Professional Documents
Culture Documents
05007-STD-P990000-HS-000001 Revision 2
Prepared for
21 July 2016
Tables
Table 2-1. Permit to Work Requirement ............................................................................................. 20
Table 2-2. Health and Safety Personnel - Experience and Qualification Requirements...................... 22
Table 2-3. Health and Safety Personnel - Staffing Requirements ....................................................... 22
Table 2-4. Health and Safety Meeting Requirements ......................................................................... 27
Table 2-5. Health and Safety Performance Measurement Procedures ............................................... 29
Table 2-6. Monthly Performance Assessment Ratings ....................................................................... 30
Table 3-1. Minimum Toilet Requirements ........................................................................................... 31
Table 3-2. Minimum First-aid Personnel Requirements ...................................................................... 34
Table 3-3. Noise Level Exposure Levels and Limits ........................................................................... 43
Table 3-5. Plant and Equipment - Training, Licencing, and Certification Requirements...................... 53
Table 3-6. Lifting Accessories (Gear) ................................................................................................. 62
Table 3-7. Lifting Equipment and Appliances ..................................................................................... 66
Table 3-8. Recommended Slinging Methods ...................................................................................... 70
Table 3-9. Recommended Minimum Levels of Illumination................................................................. 84
Table 3-10. Safety Lighting Levels ..................................................................................................... 85
Table 3-11. Example Health and Safety Goals ................................................................................. 116
Table 3-12. Recommended Method Statement Format and Content................................................ 122
Table 3-13. Recommended Risk Assessment Format and Content ................................................. 126
Table 3-12. Schedule of Required Training Standards ..................................................................... 132
Figures
Figure 1-1. Health and Safety Policy for Expo 2020 ............................................................................. 2
Figure 1-2. HSE First –Target Zero Wheel ........................................................................................... 4
Figure 2-1. Accident and Incident Reporting Process ......................................................................... 25
Figure 3-1. HAVS Exposure Table ..................................................................................................... 75
Figure 3-2. Process Model ................................................................................................................. 87
Figure 3-3. Hierarchy of Work at Height Controls ............................................................................... 96
Acronym/Abbreviation Expansion
AP Appointed Person
BS British Standard
DM Dubai Municipality
KN Kilo Newton
MS Method Statement
RA Risk Assessment
Acronym/Abbreviation Expansion
TW Temporary Works
Definitions
Term Definition
Contractor The contractor is the party, which carries out all or part of the design,
engineering, procurement, construction, commissioning or management
of a project.
Employer Any entity that enters into a contract with design consultants and/or
contractors for works to be undertaken on the Expo 2020 project site.
For the Expo 2020, employers include EX20, third-party delivery agents,
developers, and participants.
Responsibilities Duties or actions assigned to an individual. The area in which people are
expected to act on their own accord (authority) to fulfil expectations and
be accountable for the results. Responsibilities can be delegated.
05007‐STD‐P990000‐HS‐000001 Revision 2 EXPO 2020 Dubai® v
1 Introduction
This guidance document is provided to ensure that the appointed, approved/preferred contractors,
engineers, consultants, third-party delivery partners and suppliers understand the health and safety
(H&S) standards advocated on construction and consulting projects for Expo 2020.
These key health and safety standards are mandatory on all Expo 2020 construction projects.
All contractors/consultants must familiarise themselves with these standards and also ensure that
these standards are adhered to by any subcontractors/suppliers and any self-employed persons
working within their workforce.
These standards will assist the contractor in their planning and provision of satisfactory health
and safety resources on projects.
These standards will be audited in accordance with set performance measurement procedures.
As per specific audit schedule completed for every project.
Poor or non-compliance with these standards may result in the contractor being removed from the
employer’s approved contractor database.
Part 1 of this document explains the purpose of this guidance.
Part 2 of this document prescribes the employer’s requirements and expectations for health and
safety document management.
Part 3 of this document provides contractors and suppliers with guidance on the management of
typical operational health and safety risks, and the standards that contractors will be expected to
comply with.
The contractor shall comply with all local legislative and the Employer’s health and safety
requirements. Where legal requirements conflict with those set out in the Employer’s HSE
requirements, the more stringent requirement will apply.
Figure 1-1 shows the Health and Safety Policy for Expo 2020.
