Sabg Schools Phase III - Uge01 - Monthly Progress Report - April-24 Rev-00
Sabg Schools Phase III - Uge01 - Monthly Progress Report - April-24 Rev-00
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
DOCUMENT TITLE:
Page 1
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
TABLE OF CONTENTS
1. INTRODUCTION......................................................................................................................... 3
1.1 PROJECT OBJECTIVE ............................................................................................................. 3
1.2 CONTRACT DETAILS ............................................................................................................... 3
2. PROJECT SUMMARY................................................................................................................ 3
2.1 SCOPE OF WORK ..................................................................................................................... 3
2.2 EXECUTIVE SUMMARY ............................................................................................................ 4
2.3 AREAS OF CONCERN ............................................................................................................... 4
3. PROGRESS ................................................................................................................................ 5
4. HEALTH, SAFETY AND ENVIRONMENTAL STATISTICS:..................................................... 7
5. PROJECT MILESTONE ............................................................................................................ 8
6. QA/QC ....................................................................................................................................... 9
6.1 LOG BOOK ENTRY SUMMARY TABLE..…………………………………………………………...9
6.2 SANCR SUMMARY TABLE .………………………………………………………………………….9
6.3 INCR SUMMARY TABLE .…………………………………………………………………………….9
6.4 INSPECTION SUMMARY TABLE .……………………………………………………………….. ...9
7.0 ENGINEERING ......................................................................................................................... 10
7.1 ACTIVITY PERFORMED IN THE REPORTED PERIOD ......................................................... 10
7.2 ACTIVITIES PLANNED FOR THE NEXT MONTH ................................................................... 10
7.3 ENGINEERING S-CURVE ........................................................................................................ 10
8.0 PROCUREMENT ...................................................................................................................... 11
8.1 ACTIVITY PERFORMED IN THE REPORTED PERIOD ......................................................... 11
8.2 ACTIVITIES PLANNED FOR THE NEXT MONTH ................................................................... 11
8.3 PROCUREMENT S-CURVE ..................................................................................................... 12
9.0 CONSTRUCTION ..................................................................................................................... 13
9.1 ACTIVITY PERFORMED IN THE REPORTED PERIOD ......................................................... 13
9.2 ACTIVITIES PLANNED FOR THE NEXT MONTH ................................................................... 13
9.3 CONSTRUCTION S-CURVE .................................................................................................... 13
10. MANPOWER HOISTOGRAM .................................................................................................. 14
11. CRITICAL ISSUES ................................................................................................................... 15
12. TRANSMITTAL STATUS ........................................................................................................ 15
13. PROGRESS PHOTGRAPHS .................................................................................................. 16
Page 2
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
1. INTRODUCTION
The Project objective is to carry out Engineering, Procurement and Construction works for two Schools
(SABG-Phase III) Saudi Aramco build government schools in Uyoun Area location has having 2 schools,
and this shall be in accordance with Saudi Aramco Engineering Standards
CLIENT
SAUDI ARAMCO
Contract
Completion date 01-June-2025
Forecast
01-June-2025
Completion
2. PROJECT SUMMARY
The Scope of Work include Engineering, Procurement and Construction works for Uyun Girls School
(SABG-Phase III) Saudi Aramco build government schools in UYUN Area , and this shall be in
accordance to Saudi Aramco Engineering Standards, The school shall comply with applicable Saudi
Government building codes, as well as health, safety, and environment (HSE) standards, taking in
consideration the current Ministry of Education (MOE) academic and functional facilities requirements.
Scope of work is as specified in the CONTRACT and provided 30% Detailed Design Package The
description and scope of works of the project includes Building Works that are further subdivided to Civil,
Architectural, Electrical, Plumbing, HVAC, Fire Protection System, Fire Detection and Alarm System,
Communication, and Tie-ins to Utility Services and Sports Facilities.
