The following document describes the site and technical requirements to be provided when
installing the MATRIX-I FT-NIR spectrometer. To ensure optimum spectrometer
performance and operating reliability it is recommended to observe the following ambient
requirements.
Installation and initial operation of MATRIX-I will be performed by qualified Bruker service
personnel. The operating company has to prepare the spectrometer installation site in time,
and provide the utilities required. If the delivery of a data system and / or the installation of
the operating system and the application software has not been stipulated, the operating
company also needs to provide a data system that complies with the technical requirements
and has the required rights. (See enclosure.)
Contact Bruker service if you have any further questions with regard to installation
preparation procedures.
Correct Usage:
The spectrometer and its components should only be used according to the operating
instructions described in the manual or advised by a Bruker engineer. Do not perform any
technical changes on the spectrometer, components or on the spectrometer system! In case
of accessories or components produced by other manufacturers and used in connection with
the spectrometer, Bruker does not assume any liability for safe operation and proper
functioning.
When installing the spectrometer make sure that the main power supply connection can be
easily interrupted at any time, either by the safety plug, main switch or appliance inlet
connector.
Environmental Requirements:
Ideally, the spectrometer is not installed near vibration sources, e.g. ventilation hoods, air
conditioners, motors, elevators.
1
If the system was stored outside the range of the specified operating temperature, it must acclimatize before switching it on.
1. Power Supply:
Voltage: 100–240V ±10%, 50-60Hz
Overvoltage category: II according to EN 61010-1 or IEC 60664-1
Pollution degree: 2 according to EN 61010-1 or IEC 60664-1
Protection class: I according to IEC 61140
Power consumption (basic conf.): 75W typical, 180W max.
Connection: Socket outlet with earthing contact according to
VDE 0620-1 or IEC
Fuse: 16A (installation according to VDE 0100 or IEC)
2
Power cable: 3 x 1.5mm with safety plug
For safety purposes make sure that interfaces of electric accessories connected to the
spectrometer comply with SELV (safety extra low voltage) circuit requirements. This is met if
the accessory design is based on the requirements outlined in EN 61010 or EN 60950.
2. Dry Air:
For MATRIX-I no dry air is required.
3. Cooling Water:
For MATRIX-I no cooling water is required.
4. Weight, Dimension:
Weight: approx. 30kg
Dimensions: 48.8 x 31.2 x 25.3cm