05007‐STD‐P990000‐HS‐000001 Revision 2 EXPO 2020 Dubai® 1
Assurance Minimum Standards
Health and Safety
05007‐STD‐P990000‐HS‐000001 Revision 2 EXPO 2020 Dubai® 2
Assurance Minimum Standards
Health and Safety
05007‐STD‐P990000‐HS‐000001 Revision 2 EXPO 2020 Dubai® 3
Assurance Minimum Standards
Health and Safety
The HSMS document and the procedures referenced within establish the minimum acceptable
environmental standards for the employers, and are applicable to all employees and partners working
on the Expo 2020 programme delivery. The HSMS applies to the management of Expo 2020
programme during the design and construction of its projects.
All consultants and contractors are required to buy-in and actively participate and contribute to the
HSE First, Target Zero programme. This is to include aligning site safety management and
operational activities with the five elements of the HSE First, Target Zero programme listed above.
05007‐STD‐P990000‐HS‐000001 Revision 2 EXPO 2020 Dubai® 4
Assurance Minimum Standards
Health and Safety
05007‐STD‐P990000‐HS‐000001 Revision 2 EXPO 2020 Dubai® 5
Assurance Minimum Standards
Health and Safety
05007‐STD‐P990000‐HS‐000001 Revision 2 EXPO 2020 Dubai® 6
Assurance Minimum Standards
Health and Safety
At the programme level, KPIs will be defined by the employer’s H&S team. The health and safety KPIs
will be incorporated in a programme performance monitoring system. The collected data and
performance appraisals are used by the employer to form a database of information from which all
reporting can be produced.
Progress toward the achievement of performance targets (at programme and project levels) will be
assessed monthly as part of the monthly progress review.
See the PMDS and the Programme Performance Management Process for the list of
programme-level and project-level health and safety KPIs.
05007‐STD‐P990000‐HS‐000001 Revision 2 EXPO 2020 Dubai® 7
Assurance Minimum Standards
Health and Safety
05007‐STD‐P990000‐HS‐000001 Revision 2 EXPO 2020 Dubai® 8
Assurance Minimum Standards
Health and Safety
05007‐STD‐P990000‐HS‐000001 Revision 2 EXPO 2020 Dubai® 9
Assurance Minimum Standards
Health and Safety
Communicate the HSE policy, requirements, objectives and goals to all contractors working under
their supervision.
Inspect and monitor the works to ensure that all health and safety standards are being met.
Support the project managers in delivering the required health and safety standards and
performance.
Investigate and report accidents and incidents in accordance with the accident and incident
reporting procedure.
Monitor welfare facility standards and report non-conformance to the employer, as required.
Monitor contractor’s health and safety performance.
Ensure that all workers are given site inductions and further information and training needed for
the work.
Consult with the workers.
Liaise with the employer’s Project Manager and design consultant regarding ongoing design
health and safety issues.
Ensure that a project specific HSE Plan is developed in accordance with employer’s requirements
for the scope of their services, detailing the specific arrangements of how they will manage,
monitor and supervise the contractor, as well as administer and implement the employer’s HSE
requirements.
Employ a sufficient number of competent HSE staff in line with the legal requirements and the
employer’s HSE requirements, together with the necessary tools and arrangements to perform
their duties appropriately.
Ensure that the contractor provide a sufficient number of competent HSE staff and personnel in
HSE critical roles, as per the employer’s HSE requirements for contractors.
Ensure that adequate HSE information is disseminated and communicated to make the workforce
aware (in their own language) of any hazards, risks and control measures associated with their
work.
Ensure that both SC and contractor develops and implements an adequate HSE training
programme for staff and workforce. Training to be in accordance with the employer’s HSE
Requirements document.
Monitor and supervise the contractors HSE performance to ensure compliance with Legal,
Contractual and Employer requirements, and report any deficiencies to the employer.
Ensure that their personnel, and those of all Project Parties, adhere to the HSE Regulations of the
programme at all times and play a proactive role in reporting and eliminating hazards onsite.
Ensure the availability, suitability and adequacy of the HSE Plans and associated documentation
by all the contractors/Subcontractors working under them, and approve as required.
Ensure that any plant and equipment provided by the contractor and supply chain and in use
meets legal and employer’s requirements, is in serviceable condition, fit for purpose and where
relevant operated by trained and competent personnel.
Continuously monitor the HSE performance of the contractor and their supply chain, regularly
appraise their effectiveness making sure that any HSE non-conformances are rectified in a timely
manner and that appropriate protective and preventative controls are maintained in place at all
times.
May direct the contractor to suspend all or part of the Works until satisfactory corrective action
has been taken if the contractor fails to take corrective action to mitigate any risks.