Page 3
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
This Report Covers the period from 25- March -24 to 25-April-24
Page 4
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
DESCRIPTION WTG%
PLAN RECOVER ACTUAL VARIANCE PLAN RECOVER ACTUAL VARIANCE PLAN RECOVER ACTUAL VARIAN
PLAN PLAN PLAN CE
ENGINEERING 7.24% 100% 99.73% 99.80% 0.07% 0.00% 0.27% 0.20% -0.07% 100% 100.00% 100% 0.00%
-
PROCUREMENT 16.94% 59.09% 24.65% 21.67% -2.98% 2.82% 16.88% 5.70% -11.18% 61.91% 41.53% 27.37%
14.15%
CONSTRUCTION 75.82% 27.62% 9.16% 8.97% -0.19% 3.92% 3.68% 1.25% -2.43% 31.54% 12.84% 10.22% -2.62%
100.00
OVERALL 38.33% 18.34% 17.70% -0.64% 3.46% 5.67% 1.93% -3.75% 41.80% 24.01% 19.63% -4.39%
%
DESCRIPTION WTG%
PLAN RECOVER ACTUAL VARIANCE PLAN RECOVER ACTUAL VARIANCE PLAN RECOVER ACTUA VARIANCE
PLAN PLAN PLAN L
MOBILIZATION 3.68% 100.00% 100.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 100.00% 0.00%
ENGINEERING 7.24% 100.00% 99.73% 99.80% 0.06% 0.00% 0.27% 0.20% -0.06% 100.00% 100.00% 100.00% 0.00%
PROCUREMENT 16.94% 59.09% 24.65% 21.67% -2.97% 2.82% 16.88% 5.70% -11.18% 61.91% 41.53% 27.37% -14.15%
DEMOLITION
2.27% 100.00% 99.18% 95.35% -3.83% 0.00% 0.82% 0.00% -0.82% 100.00% 100.00% 95.35% -4.65%
WORKS
CONSTRUCTIO
69.21% 21.76% 1.48% 1.40% -0.08% 4.31% 4.00% 1.37% -2.64% 26.07% 5.49% 2.77% -2.72%
N
TESTING &
COMMISSIONIN 0.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
G
COMPLETION &
0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
CLOSING OUT
OVERALL 100.00% 38.33% 18.34% 17.70% -0.64% 3.46% 5.67% 1.93% -3.75% 41.80% 24.01% 19.63% -4.39%
Page 5
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
Engineering: - 0.00%
Mitigation:
Mitigation:
Page 6
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
a. MANPOWER:
INDIRECT 5
***FAT – Fatality LTI – Lost Time Injury/Illness RDI – Restricted Duty Incident MTC – Medical Treatment Case FAI –
First Aid Incident
MVA – Motor Vehicle Accident FAT – Motor Vehicle Fatality NM – Near Misses Fires PD – Property Damage
UDPW – Unsafe Driving Practice Warning – UA/UC – Unsafe Act/Unsafe Condition
CONTRACTOR INCIDENTS
*** FAT LTI RDI MTC FAI MVA MV NM FIRES PD UDPW UA/UC
- on FAT
job
# OF
INCIDENTS - 0 0 0 0 0 0 0 0 0 0 0 00
THIS
MONTH
# OF
INCIDENTS - 0 0 0 0 0 0 0 1 0 0 0 00
LAST
MONTH
# OF
INCIDENTS
0 0 0 0 0 0 0 11 0 0 0 00
–
YEAR-TO-
DATE
# OF
INCIDENTS 0 0 0 0 0 0 0 11 0 0 0 00
– PROJECT
TOTAL
OSHA Recordable Cases - (# of OSHA Recordable Cases x 200,000) / # of hours worked.
