00
400,000.00 216000.00
71,500.00 85800.00
71,500.00 14300.00
88,000.00 1760.00
88,000.00 5280.00
Jumlah 795,584.00

825,000.00 825,000.00
55,000.00 55,000.00
71,500.00 85,800.00
71,500.00 14,300.00
88,000.00 1,760.00
88,000.00 5,280.00
Jumlah 987,140.00

54,000.00 367,200.00
250,000.00 205,000.00
400,000.00 216,000.00
71,500.00 403,975.00
71,500.00 100,100.00
88,000.00 28,424.00
100,000.00 28,300.00
Jumlah 1,348,999.00
10,000.00 11,000.00
15,000.00 300.00
71,500.00 100,100.00
88,000.00 29,128.00
88,000.00 14,960.00
Jumlah 155,488.00

54,000.00 12,109.50
400,000.00 8,560.71
250,000.00 5,296.88
25,000.00 8,333.33
33,000.00 12,283.33
15,000.00 6,346.50
5,850,000.00 4,972,500.00
12,000.00 1,803.67
71,500.00 20,252.95
71,500.00 19,063.97
88,000.00 111,146.34
88,000.00 40,905.37
Jumlah 5,218,602.56

Rp. 891,000 891,000.00


Rp. 87,300 87,300.00
978,300.00
Rp. 1,069,000 85,520.00
Rp. 26,460 26,460.00
Rp. 13,860 13,860.00
125,840.00
Rp. 26,281.40 6,570.35
Rp. 5,109.33 5,109.33
Rp. 167,666.67 33,533.33
Rp. 7,664.00 7,664.00
Rp. 214,133.33 32,120.00
Rp. 50,000.00 55,000.00
Rp. 145,000.00 2,175.00
Rp. 5,109.33 5,109.33
147,281.35

54,000.00 320,653.18
400,000.00 199,750.00
250,000.00 133,815.79
33,000.00 11,022.45
25,000.00 8,118.39
15,000.00 12,803.86
12,000.00 1,800.00
15,000.00 3,650.13
71,500.00 24,231.99
71,500.00 10,154.14
88,000.00 1,257.99
88,000.00 1,503.56
Jumlah 728,761.47

54,000.00 318,750.00
400,000.00 199,750.00
250,000.00 133,815.79
33,000.00 11,085.94
25,000.00 5,957.03
15,000.00 15,351.56
12,000.00 2,160.00
15,000.00 3,317.63
71,500.00 26,069.42
71,500.00 11,707.10
88,000.00 1,445.82
88,000.00 1,614.99
Jumlah 731,025.29

54,000.00 320,418.85
400,000.00 199,750.00
250,000.00 133,815.79
33,000.00 11,012.09
25,000.00 5,986.97
15,000.00 7,655.46
12,000.00 1,080.00
15,000.00 3,317.63
71,500.00 14,914.86
71,500.00 6,130.01
88,000.00 759.41
88,000.00 928.56
Jumlah 705,769.63

54,000.00 320,418.85
400,000.00 199,750.00
250,000.00 133,815.79
33,000.00 11,012.09
25,000.00 7,066.58
15,000.00 10,246.55
12,000.00 1,440.00
15,000.00 3,483.88
71,500.00 18,688.33
71,500.00 7,994.56
88,000.00 988.89
88,000.00 1,161.26
Jumlah 716,066.78
No. Uraian Pekerjaan Bahan/T.Kerja

1 1Bh - DAUN PINTU ALUMINIUM TIPE FLOOR Ambang Bawah Daun Pintu (no. kode ** : 2000)
HINGE uk. 4" x 1 3/4" Tiang Kusen Pintu (no. kode : 2001)
Ukuran Daun Pintu : 220 cm x 90 cm Penutup Ambang Bawah & Atas Daun Pintu (no. kode : 2003)
Ambang Atas Daun Pintu (no. Kode : 2005)
Sealent ex. Dow corning atau setara col. Clear / silver
Clear Glass 6 mm
Floor Hinge ex. Dekkson
Perlengkapan alat-alat & aksesories pembantu :
- Gun Sealent
- Kain Bal
- Cutter
- Aluminium Cutting Machine
- Mesin Bor
- Mata Bor aluminium dan beton
- Sekrup dan Phiser
- Paper Tape
Upah Perakitan dan Pemasangan Daun Pintu Aluminium tipe floor
hinge (include floor hinge )
Upah pemasangan aksesories : handle & lockset
Upah Pemasangan Kaca
Upah Pekerjaan Sealent

2 1 M' Kusen Alumunium Type P1 (220x80 cm) Aluminium 3' Alexindo


Tukang
Perlengkapan alat-alat & aksesories pembantu :

2 1 bh Bouven (50x55 cm) Aluminium 3' Alexindo


Kaca 5mm
Tukang
Perlengkapan alat-alat & aksesories pembantu :
Sat.Harga Harga Sat
Analisa Sat Total Harga
Bahan/T.Kerja Pekerjaan

0.900 m¹ 60,800.0 54,720.00


4.400 m¹ 51,100.0 224,840.00
1.800 m¹ 8,600.0 15,480.00
0.900 m² 55,600.0 50,040.00
12.400 m¹ 1,100.0 13,640.00
2.011 m² 85,000.0 170,943.50
1.000 unit 250,000.0 250,000.00
1.000 Ls 10,000.0 10,000.00

1.000 unit 1,500.0 1,500.00


1.000 unit 37,500.0 37,500.00
1.980 m² 8,500.0 16,830.00
12.400 m¹ 1,500.0 18,600.00
Jumlah 864,093.50
Dibulatkan 864,000.00
1.000 m' 55,000.00 55,000.00
0.500 hr 71,500.00 35,750.00
1.000 Ls 10,000.00 10,000.00
Jumlah 100,750.00
2.100 m' 100,000.00 210,000.00
0.250 m2 85,000.00 21,250.00
1.000 hr 71,500.00 71,500.00
1.000 Ls 10,000.00 10,000.00
Jumlah 312,750.00
No. Uraian Pekerjaan Bahan/T.Kerja Analisa Sat

1 1 Buah Closet jongkok Porselen Standar Closet jongkok 1.000 bh


P.C (50 gk) 6.000 Kg
Pasir pasang 0.010 m3
Pekerja 1.000 org
Tukang batu 1.500 org
Kepala Tukang 1.500 org
Mandor 0.160 org

2 1 Buah Closet Duduk Closet duduk 1.000 bh


Pekerja 3.300 org
Tukang batu 1.100 org
Kepala Tukang 0.001 org
Mandor 0.160 org
Perlengkapan 6 % harga closet 0.060 lot

3 1 Buah Kran Ø 1/2" - 3/4" Kran air 1.000 bh


Seal tape 0.025 bh
Pekerja 0.010 org
Tukang batu 0.100 org
Kepala Tukang 0.010 org
Mandor 0.005 org

4 Memasang 1 buah Floor drain Floor drain 1.0000 bh


Pekerja 0.01 Oh
Tukang batu 0.1000 Oh
Kepala Tukang 0.01 Oh
Mandor 0.0050 Oh

5 1 Buah Bak Cuci piring Stainless steel


Pekerja 1.0000 bh
Tukang batu 0.0300 org
Kepala Tukang 0.3000 org
Mandor 0.0300 org
0.0015 org

6 Closet Duduk Lokal INA/bh Type3 Closet Duduk 1 bh


Papan Dudukan 0.0225 m3
Kenek 3 ht
Tk.Plumbing 1.5 ht
Kep.Tukang 0.5 ht
Mandor 0.1666667 ht
Bor Listrik 0.25 hk
Sat.Harga Harga Sat
Total Harga
Bahan/T.Kerja Pekerjaan

188,200.00 188,200.00
1,406.00 8,436.00
233,400.00 2,334.00
42,000.00 42,000.00
65,000.00 97,500.00
75,000.00 112,500.00
80,000.00 12,800.00
Jumlah 463,770.00
Dibulatkan 463,700.00
1,724,700.00 1,724,700.00
42,000.00 138,600.00
65,000.00 71,500.00
75,000.00 75.00
80,000.00 12,800.00
1,724,700.00 103,482.00
Jumlah 2,051,157.00
Dibulatkan 2,051,100.00
40,900.00 40,900.00
4,200.00 105.00
42,000.00 420.00
65,000.00 6,500.00
75,000.00 750.00
80,000.00 400.00
Jumlah 49,075.00
Dibulatkan 49,000.00
Rp. 66,600.00 66,600.00
Rp. 42,000.00 420.00
Rp. 65,000.00 6,500.00
Rp. 75,000.00 750.00
Rp. 80,000.00 400.00
74,670.00

Rp. 397,800.00 397,800.00


Rp. 42,000.00 1,260.00
Rp. 65,000.00 19,500.00
Rp. 75,000.00 2,250.00
Rp. 80,000.00 120.00
Jumlah 420,930.00
Dibulatkan 420,900.00
Rp. 1,250,000.00 1,250,000.00
Rp. 4,000,000.00 90,000.00
Rp. 50,000.00 150,000.00
Rp. 40,000.00 60,000.00
Rp. 60,000.00 30,000.00
Rp. 55,000.00 9,166.67
Rp. 25,000.00 6,250.00
Jumlah 1,595,416.67
Dibulatkan 1,595,400.00
1 UNIT SEPTICTANK 7.3 X 2.3 d : 2.10 ( KAPASITAS ± 3 M3 ) PRESENTASI ( TYPE 2 )
Galian tanah 64.59 m³ 45,000.00 2,906,550.00
Urugan Kembali 21.53 m³ 15,187.50 326,986.88
Perataan tanah sisa galian 43.06 m³ Rp. 14,062.50 605,531.25
Pasir urug 5 cm 0.91 m³ Rp. 355,575.00 323,573.25
Lantai kerja 5 cm 0.91 m³ Rp. 862,334.00 784,723.94
Beton 1:2:3 sloof S1 20 x 25 1.42 m³ Rp. 999,200.00 1,418,864.00
Bekisting 14.20 m² Rp. 68,315.00 970,073.00
Besi polos 220.93 kg Rp. 13,070.00 2,887,555.10
Beton 1:2:3 sloof S3 15 x 20 0.14 m³ Rp. 999,200.00 139,888.00
Bekisting 1.92 m² Rp. 68,315.00 131,164.80
Besi polos 23.98 kg Rp. 13,070.00 313,418.60
Beton 1:2:3 Plat lantai 10 cm 1.83 m³ Rp. 999,200.00 1,828,536.00
Bekisting - m² Rp. 68,315.00 -
M6 single 18.26 m2 Rp. 45,681.89 834,151.34
Beton 1:2:3 kolom 15x15 0.74 m³ Rp. 999,200.00 739,408.00
Bekisting 9.84 m² Rp. 68,315.00 672,219.60
Besi polos 148.91 kg Rp. 13,070.00 1,946,253.70
Beton 1:2:3 balok B1 20 x 30 1.70 m³ Rp. 999,200.00 1,698,640.00
Bekisting 17.04 m² Rp. 105,440.00 1,796,697.60
Besi polos / ulir 255.77 kg Rp. 13,070.00 3,342,913.90
Beton 1:2:3 balok B3 15 x 25 0.18 m³ Rp. 999,200.00 179,856.00
Bekisting 2.40 m² Rp. 105,440.00 253,056.00
Besi polos 27.59 kg Rp. 13,070.00 360,601.30
Beton 1:2:3 Plat atas 17,5 cm 2.96 m³ Rp. 999,200.00 2,957,632.00
Bekisting 22.85 m² Rp. 164,211.20 3,752,225.92
Besi polos / ulir 497.28 kg Rp. 13,070.00 6,499,449.60
Beton 1:2:3 Plat miring 6 cm 0.10 m³ Rp. 999,200.00 99,920.00
Bekisting 1.61 m² Rp. 105,440.00 169,758.40
M6 single 1.61 m2 Rp. 45,681.89 73,547.85
Pasangan bata 1:3 60.56 m² Rp. 129,682.80 7,853,590.37
Plesteran + acian dinding 73.88 m² Rp. 61,302.80 4,529,050.86
Acian lantai & plat atas 36.52 m² Rp. 15,600.00 569,712.00
Sponengan 117.60 m' Rp. 7,875.00 926,100.00
Rooster 20 x 20 3.76 m2 Rp. 412,650.00 1,551,564.00
Tutup manhole 50 x 50 beton 1.00 unit Rp. 225,000.00 225,000.00
Tutup manhole 60 x 60 beton 3.00 unit Rp. 250,000.00 750,000.00
Pipa Ø 4' Maspion D 32.10 m' Rp. 56,025.00 1,798,402.50
Pipa Ø 3' Maspion D 5.00 m' Rp. 41,100.00 205,500.00
Pipa Ø 2" Maspion D 7.20 m' Rp. 34,100.00 245,520.00
Ijuk 0.30 m³ Rp. 400,000.00 120,000.00

1 UNIT SEPTICTANK 4.60 X 1.3 ( KAPASITAS ± 4 M3 ) PRESENTASI


Galian tanah 12.96 m³ 45,000.00 583,200.00
Urugan Kembali 4.32 m³ 15,187.50 65,610.00
Perataan tanah sisa galian 8.64 m³ Rp. 14,062.50 121,500.00
Pasir urug 5 cm 0.30 m³ Rp. 355,575.00 106,672.50
Beton 1:2:3 ( sloof - Plat - Kp ) 1.21 m³ Rp. 999,200.00 1,207,033.60
Bekisting 18.60 m² Rp. 68,315.00 1,270,659.00
Besi polos 196.22 kg Rp. 13,070.00 2,564,595.40
Pasangan bata 1:3 16.74 m² Rp. 129,682.80 2,170,890.07
Plesteran + acian 19.24 m² Rp. 61,302.80 1,179,465.87
Pasangan bata kosong 9 cm 0.60 m³ Rp. 541,500.00 324,900.00
Ijuk 0.60 m³ Rp. 400,000.00 240,000.00
Tutup manhole 40 x 40 beton 3.0000 bh Rp. 150,000.00 450,000.00

1 UNIT SEPTICTANK 2.60 X 1.3 ( KAPASITAS ± 2 M3 ) POS JAGA & MUSHOLLA - P3K ( TYPE 3 )
Galian tanah 6.72 m³ 45,000.00 302,400.00
Urugan Kembali 2.24 m³ 15,187.50 34,020.00
Perataan tanah sisa galian 4.48 m³ Rp. 14,062.50 63,000.00
Pasir urug 5 cm 0.17 m³ Rp. 355,575.00 60,447.75
Beton 1:2:3 ( sloof - Plat - Kp ) 0.80 m³ Rp. 999,200.00 799,360.00
Bekisting 13.60 m² Rp. 68,315.00 929,084.00
Besi polos 141.62 kg Rp. 13,070.00 1,850,973.40
Pasangan bata 1:3 11.44 m² Rp. 129,682.80 1,483,571.23
Plesteran + acian 13.94 m² Rp. 61,302.80 854,561.03
Pasangan bata kosong 9 cm 0.34 m³ Rp. 541,500.00 184,110.00
Ijuk 0.34 m³ Rp. 400,000.00 136,000.00
Tutup manhole 40 x 40 beton 3.00 bh Rp. 150,000.00 450,000.00

1 UNIT PERESAPAN Ø 100 h = 2 m


Galian Tanah 2.26 m³ 45,000.00 101,828.57
Buangan Tanah galian 2.26 m³ 18,000.00 40,731.43
Pasir urug 10 cm 0.05 m³ Rp. 355,575.00 17,880.34
Buis Beton Ø100 2.00 bh Rp. 325,000.00 650,000.00
Upah pasang buis 2.00 bh Rp. 85,000.00 170,000.00
Kerikil 20 cm 0.10 m³ Rp. 277,575.00 27,916.11
Ijuk 5 cm 0.03 m³ Rp. 400,000.00 10,057.14
Plat Beton Tutup Peresapan 0.08 m³ Rp. 999,200.00 78,508.57
BesiTutup Peresapan 7.40 kg Rp. 13,070.00 96,675.95
###
###