In case of serious safety violation, be entitled to issue a stop-of-work order countersigned by the
employer, which shall be treated as a suspension pursuant to Sub-Clause.
Report to the employer on a regular basis on the HSE performance of all project parties, including
a submittal of a monthly HSE report and statistics.
Provide leadership, direction, guidance and technical assistance to the contractors in relation to
the HSE requirements and standards as required.
To achieve the aims of this task, the following specific services will be provided by the consultant:
Administer and lead the implementation of the behavioural based Safety Schemes (Don’t Walk By
– Observe, Engage, and Improve).
Participate in employer led HSE leadership tours, workshops and meetings as required.
Make allowance for the purchase of adequate number of licences to utilise the employer’s online
reporting system.
Mandatory use of employer’s HSEQ online reporting systems.
Carry out HSE pre-start meeting with contractors as per the employer’s agendas.
Develop and lead HSE planning/review workshops with contractor and employer.
Carry out initial Preliminary Risk Assessment of contractor activities, reviewed periodically.
Develop HSE campaign timelines based on risk profile.
Develop contractors HSE Plans/MS/RA submission plan based on programmed activities.
Ensure that contractors comply with the Assurance Minimum Standards: Doc Ref 05007-STD-
P990000--HS-000001.
Ensure that the contractor develops and issues a project specific HSE and associated plans in
accordance with the employer’s HSE requirements.
Review, approve, monitor the implementation of and audit the contractor’s documentation (not
limited to: HSE plans, Method Statements, Risk Assessments, material submissions, equipment
certification, and any other HSE related submissions) for compliance with legislation and
employer’s requirements.
Carry out monthly document review of selected contractor’s documentation.
Review contractor designs for HSE Design requirements and assessments.
Carry out daily unsafe act/condition observation reports. Intervene as required to resolve non-
conformances and unsafe practices.
Carry out joint weekly HSE Inspections with contractor’s personnel/Chair weekly HSE meetings
with contractors HSE and Management.
Carry out monthly topic specific contractor audits.
Carry out quarterly system/compliance audits of contractors.
Carry out monthly assessment of contractor’s onsite performance.
Ensure that all accidents/incidents and near misses are reported and investigated in accordance
with the employer’s protocols. Review reports and provide technical support, guidance and
recommendations as required.
Ensure that both the SC and the contractor log all HSE related data on the employer’s HSE online
reporting system.
Produce a monthly HSE progress report, to include but not be limited to executive summary,
accident/incident performance, trend and route cause analysis, KPI performance, actions
required, best practice, lessons learnt, and look ahead.
Ensure contractors develop and implement reward and recognition schemes.
Lead interviews of contractor’s HSE staff (in conjunction with the employer) – recommend for
approval to employer as required.
Ensure contractor produces H&S file as per employer’s requirements.
Assist in delivery of employer’s Training programmes as required.
Track and verify all HSE related data submitted by the contractor.
Ensure pre-access to site plant and equipment checks are carried out.
Ensure contractors hoardings, security arrangements and site set-up meet employer
requirements.
Ensure that adequate emergency arrangements are in place onsite and in site offices.
Interface, liaise, and coordinate with contractor and employer’s HSE depts.
1.9.6 Contractor
This section outlines the contractors’ procedures and requirements for meeting their health and safety
management responsibilities, in addition to minimum construction health and safety standards that
each contractor is required to comply with. The following is applicable to all contractors working on the
programme, employed directly by the employer.
The contractor, if provided access, shall adopt the health and safety management procedures held
within the PMDS and utilise the tools and standard forms and templates provided.
The contractor is required to provide proactive and visible leadership and management onsite for
health and safety, promote and support the programme on a daily basis, drive high standards, and
ensure complete compliance with the Employer’s HSE first Target zero philosophy.
In addition to the HSE First-Target Zero aims, objectives, and proactive measures, the duties and
responsibilities of lead contractors include, but are not limited to, the following:
Lifting Operations
Electrical Safety
Work at Height
Traffic Management
Temporary Works
Welfare
Occupational Health – Summer Working
Fire Safety
Emergency
Office
Security
The SC will review and assess the contractor’s plans to ensure it complies with the Employer’s
requirements.
The contractor will review and approve all other contractor relevant reports and submittals.
No work is permitted to commence until approved status is gained.
Welfare and Accommodation Facilities (Site office/Workshops/Stores)
The contractor shall make sure suitable accommodation and welfare facilities are provided from
the start and maintained throughout the construction phase. In accordance with employer’s
requirements.