Page 7
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
5. PROJECT MILESTONE
Contractual Forecast
Description Status
Dates /Actual
General
Project Commencement Date 2-Feb-23 2-Feb-23 Achieved
Submit Final Work Schedule 13-Apr-23 13-Apr-23 Achieved
Mobilization Plan and all other required safety plans
13-Apr-23 13-Apr-23 Achieved
required to initiate the "Notice to Proceed"
Engineering
Complete Design Office mobilization 19-Mar-23 19-Mar-23 Achieved
Issue early IFC site preparation drawings and tie-in
3-May-23 03-Sep-23 Completed
packages
Complete 60% Design Review Cycle and close
1-Aug-23 28-Aug-23 Completed
comments
Complete 90% Design Review Cycle and close
30-Oct-23 30-Oct-23 Completed
comments
Completed (Ref
Issue all IFC drawings and documents 29-Dec-23 29-Dec-23 Transmittal 21-April-
24)
Procurement
Award all Pos for Long-Lead and bulk Items 13-Jan-24 25-May-24 -
Construction
Complete Site mobilization Including all temporary
2-Jun-23 28-Dec-23 Completed
construction facilities for start of construction
Page 8
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
6. QA/QC STATISTICS
Page 9
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
7. ENGINEERING:
Page 10
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
8. PROCUREMENT
Procurement Status:
Under
Description Total Submitted Rejected Approved Remarks
review
1. KIC-SABGS-3-MR-16-
M.R. Package 39 39 0 0 39 R.02- Fire Water
Valves- Approved.
RFQ 39 38 3 0 35
Technical Bid
39 31 2 0 30
Evaluation
KIC-SABGS-3-AR-04- Low
Voltage Panel Board-
Under Review.
Award KIC-SABGS-3-AR-05- Low
Recommendation & 39 13 3 0 12 Voltage Switch Board-
NOL Under Review.
KIC-SABGS-3-AR-08- Fire
Detection and Alarm
System- Under Review
P.O. Placement 39 29 3 0 17
65 52 7 37 30 42 0 0 0
Page 11
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
RFQ Submission of Chilled Water Pipe insulation, Chilled water pipe cladding
MTA/TBE submission for G
PO placement of Jockey Pump, Diesel pump, Electrical Pump, Chilled Water pump,
Doors with Hardware
Floating of RFQ’S
Issuance of Purchase order
Delivery of Civil Materials
Page 12
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
9. CONSTRUCTION
Page 13
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
ACTION
Category Description ACTION BY REMARKS
REQUIRED
ENGINEERING
PROCUREMENT
Delay in release of PO will
Release all
impact the work progress and KIC
PO’S
project completion
CONSTRUCTION
Delay in invoice workflow & Expediting
release of payment will impact the workflow
SAPMT/JLL
the contractor’s payment of and release
obligation of payment
Resolve
Construction Delay due to non- vendor
availability of resources payments KIC
QA/QC
Code 1 APPROVED 1
Code 2 APPROVED WITH CONDITION 2
Code 3 APPROVED AS NOTED 3
Code 4 REVISE AND RESUBMIT 4
Code 5 REJECTED 2
Code 6 CANCEL / REVIEW NOT REQUIRED 0
UR UNDER REVIEW 25
Total Transmittal 38
Total SAMPT Response 13
Page 14
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
Page 15
Doc. No.: KIC-GEN-REP-0094
Revision: 0
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
ANNEXURE-1
Engineering S-Curve
Page 16
Doc. No.: KIC-GEN-REP-0094
Revision: 0
KHONAINI INTERNATIONAL COMPANY LTD.