7,147,527.41

1,193,598.12
Pekerjaan Persiapan
Harga
Pekerjaan satuan
(Rp.)
Direksikit m2 53.000,-
Bouwplank m1 32.000,-
Pekerjaan Pemagaran m1 33.000,-

Pekerjaan Galian dan Pondasi


Harga
Pekerjaan satuan
(Rp.)
Galian Tanah Pondasi m3 80.500,-
Pasang batu kali m3 93.000,-
Urungan Tanah leveling lantai m3 49.000,-
Lantai Kerja m2 18.000,-

Pekerjaan Beton Bertulang


Harga
Pekerjaan satuan
(Rp.)
Beton Sloof m1 52.000,-
Beton Bertulang kolom Praktis m1 42.000,-
Beton Bertulang Ring Balok m1 49.000,-
Beton Balok Dak m1 71.000,-
Beton Plat Dak m2 60.000,-

Pekerjaan Pasangan Bata


Harga
Pekerjaan satuan
(Rp.)
Pasang Bata m2 90.000,-
Pekerjaan Plester+ Aci m2 65.000,-
Sekonengan m1 55.000,-
Sudutan m1 55.000,-
Tali Air m1 55.000,-

Pekerjaan Kusen
Harga
Pekerjaan satuan
(Rp.)
Pasang Kusen Pintu unit 110.000,-
Pasang Daun Pintu Panel unit 150.000,-
Pasang Kusen Jendela unit 75.000,-
Pasang Daun Jendela unit 77.000,-

Pekerjaan Rangka Atap


Harga
Pekerjaan satuan
(Rp.)
Pasang atap ( termasuk pas Kuda2, m2 98.000,-
usuk ,reng)
Kerpus m1 80.000,-
Listplank m1 41.000,-
pekerjaan pasang talang m1 45.000,-

Pekerjaan Pasang Plafond


Harga
Pekerjaan satuan
(Rp.)
Pekerjaan pasang Plapon gypsum m2 34.000,-
Pasang List Plapon gypsum m1 10.000,-

Pekerjaan Pasangan Keramik


Harga
satuan
Pekerjaan (Rp.)
Pasang Keramik Lantai 30 × 30 m2 30.000,-
Pasang Keramik Lantai 40 × 40 m2 31.000,-
Pasang Keramik Lantai 60 × 60 m2 37.000,-
Pasang Keramik Lantai 80 × 80 m2 45.000,-
Pasang Keramik Lantai 100 × 100 m2 52.000,-
Pasang Keramik Lantai KM m2 30.000,-
Pasang Keramik Dinding m2 62.000,-
Pasang Keramik Plin m1 20.500,-

Pekerjaan Pasangan Listrik


Harga
Pekerjaan satuan
(Rp.)
Stop Kontak TITIK 75.000,-
Fiting lampu + saklar TITIK 75.000,-

Pekerjaan Sanitasi
Harga
Pekerjaan satuan
(Rp.)
Pasang Closet Duduk unit 175.000,-
Pasang Closet Jongkok unit 100.000,-
Pasang Wall Shower unit 55.000,-
Pasang Wastafel unit 160.000,-
Pasang Floordrain unit 25.000,-
Pasang Kran unit 15.000,-
Pasang Bath unit 890.000,-
Pemipaan Air Bersih m1 20.500,-
Pemipaan Air Kotor m1 22.000,-
Bak Kontrol unit 175.500,-

Pekerjaan Pengecatan
Harga
Pekerjaan satuan
(Rp.)
Cat Dinding m2 10.500,-
Cat duco kusen (berikut material) m1 90.000,-
Cat duco daun jendela (berikut m1 90.000,-
material)
Cat duco daun pintu panel (berikut pintu 900.000,-
material)
Cat duco ram/list jendela (berikut m1 40.000,-
material)

Pekerjaan Pembongkaran
Harga
Pekerjaan satuan
(Rp.)
Bongkaran Atap m2 37.500,-
Bongkaran Dinding m2 22.000,-
Pembersihan bongkaran m2 18.000,-

Harga Jasa Borongan Per Meter :


Galian tanah : Rp 80.000/m3
Pondasi beton
Pasang batu belah : Rp :140.000/m3
slop 15/20 Rp
30.000/m
Pasang kolom
beton ring10/10/ : Rp : 30.000/m
10/10/ Rp
30.000/m
Pasang batu bata : Rp 35.000/m2
Plesteran : Rp 30.000/m2
Acian : Rp
Pasang 25.000/m2
keramik lantai : Rp
50.000/m2
Pasang keramik dinding : Rp
55.000/m2
Cat dinding : Rp 20.000/m2
Instalasi listrik : Rp 65.000/m2
No. Uraian Pekerjaan Bahan/T.Kerja
1 1 M2 Genteng Kodok Genteng Kodok
Upah

2 1 M' Nok Genteng Nok genteng


Pasir
PC
Upah

3 1 M' Lisplank 3/30 lisplank 3/30 bkr


Paku
Upah

4 Atap metal galvalum t=0.50 ex. Alspan 68 / M2


Atap metal galvalum t=0.50 ex. Alspan 68
Screw
Ongkos Pasang Atap

5 Nok atap galvalume t=0.50 ex. Alspan / M1


Nok atap galvalume t=0.50 ex. Alspan
Screw
Ongkos Pasang nok

6 Listplank / M2
Galvalum ex. Alspan 68
Ongkos Pasang listplank
Rangka
Cat rangka

7 Talang / M1
Zinczlume plat sheet t=0.40
Ongkos Pasang talang
Rangka siku
Cat rangka

8 Flashing / M1
Zinczlume plat sheet t=0.40
Ongkos Pasang

9 Penutup atap transparant / M1


Penutup atap transparant
Ongkos pasang atap
Tralis di bawah atap transparant
Hollow 2x4
Besi
Cat
Ongkos pasang tralis diatas

10 Insulasi Atap Air-Cell ex. Retroshield


Kingspan Air-Cell Retroshield Bubble
Isolasi Kingspan Tape WA 006
Ongkos pasang

11 Insulasi Atap Air-Cell ex. Retroshield


Kingspan Air-Cell Retroshield Bubble
Isolasi Kingspan Tape WA 006
Ongkos pasang

12 Atap Spandex 0,50 G680


Upah
Bongkaran

13 Listplank Spandex 0,40 G680


Upah
Bongkaran

14 Cladding Spandex 0,40 G680


Upah
Bongkaran
Sat.Harga Harga Sat
Analisa Sat Total Harga
Bahan/T.Kerja Pekerjaan
25.0000 bh Rp. 6,000.00 150,000.00
1.0000 m2 Rp. 6,500.00 6,500.00 156,500.00

3.5000 bh Rp. 15,000.00 52,500.00


0.0600 m3 Rp. 370,000.00 22,200.00
0.3500 zk Rp. 54,000.00 18,900.00
1.0000 m' Rp. 15,000.00 15,000.00 108,600.00

0.0095 m3 Rp. 12,000,000.00 113,400.00


0.0100 kg Rp. 12,000.00 120.00
1.0000 m' Rp. 15,000.00 15,000.00 128,520.00

1.0500 m2 99,075.63 104,029.41


4.0000 bh 1,620.00 6,480.00
1.0000 m2 17,500.00 17,500.00
128,009.41

1.0500 m1 67,371.43 70,740.00


4.0000 bh 1,620.00 6,480.00
1.0000 m1 12,000.00 12,000.00
89,220.00

1.0000 m2 80,168.07 80,168.07


1.0000 m2 18,000.00 18,000.00
12.0750 kg 0.00
1.2840 m2 27,000.00 0.00
98,168.07

1.0800 m1 54,514.29 58,875.43


1.0000 m1 18,000.00 18,000.00
8.9985 kg 16,188.00 0.00
0.8988 kg 27,000.00 0.00
76,875.43

0.7000 m1 54,514.29 38,160.00


1.0000 m1 18,000.00 18,000.00
56,160.00

1.0000 m1 199,800.00 199,800.00


1.0000 m1 21,825.00 21,825.00

0.6667 m1 37,172.63 24,781.75


1.2340 kg 18,137.68 22,381.90
0.0933 m2 65,610.00 6,123.60
1.0000 m1 43,650.00 43,650.00
318,562.25

1.1000 m2 151,200.00 166,320.00


1.1760 m' 7,776.00 9,144.58
1.0000 m2 25,462.50 25,462.50
200,927.08

1.1000 m2 99,792.00 109,771.20


1.1760 m' 7,776.00 9,144.58
1.0000 m2 25,462.50 25,462.50
144,378.28

1.10 m2 Rp 92,976.27 102,273.90


1.00 m2 Rp 11,250.00 11,250.00
1.00 m2 Rp 1,000.00 1,000.00
114,523.90

1.10 m2 Rp 75,659.53 83,225.48


1.00 m2 Rp 11,250.00 11,250.00
1.00 m2 Rp 1,000.00 1,000.00
95,475.48

1.15 m2 Rp 75,659.53 87,008.45


1.00 m2 Rp 11,250.00 11,250.00
1.00 m2 Rp 1,000.00 1,000.00
99,258.45
No. Uraian Pekerjaan Bahan/T.Kerja Analisa Sat

1 1 M2 Pengecatan Tembok Baru Setara ICI Plamir tembok 0.100 Kg


Cat dasar 0.100 Kg
Cat penutup 2x setara ICI 0.260 Kg
Pekerja 0.020 Oh
Tukang cat 0.063 Oh
Kepala tukang 0.006 Oh
Mandor 0.003 Oh

2 1 M2 Pengecatan Tembok Lama Setara ICI Cat dasar 0.120 Kg


Cat penutup 2x setara ICI 0.180 Kg
Pekerja 0.028 Oh
Tukang cat 0.042 Oh
Kepala tukang 0.004 Oh
Mandor 0.003 Oh

1 M2 Pengecatan Tembok Baru Setara Vinilex (3 x


3 Plamir tembok 0.100 Kg
laburan)
Cat dasar 0.100 Kg
Cat penutup 3x setara vinilex 0.390 Kg
Pekerja 0.030 Oh
Tukang cat 0.095 Oh
Kepala tukang 0.010 Oh
Mandor 0.004 Oh

4 Cat eksterior ex. Mowilex Weathershield / M2 Cat eksterior ex. Mowilex Weathershield 0.010 pail
Cat dasar eksterior ex. Mowilex 0.007 pail
Amplas + material bantu 1.000 m2
Ongkos tukang 1.000 m2

5 Cat interior ex. Mowilex / M2 Cat interior ex. Mowilex 0.010 pail
Cat dasar interior ex. Mowilex 0.007 pail
Amplas + material bantu 1.000 m2
Ongkos tukang 1.000 m2
Sat.Harga Harga Sat
Total Harga
Bahan/T.Kerja Pekerjaan

25,000.00 2,500.00
30,000.00 3,000.00
75,000.00 19,500.00
42,000.00 840.00
65,000.00 4,095.00
75,000.00 472.50
80,000.00 200.00
Jumlah 30,607.50
Dibulatkan 30,600.00
30,000.00 3,600.00
75,000.00 13,500.00
42,000.00 1,176.00
65,000.00 2,730.00
75,000.00 315.00
80,000.00 200.00
Jumlah 21,521.00
Dibulatkan 21,500.00
25,000.00 2,500.00
30,000.00 3,000.00
25,000.00 9,750.00
42,000.00 1,260.00
65,000.00 6,142.50
75,000.00 712.50
80,000.00 304.00
Jumlah 23,669.00
Dibulatkan 23,600.00
1,877,904.00 18,779.04
941,868.00 6,279.12
3,240.00 3,240.00
5,000.00 5,000.00
Jumlah 33,602.16
Dibulatkan 33,600.00
1,116,828.00 11,168.28
941,868.00 6,279.12
3,240.00 3,240.00
5,000.00 5,000.00
Jumlah 25,687.40
Dibulatkan 25,600.00
No. Uraian Pekerjaan Bahan/T.Kerja Analisa Sat

1 1 m' Pipa PVC class AW 1/2" Pipa PVC class AW 1/2" 0.30 Btg
Sambungan, Fitting, Lem 1 ls
Alat bantu 1 ls
Upah pasang 1 m'

2 1 m' Pipa PVC class AW 3/4" Pipa PVC class AW 3/4" 0.30 Btg
Sambungan, Fitting, Lem 1 ls
Alat bantu 1 ls
Upah pasang 1 m'

3 1 m' Pipa PVC class AW 1" Pipa PVC class AW 1" 0.30 Btg
Sambungan, Fitting, Lem 1 ls
Alat bantu 1 ls
Upah pasang 1 m'

4 1 m' Pipa PVC class AW 1-1/4" Pipa PVC class AW 1-1/4" 0.30 Btg
Sambungan, Fitting, Lem 1 ls
Alat bantu 1 ls
Upah pasang 1 m'

5 1 m' Pipa PVC class AW 1-1/2" Pipa PVC class AW 1-1/2" 0.30 Btg
Sambungan, Fitting, Lem 1 ls
Alat bantu 1 ls
Upah pasang 1 m'

6 1 m' Pipa PVC class AW 2" Pipa PVC class AW 2" 0.30 Btg
Sambungan, Fitting, Lem 1 ls
Alat bantu 1 ls
Upah pasang 1 m'

7 1 m' Pipa PVC class AW 2-1/2" Pipa PVC class AW 2" 0.30 Btg
Sambungan, Fitting, Lem 1 ls
Alat bantu 1 ls
Upah pasang 1 m'

8 1 m' Pipa PVC class AW 3" Pipa PVC class AW 3" 0.30 Btg
Sambungan, Fitting, Lem 1 ls
Alat bantu 1 ls
Upah pasang 1 m'

9 1 m' Pipa PVC class AW 4" Pipa PVC class AW 3" 0.30 Btg
Sambungan, Fitting, Lem 1 ls
Alat bantu 1 ls
Upah pasang 1 m'

4 1 M' PIPA PVC MASPION AW 1/2" Pipa 1.0500 M'


Alat bantu 0.0000 ls
Lem 0.1000 m'
Aksesories / fitting 0.2500 ls
Upah 1.0000 m'

5 1 M' PIPA PVC MASPION AW 3/4" Pipa 1.0500 M'


Lem 0.1000 m'
Aksesories / fitting 0.2500 ls
Upah 1.0000 m'

6 1 M' PIPA PVC MASPION AW 1" Pipa 1.0500 M'


Lem 0.1000 m'
Aksesories / fitting 0.2500 ls
Upah 1.0000 m'

7 1 M' PIPA PVC MASPION AW 1 1/2" Pipa 1.0500 M'


Lem 0.1000 m'
Aksesories / fitting 0.2500 ls
Upah 1.0000 m'

8 1 M' PIPA PVC MASPION AW 2" Pipa 1.0500 M'


Lem 0.1000 m'
Aksesories / fitting 0.2500 ls
Upah 1.0000 m'

9 1 M' PIPA PVC MASPION D 2" Pipa 1.0500 M'


Lem 0.1000 m'
Aksesories / fitting 0.2500 ls
Upah 1.0000 m'

10 1 Ttk PIPA PVC MASPION D 2" + IJUK Pipa 0.3500 M'


Ijuk 0.0008 m3
Upah 0.3500 m'

11 1 M' PIPA PVC MASPION D 3" Pipa 1.0500 M'


Lem 0.1000 m'
Aksesories / fitting 0.2500 ls
Upah 1.0000 m'

12 1 M' PIPA PVC MASPION D 4" Pipa 1.0500 M'