All facilities will be constructed of flame retardant, non-combustible materials.
All facilities shall be fitted with adequate automatic fire detection, alarm systems and extinguishing
medium.
Layout and specifications to be submitted to the SC and the employer for review and approval.
All facilities shall be Civil Defence compliant.
Risk Management and Hazard Identification
The contract is required to assess risk and implement controls as required by the hierarchy of risk
management.
The contractor shall prepare a risk register for the overall project scope of works.
The risk register shall be reviewed at regular intervals by the contractor.
Method Statements/Risk Assessments
The contractor shall develop MS/RA issuance plan, in accordance with the construction schedule.
The contractor shall provide project/activity specific and detailed method statements and risk
assessments (MS/RA) explaining his approach for each activity undertaken. Guidance on format and
content can be found in the employer’s health and safety requirements.
To allow adequate review and approval timescales by the SC and the employer, MS/RA must be
issued by the contractor at least 21 days in advance of commencement of activities.
No work is permitted to commence until approved status is gained.
Four Steps to Safety – the contractor shall comply with the principals of the employer’s Four Steps to
Safety strategy, and build into its own systems and procedures.
Consultation – The contractor shall actively engage and consult with his workforce.
Observe, Engage, Improve – Don’t Walk By Behavioural intervention programme
'Observe, Engage, Improve – Don't Walk By' is an initiative aimed at creating an environment of
awareness and openness - one in which people have the confidence to identify and challenge
unsafe acts and conditions. It is about changing attitudes and behaviour by ensuring that we all
understand and are committed to the undisputed benefits of a safe working environment.
Achieving this needs the involvement of everyone. That is why the ‘Don't Walk By’ philosophy runs
from the employer through every stage and function of all projects from tender to hand over.
The contractor shall implement a behavioural intervention programme in accordance with the
employer’s requirements. Where the contractor already has a scheme he will be required to issue to
the SC for approval to use.
Plant and Equipment
All plant and equipment shall meet the employer’s HSE requirements contained within this document
No plant maintenance facility is permitted to be constructed on any Expo 2020 site without prior
approval of the SC and the employer.
Operator competencies are detailed in the employer’s HSE requirements contained in the PMDS.
Resource and Competency
The contractor must ensure that adequate competent resources are allocated to ensure effective
health and safety management throughout the duration of the contract and to monitor the
effectiveness of f their HSMS and HSP
The contractor will allocate one non-working supervisor per eight workers (minimum).
Additional supervisors may be required dependent on risk assessment.
Managers and supervisor will be required to be trained in accordance with the Employers
Representatives HSE Requirements contained in the PMDS
The contractor will ensure and check that all workers are competent to carry out the activities for
which they are engaged. Specific competencies can be found in the PMDS.
Certain roles and functions require specific training and competencies, as referenced in the
Employers Representative’s HSE requirements in the PMDS.
HSE Resource and Competency
The contractor must ensure that adequate competent resources are allocated to ensure effective
health and safety management throughout the duration of the contract and to monitor the
effectiveness of their HSMS and HSP.
One safety officer is to be deployed per 75 workers, one senior safety officer per 10 Safety
Officers, and one full time HSE manager per 1500 persons.
Additional staff may be required to be engaged by the contractor based on any local legislative
requirements and/or risk assessment.
All persons must be a suitably qualified and experienced in accordance with the Employers
Representatives criteria contained in the Employers Representatives HSE requirements
contained in the PMDS.
The contractor will review its staff against given criteria and forward on to the SC and the
employer for final approval upon their assessment of suitable health and safety staff.
Health and Safety Surveillance
The process for the inspection and monitoring of activities by the contractor, as well as the frequency
of monitoring and any further details, shall be included in the contractor HSP. This process shall align
with the employer’s HSE requirements in the PMDS. Refer to the Audit and Inspection Processes on
the PMDS for further information and relevant tools.
The contractor shall undertake formal internal inspections and audits to monitor their performance and
implement improvement plans. The purpose of each inspection and audit is to examine the
Contractor’s HSMS System and HSP compliance status to verify that they meet the programme
requirements and they have been fully implemented on the project.
The contractor shall develop a schedule for auditing and inspecting their own activities. The
employer and/or consultant may accompany the contractor on selected audits and inspections.