SABG SCHOOLS PHASE III UYUN GIRLS ELEMENTARY SCHOOL
( C/No: 6601000200 / BI.No:23-10883)
`
ENGINEERING MONTHLY PROGRESS S-CURVE
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
20.00% 100.00%
99.80% 99.80% 100.00%
99.80% 100.00%
100.00% 100.00% 100.00% 100.00% 100.00%
100.00% 100.00%
100.00% 100.00%
100.00% 100.00%
100.00% 100.00%
100.00% 100.00%
100.00% 100.00% 100.00%
100.00% 100.00% 100.00%
100.00% 100.00%
100.00%
98.43%
99.80%
92.41%
92.54%
18.00% 87.83% 90.00%
83.32%
73.53%
52.03%
Issue IFC
Milestone
42.63%
0.00% 0.00%
0.00%
DURATION
31-Jul-23
31-Jul-24
31-Jan-24
31-Jan-25
30-Jun-23
30-Jun-24
30-Jun-25
31-Oct-23
31-Oct-24
28-Feb-23
29-Feb-24
28-Feb-25
30-Apr-23
30-Apr-24
30-Apr-25
30-Sep-23
30-Sep-24
31-Dec-23
31-Dec-24
31-Aug-23
31-Aug-24
30-Nov-23
30-Nov-24
31-Mar-23
31-Mar-24
31-Mar-25
31-May-23
31-May-24
31-May-25
BL Plan Progress % RS Plan Progress % Actual Progress % BL Plan Cumulative Progress % Actual Cumulative Progress % RS Plan Cumulative Progress %
Start of Month 01-Jan-23 01-Feb-23 01-Mar-23 01-Apr-23 01-May-23 01-Jun-23 01-Jul-23 01-Aug-23 01-Sep-23 01-Oct-23 01-Nov-23 01-Dec-23 01-Jan-24 01-Feb-24 01-Mar-24 01-Apr-24 01-May-24 01-Jun-24 01-Jul-24 01-Aug-24 01-Sep-24 01-Oct-24 01-Nov-24 01-Dec-24 01-Jan-25 01-Feb-25 01-Mar-25 01-Apr-25 01-May-25 01-Jun-25
End of Month 31-Jan-23 28-Feb-23 31-Mar-23 30-Apr-23 31-May-23 30-Jun-23 31-Jul-23 31-Aug-23 30-Sep-23 31-Oct-23 30-Nov-23 31-Dec-23 31-Jan-24 29-Feb-24 31-Mar-24 30-Apr-24 31-May-24 30-Jun-24 31-Jul-24 31-Aug-24 30-Sep-24 31-Oct-24 30-Nov-24 31-Dec-24 31-Jan-25 28-Feb-25 31-Mar-25 30-Apr-25 31-May-25 30-Jun-25
DETAIL DESIGN
BL Plan Progress % 0.00% 3.51% 6.89% 15.55% 16.68% 9.40% 9.56% 11.94% 9.79% 4.51% 4.58% 7.59% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
RS Plan Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Actual Progress % 0.00% 3.51% 6.57% 15.55% 16.64% 9.48% 9.66% 2.65% 6.57% 10.53% 11.36% 5.89% 1.36% 0.00% 0.00% 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
BL Plan Cumulative Progress % 0.00% 3.51% 10.40% 25.95% 42.63% 52.03% 61.59% 73.53% 83.32% 87.83% 92.41% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
RS Plan Cumulative Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Actual Cumulative Progress % 0.00% 3.51% 10.08% 25.63% 42.27% 51.75% 61.41% 64.06% 70.64% 81.17% 92.54% 98.43% 99.80% 99.80% 99.80% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
BL Plan Man-Hours 0 1365.2 2679.44 6050.97 6490.88 3656.54 3720.17 4646.04 3810.48 1754.29 1780.44 2953.56
Actual Man-Hours 0 1365.2 2556.52 6049.88 6475.22 3689.3 3758.88 1031.21 2558.15 4098.84 4421.13 2293.18 530.99 0 0 79.51
BL Plan Cumulative Man-Hours 0 1365.2 4044.64 10095.61 16586.49 20243.03 23963.2 28609.24 32419.72 34174.01 35954.45 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01
RS Plan Cumulative Man-Hours 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01
Actual Cumulative Man-Hours 0 1365.2 3921.72 9971.6 16446.82 20136.12 23895 24926.21 27484.36 31583.2 36004.33 38297.51 38828.5 38828.5 38828.5 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01 38908.01
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
ANNEXURE-2
Procurement S-Curve
Page 17
Doc. No.: KIC-GEN-REP-0094
Revision: 0
KHONAINI INTERNATIONAL COMPANY LTD.