Lem 0.1000 m'
Aksesories / fitting 0.2500 ls
Upah 1.0000 m'

13 1 M' PIPA PVC MASPION D 5" Pipa 1.0500 M'


Lem 0.1000 m'
Aksesories / fitting 0.2500 ls
Upah 1.0000 m'
Sat.Harga Harga Sat
Total Harga
Bahan/T.Kerja Pekerjaan

21,100.00 6,330.00
2,216.00 2,216.00
317.00 317.00
8,000.00 8,000.00
Jumlah 16,863.00
Dibulatkan 16,800.00
28,800.00 8,640.00
3,020.00 3,020.00
432.00 432.00
12,000.00 12,000.00
Jumlah 24,092.00
Dibulatkan 24,000.00
39,300.00 11,790.00
4,130.00 4,130.00
590.00 590.00
16,000.00 16,000.00
Jumlah 32,510.00
Dibulatkan 32,500.00
58,900.00 17,670.00
6,190.00 6,190.00
884.00 884.00
20,000.00 20,000.00
Jumlah 44,744.00
Dibulatkan 44,700.00
67,600.00 20,280.00
7,100.00 7,100.00
1,010.00 1,010.00
24,000.00 24,000.00
Jumlah 52,390.00
Dibulatkan 52,300.00
86500.00 25,950.00
9080.00 9,080.00
1300.00 1,300.00
32000.00 32,000.00
Jumlah 68,330.00
Dibulatkan 68,300.00
126200.00 37,860.00
13250.00 13,250.00
1890.00 1,890.00
40000.00 40,000.00
Jumlah 93,000.00
Dibulatkan 93,000.00
177800.00 53,340.00
18670.00 18,670.00
2670.00 2,670.00
48000.00 48,000.00
Jumlah 122,680.00
Dibulatkan 122,600.00
294600.00 88,380.00
30930.00 30,930.00
4420.00 4,420.00
64000.00 64,000.00
Jumlah 187,730.00
Dibulatkan 187,700.00

Rp. 5,375.00 5,643.75


Rp. 6,000.00 -
93,023.10 9,302.31
Rp. 6,000.00 1,500.00
Rp. 6,500.00 6,500.00 22,946.06

Rp. 6,625.00 6,956.25


93,023.10 9,302.31
Rp. 6,625.00 1,656.25
Rp. 6,500.00 6,500.00 24,414.81

Rp. 8,250.00 8,662.50


93,023.10 9,302.31
Rp. 8,250.00 2,062.50
Rp. 6,500.00 6,500.00 26,527.31

Rp. 15,125.00 15,881.25


93,023.10 9,302.31
Rp. 15,125.00 3,781.25
Rp. 6,500.00 6,500.00 35,464.81

Rp. 22,500.00 23,625.00


93,023.10 9,302.31
Rp. 22,500.00 5,625.00
Rp. 6,500.00 6,500.00 45,052.31

Rp. 10,750.00 11,287.50


93,023.10 9,302.31
Rp. 10,750.00 2,687.50
Rp. 7,500.00 7,500.00 30,777.31

Rp. 10,750.00 3,762.50


Rp. 400,000.00 302.23
Rp. 7,500.00 2,625.00 6,689.73

Rp. 23,125.00 24,281.25


93,023.10 9,302.31
Rp. 23,125.00 5,781.25
Rp. 7,500.00 7,500.00 46,864.81

Rp. 32,500.00 34,125.00


93,023.10 9,302.31
Rp. 32,500.00 8,125.00
Rp. 7,500.00 7,500.00 59,052.31

Rp. 55,000.00 57,750.00


93,023.10 9,302.31
Rp. 55,000.00 13,750.00
Rp. 10,000.00 10,000.00 90,802.31
No. Uraian Pekerjaan Bahan/T.Kerja Analisa Sat

1 Membersihkan lapangan & perataan per 1 M2 Pekerja 0.1000 Oh


Mandor 0.0500 Oh

2 Uitzet dan Bouwplank /M1 Usuk 5/7 0.0007 m3


Papan meranti 3/20 0.0013 m3
Paku 0.0100 kg
Ongkos bouwplank 1.0000 m1

3 Air kerja (menggunakan sumur existing) / Ls Biaya pasang PDAM 1.0000 ls


Biaya abunemen PDAM 8.0000 bln
Selang, dll 1.0000 ls
Torn air 1.0000 unit

4 Listrik kerja / Ls Pindah KWH meter 1.0000 ls


Lampu, kabel, dll 1.0000 ls
Rekening bulanan 8.0000 bln

5 Galian tanah / M3 Ongkos gali tanah 1.0000 m3

6 Urugan tanah kembali / M3 Ongkos urugan kembali 1.0000 m3

7 Pemadatan Tanah Pondasi/m2 (dgn Mesin


Stamper) Tk.Gali 0.0275 ht
Kep.Tukang 0.0055 ht
Mandor 0.0018 ht
Mesin Stamper 0.0200 bh

8 Urugan tanah / M3 Tanah urug 1.3000 m3


Ongkos urug tanah 1.0000 m3

9 Urug pasir bawah pondasi dan lantai / M3 Pasir muntilan 1.3000 m3


Ongkos urug pasir bawah pondasi / lantai 1.0000 m3

10 Aanstamping / M3 Batu belah 1.3500 m3


Ongkos Aanstamping 1.0000 m3

11 Pondasi batu kali 1 : 6 / M3 Batu belah 1.4000 m3


Semen portland 3.4000 zak
Pasir muntilan 0.5440 m3
Ongkos pondasi batu kali 1.0000 m3

12 Pasangan batu bata 1:3 / m2 Batu bata 72.0000 bh


Semen portland 0.5325 zak
Pasir muntilan 0.0570 m3
Steiger 1.0000 ls
Ongkos pasang dinding bata lt. Dasar 1.0000 m2

13 Plesteran 1:3 Lt. Dasar / M2 Semen portland 0.3240 zak


Pasir muntilan 0.0280 m3
Steiger 1.0000 ls
Ongkos plesteran lt. Dasar 1.0000 m2

14 Acian bata Lt. Dasar / M2 Semen portland 0.0600 zak


Steiger 1.0000 ls
Ongkos acian bata lantai Dasar 1.0000 m2

15 Sponengan / M1 Semen portland 0.0125 zak


Steiger 1.0000 ls
Ongkos sponengan sudut lantai Dasar 1.0000 m'

16 Beton Lantai kerja 1:3:5 / M3 Semen portland 5.6700 zak


Pasir beton 0.5400 m3
Split 1/2 0.9100 m3
Ongkos cor beton lantai kerja 1.0000 m3

17 Beton Ready mix K 300 lantai Dasar / M3 Beton readymix K 300 1.0000 m3
Ongkos cor beton readymix lantai Dasar 1.0000 m3

18 1 m2 Rabat Beton Expose + Acian Beton 1:2:3 8 cm 0.0800 m3


Acian 1.0000 m2
Tali air 1.0000 m'

19 Beton Site Mix u/ lantai Dasar / M3 Semen portland 8.0000 zak


Pasir beton 0.5400 m3
Split 1/2 0.8200 m3
Ongkos cor beton lantai Dasar 1.0000 m3

20 Kolom praktis lantai dasar / M3 Beton site mix lantai dasar 1.0000 m3
Bekisting beton lantai dasar 13.3333 m2
Besi beton polos lantai dasar 164.0711 kg

21 Beton 1:2:3 SM Semen 6.8000 Zak


Kris 0.8200 M3
Pasir Muntilan 0.5400 M3
Upah lt.1 1.0000 M3

Upah rata2 1.2000 M2

22 1 M3 BETON PRAKTIS 1:2:3 Beton 1:2:3 SM 1.0000 M3


Besi beton 150.0000 kg
Bekesting 13.3333 M2

22 Beton Ready mix K 300 lantai Atap / M3 Beton readymix K 300 1.0000 m3
Plat Dak Beton Pompa readymix 1.0000 m3
Ongkos cor beton readymix lantai Atap 1.0000 m3

23 1 M2 Cat Dinding Luar Cat Tembok 0.1540 Kg


Mowilex Weathercoat ( Ulang ) Wallsealer 0.0499 Kg
Ambril 0.0600 Lb
Upah lt. 1 1.0000 M2
Upah rata2 1.2000 M2
23 1 M2 Cat Dinding Dalam Cat Tembok 0.1540 Kg
Mowilex ( Ulang ) Wallsealer 0.0499 Kg
Ambril 0.0600 Lb
Upah lt. 1 1.0000 M2
Upah rata2 1.2000 M2

24 1 M2 Keramik lantai 60 x 60 Keramik 1.1000 M2


AM 50 nat 0.3330 Kg
Semen 0.1632 Zak
Pasir muntilan 0.0194 M3
Upah lt. 1 1.0000 M2
Upah lt.2 1.2000 M2

25 1 M2 Keramik lantai 30 x 30 Keramik 1.1000 M2


AM 50 nat 0.333 Kg
Semen 0.1632 Zak
Pasir muntilan 0.0194 M3
Upah lt. 1 1.0000 M2
Upah lt.2 1.2 M2

25 1 M2 Keramik Lantai 20x20 Keramik 1.1000 M2


26 Roxy Black Asia Tile AM 50 nat 0.333 Kg
Semen 0.1632 Zak
Pasir muntilan 0.0194 M3
Upah lt. 1 1.0000 M2
Upah lt.2 1.4 M2
27 Pintu Kusen Alumunium Type P1 /m'
28 Pintu Kusen Alumunium Type P2 /m'
29 Pintu+jJendela Kusen Alumunium Type PJ1 /m'
30 Bouven Type BV1
31 Carport Pas.Paving Blok T.6cm/m2 Galian Tanah 0.250 m3
Pemadatan Tanah dgn Stamper 1.000 m2
Urugan Sirtu T.20cm 0.200 m3
Pemadatan Sirtu dgn Stamper 1.000 m2
Urugan Pasir Extra Beton T.10cm 0.150 m3
Paving Blok T.6cm 1.100 m2
Pasir Pengisi Pasir Urug 0.015 m3
Pemadatan Paving dgn Stamper 1.000 m2

`` 32 Atap metal galvalum t=0.50 ex. Alspan 68 / M2 Atap metal galvalum t=0.50 ex. Alspan 68 1.0500 m2
Screw 4.0000 bh
`` Ongkos Pasang Atap 1.0000 m2

33 1 m² Pasang Kuda-kuda Baja ringan + reng untuk Bahan


`` atap genteng biasa/metal C-75 , 0.8 1.4880 m'
C-75 , 0.6 2.2320 m'
`` Baut (screw driver) 38.0000 bh
Dynabolt 1.6000 bh
`` Reng 5.4000 m'
Talang jurai 0.1240 m'
``
Tenaga
`` Pekerja 0.2000 Oh
Tukang Besi 0.4500 Oh
Kepala Tukang 0.0100 Oh
`` Mandor 0.0500 Oh

`` 34 1 M2 Pasang Atap Genteng Metal Genteng metal 1.0000 M2


Paku biasa 2" - 5" 0.2000 Kg
Pekerja 0.2000 Oh
`` Tukang Kayu 0.1000 Oh
Kepala Tukang 0.0100 Oh
Mandor 0.0010 Oh
``
35 1 M2 Langit-langit GRC t = 4 mm + Rangka Besi Hollow 4/4 Zincromate 0.4150 btg
Hollow Hollow 2/4 Zincromate 0.1500 btg
`` GRC (120 x 240 x 4) mm 0.3640 Lbr
Paku GRC 0.1100 Kg
Ramset/Dina Bolt 4.0000 buah
`` Cotton Plaster 0.0720 buah
Compoun 0.1250 Zak
Pekerja 0.1000 Oh
`` Tukang Kayu 0.0500 Oh
Kepala Tukang 0.0050 Oh
Mandor 0.005 Oh

36 Memasang 1 buah closet duduk Closet duduk standar TOTO 1 buah


Perlengkapan (6%) 0.0600 lot
Pekerja 3.3 Oh
Tukang batu 1.1000 Oh
Kepala Tukang 0.011 Oh
Mandor 0.1600 Oh

37 Memasang 1 buah Floor drain Floor drain 1.0000 bh


Pekerja 0.01 Oh
Tukang batu 0.1000 Oh
Kepala Tukang 0.01 Oh
Mandor 0.0050 Oh

38 Kran dapur exs. ONDA


39 1 M2 Keramik Dinding 20x25 Keramik 1.1000 M2
Metro Basic Asia Tile AM 50 nat 0.333 Kg
Semen 0.1632 Zak
Pasir muntilan 0.0194 M3
Upah lt. 1 1.0000 M2
Upah lt.2 1.2 M2

40 1 M3 Tangga Beton Tulang (90 kg besi+bekisting) Kayu papan terentang 0.25 M3


Paku Biasa 2" - 5" 3.0000 Kg
Minyak Bekisting 1.2 Ltr
Besi Beton 90.0000 Kg
Kawat Beton 3 Kg
Semen Portland 6.8000 Kg
Pasir Beton 0.52 M3
Koral Beton 2/3 0.7800 M3
Kayu Balok Terentang 0.105 M3
Kayu 5/7 14.0000 Btg
Pekerja 5.6 Oh
Tukang Batu 0.3500 Oh
Tukang Kayu 2.3 Oh
Tukang Besi 1.4000 Oh
Kepala Tukang 0.405 Oh
Mandor 0.2020 Oh

1 M3 Membuat Plat Lantai Tb. 10 Cm Beton


41 Kayu Terentang 0.4 M3
Bertulang ( 90 Kg Besi + Bekisting )
Paku Biasa 2" - 5" 4.0000 Kg
Minyak Bekisting 2 Ltr
Besi Beton Polos 90.0000 Kg
Kawat Beton 3 Kg
Kayu Balok Terentang 0.1050 M3
Plywood Tebal 9 mm 3.5 Lbr
Dolken kayu Galam o - 8-10/4 m 60.0000 Btg
Semen Portland 323 Kg
Pasir Beton 0.5200 M3
Koral Beton 2/3 0.78 M3
Pekerja 5.2000 Oh
Tukang Batu 0.35 Oh
Tukang Kayu 3.3000 Oh
Kepala Tukang 0.365 Oh
Mandor 1.0600 Oh

42 1 M2 Plesteran 1: 5 Semen 0.11 Zak


Pasir muntilan 0.02 M3
Upah 1.15 M2
43 1 M' Railing

44 1 M' Pipa PVC Ø 4" (AW) Pipa pvc Ø 4" 1.2 m'
Pekerja 0.081 org
Tukang batu 0.135 org
Kepala Tukang 0.0135 org
Mandor 0.0041 org
Perlengkapan 35 % harga pipa 0.35 lot
Jumlah
Sat.Harga Harga Sat
Total Harga
Bahan/T.Kerja Pekerjaan

Rp. 71,500 7,150.00


Rp. 88,000 4,400.00
11,550.00
Rp. 4,098,600 2,732.40
Rp. 2,592,000 3,456.00
Rp. 12,204 122.04
Rp. 14,841 14,841.00
21,151.44
Rp. 1,545,000 1,545,000.00
Rp. 633,000 5,064,000.00
Rp. 2,234,125 2,234,124.97
Rp. 2,437,500 2,437,500.00
11,280,624.97
Rp. 1,582,500 1,582,500.00
Rp. 1,846,250 1,846,250.00
Rp. 633,000 5,064,000.00
8,492,750.00
Rp. 65,000 65,000.00
65,000.00
Rp. 17,460 17,460.00
17,460.00