The contractor shall monitor and ensure the full implementation of the HSP onsite through the
following minimum methods:
Monthly Leadership tours (led by the contractor’s senior management)
Daily site tours and observations
Weekly inspections (can be conducted jointly or combined with engineer and employer in
accordance with the contractor’s inspection schedule where needed)
Specialised training shall be also given to all personnel assigned to working on the project site
depending on their tasks and as required by the employer’s HSE Requirements.
All training materials shall be prepared by a designated competent trainer and reviewed by the SC
and employer.
The contractor shall provide a dedicated training centre, complete with adequate audio visual
equipment and furniture. Layout and specification to be submitted for review and approval.
The contractor will keep an updated training matrix in place showing all types of induction and
training courses available, and to which category type of employees these courses will be
delivered. A training schedule must be in place as well showing the timing/period during which the
training courses will be given to required staff.
In addition to sign-in sheets that shall be filled at each induction and training course presentation,
the contractor shall keep a Training Register stating the topic of training or induction conducted,
attendees’ details, dates of presentations, and trainer details. The register must be kept up-to-
date at the worksite office to ensure that all staff on the work site has had the proper trainings and
induction.
Induction
All new contractor and sub-contractor’s site personnel including management, supervisors and
workers must attend Induction training on arrival at the site. The instructor delivering the induction
training shall be a competent trainer.
The key elements of the induction training for new site personnel will be detailed in the employer’s
HSE requirements.
Contractor’s induction presentations must be issued to the SC for review and approval.
A list of attendees at all induction training sessions shall be taken (sign-in sheets) and an up-to-
date register shall be retained by the contractor.
Daily Activity Briefings/Night Activity Briefings
The contractor is required to deliver a daily activity briefing/night activity to every worker, prior to
them starting their planned work activities. Records must be kept.
Toolbox Talks
The contractor is required to deliver weekly toolbox talks to it workforce and supply chain.
Accident Incident Reporting and Management
The contractor is required to develop an accident and incident reporting and investigation
procedure that aligns with the employer’s incident reporting and investigation requirements. See
the PMDS for incident reporting process.
The contractor will keep a register of all accidents/incidents/near misses.
The employer must be made aware within one hour of any significant events.
The contractor will issue a 24-hour report interim report to the engineer.
The contractor will log all accident and incidents on the employer’s online reporting system.
Any statutory notification reports made by the contractor will be made available to the SC and
employer.
Where a fully detailed investigation report is required to be produced, it will be produced by the
contractor in accordance with an industry recognised standard (such as DNV SCAT, Taproot,
ICAM, or fishbone analysis) and detail preventative and corrective actions as required. All reports
will be issued to the SC and employer for review, comment, and recommendation, in accordance
with timescales contained within the employer’s HSE requirements, contained within the PMDS.
Reward and recognition programmes
The employer is committed to having the highest standards of health and safety across the
programme, this is supported by recognition and reward of those individuals and companies that
are proactive and successful in their Health and Safety Performance.
The contractor is required to implement a reward and recognition scheme.
Design
Where the contractors scope includes design responsibility they shall develop design
management plan, containing procedures, plans and specific design risk assessments identifying
how risk during construction phase, maintenance and end use, will be eliminated and/or mitigated
by the design phase process.
Review/Update
The contractor shall conduct reviews and updates to their HSP and other associated procedures
and tools on a quarterly basis, or after significant events so as to ensure continuous improvement
of their Health and Safety performance.
Breach
In the event of breach of contract, the employer’s HSE requirements, failure to adequately
manage Health and Safety or in the event of significant accidents and incidents the SC and/or the
employer reserves the right to suspend the contractor’s works anytime and cost implications
associated with stoppages shall be borne by the contractor.
Health and Safety Deliverables
The contractor shall prepare:
Health and Safety policy and Management System (HSMS)
Register of Health and Safety approvals, permits, and licences
Health and Safety Plan (HSP)
Health and Safety organisation chart
Management plans and procedures
Accident and Incident reports
Project risk register
Method Statements and Risk Assessments
Behavioural Observation scheme
Schedule of tours, audits and inspections
Observations, findings, action reports, and register
Weekly, Monthly, Quarterly and Annual Health and Safety Performance Reports
Training Plan, matrix, register and competence certificates
Reward and recognition scheme
HSE
Minimum Experience
Qualification Professional
(years)
Membership
HSE
N/A Yes Optional 5
Officer
The following HSE personnel will be required as a minimum to be deployed by the contractor:
A full time dedicated Health and Safety Manager must be appointed by the main contractor for
more than 1500 employees onsite (inclusive of supply chain and/or sub-contractors).