SABG SCHOOLS PHASE III UYUN GIRLS ELEMENTARY SCHOOL
( C/No: 6601000200 / BI.No:23-10883)
86.46%
RS Plan Progress %
70.87%
Milestone
73.56%
70.00%
16.27%
57.36%
Recovery Schedule
54.95%
15.49%
Actual Cumulative Progress %
15.00% 50.00%
46.28%
13.89%
RS Plan Cumulative Progress %
12.00% 40.00%
38.68%
10.27%
10.26%
30.79%
8.90%
30.00%
8.53%
9.00% 27.37%
8.14%
7.53%
7.22%
24.78% 21.67%
6.46%
6.44%
6.02%
5.93%
19.12%
5.70%
5.68%
5.61%
6.00% 20.00%
15.49%
4.71%
3.63%
3.60%
3.47%
14.53%
3.37%
3.35%
3.18%
9.56%
3.06%
2.83%
2.72%
8.08%
2.55%
10.00%
2.49%
3.00%
2.41%
2.36%
6.68%
2.09%
1.95%
1.60%
8.08%
1.48%
1.48%
1.40%
1.25%
0.91%
0.80%
1.96%
0.71%
4.91%
0.50%
0.36%
0.36%
0.23%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00% 0.73%
1.53% 0.00%
0.00% 0.00% 0.00% 0.00% 0.23%
DURATION
31-Jul-23
31-Jul-24
31-Jan-24
31-Jan-25
30-Jun-23
30-Jun-24
30-Jun-25
31-Oct-23
31-Oct-24
28-Feb-23
29-Feb-24
28-Feb-25
30-Apr-23
30-Apr-24
30-Apr-25
30-Sep-23
30-Sep-24
31-Dec-23
31-Dec-24
31-Aug-23
31-Aug-24
30-Nov-23
30-Nov-24
31-Mar-23
31-Mar-24
31-Mar-25
31-May-23
31-May-24
31-May-25
Start of Month 01-Jan-23 01-Feb-23 01-Mar-23 01-Apr-23 01-May-23 01-Jun-23 01-Jul-23 01-Aug-23 01-Sep-23 01-Oct-23 01-Nov-23 01-Dec-23 01-Jan-24 01-Feb-24 01-Mar-24 01-Apr-24 01-May-24 01-Jun-24 01-Jul-24 01-Aug-24 01-Sep-24 01-Oct-24 01-Nov-24 01-Dec-24 01-Jan-25 01-Feb-25 01-Mar-25 01-Apr-25 01-May-25 01-Jun-25
End of Month 31-Jan-23 28-Feb-23 31-Mar-23 30-Apr-23 31-May-23 30-Jun-23 31-Jul-23 31-Aug-23 30-Sep-23 31-Oct-23 30-Nov-23 31-Dec-23 31-Jan-24 29-Feb-24 31-Mar-24 30-Apr-24 31-May-24 30-Jun-24 31-Jul-24 31-Aug-24 30-Sep-24 31-Oct-24 30-Nov-24 31-Dec-24 31-Jan-25 28-Feb-25 31-Mar-25 30-Apr-25 31-May-25 30-Jun-25
MATERIAL PROCUREMENT
BL Plan Progress % 0.00% 0.00% 0.00% 0.00% 0.23% 0.50% 0.80% 3.37% 3.18% 6.44% 10.26% 13.89% 16.27% 2.41% 2.72% 2.49% 1.95% 2.09% 3.60% 3.35% 5.68% 7.22% 5.61% 2.83% 2.36% 1.25% 1.48% 0.00% 0.00% 0.00%
RS Plan Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.27% 15.49% 8.14% 0.91% 3.06% 6.02% 6.46% 7.53% 8.53% 8.90% 3.47% 0.71% 0.00% 0.00% 0.00% 0.00%
Actual Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.36% 1.60% 4.71% 1.40% 1.48% 5.93% 3.63% 2.55% 5.70%
BL Plan Cumulative Progress % 0.00% 0.00% 0.00% 0.00% 0.23% 0.73% 1.53% 4.91% 8.08% 14.53% 24.78% 38.68% 54.95% 57.36% 60.08% 62.57% 64.52% 66.62% 70.22% 73.56% 79.24% 86.46% 92.07% 94.91% 97.27% 98.52% 100.00% 100.00% 100.00% 100.00%