Rp. 55,000 1,512.50


Rp. 60,000 330.00
Rp. 55,000 100.83
Rp. 100,000 2,000.00
3,943.33
Rp. 81,000 105,300.00
Rp. 17,460 17,460.00
122,760.00
Rp. 310,500 403,650.00
Rp. 17,460 17,460.00
421,110.00
Rp. 151,200 204,120.00
Rp. 43,650 43,650.00
247,770.00
Rp. 151,200 211,680.00
Rp. 56,983 193,741.71
Rp. 310,500 168,912.00
Rp. 69,840 69,840.00
644,173.71
Rp. 853 61,430.40
Rp. 56,983 30,343.37
Rp. 310,500 17,698.50
Rp. 9,720 9,720.00
Rp. 17,460 17,460.00
136,652.27
Rp. 56,983 18,462.45
Rp. 310,500 8,694.00
Rp. 9,720 9,720.00
Rp. 14,841 14,841.00
51,717.45
Rp. 56,983 3,418.97
Rp. 9,720 9,720.00
Rp. 13,095 13,095.00
26,233.97
Rp. 56,983 712.29
Rp. 9,720 9,720.00
Rp. 7,857 7,857.00
18,289.29
Rp. 56,983 323,092.80
Rp. 310,500 167,670.00
Rp. 280,800 255,528.00
Rp. 96,030 96,030.00
842,320.80
Rp. 891,000 891,000.00
Rp. 87,300 87,300.00
978,300.00
Rp. 1,069,000 85,520.00
Rp. 26,460 26,460.00
Rp. 13,860 13,860.00
125,840.00
Rp. 56,983 455,862.86
Rp. 310,500 167,670.00
Rp. 280,800 230,256.00
Rp. 130,950 130,950.00
984,738.86
Rp. 984,739 984,738.86
Rp. 135,682 1,809,087.27
Rp. 12,596 2,066,620.96
4,860,447.09
Rp. 54,000 367,200.00
Rp. 250,000 205,000.00
Rp. 370,000 199,800.00
Rp. 297,000 297,000.00
1,069,000.00
Rp. 297,000 356,400.00
1,128,400.00
Rp. 1,069,000.00 1,069,000.00
Rp. 15,260.00 2,289,000.00
Rp. 54,915.00 732,199.82
4,090,199.82
Rp. 891,000 891,000.00
Rp. 75,600 75,600.00
Rp. 89,483 89,482.50
1,056,082.50

Rp 70,565.20 10,867.04
Rp 27,750.00 1,384.73
Rp 3,000.00 180.00
Rp 7,560.00 7,560.00 19,991.77
Rp 7,560.00 9,072.00 21,503.77
Rp 44,632.00 6,873.33
Rp 27,750.00 1,384.73
Rp 3,000.00 180.00
Rp 7,560.00 7,560.00 15,998.05
Rp 7,560.00 9,072.00 17,510.05

Rp 75,000.00 82,500.00
Rp 14,500.00 4,828.50
Rp 54,000.00 8,812.80
Rp 400,000.00 7,760.00
Rp 43,560.00 43,560.00 147,461.30
Rp 43,560.00 52,272.00 156,173.30

Rp. 75,000.00 82,500.00


Rp. 14,500.00 4,828.50
Rp. 54,000.00 8,812.80
Rp. 400,000.00 7,760.00
Rp. 43,560.00 43,560.00 147,461.30
Rp. 43,560.00 52,272.00 156,173.30

Rp. 55,000.00 60,500.00


Rp. 14,500.00 4,828.50
Rp. 54,000.00 8,812.80
Rp. 400,000.00 7,760.00
Rp. 49,500.00 49,500.00 131,401.30
Rp. 49,500.00 69,300.00 151,201.30

Rp. 26,281.40 6,570.35


Rp. 5,109.33 5,109.33
Rp. 167,666.67 33,533.33
Rp. 7,664.00 7,664.00
Rp. 214,133.33 32,120.00
Rp. 50,000.00 55,000.00
Rp. 145,000.00 2,175.00
Rp. 5,109.33 5,109.33
147,281.35
99,075.63 104,029.41
1,620.00 6,480.00
17,500.00 17,500.00
128,009.41

Rp. 14,166.67 21,080.00


Rp. 12,666.67 28,272.00
Rp. 350.00 13,300.00
Rp. 3,500.00 5,600.00
Rp. 7,000.00 37,800.00
Rp. 48,000.00 5,952.00
a= 112,004.00
Rp. 52,500.00 10,500.00
Rp. 80,000.00 36,000.00
Rp. 95,000.00 950.00
Rp. 100,000.00 5,000.00
b= 52,450.00
a+b = 164,454.00
Rp. 90,021.80 90,021.80
Rp. 24,057.55 4,811.51
Rp. 70,593.60 14,118.72
Rp. 105,890.40 10,589.04
Rp. 112,949.76 1,129.50
Rp. 120,009.12 120.01
120,790.58
Rp. 29,200.00 12,118.00
Rp. 22,600.00 3,390.00
Rp. 67,500.00 24,570.00
Rp. 35,000.00 3,850.00
Rp. 7,200.00 28,800.00
Rp. 15,000.00 1,080.00
Rp. 75,000.00 9,375.00
Rp. 42,000.00 4,200.00
Rp. 65,000.00 3,250.00
Rp. 75,000.00 375.00
Rp. 80,000.00 400.00
91,408.00
Dibulatkan 91,400.00
Rp. 2,775,154.80 2,775,154.80
Rp. 2,775,154.80 166,509.29
Rp. 70,593.60 232,958.88
Rp. 98,831.04 108,714.14
Rp. 112,949.76 1,242.45
Rp. 120,009.12 19,201.46
3,303,781.02
Rp. 66,600.00 66,600.00
Rp. 42,000.00 420.00
Rp. 65,000.00 6,500.00
Rp. 75,000.00 750.00
Rp. 80,000.00 400.00
74,670.00

Rp. 55,000.00 60,500.00


Rp. 14,500.00 4,828.50
Rp. 54,000.00 8,812.80
Rp. 400,000.00 7,760.00
Rp. 61,380.00 61,380.00 143,281.30
Rp. 61,380.00 73,656.00 155,557.30

Rp. 2,850,000.00 712,500.00


Rp. 23,400.00 70,200.00
Rp. - -
Rp. 11,500.00 1,035,000.00
Rp. 11,500.00 34,500.00
Rp. 54,000.00 367,200.00 0.136
Rp. 225,000.00 117,000.00
Rp. 200,000.00 156,000.00
Rp. 2,640,000.00 277,200.00
Rp. 15,000.00 210,000.00
Rp. 55,000.00 308,000.00 0.612 3.4272
Rp. 70,000.00 24,500.00 0.2142
Rp. 70,000.00 161,000.00 1.4076
Rp. 70,000.00 98,000.00 0.8568
Rp. 80,000.00 32,400.00 0.24786
Rp. 85,000.00 17,170.00 0.123624
3,620,670.00
Rp. 2,850,000.00 1,140,000.00
Rp. 23,400.00 93,600.00
Rp. 40,500.00 81,000.00
Rp. 16,500.00 1,485,000.00
Rp. 27,700.00 83,100.00
Rp. 151,100.00 15,865.50
Rp. 151,100.00 528,850.00
Rp. 15,000.00 900,000.00
Rp. 1,200.00 387,600.00
Rp. 225,000.00 117,000.00
Rp. 200,000.00 156,000.00
Rp. 55,000.00 286,000.00
Rp. 70,000.00 24,500.00
Rp. 70,000.00 231,000.00
Rp. 80,000.00 29,200.00
Rp. 85,000.00 90,100.00
5,648,815.50
Rp. 52,000.00 5,834
Rp. 280,000.00 6,160
Rp. 24,046.88 27,654 39,648
450,000.00

Rp. 86,975.00 104,370


Rp. 42,000.00 3,402
Rp. 65,000.00 8,775
Rp. 75,000.00 1,013
Rp. 80,000.00 328
Rp. 104,370.00 36,530
154,417
4
1
2
1
1
1
No. Jenis Pekerjaan P L T

I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi Awal
1 Pembersihan lokasi Awal
2 Buangan sampah pembersihan lokasi
3 Pasang Bouwplank (Luas Tanah) 91.88
Pasang Bouwplank (Rencana bangunan) 96.83

4 Direksi keet / Bedeng 6.00 4.00

II PEKERJAAN TANAH
1 Galian tanah
a Galian tanah pondasi batu kali 254.72 0.58 0.50
b Galian tanah pondasi Foot plat
2 Urugan
a Urugan tanah kembali
b Pemadatan tanah 254.72 0.50
3 Tanah padas
a Urugan tanah padas 432.46 0.60
Pemadatan tanah Padas

III PEKERJAAN PASANGAN


1 Urugan Pasir
a Urugan pasir bawah pondasi (t=5cm) 254.72 0.50 0.05
2 Pasangan Aanstamping 254.72 0.50 0.20
3 Pasangan Pondasi Batu Belah 1:6
4 Pasangan bata ringan t=10cm
a sisi depan 107.78 7.50 78.20
b sisi dalam 146.94 7.50 90.59
5 Plesteran PM t=1cm
a sisi depan
b sisi dalam
6 Acian PM t=3mm
a sisi depan
b sisi dalam
7 Sponeng
a sisi depan 334.00
b sisi dalam 293.00

IV PEKERJAAN BETON
1 Beton Lantai kerja 1:3:5 / m3 25.88 0.06
2 Pondasi Footplat
3 Sloof beton
a sisi depan 107.78 0.15 0.25
b sisi dalam 146.94 0.15 0.25
4 Kolom Footplate
a sisi depan
b sisi dalam
5 Kolom Praktis
a sisi depan
b sisi dalam
6 Rabat Beton
a sisi depan
b sisi dalam
6 Tiebalk 15/15
a sisi depan 137.71 0.15 0.15
b sisi dalam 117.01 0.15 0.15
7 RingBalk 15/20
a sisi depan 137.71 0.15 0.15
b sisi dalam 117.01 0.15 0.15
8 Dak Beton t=12cm
a sisi depan 0.12 145.33
b sisi dalam 0.12 141.33
9 Carport Pas.Paving Blok
10 Tangga Beton
a sisi depan 0.30 0.20 0.85 20.00
Plat Tangga t=10cm 7.20 0.85 0.10
plesteran t=3cm 0.50 0.85 20.00
b sisi dalam 0.30 0.20 0.85 20.00
Plat Tangga t=10cm 7.21 0.85 0.10
plesteran t=3cm 0.50 0.85 20.00

V PEKERJAAN PINTU & JENDELA


1 Kusen Alumunium Type P1 /m'
sisi depan 7.24 -
sisi dalam 7.24 2.0
2 Kusen Alumunium Type P2 /m'
sisi depan 5.20 13.0
sisi dalam 5.20 16.0
3 Kusen Alumunium Type PJ1 /m'
sisi depan 10.47 15.0
sisi dalam 10.47 16.0
4 Bouven Type BV1
sisi depan
sisi dalam
2 kusen lt2
p1 0.92 2.70 1
p2 0.82 2.20 8.0
pj1 0.68 1.33 16.0
0.88 2.70 16.0
Bouven 0.50 0.54 8

3 Daun jendela alumunium


sisi depan
sisi dalam
4 Daun Pintu alumunium
sisi depan

V PEKERJAAN PENGUNCI & KACA


1 Kunci 2x putar terpasang
sisi depan
sisi dalam
2 Engsel pintu terpasang
sisi depan
sisi dalam
3 Engsel jendela terpasang
sisi depan
sisi dalam
4 Hak angin jendela
sisi depan
sisi dalam
6 Kaca riben 5 mm terpasang PJ1 + BV1
sisi depan 15.5
sisi dalam 19.1

VI PEKERJAAN LANTAI
1 Keramik 60x60 cm
a K Tidur sisi depan
Ruang Tamu 3.00 2.62
Dapur 3.00 2.00
teras luar
b K Tidur sisi dalam
teras luar
2 Keramik lantai KM 20 x 20 cm
a sisi depan 1.50 1.50 12
b sisi dalam 1.50 1.50 16
2 Keramik dinding KM 20 x 25 cm h=2m
a sisi depan 6.00 2.05 12
b sisi dalam 6.00 2.05 16

VII PEKERJAAN CAT


1 cat dinding sisi depan 123.77 7.5
2 cat dinding sisi dalam 130.95 7.5

VIII PEKERJAAN ATAP


1 Atap Plafon GRC t = 4 mm + Rangka Besi Hollow -
a sisi depan
sisi luar 32.71 1.05
b sisi dalam
sisi luar 31.93 1.05
2 Rangka Atap -
a sisi depan
b sisi dalam

IX PEKERJAAN LAIN-LAIN
1 Railing Tangga
depan 3.29
1.08
2.90
7.27
dalam 3.57
0.90
2.54
7.01

2 Railing Pagar Lantai 2 dan Penghubung


a sisi depan
b sisi dalam
c sisi tengah

Pipa pvc Ø 4" Air Kotor


Pipa pvc Ø 3" Air Domestik
Pipa pvc Ø 3/4" Air Bersih
Hitungan Sloof 15x25 pjg jml
m3 Cor Beton 4.04
semen 1,208 50 24.17 zak
pasir 3,229 1,400 2.31 m3
kerikil 4,110 1,800 2.28 m3
pekerja 4.04 1.650 2.45 oh
tukang 4.04 0.275 14.70 oh
kepala 4.04 0.030 134.73 oh
mandor 4.04 0.083 48.70 oh
1 Kg Besi
Tul. Pokok 4D-10 107.78 4 12 36 btg
36 7.4 266 kg
Begel 8D-15 107.78 0.15 719 bh
1bh besi=?cm 77 cm
Total Kg Begel 719 0.67 40 btg
4.74 190 kg
Total Besi Beton Sloof 265.86 190.16 456
Bendrat 456 0.1 46
pekerja 456 0.0070 3.19 oh
tukang 456 0.0007 0.32 oh
kepala 456 0.00007 0.03 oh
mandor 456 0.0004 0.18 oh

Bekisting
Luas bekisting 107.8 0.25 2 54
papan 2/20x3m 54 1.7 92
paku 2"-5" 54 0.30 16.2
pekerja 54 0.52 28.1
tukang 54 0.26 14.0
kepala tukang 54 0.026 1.4
mandor 54 0.026 1.4

Kebutuhan m3 sloof 15/25 L=107.8


semen 24 zak
pasir 2.31 m3
kerikil 2.28 m3
Besi Beton D-10 36 btg
Besi Beton D-8 40 btg
Bendrat 46 kg
Papan 2/20 92 lbr
Paku 2"- 5" 16.2 kg
pekerja 31 oh
tukang 29 oh
kepala 136 oh
mandor 50 oh
1m3 Sloof 15/25 107.8
semen 0.22 zak
pasir 0.02 m3
kerikil 0.02 m3
Besi Beton D-10 0.33 btg
Besi Beton D-8 0.37 btg
Bendrat 0.42 kg
Papan 2/20 0.85 lbr
Paku 2"- 5" 0.15 kg
pekerja 0.28 oh
tukang 0.27 oh
kepala 1.26 oh
mandor 0.46 oh

Hitungan Kolom 15x15 pjg jml


m3 Cor Beton 1.00
semen 299 50 5.98 zak
pasir 799 1,600 0.50 m3
kerikil 1,017 1,900 0.54 m3
pekerja 1.00 1.650 0.61 oh
tukang 1.00 0.275 3.64 oh
kepala 1.00 0.030 33.33 oh
mandor 1.00 0.083 12.05 oh
1 Kg Besi
Tul. Pokok 4D-8 1.00 4 12 0.33 btg
0.33 7.4 2 kg
Begel 6D-20 1.00 0.20 5 bh
1bh besi=?cm 57 cm
Total Kg Begel 5 0.67 0.28 btg
4.74 1.32 kg
Total Besi Beton Sloof 2.47 1.32 3.79
Bendrat 3.79 0.1 0.38
pekerja 3.79 0.0070 0.0265 oh
tukang 3.79 0.0007 0.0027 oh
kepala 3.79 0.00007 0.0003 oh
mandor 3.79 0.0004 0.0015 oh