In cases where the contractor has less than 1500 employees onsite, a competent Health and
Safety Manager must be available to provide support, as required.
One Safety Officer per 75 workers
One senior safety officer per 10 Safety Officers
The health and safety staffing requirements are listed in Table 2-3.
Table 2-3. Health and Safety Personnel - Staffing Requirements
Less than 75
1 (full time) - -
employees
526 – 750 8 – 10 1 -
1501 + 20 + 2+ 1
All contractor accident and incident investigations are to cover the following elements as a
minimum and are to be provided in a timely fashion to the SC and the employer for review and
comment. Contractors are also expected to follow the procedure shown in Figure 2-1.
Aims and objectives
Incident details and events
Investigation method
Investigation team details
Findings of site visit
Findings of documentation review
Findings of employee/witness interviews
Findings in relation to supervision and management
Findings in relation to behaviour and human factors
Findings in relation to technology and equipment
Findings in relation to environmental factors
Immediate cause
Root cause
Conclusion
Recommendations
Contractor Prior to the To close out all key H&S issues Employer/Engineer and
Start of works prior to commencement onsite Contractor Management
Pre-Mobilisation
Frequency
Procedure Description
Engineers/
Employer Measurement
Contractors
H&S Physical inspections of One per week Online reporting As agreed with
Inspections site H&S standards (norm) system/hard the employer
copy
Undertaken by H&S
Manager/Advisor
H&S Audits Audit review of One per Online reporting As agreed with
procedural compliance month (norm) system/hard the employer
copy
Undertaken by H&S
Manager/ Advisor
Coordinated The SC’s H&S Manager One per Online reporting One per month
H&S Reviews and contractor’s H&S month (norm) system/Hard (norm)
Managers undertake a copy
combined, coordinated
review of H&S
standards and
compliance on the
project.
Frequency
Procedure Description
Engineers/
Employer Measurement
Contractors
3 41 - 60 Reasonable White
2 21 - 40 Poor Blue
50 2 2
100 4 3
200 7 6
400 13 10
600 19 14
1000 31 22
For every additional 100 personnel onsite, four additional WCs are required. For every additional 100
personnel onsite, two additional urinals are required.
If the drinking water is from taps directly from the mains, they need not be marked ‘Drinking
Water’. If, for instance taps are fed from a water storage tank and one tap is fed direct from the
water main this tap must be clearly marked ‘Drinking Water’.
Fixed drinking water stations must be provided, as a guide, at a ratio of one station per 50
persons as a guide.
1 – 20 1 - - 1
21 – 50 1 1 - 1
51 – 100 1 2 - 1
101 – 150 1 3 - 1
151 – 249 1 4 - 2
250 – 300 1 5 1 2
451 – 600 1 9 – 11 1 4
601 – 750 1 12 – 14 1 5
751 – 900 1 15 – 17 1 6
901 – 1050 1 17 – 19 2 7
1051 – 1200 1 20 - 22 2 8
1201 - 1350 1 23 - 25 2 9
1351 - 1500 2 26 - 28 2 10
5000 + 2 1 100 + 3 34 +
No construction materials, waste or for use, must block or impede vehicle and pedestrian routes
inside or outside of the site. Site vehicles likely to contain significant mud or dirt must have their
wheels cleaned prior to entering public roads. All loads must be covered and/or sufficiently secured
and tied down prior to leaving site.
Wherever public/common pedestrian routes are impeded due to construction activity, the following
collective measures must be in place:
A suitable pedestrian detour must be in place. Where the detour brings pedestrians closer to
vehicle traffic, a physical barrier must be in place (e.g. concrete or water-filled barrier) to protect
pedestrians from potential vehicle incursions.
Pedestrian crossing points created due to the construction activity must be suitably marked and
must have either traffic lights or special pedestrian crossing points created to ensure that
pedestrians have signalled or ongoing right of way.
If the pedestrian path is on the site boundary, there must be sufficient public protection at the site
boundary, including covered walkways.
Adequate signage highlighting warnings of the changed pedestrian and/or road conditions must
be in place at all vantage points. The signs must be clearly visible to pedestrians as well as
vehicles.
3.3 Logistics
3.3.1 Site Access Control
Movement of all personnel entering or leaving the project location must be recorded for accounting
purposes in emergency situations.
Guard houses and security personnel plus a physical barrier must be provided for each access gates
and will be manned by each contractor’s designated security service. The guards for each gate will be
record details of all vehicles vehicle entering his area. Visitors will be permitted as per procedures
defined by the Employer.