RS Plan Cumulative Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 8.08% 0.00% 0.00% 19.12% 30.79% 46.28% 54.42% 55.33% 58.39% 64.41% 70.87% 78.40% 86.93% 95.82% 99.29% 100.00% 100.00% 100.00% 100.00% 100.00%
Actual Cumulative Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.36% 1.96% 6.68% 8.08% 9.56% 15.49% 19.12% 21.67% 27.37%
BL Plan Man-Hours 207.14 457.14 732.38 3069.82 2890.48 5861.85 9335.36 12644.17 14808.33 2194.21 2474.86 2265.73 1775.89 1903.52 3275.11 3044.48 5168.48 6568.14 5108.62 2578.43 2149.48 1140.67 1345.71
RS Plan Man-Hours 9348.75 14097.59 7407.49 824.95 2781.42 5479.5 5879.21 6852.9 7760.42 8095.05 3157.36 642.86 0 0 0 0
Actual Man-Hours 0 0 0 0 0 0 331.05 1455.22 4289.57 1274.16 1349.60 5396.30 3304.10 2323 5188
BL Plan Cumulative Man-Hours 0 0 0 0 207.14 664.28 1396.66 4466.48 7356.96 13218.81 22554.17 35198.34 50006.67 52200.88 54675.74 56941.47 58717.36 60620.88 63895.99 66940.47 72108.95 78677.09 83785.71 86364.14 88513.62 89654.29 91000.00 91000.00 91000.00 91000.00
RS Plan Cumulative Man-Hours 28021.25 42118.84 49526.33 50351.28 53132.70 58612.20 64491.41 71344.31 79104.73 87199.78 90357.14 91000.00 91000.00 91000.00 91000.00 91000.00
Actual Cumulative Man-Hours 0 0 0 0 0 0 0 331.049927 1786.26961 6075.83866 7349.99838 8699.6 14095.9 17400.00 19723.00 24911.00
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
ANNEXURE-3
Construction S-Curve
Page 18
Doc. No.: KIC-GEN-REP-0094
Revision: 0
KHONAINI INTERNATIONAL COMPANY LTD.
SABG SCHOOLS PHASE III UYUN GIRLS ELEMENTARY SCHOOL
( C/No: 6601000200 / BI.No:23-10883)
89.04%
27.00% 90.00%
90.17%
83.29%
RS Plan Progress %
21.00% 68.02% 70.00%
Actual Progress %
66.71%
Recovery Schedule
50.99% 55.24%
Actual Cumulative Progress %
15.00% 50.00%
43.44%
12.65%
44.80%
12.00% 38.14%
11.47%
40.00%
10.80%
10.45%
32.61% 35.76%
Milestone
9.18%
9.04%
8.81%
8.81%
9.00% 28.72% 30.00%
7.97%
26.41%
7.85%
7.55%
24.45%
Substantial Completion
26.95%
21.60%
6.49%
6.46%
20.44%
5.75%
5.53%
6.00% 20.00%
5.30%
20.46%
4.91%
15.84%
4.60%
4.13%
3.99%
3.89%
12.54% 16.47%
3.45%
3.36%
3.30%
10.45% 10.22%
3.00%
13.47%
2.84%
8.89% 8.97%
2.58%
2.56%
3.00% 8.09% 7.82% 8.03% 8.30% 10.00%
2.31%
2.27%
7.17% 10.89%
2.11%
2.09%
6.46%
1.97%
1.87%
1.79%
1.56%
1.45%
1.25%
1.16%
2.58%
0.79%
2.36% 2.42%
0.71%
2.18%
0.67%
0.66%
0.45%
0.28%
0.28%
0.27%