Bekisting
Luas bekisting 1.0 0.15 2 0.30
papan 2/20x3m 0.30 1.7 0.51
paku 2"-5" 0.30 0.30 0.09
pekerja 0.30 0.52 0.16
tukang 0.30 0.26 0.08
kepala tukang 0.30 0.026 0.01
mandor 0.30 0.026 0.01

1 m3 Kebutuhan m3 sloof 15/15


semen 6.0 zak
pasir 0.50 m3
kerikil 0.54 m3
Besi Beton D-8 0.33 btg
Besi Beton D-6 0.28 btg
Bendrat 0.38 kg
Papan 2/20 0.51 lbr
Paku 2"- 5" 0.09 kg
pekerja 0.76 oh
tukang 3.71 oh
kepala 33.34 oh
mandor 12.06 oh

Hitungan Sloof 15x25 pjg jml


m3 Cor Beton 1.00
semen 299 50 5.98 zak
pasir 799 1,600 0.50 m3
kerikil 1,017 1,900 0.54 m3
pekerja 1.00 1.650 0.61 oh
tukang 1.00 0.275 3.64 oh
kepala 1.00 0.030 33.33 oh
mandor 1.00 0.083 12.05 oh
1 Kg Besi
Tul. Pokok 4D-8 1.00 4 12 0.33 btg
0.33 7.4 2 kg
Begel 6D-20 1.00 0.20 5 bh
1bh besi=?cm 57 cm
Total Kg Begel 5 0.67 0.28 btg
4.74 1.32 kg
Total Besi Beton Sloof 2.47 1.32 3.79
Bendrat 3.79 0.1 0.38
pekerja 3.79 0.0070 0.0265 oh
tukang 3.79 0.0007 0.0027 oh
kepala 3.79 0.00007 0.0003 oh
mandor 3.79 0.0004 0.0015 oh

Bekisting
Luas bekisting 1.0 0.25 2 0.50
papan 2/20x3m 0.50 1.7 0.85
paku 2"-5" 0.50 0.30 0.15
pekerja 0.50 0.52 0.26
tukang 0.50 0.26 0.13
kepala tukang 0.50 0.026 0.01
mandor 0.50 0.026 0.01

1 m3 Kebutuhan m3 sloof 15/15


semen 5.98 zak
pasir 0.50 m3
kerikil 0.54 m3
Besi Beton D-8 0.33 btg
Besi Beton D-6 0.28 btg
Bendrat 0.38 kg
Papan 2/20 0.85 lbr
Paku 2"- 5" 0.15 kg
pekerja 0.87 oh
tukang 3.77 oh
kepala 33.35 oh
mandor 12.06 oh
Luas Tanah Bouwplank Luas Tanah Bouwplank Rnc.Bngnan galian tanah pondasi batu kali
4,324,557.48 14.66 33.22 dalam
33.25 32.29 pjg total
12.57 31.32 36.00
15.85 96.83 14.94
15.93
432.46 3.54
4.00
91.88 2.00
96.83 2.00
188.71 0.55 4.00
24.00 15.00 2.06
91.88 3.62
4.15
Galian tanah Pondasi Footplat 3.62
73.23 fp1k1= 4bh fp2k2=17bh fp3k3=24 4.15
31.06 3.89 13.06 14.11 3.62
31.06 3.08
34.76 3.61
127.36 3.08
3.61
259.47 padas
259.47 dalam 1,027,522.56 0.60
depan 1,047,968.45 0.60
tengah 1,881,136.01 0.34
117.01
6.37 254.72
25.47
42.85

730.15
1,011.46
0.16 0.54 0.59
1,460.30 3.24 10.88 11.76
2,022.91
Galian tanah Pondasi 250.41
1,460.30 fp1k1= 4bh fp2k2=17bh fp3k3=24
2,022.91
3.89 13.06 14.11
334.00 0.16 0.54 0.59
293.00 3.24 10.88 11.76

1.55
8.03
fp1 fp2 fp3
4.04
5.51 1.03 3.36 3.64
9.84 kolom1 kolom2 kolom3
5.40 1.44 4.08 4.32
6.80

2.52
3.24 rabat beton
1,243,254
124.33 33,830 235,508 872,993
114.23

3.10
2.63
- 117.01 137.71 254.72
3.10
2.63

17.44 13.185
16.96 11.858976
146.56

0.51
0.61 2x8 anak tangga+4 anak tangga 1465574.5002
8.50
0.51
0.61
8.50

-
14.48

67.60
83.20 0.92 2.70 2.00
0.82 2.20 13.00
157.05 0.68 1.33 30.00
167.52 0.88 2.70 30.00
0.50 0.54 16.00
12.00
16.00

2.48 254.72
14.43
14.43
38.02
2.16
71.52

15.00
16.00
254.72
15.00

pintu jendela bouven


28.00 lt1
34.00 0.92
0.82
56.00 0.68
68.00 0.88
0.50
15.00
16.00

15.00
16.00

15.50
19.15 .

126.96 PJ1 BV1


7.86 0.34 0.10
6.00 0.53 0.11
151.94 0.87 0.21
188.18
25.11
luas lantai
27.00 sisi dalam sisi depan R. Tidur Penjaga
36.00 76.02 21.48 10.50
25.92 73.50
147.60 64.68 21.48
196.80 21.56
188.18 116.46 10.50
teras
982.13 25.11 6.12
928.28 234.85 122.58 10.50
teras
25.11 6.12
17.12
104.81
34.35
141.33
33.53

179.91
187.17

Plafon t=5cm
109.88
5.07

104.81
7.50

7.50

29.00
28.72
7.00

177.79
161.18
296.20
31.06

kg
kg

m2
lbr
kg
oh kusen lt2
oh p1 0.92
oh p2 0.82
oh pj1 0.68
0.88
Bouven 0.50

kusen lt1
p1 0.92
p2 0.82
pj1 0.68
0.88
Bouven 0.50

kusen depan dalam


p1 2.00
p2 14.00 16.00
pj1 15.00 16.00
Bouven 14.00 16.00

Pipa pvc Ø 4"


2.55 16.00
1.34 4.00
2.44
2.44
4.85
4.69
4.69
2.44
2.44
4.69
2.44
4.69
2.22
4.05
19.50
65.47 64.00
177.79

kg
kg

m2
lbr
kg
oh
oh
oh
oh
kg
kg

m2
lbr
kg
oh
oh
oh
oh
an tanah pondasi batu kali Pondasi Batu Belah Luas Bgnan lt 1
depan total panjang 196.22 58.50 depan
254.72 0.17 0.18 13.85
27.00 pengurangan 32.38 10.47 22.59
6.05 14.66 45.32
2.00 14.94 81.75
2.00 0.55
2.00 15.93
4.00 12.42
2.05 58.50
3.00
3.00
3.00 mendatar tegak
3.00
3.53 1,494.00 362.00
3.50 1,592.00 415.00
3.50 4,200.00 362.00
3.53 354.00 150.00
3.00 400.00 150.00
3.53 200.00 150.00
14.66 200.00 415.00
17.05 400.00 150.00
1.85 207.00 362.00
14.04 143.00 308.00
12.42 461.00 150.00
137.71 200.00 361.00
200.00 150.00
400.00 308.00
204.00 150.00
461.00 150.00
700.00 300.00
184.00 300.00
1,403.00 300.00
300.00
20,162.00 13,403.00 5,293.00

dak beton t=12cm + jembatan


total 2,988,289.20
dalam 1,470,217.21 56,887.48 1,413,329.74
depan 1,518,071.99 64,749.97 1,453,322.02

dak beton 12cm sponengan


t=4m sisi depan sisi dalam lantai 1
9.84 42.00 38.01 depan
8.84 12.96 180.00
42.09 4.49
10.59 32.34
6.36 11.03
109.88 98.82
1,142,331.00

kolom1 kolom2 kolom3 t=4m


1.44 4.08 4.32 9.84

dalam depan
pjg total
36.00 27.00
14.94 6.05
15.93 2.00
3.54 2.00
4.00 2.00
2.00 4.00
2.00 2.05
4.00 3.00
2.06 3.00
3.62 3.00
4.15 3.00
3.62 3.53
4.15 3.50 300.00
3.62 3.50 150.00
3.08 3.53 353.00
3.61 3.00 150.00
3.08 3.53 350.00
3.61 14.66 350.00
17.05 353.00
1.85 150.00
14.04
12.42
117.01 137.71

sloop thp 1 sloop thp 2


117.01 107.78
14.66
12.42
0.5
0.5
1.85
146.94 107.78

tu jendela bouven

2.70 1 2.48
2.20 5.0 9.02
1.33 14.0 12.62
2.70 14.0 33.26 300.00
0.54 8 2.16
59.55
131.49
160.13
6.35
297.97
7.50
P1 lantai 1 R.tidur lantai 2 R.tidur R. Tidur Penjaga Ruang Tamu
0.68 45.56 45.56 6.35 7.50
0.30 38.19 38.19
0.98 47.74 76.38
131.49 160.13 6.35

idur Penjaga

315.14

367.93

Atap
depan dalam
32.71 16.02 15.91
5.50 6.22 5.50
179.91 99.64 87.52

350.00

353.00
150.00
350.00
350.00
353.00
150.00
350.00
dalam depan 350.00
pjg total 1,494 14.94 353.00
36.00 27.00 1,592 15.92 150.00
14.94 6.05 354 3.54 350.00
15.93 2.00 400 4.00 350.00
3.54 2.00 200 2.00 353.00
4.00 2.00 200 2.00 150.00
2.00 4.00 400 4.00 350.00
2.00 2.05 207 2.07 350.00
4.00 3.00 3,600 36.00 353.00
2.06 3.00 362 3.62 150.00
3.62 3.00 416 4.16 350.00
4.15 3.00 362 3.62 350.00
3.62 3.53 415 4.15 353.00
4.15 3.50 362 3.62 150.00
3.62 3.50 308 3.08 350.00
3.08 3.53 361 3.61 350.00

3.61 3.00 308 3.08 353.00


3.08 3.53 361 3.61 150.00
3.61 14.66 miring 308 3.08 350.00
17.05 367 3.67 350.00
1.85 12,377 123.77 353.00
14.04 150.00
12.42 350.00
254.72 117.01 137.71 350.00
130.95 353.00
150.00
350.00
350.00
353.00
150.00
350.00
350.00
2.70 1 2.48 150.00
2.20 8.0 14.43 353.00
1.33 16.0 14.43 150.00
2.70 16.0 38.02 300.00
0.54 8 2.16 150.00
71.52 353.00
150.00
1,218.00
2.70 1 2.48
2.20 5.0 9.02 148,900.46 2,897,343.59
1.33 14.0 12.62
2.70 14.0 33.26
0.54 8 2.16
59.55

luasan total depan total blkg


2.48 - 4.97
1.80 25.26 28.86
3.28 49.17 52.44
0.27 3.78 4.32
78.20 90.59

Pipa pvc Ø 3"


6.93 1.24 0.80 1.12
2.61 1.21 1.26 1.12
2.61 0.63 1.26 1.48
2.61 0.73 21.58 1.48
4.78 0.31 19.84 1.26
4.78 1.43 2.61 1.26
24.00 1.83 1.34 64.00
5.13 1.12
4.25 1.12
2.55 2.61
2.84 1.34
2.61 1.12
1.39 1.12
1.12 2.61
1.12 1.34
48.32 161.18

Pipa pvc Ø 3/4"


9.21 3.32
27.84 0.89
29.71 0.96

5.17 4.00
32.00 16.00
66.76 165.44 64.00

296.20

padas
dalam 1,027,522.56 0.60
depan 1,047,968.45 0.60
tengah 1,881,136.01 0.34
Luas Bgnan lt 2
dalam depan dalam
46.45 45.30 105.15
58.70 45.18

105.15 90.48 105.15


382.53

miring kolom praktis k1 k2


dalam depan tahap 1 dalam 2.00 8.00
1,466.00 36.00 28.00 tahap 2 depan 2.00 9.00
0.15 0.15
0.15 0.15 volume t=7.5m k1 k2
4.00 4.00 0.68 0.45
3.24 2.52 dalam 1.35 3.60
5.76 depan 1.35 4.05

112
144
256

1,466.00

sponengan
lantai 2 lantai 1 lantai 2
depan dalam dalam
154.00 160.00 133.00
300.00
150.00
350.00
353.00
150.00
350.00
350.00
150.00
350.00
350.00
353.00
350.00
350.00

150.00
350.00
350.00
7,842.00 3,054,086.05
kp
k3 k4
41.00 41.00
- 25.00

k3
0.05
1.85
-
Harga Sat
No. Uraian Pekerjaan Total Harga
Pekerjaan

1 PEKERJAAN PERSIAPAN
1 m2 Pembersihan lokasi Awal 11,550.00
1 Rit Buangan sampah pembersihan lokasi
1 m' Pasang Bouwplank 26,931.67
1 Ls Air Kerja
1 Ls Listrik Kerja
1 Ls Administrasi

2 PEKERJAAN TANAH
1m3 Galian tanah 55,825.00
1m3 Urugan tanah Kembali Galian tanah biasa sedalam 1 meter 18,605.40
1 m3 Urugan tanah padas 97,330.00
1m2 Pemadatan Tanah Pondasi (dgn Mesin Stamper) 4,611.58
1m3 Pasir Urug 502,330.00

3 PEKERJAAN PASANGAN
1 m3 Pasangan Aanstamping 312,519.00
1 m3 Pasangan Pondasi Batu Belah 1:6 734,790.00
1 m2 Pasangan bata Ringan t=10 cm 136,100.00
1 m2 Plesteran PM t=1cm 43,300.00
1 m2 Acian PM t=3mm 19,000.00
1 m' Sponeng 18,289.29

4 PEKERJAAN BETON
1 m3 Lantai Kerja 1:3:5 795,584.00
1 m3 Pondasi Footplat 987,140.00
1 m3 Sloof beton 728,761.47
1 m3 Kolom Setempat 978,300.00
1 m3 Kolom Praktis 731,025.29
1 m2 Rabat Beton 125,840.00
1 m3 Tiebalk 15/15 705,769.63
1 m3 Ringbalk 15/20 716,066.78
1 m3 Dak Beton t=12cm 1,024,000.00
1 m2 Vehicles Pas.Paving Blok 147,281.35
1 m3 Tangga Beton (Bata)
1 m3 Plat Tangga t=10cm
1 m2 plesteran t=3cm

5 PEKERJAAN PINTU DAN JENDELA


1 m' Kusen Alumunium Type P1
1 m'Kusen Alumunium Type P2
1 m' Kusen Alumunium Type PJ1
1 bh Bouven Type BV1
1 bh Daun jendela alumunium
1 bh Daun Pintu alumunium

6 PEKERJAAN PENGUNCI & KACA


1 bh Kunci 2x putar terpasang
1 bh Engsel pintu terpasang
1 bh Engsel jendela terpasang
1 bh Hak angin jendela
1 bh Kaca riben 5 mm terpasang exs. ASAHI

7 PEKERJAAN LANTAI
1m2 Keramik lantai 60x60 cm
1m2 Keramik lantai KM 20x20 cm

8 PEKERJAAN CAT
1 m2 cat dinding dalam
1 m2 cat dinding luar

8 PEKERJAAN ATAP
1 m2 Atap Plafon GRC t = 4 mm + Rangka Besi Hollow
1 m2 Rangka Atap Baja Ringan
1 m2 Atap Genteng Metal

9 PEKERJAAN SANITASI
Closet Duduk
Kran Air
Shower mandi exs. WASHER
Floor Drain
Bak Dapur
Pipa pvc Ø 4"
Pipa pvc Ø 3"
Pipa pvc Ø 3/4"
Torn air 2000 liter
1 Unit Septictank 2.60 X 1.3 ( KAPASITAS ± 2 M3 )
1 Unit Peresapan Ø 100 h = 2 m

10 PEKERJAAN LAIN-LAIN
Railing Tangga
Railing Pagar Lantai 2 dan Penghubung
Proyek : Rumah Kos Kosan
Lokasi : Kudus
Owner/Pemilik : Bpk Gunawan
Tahun : 2018
RENCANA ANGGARAN BIAYA (RAB)
HARGA SATUAN
NO ITEM PEKERJAAN VOLUME SATUAN
Rp.