A computer controlled access system together with an entry and exit turnstile is the optimum way of
controlling pedestrian entry onto a site. Where computerised access is not available, a manual system
of site access control must be implemented by the contractor. The site access must be manned
during working hours and the contractor’s security/access control team will be responsible for the
following:
Guarding security control/pedestrian access point and all material delivery points
Logging number of operatives
Continuous external traffic monitor
Ensuring that the site is controlled and secure with a full knowledge of all personnel at all times
Ensuring that there is no ‘unknown’ presence on the site at any time
Restricting access and egress to and from site
Identifying breakdowns in the system immediately, must the situation arise
Maintaining a full knowledge of the fire safety plan and cooperating in fire procedures with fire
marshal
Ensuring that all doors are kept closed, controlling issue of keys, signing in/out log for the
hoarding entry points, goods and pedestrian, and temporary site accommodation
Securing the site at the end of each working day
Completion and issuing of daily log sheet, weekly reports, vehicle log and daily site attendance
report (if required).
Controlling site access only to authorised vehicles and personnel
Guiding/marshalling vehicles into the site and out of the site to ensure the public, or others, are
not put at risk
Traffic and vehicle marshals are trained and competent to perform the role
Patrolling the site boundary to ensure the site remains secure against unauthorised access a log
of daily inspections must be maintained by the contractor.
Assisting, as necessary, with traffic management duties
Designated safe access/egress routes must be provided to all work areas/work platforms. These must
be maintained free from obstructions at all times to ensure:
Safe movement of personnel in the event of an evacuation
Elimination of trip hazards
General traffic rules such as seat belts, 360 vision and speed limits
3.3.3 Fencing
The contractor is required to erect a suitable temporary hoarding around their respective plots. The
fencing will be complete with pedestrian and road access points. No one will be allowed to enter the
fenced area without permission or specific authorisation. Regular documented checks of the hoarding
will be conducted to ensure its continual integrity. All hoardings must be designed in accordance with
temporary works requirements.
Any temporary works which occur beyond the original project perimeter, or affect major vehicle and
pedestrian routes, must ensure that the fencing or hoarding serve as a suitable barrier to other site
operatives and/or members of the public.
The fencing or hoarding must ensure that unauthorised access is prevented. The barrier erected must
also address any relevant noise or dust issues to prevent harm to persons in the vicinity of the
affected area.
3.3.4 Signage
Access points and site rules must be pictorial, available in multiple languages and must be clearly
displayed on the site.
Site signboards will be suitably determined and installed for:
The project (to be affixed in correspondence with entrances, and in conformity with contractual
requirements)
Directional signboard outside the site, so as to suitably direct those who have to reach the site (to
be agreed with the proposed authority)
Directional and informative signboards within the site area, for suitable viability regulations, and
identifying and separating the pedestrian pathways from vehicles routes
Informative signboards in accordance with safety regulations (and in accordance with the various
safety plans)
Hydrants and fire extinguishers signs
No smoking signs where necessary, and specifically in areas or particular risks etc.
Changeable signs highlighting the ‘Five Top Risks of the Week’ in multiple languages
Health and Safety performance
electronic access point or via a manual sign-in register placed at the security watch house or
booth.
Vehicle access will be via a guarded access point where site entry will be restricted by manual or
automatic vehicle barriers. All vehicle occupants must be suitably signed-in prior to proceeding
into the site.
For large and/or remote projects where pedestrian access into the site is not required, vehicle only
access points are sufficient.
Pedestrian/vehicle separation guidance must be included in the induction process to the site. This will
ensure that all workers and visitors are aware of pedestrian routes, and that drivers and plant
operators are aware of their responsibilities.
3.3.7 Parking
Parking areas for different kinds of vehicles must be created for the project by the contractor. Delivery
truck and commercial vehicles must be parked separately from private vehicles.
A strict procedure for controlling trucks arriving to deliver construction materials to the construction
site will be enforced. This will include strict adherence to the use of the temporary access road and
interior haul road. Delivery must be controlled via a simple delivery booking system and restricted to
an assigned truck holding area. Specific details will be communicated by the employer’s Logistics
team.
All delivery trucks must be accompanied by a delivery note that must detail the following:
Location plan of construction area to which the material is to be delivered and routing plan to
reach the location
Consignee (contractor receiving materials)
Name of on-site contract person with telephone number
Intended offloading location
Driver’s security pass and vehicle number
All equipment and materials must be delivered directly to the contractor’s lay down/staging areas for
each main construction zone.
