Professional Documents
Culture Documents
CP - ESP Air Leak Test PDF
CP - ESP Air Leak Test PDF
BHEL/TSX/JPL/BLR-CP/01
Stage II: (4X600 MW)
Plant Area: Boiler
Commissioning Procedure for Air in Leak test of ESP
Name
Sign
Signatures
JPL BHEL
Station: JPL, Tamnar Page 3 of 12
BHEL/TSX/JPL/BLR-CP/01
Stage II: (4X600 MW)
Plant Area: Boiler
Commissioning Procedure for Air in Leak test of ESP
List of Contents
2.0 Objectives
3.0 Proposals
8.0 Method
10.0 Appendices
a) Drawing
c) Log Sheets
Signatures
JPL BHEL
Station: JPL, Tamnar Page 4 of 12
BHEL/TSX/JPL/BLR-CP/01
Stage II: (4X600 MW)
Plant Area: Boiler
Commissioning Procedure for Air in Leak test of ESP
Specifications of ESP
2.0 OBJECTIVE
Signatures
JPL BHEL
Station: JPL, Tamnar Page 5 of 12
BHEL/TSX/JPL/BLR-CP/01
Stage II: (4X600 MW)
Plant Area: Boiler
Commissioning Procedure for Air in Leak test of ESP
3.0 PROPOSAL
5.1 First Aid Box should be available near the test area.
5.5 The area where test fan is located should be clearly marked to
avoid any accident / human injury.
Signatures
JPL BHEL
Station: JPL, Tamnar Page 6 of 12
BHEL/TSX/JPL/BLR-CP/01
Stage II: (4X600 MW)
Plant Area: Boiler
Commissioning Procedure for Air in Leak test of ESP
7.3 Hopper outlet opening is closed by suitable plates and Fly Ash
removal system is not connected to the hopper.
7.4 All manhole doors on the roof, inspection doors on the casing
and hoppers are closed.
Signatures
JPL BHEL
Station: JPL, Tamnar Page 7 of 12
BHEL/TSX/JPL/BLR-CP/01
Stage II: (4X600 MW)
Plant Area: Boiler
Commissioning Procedure for Air in Leak test of ESP
8.0 METHOD
8.1 Start the fan keeping the control damper of the fan in
minimum position and allow the fan to reach its full speed.
8.2 Regulate the damper slowly and pressurize ESP such that
constant pressure differential is maintained in ‘U’ tube
manometer mounted on the hopper.
8.4 Repeat the test for different pressures in ESP viz., 100, 150,
200, 250 and 300 mmwc by suitably varying the damper
control of fan and note down corresponding pressure
differentials across the venturimeter
8.5 Using the above observations, the air leakage per pass is
calculated as per steps given below:
8.5.1 When stable conditions are established, the mass flow rate of
air through the fan, Venturimeter and the precipitator must
be constant.
mf = Qxγ
where
Q = volumetric flow of air in m3 / hr
γ = density of air at test conditions in kg / m3
8.5.3 The mass flow rate through the Venturimeter can be written
as a function of the pressure differential and the co-efficient of
discharge of the Venturi.
where
γ1 = density of air in Kg / m3
Signatures
JPL BHEL
Station: JPL, Tamnar Page 8 of 12
BHEL/TSX/JPL/BLR-CP/01
Stage II: (4X600 MW)
Plant Area: Boiler
Commissioning Procedure for Air in Leak test of ESP
8.5.4 The mass leakage of air through ESP pass can be expressed
as
where
8.5.5 Since
mv = mfilter
γ1 = γ2
Therefore
where
8.5.7 The tests are conducted for different Psfilter conditions viz.,
100, 150, 200, 250 and 300 mmwc by suitably varying the
Fan control damper.
Signatures
JPL BHEL
Station: JPL, Tamnar Page 9 of 12
BHEL/TSX/JPL/BLR-CP/01
Stage II: (4X600 MW)
Plant Area: Boiler
Commissioning Procedure for Air in Leak test of ESP
Kfilter = 0.03
γfilter = 0.87
Psfilter = 200
Therefore
= 0.455 m3/sec
Signatures
JPL BHEL
Station: JPL, Tamnar Page 10 of 12
BHEL/TSX/JPL/BLR-CP/01
Stage II: (4X600 MW)
Plant Area: Boiler
Commissioning Procedure for Air in Leak test of ESP
Signatures
JPL BHEL
Station: JPL, Tamnar Page 11 of 12
BHEL/TSX/JPL/BLR-CP/01
Stage II: (4X600 MW)
Plant Area: Boiler
Commissioning Procedure for Air in Leak test of ESP
Signatures
JPL BHEL
Station: JPL, Tamnar Page 12 of 12
BHEL/TSX/JPL/BLR-CP/01
Stage II: (4X600 MW)
Plant Area: Boiler
Commissioning Procedure for Air in Leak test of ESP
1.
2.
3.
4.
5.
6.
7.
8.
9.
Signatures
JPL BHEL