I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi Awal 432.46 m2 11,550.00
2 Buangan sampah pembersihan lokasi rit
3 Pasang Bouwplank 188.71 m' 26,931.67
4 Air Kerja 1.00 ls
5 Listrik Kerja 1.00 ls
6 Administrasi 1.00 ls

II PEKERJAAN TANAH
1 Galian tanah
a Galian tanah pondasi batu kali 73.23 m3 55,825.00
b Galian tanah pondasi Foot plat 31.06 m3 55,825.00
2 Urugan tanah kembali 34.76 m3 18,605.40
3 Tanah padas
a Urugan tanah padas 259.47 m3 97,330.00
b Pemadatan tanah Padas 259.47 m2 4,611.58
4 Urugan Pasir bawah Pondasi 6.37 m2 502,330.00

III PEKERJAAN PASANGAN


1 Pasangan Aanstamping 25.47 m3 312,519.00
2 Pasangan Pondasi Batu Belah 1:6 42.85 m3 734,790.00
3 Pasangan bata Ringan t=10 cm
a sisi depan 730.15 m2 136,100.00
b sisi dalam 1,011.46 m2 136,100.00
4 Plesteran PM t=1cm
a sisi depan 1,460.30 m2 43,300.00
b sisi dalam 2,022.91 m2 43,300.00
5 Acian PM t=3mm
a sisi depan 1,460.30 m2 19,000.00
b sisi dalam 2,022.91 m2 19,000.00
6 Sponeng
a sisi depan 334.00 m' 18,289.29
b sisi dalam 293.00 m' 18,289.29

IV PEKERJAAN BETON
1 Lantai Kerja 1:3:5 1.55 m3 795,584.00
2 Pondasi Footplat 8.03 m3 987,140.00
3 Sloof beton
a sisi depan 4.04 m3 728,761.47
b sisi dalam 5.51 m3 728,761.47
4 Kolom Setempat
a sisi depan 5.40 m3 978,300.00
b sisi dalam 6.80 m3 978,300.00
5Kolom Praktis
asisi depan 2.52 m3 731,025.29
bsisi dalam 3.24 m3 731,025.29
6Rabat Beton
asisi depan 124.33 m2 125,840.00
bsisi dalam 114.23 m2 125,840.00
7Tiebalk 15/15
asisi depan 3.10 m3 705,769.63
bsisi dalam 2.63 m3 705,769.63
8Ringbalk 15/20
asisi depan 3.10 m3 716,066.78
bsisi dalam 2.63 m3 716,066.78
9Dak Beton t=12cm
asisi depan 17.44 m3 1,024,000.00
bsisi dalam 16.96 m3 1,024,000.00
10Vehicles Pas.Paving Blok 146.56 m2 147,281.35
11Tangga Beton
asisi depan 0.51 m3 3,620,670.00
Plat Tangga t=10cm 0.61 m3 3,620,670.00
plesteran t=3cm 8.50 m2 39,648.31
b sisi dalam 0.51 m3 3,620,670.00
Plat Tangga t=10cm 0.61 m3 3,620,670.00
plesteran t=3cm 8.50 m2 39,648.31

V PEKERJAAN PINTU DAN JENDELA


1 Kusen Alumunium Type P1 /m'
a sisi dalam 14.48 m' 100,750.00
2 Kusen Alumunium Type P2 /m'
a sisi depan 67.60 m' 100,750.00
b sisi dalam 83.20 m' 100,750.00
3 Kusen Alumunium Type PJ1 /m'
a sisi depan 157.05 m' 100,750.00
b sisi dalam 167.52 m' 100,750.00
4 Bouven Type BV1 /bh
a sisi depan 12.00 bh 402,500.00
b sisi dalam 16.00 bh 402,500.00
5 Daun jendela alumunium
a sisi depan 15.00 bh 546,250.00
b sisi dalam 16.00 bh 546,250.00
6 Daun Pintu alumunium
a sisi depan 15.00 bh 864,000.00
b sisi dalam 18.00 bh 864,000.00

VI PEKERJAAN PENGUNCI & KACA


1 Kunci 2x putar terpasang
a sisi depan 28.00 bh 316,250.00
b sisi dalam 34.00 bh 316,250.00
2 Engsel pintu terpasang
a sisi depan 56.00 bh 63,250.00
b sisi dalam 68.00 bh 63,250.00
3 Engsel jendela terpasang
a sisi depan 15.00 bh 40,250.00
b sisi dalam 16.00 bh 40,250.00
4 Hak angin jendela
a sisi depan 15.00 bh 40,250.00
b sisi dalam 16.00 bh 40,250.00
5 Kaca riben 5 mm terpasang exs. ASAHI
a sisi depan 15.50 m2 143,750.00
b sisi dalam 19.15 m2 143,750.00

VI PEKERJAAN LANTAI
1 Keramik lantai 60x60 cm
a K Tidur sisi depan+ R Jaga 126.96 m2 156,173.30
Ruang Tamu 7.86 m2 156,173.30
Dapur 6.00 m2 156,173.30
teras luar 151.94 m2 156,173.30
b K Tidur sisi dalam 188.18 m2 156,173.30
teras luar 25.11 m2 156,173.30
2 Keramik Lantai KM 20x 20 cm
a KM sisi depan 27.00 m2 151,201.30
b KM sisi dalam 36.00 m2 151,201.30
3 Keramik Dinding KM
a KM sisi depan 147.60 m2 155,557.30
b KM sisi dalam 196.80 m2 155,557.30

VII PEKERJAAN CAT


1 cat dinding sisi depan
a sisi depan bagian luar 982.13 m2 33,600.00
b sisi depan bagian dalam 928.28 m2 25,600.00
2 cat dinding sisi dalam
a sisi dalam bagian luar 928.28 m2 33,600.00
b sisi dalam bagian dalam 928.28 m2 25,600.00

VIII PEKERJAAN ATAP


1 Atap Plafon GRC t = 4 mm + Rangka Besi Hollow
a sisi depan 104.81 m2 91,400.00
sisi luar 34.35 m2 91,400.00
b sisi dalam 141.33 m2 91,400.00
sisi luar 33.53 m2 91,400.00
2 Rangka Atap Baja Ringan
a sisi depan 179.91 m2 164,454.00
b sisi dalam 187.17 m2 164,454.00
3 Atap Genteng Metal
a sisi depan 179.91 m2 120,790.58
b sisi dalam 187.17 m2 120,790.58

IX PEKERJAAN SANITASI
1 Closet Duduk
a sisi depan 14.00 bh 1,595,400.00
b sisi dalam 16.00 bh 1,595,400.00
2 Kran Air
a sisi depan 28.00 bh 49,000.00
b sisi dalam 32.00 bh 49,000.00
3 Shower mandi exs. WASHER
a sisi depan 14.00 bh 431,250.00
b sisi dalam 16.00 bh 431,250.00
4 Floor Drain
a sisi depan 15.00 bh 74,670.00
b sisi dalam 16.00 bh 74,670.00
5 Bak Dapur 1.00 bh 420,900
8 Pipa pvc Ø 4" 177.79 m' 59,052.31
9 Pipa pvc Ø 3" 161.18 m' 46,864.81
10 Pipa pvc Ø 3/4" 296.20 m' 24,414.81
11 Torn air 2000 liter 2.00 bh 2,500,000.00
12 1 Unit Septictank 2.60 X 1.3 ( KAPASITAS ± 2 M3 ) 1.00 unit 7,147,527.41
13 1 Unit Peresapan Ø 100 h = 2 m 1.00 unit 1,193,598.12

X PEKERJAAN LAIN-LAIN
1 Railing Tangga
a sisi depan 7.50 m' 450,000.00
b sisi dalam 7.50 m' 450,000.00
2 Railing Pagar Lantai 2 dan Penghubung
a sisi depan 29.00 m' 450,000.00
b sisi dalam 28.72 m' 450,000.00
c sisi tengah 7.00 m' 450,000.00

Terbilang : TOTAL
Enam Belas Juta Empat Ratus Delapan Puluh Satu Ribu Rupiah FEE JASA 6%
GRAND TOTAL
PEMBULATAN

Kudus, 11 April 2018


Mengajukan,

(Yuspika Juantoro)
PIMPINAN
Catatan :
1 Harga diatas tidak mengikat, dapat berubah sewaktu-waktu.
2 Apabila ada kerja tambah kurang, akan diperhitungkan kemudian.
3 Penawaran ini berlaku selama 1 bulan sejak diterbitkan.
JUMLAH HARGA sisi depan= bagian depan jalan masuk (Tahap II)
Rp. sisi dalam= bagian belakang (Tahap I)
1,322,902,848.01 total biaya
10,077,138.71 382.530 luas tanah
4,994,863.89 3,458,296.49 harga per m2
-
5,082,274.82

36,118,622.58

4,088,176.40 55,825.00
1,733,701.20 55,825.00
646,773.32 18,605.40

25,254,550.79 122,760.00
1,196,583.43 3,943.33
3,198,837.44 421,110.00

504,948,143.02
7,960,483.97 247,770.00
31,484,134.96 644,173.71

99,373,251.68 139,400.00
137,659,041.83 139,400.00

63,230,886.08 43,300.00
87,592,013.39 43,300.00

27,745,654.40 19,000.00
38,435,294.56 19,000.00

6,108,621.43 18,289.29
5,358,760.71 18,289.29

136,047,453.09
1,235,382.84 842,320.80
7,928,362.98 978,300.00

2,945,471.67 3,862,720.00
4,015,657.88 3,862,720.00

5,282,820.00 978,300.00
6,647,548.50 978,300.00
1,842,183.72 3,862,720.00
2,368,521.93 3,862,720.00

15,645,103.36 125,840.00
14,375,093.30 125,840.00

2,186,809.56 3,862,720.00
1,858,097.35 3,862,720.00

2,218,715.02 3,862,720.00
1,885,206.92 3,862,720.00

17,858,420.92 1,024,000.00
17,366,995.79 1,024,000.00
21,585,179.09 147,281.35 1465574.5002

1,846,541.70 3,620,670.00
2,215,850.04 3,620,670.00
337,010.60 39,648.31
1,846,541.70 3,620,670.00
2,218,927.61 3,620,670.00
337,010.60 39,648.31

106,068,137.50

1,458,860.00 97,750.00

6,810,700.00 97,750.00
8,382,400.00 97,750.00

15,822,787.50 97,750.00
16,877,640.00 97,750.00

4,830,000.00 402,500.00
6,440,000.00 402,500.00

8,193,750.00 546,250.00
8,740,000.00 546,250.00

12,960,000.00 864,000.00
15,552,000.00 864,000.00

34,925,902.50

8,855,000.00 316,250.00
10,752,500.00 316,250.00

3,542,000.00 63,250.00
4,301,000.00 63,250.00

603,750.00 40,250.00
644,000.00 40,250.00
603,750.00 40,250.00
644,000.00 40,250.00

2,227,492.50 143,750.00
2,752,410.00 143,750.00

75,109,455.91 50673306.868
-
19,827,762.17 156,173.30
1,227,522.14 156,173.30
937,039.80 156,173.30
23,728,565.15 156,173.30
29,388,566.66 156,173.30
3,922,058.17 156,173.30

4,082,435.10 151,201.30
5,443,246.80 151,201.30

22,960,257.48 155,557.30
30,613,676.64 155,557.30

111,717,120.00

32,999,400.00 33,600.00
23,763,840.00 25,600.00

31,190,040.00 33,600.00
23,763,840.00 25,600.00

133,405,495.08

9,579,177.00 91,400.00
3,139,178.70 91,400.00
12,917,833.78 91,400.00
3,064,322.10 91,400.00

29,586,096.87 164,454.00
30,780,180.92 164,454.00

21,730,828.70 120,790.58
22,607,877.00 120,790.58

105,100,542.53

22,335,600.00 1,595,400.00
25,526,400.00 1,595,400.00
-
1,372,000.00 49,000.00
1,568,000.00 49,000.00

6,037,500.00 431,250.00
6,900,000.00 431,250.00

1,120,050.00 74,670.00
1,194,720.00 74,670.00
420,900.00 420,900.00
10,498,910.19 59,052.31
7,553,670.08 46,864.81
7,231,666.72 24,414.81
5,000,000.00 2,500,000.00
7,147,527.41 7,147,527.41
1,193,598.12 1,193,598.12

35,874,000.00

3,375,000.00 450,000.00
3,375,000.00 450,000.00

13,050,000.00 450,000.00
12,924,000.00 450,000.00
3,150,000.00 450,000.00

1,322,902,848.01 1,485,753,582.06
79,374,170.88
1,402,277,018.89
1,402,277,000.00

Kudus, 11 April 2018


ANALISA SATUAN PEKERJAAN
RENOVASI SKT SUDIMORO
PT. DJARUM - UNIT SKT SUDIMORO - KUDUS

No. Uraian Pekerjaan Bahan/T.Kerja Analisa Sat Sat.Harga Harga Sat


Bahan/T.Kerja Pekerjaan
I Pekerjaan TANAH
1 Bouwplank / Uitzet Papan randu 0.3000 lbr Rp. 13,500.00 Rp. 4,050.00
Paku 4' 0.0140 Kg Rp. 11,500.00 Rp. 161.00
Bambu Apus 0.5000 Bt Rp. 15,000.00 Rp. 7,500.00
Upah 1.0000 M' Rp. 5,625.00 Rp. 5,625.00
2 1 M3 Galian Tanah Upah 1.0000 M3 Rp. 45,000.00 45,000.00
3 1 M3 Urugan Kembali Upah 1.0000 M3 Rp. 15,187.50 15,187.50
4 1 M3 Urugan Tanah Tanah Urug 1.2000 M3 Rp. 60,000.00 72,000.00
Upah 1.0000 M3 Rp. 16,312.50 16,312.50
5 1 M3 Urugan Pasir Muntilan Pasir Muntilan 1.2000 M3 Rp. 285,000.00 342,000.00
Upah 1.0000 M3 Rp. 15,187.50 15,187.50

