PROJECT: SAN ANTONIO RESIDENCE PROJECT

LOCATION: Sen. Gil Puyat, Malugay St., Makati City


SUBJECT: 2ND-6TH FLOOR EE & AUX ROOM SCHEDULE
DATE: 14-Jan-19

Stiffener
LEVEL CHB Laying Column, Lintel Plastering Remarks
Beams

6th Floor

EE Room 08-Feb-19 12-Feb-19 16-Feb-19

Aux Room 1 31-Jan-19 04-Feb-19 12-Feb-19

Aux Room 2 23-Jan-19 27-Jan-19 08-Feb-19

ME Pipe Chase 14-Feb-19 18-Feb-19 26-Feb-19

5th Floor

EE Room done 22-Jan-19 12-Feb-19

Aux Room done 20-Jan-19 04-Feb-19

ME Pipe Chase 06-Feb-19 10-Feb-19 14-Feb-19

4th Floor

EE Room done 18-Jan-19 08-Feb-19

Aux Room done 16-Jan-19 31-Jan-19

ME Pipe Chase 02-Feb-19 06-Feb-19 10-Feb-19

3rd Floor

EE Room done done 04-Feb-19

Aux Room done done 27-Jan-19

ME Pipe Chase 29-Jan-19 02-Feb-19 06-Feb-19

2nd Floor

EE Room 25-Jan-19 done 31-Jan-19

Aux Room done done 23-Jan-19


ME Pipe Chases (except
chases from G/F) 25-Jan-19 29-Jan-19 02-Feb-19

ME Hand-over 17-Jan-19