0.25%
0.20%
0.18%
0.51%
0.16%
0.31%
0.13%
0.13%
0.06%
0.00% 0.06%
0.03%
0.03%
0.03%
0.03%
0.03%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00% 0.00%
DURATION
31-Jul-23
31-Jul-24
31-Jan-24
31-Jan-25
30-Jun-23
30-Jun-24
30-Jun-25
31-Oct-23
31-Oct-24
28-Feb-23
29-Feb-24
28-Feb-25
30-Apr-23
30-Apr-24
30-Apr-25
30-Sep-23
30-Sep-24
31-Dec-23
31-Dec-24
31-Aug-23
31-Aug-24
30-Nov-23
30-Nov-24
31-Mar-23
31-Mar-24
31-Mar-25
31-May-23
31-May-24
31-May-25
Start of Month 01-Jan-23 01-Feb-23 01-Mar-23 01-Apr-23 01-May-23 01-Jun-23 01-Jul-23 01-Aug-23 01-Sep-23 01-Oct-23 01-Nov-23 01-Dec-23 01-Jan-24 01-Feb-24 01-Mar-24 01-Apr-24 01-May-24 01-Jun-24 01-Jul-24 01-Aug-24 01-Sep-24 01-Oct-24 01-Nov-24 01-Dec-24 01-Jan-25 01-Feb-25 01-Mar-25 01-Apr-25 01-May-25 01-Jun-25
End of Month 31-Jan-23 28-Feb-23 31-Mar-23 30-Apr-23 31-May-23 30-Jun-23 31-Jul-23 31-Aug-23 30-Sep-23 31-Oct-23 30-Nov-23 31-Dec-23 31-Jan-24 29-Feb-24 31-Mar-24 30-Apr-24 31-May-24 30-Jun-24 31-Jul-24 31-Aug-24 30-Sep-24 31-Oct-24 30-Nov-24 31-Dec-24 31-Jan-25 28-Feb-25 31-Mar-25 30-Apr-25 31-May-25 30-Jun-25
CONSTRUCTION
BL Plan Progress % 0.00% 0.03% 0.03% 0.45% 4.13% 3.45% 0.79% 1.56% 2.09% 3.30% 4.60% 1.16% 2.84% 1.97% 2.31% 3.89% 5.53% 5.30% 7.55% 9.18% 7.85% 8.81% 6.46% 5.75% 4.91% 3.36% 2.27% 0.28% 0.13% 0.00%
RS Plan Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.56% 2.58% 3.00% 3.99% 6.49% 8.81% 9.04% 10.45% 11.47% 12.65% 10.80% 7.97% 1.45% 0.28% 0.13% 0.00%
Actual Progress % 0.00% 0.03% 0.03% 0.25% 1.87% 0.18% 0.06% 0.16% 1.79% 2.11% 0.71% 0.66% 0.20% 0.27% 0.67% 1.25%
BL Plan Cumulative Progress % 0.00% 0.03% 0.06% 0.51% 4.64% 8.09% 8.89% 10.45% 12.54% 15.84% 20.44% 21.60% 24.45% 26.41% 28.72% 32.61% 38.14% 43.44% 50.99% 60.17% 68.02% 76.83% 83.29% 89.04% 93.95% 97.32% 99.59% 99.87% 100.00% 100.00%
RS Plan Cumulative Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 8.30% 10.89% 13.47% 16.47% 20.46% 26.95% 35.76% 44.80% 55.24% 66.71% 79.36% 90.17% 98.14% 99.59% 99.87% 100.00% 100.00%
Actual Cumulative Progress % 0.00% 0.03% 0.06% 0.31% 2.18% 2.36% 2.42% 2.58% 4.36% 6.46% 7.17% 7.82% 8.03% 8.30% 8.97% 10.22%
BL Plan Man-Hours 0 134.87 128.13 1805 16744.29 13998.42 3220 6319.29 8470.89 13367.73 18659.95 4713.1 11528.69 7966.52 9368.6 15753.29 22412.87 21492.29 30618.34 37210.05 31808.64 35704.94 26199.35 23294.75 19914.96 13634 9198.24 1147.13 517.67 8