II Pekerjaan PASANGAN - PLESTERAN


1 1 M3 Pondasi Batu Kali 1: 5 Batu Belah 1.2000 M3 Rp. 170,000.00 204,000.00
Semen 2.7200 Zak Rp. 69,000.00 187,680.00
Pasir Muntilan 0.5540 M3 Rp. 285,000.00 157,890.00
Upah 1.0000 M3 Rp. 140,625.00 140,625.00
2 1 M2 Beraben Pondasi 1: 5 Semen 0.0626 Zak Rp. 69,000.00 4,319.40
Pasir Muntilan 0.0220 M3 Rp. 285,000.00 6,270.00
Upah 1.0000 M2 Rp. 11,475.00 11,475.00
3 1 M2 Plesteran 1: 5 + acian Semen 0.1522 Zak Rp. 69,000.00 10,501.80
Pasir muntilan 0.0220 M3 Rp. 285,000.00 6,270.00
Upah 1.0000 M2 Rp. 34,875.00 34,875.00
1 M2 Plesteran galur horisontal Semen 0.3805 Zak Rp. 69,000.00 26,254.50
Pasir muntilan 0.0220 M3 Rp. 285,000.00 6,270.00
Upah 1.0000 M2 Rp. 90,000.00 90,000.00
4 1 M2 Plesteran 1: 3 + acian Semen 0.2032 Zak Rp. 69,000.00 14,020.80
Pasir muntilan 0.0194 M3 Rp. 285,000.00 5,529.00
Upah 1.0000 M2 Rp. 34,875.00 34,875.00
1 M2 Plesteran beton 1: 3 + acian Semen 0.2032 Zak Rp. 69,000.00 14,020.80
Pasir muntilan 0.0194 M3 Rp. 285,000.00 5,529.00
Upah 1.0000 M2 Rp. 38,250.00 38,250.00
5 1 M2 Sreed 3 cm 1: 3 Penutup WP Semen 0.3264 Zak Rp. 69,000.00 22,521.60
Pasir muntilan 0.0388 M3 Rp. 285,000.00 11,058.00
kawat ayam 1.1000 M2 Rp. 12,000.00 13,200.00
Upah 1.0000 M2 Rp. 20,812.50 20,812.50
6 1 M2 Pasang Batu Merah 1: 5 Batu Merah 65.0000 Bj Rp. 700.00 45,500.00
1 PC : 5 PS Semen 0.3725 Zak Rp. 69,000.00 25,701.44
Pasir Muntilan 0.0450 M3 Rp. 285,000.00 12,825.00
Upah 1.0000 M2 Rp. 27,000.00 27,000.00
7 1 M3 Pasang Batu Merah 1: 3 Batu Merah 465.0000 Bj Rp. 700.00 325,500.00
Semen 3.1480 Zak Rp. 69,000.00 217,212.00
Pasir Muntilan 0.3780 M3 Rp. 285,000.00 107,730.00
Upah 1.0000 M3 Rp. 180,000.00 180,000.00
Per m2 bata 1:3

8 1 M3 Pasang Batu Merah Kosong Batu Merah 465.0000 Bj Rp. 700.00 325,500.00
Upah 1.0000 M3 Rp. 180,000.00 180,000.00
9 1 M2 Acian plat / lantai / rabat Semen 0.0500 Zak Rp. 69,000.00 3,450.00
Upah 1.0000 M2 Rp. 10,125.00 10,125.00

9 1 M2 Acian dinding Semen 0.0500 Zak Rp. 69,000.00 3,450.00


Upah 1.0000 M2 Rp. 13,500.00 13,500.00

9 1 M' Sponengan Upah 1.0000 M' Rp. 7,875.00 7,875.00

10 1 M2 Cat Dinding dalam Cat Tembok 2x 0.2500 Ltr Rp. 44,632.00 11,158.00
Mowilex ( BARU ) 2 x roll Alkali Resist Sealer 1x 0.1250 Ltr Rp. 38,605.00 4,825.63
Media Dinding dg SEMEN INSTANT Ambril 0.1500 Lb Rp. 3,135.00 470.25
Upah 1.0000 M2 Rp. 9,000.00 9,000.00
11 1 M2 Cat Dinding Luar Cat Tembok 2x 0.2500 Ltr Rp. 70,565.20 17,641.30
Mowilex Weathercoat ( BARU ) 2x roll Alkali Resist Sealer 1x 0.1250 Ltr Rp. 38,605.00 4,825.63
Media Dinding dg SEMEN INSTANT Ambril 0.1500 Lb Rp. 3,135.00 470.25
Upah 1.0000 M2 Rp. 9,000.00 9,000.00

12 1 M2 Cat Dinding INTERIOR Cat Tembok 2x 0.25 Ltr Rp. 44,632.00 Rp. 11,158.0
Mowilex ( CAT ULANG ) 2 x roll Wallsealer 1X 0.0625 Ltr Rp. 35,950.00 Rp. 2,246.9
Ambril 0.15 Lbr Rp. 3,135.00 Rp. 470.3
Upah 1.0000 M2 Rp. 10,000.00 Rp. 10,000.0

13 1 M2 Cat Dinding EXTERIOR Cat Tembok 2x 0.25 Ltr Rp. 70,565.2 Rp. 17,641.3
Mowilex Weathercoat Wallsealer 1X 0.0625 Ltr Rp. 35,950.00 Rp. 2,246.9
( CAT ULANG ) 2 x roll Ambril 0.15 Lb Rp. 3,135.00 Rp. 470.3
Upah 1.0000 M2 Rp. 10,000.00 Rp. 10,000.0

14 1 M2 Cat kayu BARU Cat kayu 0.2500 Kg Rp. 79,840.00 19,960.00


ex nippon paint Thinner 0.2000 ltr Rp. 27,500.00 5,500.00
Meni kayu 0.1500 Kg Rp. 48,000.00 7,200.00
Plamur kayu 0.0700 Kg Rp. 30,000.00 2,100.00
Ambril 0.1500 Lb Rp. 3,135.00 470.25
Upah 1.0000 M2 Rp. 7,875.00 7,875.00

15 1 M2 Cat kayu ULANG Cat kayu 0.2000 Kg Rp. 79,840.00 15,968.00


ex nippon paint Thinner 0.2000 ltr Rp. 27,500.00 5,500.00
Ambril 0.1500 Lb Rp. 3,135.00 470.25
Upah 1.0000 M2 Rp. 7,875.00 7,875.00

16 1 M2 Pasang Rooster Naco 1: 3 Rooster 23.0000 Bj Rp. 13,000.00 299,000.00


15 x 30 cm Semen 0.1000 Zak Rp. 69,000.00 6,900.00
Pasir Muntilan 0.0100 M3 Rp. 285,000.00 2,850.00
Upah 1.0000 M2 Rp. 75,375.00 75,375.00

17 1 unit BAK KONTROL 50x50 Galian tanah 0.5100 M3 Rp. 45,000.00 22,950.00
Buangan tanah keluar 0.5100 M3 Rp. 54,000.00 27,540.00
Urugan pasir 5 cm 0.0320 M3 Rp. 357,187.50 11,430.00
Pas bata 1:3 0.1500 m2 Rp. 124,566.30 18,684.95
Plesteran 1:3 1.4500 m2 Rp. 54,424.80 78,915.96
Siku pengaman 2 sisi 15.0000 Kg Rp. 14,200.00 213,000.00

18 1 M2 Batu andhesite bakar 20x20 Andhesite bakar 1.1000 M2 Rp. 200,000.00 220,000.00
Semen 0.1632 Zak Rp. 69,000.00 11,260.80
Pasir muntilan 0.0194 M3 Rp. 285,000.00 5,529.00
Upah 1.0000 M2 Rp. 34,875.00 34,875.00

19 1 M' SALURAN BATU BELAH Galian tanah 0.9000 M3 Rp. 45,000.00 40,500.00
Buangan tanah keluar 0.9000 M3 Rp. 54,000.00 48,600.00
Urugan pasir 5 cm 0.0500 M3 Rp. 357,187.50 17,859.38
Pas batu belah 1:5 0.6400 m3 Rp. 690,195.00 441,724.80
Beraben 1:5 2.0000 m2 Rp. 22,064.40 44,128.80
Plesteran 1:3 2.0000 m2 Rp. 54,424.80 108,849.60
Sponengan 3.0000 m' Rp. 7,875.00 23,625.00

20 1 m2 Paving Block 8 cm Paving baru 1.0000 M2 Rp. 124,600.00 Rp. 124,600.00


Paving BARU Kolot pasir mtln 0.0150 m3 Rp. 285,000.00 Rp. 4,275.00
UNIPAVE Pasir urug Mtln 0.0000 m3 Rp. 285,000.00 Rp. -
Upah 1.0000 M2 Rp. 16,875.00 Rp. 16,875.00

III Pekerjaan KERAMIK LANTAI dan DINDING

1 1 M2 Keramik Lantai 20x20 Keramik 1.1000 M2 Rp. 41,000.00 45,100.00


Roxy Blue KW I Biru Asia Tile AM 50 0.2000 Kg Rp. 15,910.00 3,182.00
Semen 0.1632 Zak Rp. 69,000.00 11,260.80
Pasir muntilan 0.0194 M3 Rp. 285,000.00 5,529.00
Upah 1.0000 M2 Rp. 28,125.00 28,125.00

2 1 M2 Keramik Dinding 20x20 Keramik 1.1000 M2 Rp. 77,272.00 84,999.20


Gress 227106 KW I Putih ROMAN AM 30 0.2000 Kg Rp. 20,727.00 4,145.40
Semen 0.1632 Zak Rp. 69,000.00 11,260.80
Pasir muntilan 0.0194 M3 Rp. 285,000.00 5,529.00
Upah 1.0000 M2 Rp. 34,875.00 34,875.00

3 1 M2 Keramik Lantai 33x33 Keramik 1.1000 M2 Rp. 80,454.00 88,499.40


Strata beige Roman KW 1 AM 55 nat 0.2000 Kg Rp. 70,350.00 14,070.00
Semen 0.1632 Zak Rp. 69,000.00 11,260.80
Pasir muntilan 0.0194 M3 Rp. 285,000.00 5,529.00
Upah 1.0000 M2 Rp. 24,750.00 24,750.00

4 1 M2 Keramik Lantai 30x30 Keramik 1.1000 M2 Rp. 42,500.00 46,750.00


Murano KW I Putih Asia Tile AM 50 0.2000 Kg Rp. 15,910.00 3,182.00
Semen 0.1632 Zak Rp. 69,000.00 11,260.80
Pasir muntilan 0.0194 M3 Rp. 285,000.00 5,529.00
Upah 1.0000 M2 Rp. 24,750.00 24,750.00

5 1 M2 Keramik Dinding 30x30 Keramik 1.1000 M2 Rp. 42,500.00 46,750.00


Murano KW I Putih Asia Tile AM 50 0.2000 Kg Rp. 15,910.00 3,182.00
Semen 0.1632 Zak Rp. 69,000.00 11,260.80
Pasir muntilan 0.0194 M3 Rp. 285,000.00 5,529.00
Upah 1.0000 M2 Rp. 34,875.00 34,875.00

6 1 M1 Plint Keramik Lantai 7x30 Keramik 0.1100 M2 Rp. 42,500.00 4,675.00


Murano KW I Putih Asia Tile AM 50 0.0200 Kg Rp. 15,910.00 318.20
Semen 0.0163 Zak Rp. 69,000.00 1,126.08
Pasir muntilan 0.0019 M3 Rp. 285,000.00 552.90
Sponengan tali air 1.0000 M' Rp. 7,875.00 7,875.00
Upah 1.0000 M' Rp. 11,250.00 11,250.00

IV Pekerjaan BETON BERTULANG

A BETON SLOOF PRAKTIS 15x20 1:2:3 SITE MIX


1 Beton 1:2:3 Semen 6.8000 Zak Rp. 69,000.00 469,200.00
Kris 0.8200 M3 Rp. 215,000.00 176,300.00
Pasir Muntilan 0.5400 M3 Rp. 285,000.00 153,900.00
Upah 1.0000 M3 Rp. 168,750.00 168,750.00
1 M3 Beton Sloof 968,150.00

2 Besi Beton Besi Beton 1.1000 Kg Rp. 9,200.00 10,120.00


Bendrat 0.0200 Kg Rp. 12,500.00 250.00
Upah 1.0000 Kg Rp. 2,250.00 2,250.00
1 Kg Besi Beton 12,620.00

3 Begesting Multiplex 12 mm 0.3500 Lb Rp. 205,000.00 71,750.00


Kaso 4/6 Meranti 0.0064 M3 Rp. 5,200,000.00 33,280.00
Paku 0.4000 Kg Rp. 11,500.00 4,600.00
Upah 1.0000 M2 Rp. 22,500.00 22,500.00
132,130.00
1 M2 Cetakan/ Begesting 0.4 x Rp. 132,130.00 52,852.00

B BETON KOLOM PRAKTIS / RING PRAKTIS 15x15 1:2:3


1 Beton 1:2:3 Semen 6.8000 Zak Rp. 69,000.00 469,200.00
Kris 0.8200 M3 Rp. 215,000.00 176,300.00
Pasir Muntilan 0.5400 M3 Rp. 285,000.00 153,900.00
Upah 1.0000 M3 Rp. 168,750.00 168,750.00
1 M3 Beton KP 968,150.00

2 Besi Beton Besi Beton 1.1000 Kg Rp. 9,200.00 10,120.00


Bendrat 0.0200 Kg Rp. 12,500.00 250.00
Upah 1.0000 Kg Rp. 2,250.00 2,250.00
1 Kg Besi Beton 12,620.00

3 Begesting Multiplex 12 mm 0.3500 Lb Rp. 205,000.00 71,750.00


Kaso 4/6 Meranti 0.0064 M3 Rp. 5,200,000.00 33,280.00
Paku 0.4000 Kg Rp. 11,500.00 4,600.00
Upah 1.0000 M2 Rp. 22,500.00 22,500.00
132,130.00
1 M2 Cetakan/ Begesting 0.4 x Rp. 132,130.00 52,852.00

C BETON KOLOM / BALOK/ PLAT DAG 12 cm 1:2:3


1 Beton 1:2:3 Semen 6.8000 Zak Rp. 69,000.00 469,200.00
Kris 0.8200 M3 Rp. 215,000.00 176,300.00
Pasir Muntilan 0.5400 M3 Rp. 285,000.00 153,900.00
Upah 1.0000 M3 Rp. 225,000.00 225,000.00
1 M3 Beton kolom / balok 1,024,400.00

2 Besi Beton Kolom / balok Besi Beton 1.1000 Kg Rp. 9,200.00 10,120.00
Bendrat 0.0200 Kg Rp. 12,500.00 250.00
Upah 1.0000 Kg Rp. 2,250.00 2,250.00
12,620.00

3 Begesting Multiplex 12 mm 0.3500 Lb Rp. 205,000.00 71,750.00


Kaso 4/6 Meranti 0.0048 M3 Rp. 5,200,000.00 24,960.00
Paku 0.4000 Kg Rp. 11,500.00 4,600.00
Upah 1.0000 M2 Rp. 84,375.00 84,375.00
185,685.00
1 M2 Cetakan/ Begesting 1x pakai 1 x Rp. 185,685.00 185,685.00

4 Perancah Kaso 4/6 Meranti 0.0576 M3 Rp. 5,200,000.00 299,520.00


Papan suri 12.0000 Lbr Rp. 13,500.00 162,000.00
Paku 0.4000 Kg Rp. 11,500.00 4,600.00
Upah 1.0000 M2 Rp. 29,700.00 29,700.00
495,820.00
1 M2 Perancah balok 0.21 x Rp. 495,820.00 104,122.20

5 Begesting Multiplex 12 mm 0.3500 Lb Rp. - -


( Material kayu by Djarum ) Kaso 4/6 Meranti 0.0048 M3 Rp. - -
Paku 0.4000 Kg Rp. 11,500.00 4,600.00
Upah 1.0000 M2 Rp. 84,375.00 84,375.00
88,975.00
1 M2 Cetakan/ Begesting 1x pakai 1 x Rp. 88,975.00 88,975.00

D LANTAI KERJA
1 BETON 1:2:3 Semen 6.8000 Zak Rp. 69,000.00 469,200.00
Kris 0.8200 M3 Rp. 215,000.00 176,300.00
Pasir Muntilan 0.5400 M3 Rp. 285,000.00 153,900.00
Upah Cor 1.0000 M3 Rp. 168,750.00 168,750.00
1 M3 Beton Lantai Kerja 968,150.00

2 BETON 1:3:5 Semen 4.5360 Zak Rp. 69,000.00 312,984.00


Kris 0.9100 M3 Rp. 215,000.00 195,650.00
Pasir Muntilan 0.5400 M3 Rp. 285,000.00 153,900.00
Upah Cor 1.0000 M3 Rp. 168,750.00 168,750.00
1 M3 Beton Lantai Kerja 831,284.00

