Method Statement for Anti-termite

Treatment
One important activity on site is the application of Anti-termite. By the way, this is
always written in the specification.

This activity shall be done before the Blinding Works. But before we submit a Method
Statement for this activity to the Engineer we should first read again the specification in
order to comply the specific requirements being written on it.

Here is the Method Statement for Anti-termite Treatment.

1. Title
Method Statement for Anti-termite Treatment

2. Purpose and scope


1. The scope of the work is a proper way of Anti-termite Treatment ( vertically and
horizontally ) with the use of (approved Anti-termite Material ) on all concrete in
contact with the soil.
3. Work Procedure
1. Preliminary Activities
 Properly coordinate with the concerned party or main contractor on how the
process will be done with regards to application scheduling and area
preparation.
 Coordinate and confirmation of people site access. And the water source
accessibility on site.
 The Method Statement ( MS ), Material Safety Data Sheet ( MSDS ) and
Material Approval Request ( MAR) must be on hand with the QA/QC
Engineer before the commencement of the work.
2. Preconstruction Activities
 Remove all wooden pieces, concrete debris, plastic strips, tree stump roots,
deleterious materials etc.
 The soil shall be leveled and compacted if in case bottom of the blinding
before treatment starts.
 All construction related tests shall be approved by the Engineer prior to
treatment.
3. Construction Activities
 Under PCC of Foundation
 After the advice of the Engineer to proceed, the application shall immediately
begin by first preparing and mixing the solutions of Approved Anti-termite
material diluted with water at a rate of 1:49 Liter water as per manufacturer’s
recommendation.
 A solution of approved Anti-termite material diluted with water at a rate of
1:49 Liter shall be sprayed prior to casting of blinding of footing or any
foundation type with the application rate of 4 to 5 liter per square meter.
 The treated area shall then be covered with polythene sheet, it can be opened
free until 2 hours, and then casting can be started. Casting must be completed
by 2 to 24 hours after the Anti-termite application.

 Trench Around the Foundation Wall


 Backfill the sides up to the top level of the proposed foundation ( considering
that the height of the foundation will exceed more than 1 meter ).
 Make a trench with 150mm width by a 150mm depth along the perimeter of
the foundation.
 A solution of Approved Anti-termite material diluted with water at a rate of
1:49 Liter shall be sprayed with an application rate of 5 -6 Liter per linear
meter int the trench along the perimeter of the foundation.
 The trench shall be backfilled within 24 hours of treatment.
 Under PCC of Tie Beam
 A solution of Approved Anti-termite material diluted with water at a rate of
1:49 Liter shall be sprayed prior to the casting of PCC of tie beams with the
application rate of 4 to 5 Liter square meter.
 The treated area must be immediately covered by polythene sheet, it can be
uncovered for 2 hours before casting. And castingmust be completed by 2 to
24 hours after Anti-termite application.
Polythene sheet covering
 Underground Slab and Along the Side of the Beams
 The trench shall be constructed with a measure of 150mm by a 150mm depth
along the perimeter of the tie beams.
 A solution of the Approved Anti-termite material diluted with water at a rate
of 1:49 Liter will be sprayed prior to ground slab casting with the application
rate of 4 to 5 per square meter.
 With the same solution of Approved Anti-termite material, apply 5 to 6 Liter
per linear meter into the trench along the perimeter of the tie beams. Backfill
the trench after letting the termiticide subside within 2 hours. The backfilling
must be done within 2 to 24 hours after anti-termite application.
 Along the Outside Perimeter of the Building
 Make a trench, 150mm in width and 150mm in depth, along with the external
perimeter of the building at the same level of the landscape.
 A solution of Approved Anti-termite material diluted with water at a rate of
1:49 Liter will be sprayed into the trench along the external perimeter of the
building with an application rate of 5 to 6 Liter per linear meter.
 Back fill the trench within 2 to 24 hours after the treatment.
4. Safety
1. All works shall comply with the safety procedure or instruction as set out in project
safety plan and municipality rules and regulations.
2. Basic Personal Protective Equipment ( PPE ) shall be worn by all staff or laborers.
3. All operatives shall be inducted before entering the site.
4. Tool box talk shall be conducted before the activity.
5. Equipment and Tools
1. Power Sprayer (diesel – driven) fixed at the carriage of the service car
2. Spray Nozzle ( used to facilitate the formations of spray in the targeted area)
3. Personal Protective Equipment, Safety helmet, Safety gloves, Safety shoes, eye
protection or goggles, approved respirator and safety jacket.
6. Materials and Reference
1. Approved Anti-termite Material
2. Approved Shop Drawing or Sketch