RS Plan Man-Hours 10423.5 10516.35 12230.81 16250.53 26429.47 35890.03 36810.42 42548.8 46706.55 51548.04 43995.41 32468.98 5918.29 1147.13 517.67 8
Actual Man-Hours 0 123.70 123.70 1030.85 7587.06 742.21 247.40 659.74 7257.19 8535.44 2886.38 2680.21 824.68 1113.32 2732.11 5086
BL Plan Cumulative Man-Hours 0 134.87 263 2068 18812.29 32810.71 36030.71 42350 50820.89 64188.62 82848.57 87561.67 99090.36 107056.88 116425.48 132178.77 154591.64 176083.93 206702.27 243912.32 275720.96 311425.9 337625.25 360920 380834.96 394468.96 403667.2 404814.33 405332 405340
RS Plan Cumulative Man-Hours 44353.65 54870 67100.81 83351.34 109780.81 145670.84 182481.26 225030.06 271736.61 323284.65 367280.06 399749.04 405667.33 406814.46 407332.13 407340.13
Actual Cumulative Man-Hours 0.00 123.70 247.40 1278.25 8865.31 9607.53 9854.93 10514.67 17771.86 26307.30 29193.68 31873.90 32698.58 33811.89 36544.00 41630.00
PROJECT SAUDI ARAMCO BUILT GOVERNMENT SCHOOLS PHASE III
AT UYUN (UYGE01)
MONTHLY PROGRESS REPORT APRIL- 2024
ANNEXURE-4
Manpower Histogram
Page 19
Doc. No.: KIC-GEN-REP-0094
Revision: 0
KHONAINI INTERNATIONAL COMPANY LTD.
SABG SCHOOLS PHASE III UYUN BOYS ELEMENTARY SCHOOL
( C/No: 6601000200 / BI.No:23-10883)
220
199
200
180
180
170
164
160
142
139
140
125
120
102
100
80
63
60
48
41
41
40
31
31
31
25
25
23
20
16
13
13
11
11
5
2
1
31-Jul-23
31-Jul-24
31-Jan-24
31-Jan-25
30-Jun-23
30-Jun-24
30-Jun-25
31-Oct-23
31-Oct-24
28-Feb-23
29-Feb-24
28-Feb-25
30-Apr-23
30-Apr-24
30-Apr-25
30-Sep-23
30-Sep-24
31-Dec-23
31-Dec-24
31-Aug-23
31-Aug-24
30-Nov-23
30-Nov-24
31-Mar-23
31-Mar-24
31-Mar-25
31-May-23
31-May-24
31-May-25
DURATION
Start of Month 01-Jan-23 01-Feb-23 01-Mar-23 01-Apr-23 01-May-23 01-Jun-23 01-Jul-23 01-Aug-23 01-Sep-23 01-Oct-23 01-Nov-23 01-Dec-23 01-Jan-24 01-Feb-24 01-Mar-24 01-Apr-24 01-May-24 01-Jun-24 01-Jul-24 01-Aug-24 01-Sep-24 01-Oct-24 01-Nov-24 01-Dec-24 01-Jan-25 01-Feb-25 01-Mar-25 01-Apr-25 01-May-25 01-Jun-25
End of Month 31-Jan-23 28-Feb-23 31-Mar-23 30-Apr-23 31-May-23 30-Jun-23 31-Jul-23 31-Aug-23 30-Sep-23 31-Oct-23 30-Nov-23 31-Dec-23 31-Jan-24 29-Feb-24 31-Mar-24 30-Apr-24 31-May-24 30-Jun-24 31-Jul-24 31-Aug-24 30-Sep-24 31-Oct-24 30-Nov-24 31-Dec-24 31-Jan-25 28-Feb-25 31-Mar-25 30-Apr-25 31-May-25 30-Jun-25
CONSTRUCTION
Plan Man-Hours 11 25 13 31 41 41 48 63 102 139 142 164 180 199 170 125 23 5 2 1
Actual Man-Hours 11 25 13 31 31 16