F BESI WM-6 SINGLE


1 BESI WM-6 SINGLE M-6 single 0.0978 Lbr Rp. 375,000.00 36,656.89
Bendrat 0.0200 Kg Rp. 12,500.00 250.00
Upah pasang 1.0000 m2 Rp. 7,312.50 7,312.50
1 M2 Terpasang 44,219.39

G BESI WM-8 SINGLE


1 BESI WM-8 SINGLE M-8 single 0.0978 Lbr Rp. 635,000.00 62,072.34
Bendrat 0.0200 Kg Rp. 12,500.00 250.00
Upah pasang 1.0000 m2 Rp. 7,312.50 7,312.50
1 M2 Terpasang 69,634.84

H BESI WM-8 DOUBLE


1 BESI WM-8 DOUBLE M-8 double 0.1955 Lbr Rp. 635,000.00 124,144.67
Bendrat 0.0400 Kg Rp. 12,500.00 500.00
Besi Beton cakar ayam 1.5400 Kg Rp. 12,620.00 19,434.80
Upah pasang 1.0000 m2 Rp. 14,625.00 14,625.00
1 M2 Terpasang 158,704.47

I BETON READY MIX K-250


1 Beton Ready Mix K-250 Ready Mix 1.0000 M3 Rp. 775,000.00 775,000.00
Sewa Pompa 1.0000 M3 Rp. 55,000.00 55,000.00
Upah Cor 1.0000 M3 Rp. 157,500.00 157,500.00
1 M3 Beton Ready mix K-250 987,500.00

J BETON READY MIX K-225


1 Beton Ready Mix K-225 Ready Mix 1.0000 M3 Rp. 750,000.00 750,000.00
Sewa Pompa 1.0000 M3 Rp. 55,000.00 55,000.00
Upah Cor 1.0000 M3 Rp. 157,500.00 157,500.00
1 M3 Beton Ready mix K-225 962,500.00

K DOWEL LANTAI
1 Dowel LANTAI Besi Ø 16 mm 1.3800 kg Rp. 9,200.00 12,696.00
Ø 16 L = 100 cm tiap jarak 50 cm Selang pelindung 50 c 0.5000 M' Rp. 10,000.00 5,000.00
Upah pasang 1.0000 bh Rp. 562.50 562.50
18,258.50
Tahun 2016

upah baru
+12,5 %

Total Harga

17,336.00
45,000.00 Rp. 22,000.00
15,187.50 Rp. 7,000.00

88,312.50

357,187.50 Rp. 7,000.00

690,195.00

22,064.40
OK terupdate

51,646.80 Rp. 12,500.00

122,524.50 Rp. 30,000.00


OK terupdate

54,424.80 Rp. 12,500.00


OK terupdate

57,799.80 Rp. 30,000.00

Rp. 12,000.00
67,592.10 Rp. 10,000.00

111,026.44 Rp. 11,000.00


830,442.00 Rp. 70,000.00
124,566.30

505,500.00 Rp. 70,000.00

13,575.00 Rp. 5,000.00

16,950.00

7,875.00 Rp. 3,500.00

25,453.88

31,937.18

23,875.13

30,358.43

43,105.25

29,813.25
384,125.00

372,520.91

271,664.80

725,287.58

Rp 145,750.00

93,196.80

140,809.40
144,109.20

91,471.80

101,596.80

25,797.18

OK terupdate
Rp. 75,000.00

Rp. 900.00

Rp. 7,500.00

OK terupdate

Rp. 80,000.00

Rp. 900.00

Rp. 25,000.00

Rp. 10,000.00
Rp. 65,000.00

Rp. 65,000.00

Rp. 2,500.00

Rp. 2,500.00

Rp. 65,000.00
No. Nama Material Berat Jenis Tabel berat Besi
1 Pasir
Kerikil, Koral, Split 1.400 kg/m3 mm
2 (kering/lembab)
Tanah, Lempung 1.800 kg/m3 6
3 (kering/lembab) 1.700 kg/m3 8
4 Tanah, Lempung (basah) 2.000 kg/m3 10
5 Batu
Batu Alam
Belah, Batu Bulat, 2.600 kg/m3 12
6 Batu Gunung 1.500 kg/m3
7 Batu Karang 700 kg/m3
8 Batu Pecah 1.450 kg/m3
9 Pasangan Bata Belah,
Pasangan Batu Merah 1.700 kg/m3
10 Bulat, Gunung 2.200 kg/m3
11 Pasangan Batu Cetak 2.200 kg/m3
12 Pasangan Batu Karang 1.450 kg/m3
13 Kayu (Kelas I) 1.000 kg/m3
14 Beton 2.200 kg/m3
15 Beton Bertulang 2.400 kg/m3
16 Besi Tuang 7.250 kg/m3
17 Baja 7.850 kg/m3
18 Timah/Timbel 11.400 kg/m3

Nama Produk Diameter Panjang Berat


Besi Beton Polos 6 mm 12 meter 2,66 kg
Besi Beton Polos 7 mm 12 meter 3,63 kg
Besi Beton Polos 8 mm 12 meter 4,74 kg
Besi Beton Polos 9 mm 12 meter 6,00 kg
Besi Beton Polos 10 mm 12 meter 7,40 kg
Besi Beton Polos 11 mm 12 meter 8,95 kg
Besi Beton Polos 12 mm 12 meter 10,70 kg
Besi Beton Polos 16 mm 12 meter 19,00 kg
Besi Beton Polos 19 mm 12 meter 26,80 kg
Besi Beton Polos 22 mm 12 meter 35,80 kg
Besi Beton Polos 25 mm 12 meter 46,20 kg
Besi Beton Polos 28 mm 12 meter 58,00 kg
Besi Beton Polos 32 mm 12 meter 75,72 kg
Tabel berat Besi
kg
0.222
0.395
0.617
0.888

Semen
Mutu Beton (kg) Pasir (kg) Kerikil (kg) Air (liter) w/c ratio
7.4 MPa (K 100) 247 869 999 215 0.87
9.8 MPa (K 125) 276 828 1012 215 0.78
12.2 MPa (K 150) 299 799 1017 215 0.72
14.5 MPa (K 175) 326 760 1029 215 0.66
16.9 MPa (K 200) 352 731 1031 215 0.61
19.3 MPa (K 225) 371 698 1047 215 0.58
21.7 MPa (K 250) 384 692 1039 215 0.56
24.0 MPa (K 275) 406 684 1026 215 0.53
26.4 MPa (K 300) 413 681 1021 215 0.52
28.8 MPa (K 325) 439 670 1006 215 0.49
31.2 MPa (K 350) 448 667 1000 215 0.48

m3
1m3 sloof 15x25 4.04 tabel
1 1m3 beton
semen 4.04 299 1,208.48 kg 24 zak
pasir 4.04 799 3,229.36 kg 2.0 m3
kerikil 4.04 1017 4,110.46 kg 2.2 m3
pekerja 4.04 1.65 6.67 oh
tukang 4.04 0.275 1.11 oh
kepala tukang 4.04 0.03 0.12 oh
mandor 4.04 0.083 0.34 oh

2 pembesian 107.78 m x tbl


tul.pokok 4d8 107.78 35.93 btg 170.29 kg
sengkang d6-20 538.9 bh
pjg sengkang 0.77 m
tot.pjg sengkang 414.95 m
34.58 btg 91.98 kg
Total keb.besi 262.27 kg
Bendrat 10% 26.23 kg
pekerja 262.27 0.007 1.84 oh
tukang 262.27 0.0007 0.18 oh
kepala tukang 262.27 0.00007 0.02 oh
mandor 262.27 0.0004 0.10 oh

3 bekisting 107.78
luas 0.25 2 53.89 m2
papan 53.89 1.7 91.613 lbr
paku 53.89 0.3 16.167 kg
pekerja 53.89 0.52 28.0228 oh
tukang 53.89 0.26 14.0114 oh
kepala tukang 53.89 0.026 1.40114 oh
mandor 53.89 0.026 1.40114 oh

total kebutuhan L=107.78m V=4.04m3


semen 24.00 zak
pasir 2.02 m3
kerikil 2.16 m3
besi d8 36.00 btg
besi d6 35.00 btg
papan 92.00 lbr
paku 16.167 kg
bendrat 26.23 kg
pekerja 36.53 oh
tukang 15.31 oh
kepala tukang 1.54 oh
mandor 1.84 oh

1 m3 beton sloof 15x25 8D6


semen 24.00 5.94 zak
pasir 2.02 0.50 m3
kerikil 2.16 0.54 m3
besi d8 36.00 0.33 btg
besi d6 35.00 0.32 btg
papan 92.00 0.85 lbr
paku 16.17 0.15 kg
bendrat 26.23 0.24 kg
pekerja 36.53 0.34 oh
tukang 15.31 0.14 oh
kepala tukang 1.54 0.01 oh
mandor 1.84 0.02 oh
m3
1m3 kolom 15x15 5.76 tabel
1 1m3 beton
semen 5.76 299 1,722.24 kg 34 zak
pasir 5.76 799 4,602.24 kg 2.88 m3
kerikil 5.76 1017 5,857.92 kg 3.08 m3
pekerja 5.76 1.65 9.50 oh
tukang 5.76 0.275 1.58 oh
kepala tukang 5.76 0.03 0.17 oh
mandor 5.76 0.083 0.48 oh

2 pembesian 256.00 m x tbl


tul.pokok 4d8 256.00 85.33333 btg 404.48 kg
sengkang d6-20 1,280.00 bh
pjg sengkang 0.57 m
tot.pjg sengkang 729.6 m
60.8 btg 161.728 kg
Total keb.besi 566.208 kg
Bendrat 10% 56.6208 kg
pekerja 566.208 0.007 3.963456 oh
tukang 566.208 0.0007 0.3963456 oh
kepala tukang 566.208 0.00007 0.0396346 oh
mandor 566.208 0.0004 0.2264832 oh

3 bekisting 256
luas 0.15 4 153.6 m2
papan 153.6 1.7 261.12 lbr
paku 153.6 0.3 46.08 kg
pekerja 153.6 0.52 79.872 oh
tukang 153.6 0.26 39.936 oh
kepala tukang 153.6 0.026 3.9936 oh
mandor 153.6 0.026 3.9936 oh

total kebutuhan L=256m V=5.76m3


semen 34.00 zak
pasir 2.88 m3
kerikil 3.08 m3
besi d8 86.00 btg
besi d6 61.00 btg
papan 262.00 lbr
paku 46.08 kg
bendrat 56.62 kg
pekerja 93.34 oh
tukang 41.92 oh
kepala tukang 4.21 oh
mandor 4.70 oh

1 m3 kolom 15x15 8D6


semen 34.00 5.90 zak
pasir 2.88 0.50 m3
kerikil 3.08 0.54 m3
besi d8 86.00 0.34 btg
besi d6 61.00 0.24 btg
papan 262.00 1.02 lbr
paku 46.08 0.18 kg
bendrat 56.62 0.22 kg
pekerja 93.34 0.36 oh
tukang 41.92 0.16 oh
kepala tukang 4.21 0.02 oh
mandor 4.70 0.02 oh
m3
1m3 Tiebalk 15x15 5.73 tabel
1 1m3 beton
semen 5.73 299 1,713.27 kg 34 zak
pasir 5.73 799 4,578.27 kg 2.86 m3
kerikil 5.73 1017 5,827.41 kg 3.07 m3
pekerja 5.73 1.65 9.45 oh
tukang 5.73 0.275 1.58 oh
kepala tukang 5.73 0.03 0.17 oh
mandor 5.73 0.083 0.48 oh

2 pembesian 254.72 m x tbl


tul.pokok 4d8 254.72 84.90667 btg 402.4576 kg
sengkang d6-20 1,273.60 bh
pjg sengkang 0.57 m
tot.pjg sengkang 725.952 m
60.496 btg 160.9194 kg
Total keb.besi 563.377 kg
Bendrat 10% 56.3377 kg
pekerja 563.377 0.007 3.9436387 oh
tukang 563.377 0.0007 0.3943639 oh
kepala tukang 563.377 0.00007 0.0394364 oh
mandor 563.377 0.0004 0.2253508 oh

3 bekisting 254.72
luas 0.15 2 76.416 m2
papan 76.416 1.7 129.9072 lbr
paku 76.416 0.3 22.9248 kg
pekerja 76.416 0.52 39.73632 oh
tukang 76.416 0.26 19.86816 oh
kepala tukang 76.416 0.026 1.986816 oh
mandor 76.416 0.026 1.986816 oh

total kebutuhan L=254.72m V=5.73m3


semen 34.00 zak
pasir 2.86 m3
kerikil 3.07 m3
besi d8 85.00 btg
besi d6 61.00 btg
papan 130.00 lbr
paku 22.92 kg
bendrat 56.34 kg
pekerja 53.13 oh
tukang 21.84 oh
kepala tukang 2.20 oh
mandor 2.69 oh

1 m3 tiebalk 15x15 8D6


semen 34.00 5.93 zak
pasir 2.86 0.50 m3
kerikil 3.07 0.54 m3
besi d8 85.00 0.33 btg
besi d6 61.00 0.24 btg
papan 130.00 0.51 lbr
paku 22.92 0.09 kg
bendrat 56.34 0.22 kg
pekerja 53.13 0.21 oh
tukang 21.84 0.09 oh
kepala tukang 2.20 0.01 oh
mandor 2.69 0.01 oh
m3
1m3 RingBalk 15x20 5.73 tabel
1 1m3 beton
semen 5.73 299 1,713.27 kg 34 zak
pasir 5.73 799 4,578.27 kg 2.9 m3
kerikil 5.73 1017 5,827.41 kg 3.1 m3
pekerja 5.73 1.65 9.45 oh
tukang 5.73 0.275 1.58 oh
kepala tukang 5.73 0.03 0.17 oh
mandor 5.73 0.083 0.48 oh

2 pembesian 254.72 m x tbl


tul.pokok 4d8 254.72 84.91 btg 402.46 kg
sengkang d6-20 1273.6 bh
pjg sengkang 0.67 m
tot.pjg sengkang 853.31 m
71.11 btg 189.15 kg
Total keb.besi 591.61 kg
Bendrat 10% 59.16 kg
pekerja 591.61 0.007 4.14 oh
tukang 591.61 0.0007 0.41 oh
kepala tukang 591.61 0.00007 0.04 oh
mandor 591.61 0.0004 0.24 oh

3 bekisting 254.72
luas 0.20 2 101.89 m2
papan 101.89 1.7 173.21 lbr
paku 101.89 0.3 30.57 kg
pekerja 101.89 0.52 52.98 oh
tukang 101.89 0.26 26.49 oh
kepala tukang 101.89 0.026 2.65 oh
mandor 101.89 0.026 2.65 oh

total kebutuhan L=254.72m V=5.73m3


semen 34.00 zak
pasir 2.86 m3
kerikil 3.07 m3
besi d8 85.00 btg
besi d6 72.00 btg
papan 174.00 lbr
paku 30.57 kg
bendrat 59.16 kg
pekerja 66.58 oh
tukang 28.48 oh
kepala tukang 2.86 oh
mandor 3.36 oh

1 m3 beton RingBalk 15x20 8D6


semen 34.00 5.93 zak
pasir 2.86 0.50 m3
kerikil 3.07 0.54 m3
besi d8 85.00 0.33 btg
besi d6 72.00 0.28 btg
papan 174.00 0.68 lbr
paku 30.57 0.12 kg
bendrat 59.16 0.23 kg
pekerja 66.58 0.26 oh
tukang 28.48 0.11 oh
kepala tukang 2.86 0.01 oh
mandor 3.36 0.01 oh