Specific vehicle entrance requirements will be subject to the employer’s Logistic Team Project
Execution Plan. It is sometimes necessary to provide a truck holding area where large volumes of
trucks and truck movements are expected. All trucks entering the development construction zone,
except muck away (excavation spoil), cement, sand, aggregates and waste removal trucks, may be
required to proceed to a truck holding area on arrival. The driver will park the vehicle and report to the
guard post or security cabin.
Trucks carrying sand, aggregate, and cement may proceed directly to concrete supply and/or
batching plants by agreed routes. The areas for the batching plants would be indicated within the site
logistics drawing, as appropriate.
Prior to commencing export of excavation spoil, the contractor must agree on a procedure for
controlling muck away trucks with the project manager. When necessary, parking/waiting space in a
traffic holding area will be provided from where the contractor shall call forward trucks.
Small pickup trucks and vans will be allowed to proceed direct to construction sites assuming they
have the requisite entry passes. However, only personal cars of approved senior staff shall be
allowed to proceed to the engineer’s and contractor’s office areas. Visitors will be required to have
advised attendance in advance. A notification is to be sent by the contractors to the gatehouse
advising of the visitor attendance.
All drivers exiting their vehicles will be required to wear mandatory five-point Personal Protective
Equipment (PPE), when anywhere other than a PPE free zone (See Section 3.9).
3.3.10 Housekeeping
On construction sites, housekeeping issues are ever-present but are rarely unavoidable. However,
the potential for persons slipping and tripping as a result of poor housekeeping is foreseeable and
therefore any consequential accidents are avoidable.
The Contractor will be responsible for maintaining an acceptable standard of site cleanliness within
their area of works in accordance with the standards identified by the employer.
All rubbish and debris must be cleared from the work site on a daily basis in progress with the
work.
No excess rubbish or debris will be permitted to be left onsite at the end of the working shift.
Sufficient bins must be available for the Contractor at each work face to cope with debris
generated
Bins must be emptied/changed immediately when full
Adequate brushes, brooms, shovels, heavy duty refuse bags, vacuum cleaners and the likes must
be available at all times.
Stock piling of rubbish will not be permitted. All contractors will contribute toward effective
housekeeping via their own workforce or by involving a dedicated service gang.
The Contractor and/or progressive cleaning gang must have sufficient number of operatives to be
responsible for:
Emptying and re-siting of wheelie bins to floor area
Cleaning of general areas, floors and access emergency escape routes on a daily basis
Re-siting of materials, as directed management.
Note: The contractor may be subjected to a ‘suspension of works notice’ if an adequate response to a rubbish
removal instruction is not observed. The suspension will remain in effect until the instruction is complied with in
full and the loss of production will be at the expense of the Contractor.
Specific Training
Occupational Health Specialist/Hygienist Advice
3.4.1 Noise
Areas and activities producing noise levels above 80 dB (A) must have noise warning signs posted
stating that hearing protection aids must be worn. Appropriate hearing protection must be provided to,
and worn by, all those at risk of sustaining damage to their hearing.
The danger levels for noise are identified between 85dBA and 90dBA. At 85 dB (A) which is known as
the first action level, employees will probably have to shout to be heard at a distance of 2m away from
the person they are talking to, and must be provided with hearing protection at their request.
All practicable methods must be used to reduce noise levels, but where these remain excessive and
harmful, ear protectors must be worn. Ear protectors are not a substitute for other methods of noise
control. Recommended maximum exposure without protection is shown in Table 3-3.
Table 3-3. Noise Level Exposure Levels and Limits
Average Noise Level dB (A) at the ear Maximum Exposure In one working day
85 8 hours
87 6 hours
90 4 hours
92 3 hours
95 2 hours
97 90 minutes
100 60 minutes
102 45 minutes
105 30 minutes
110 15 minutes
supervisor of the works where hand digging is carried out. The permit must detail the service
detection investigation method utilised by the contractor (that is, Cat and Genny, GPR). Prior to the
works starting, all operatives/plant operators involved must be briefed regarding the method
statement/risk assessment and the contents of the ‘Permit to Excavate’. The permit must identify the
approved profile of each excavation and detail hold points associated with the excavation process.
During the excavation process, works must immediately stop and further guidance be obtained if any
variance from the expected location of services or other conditions is found.
Barriers may be removed to permit access of men, plant and equipment but must be replaced
immediately after.
During darkness or low light conditions, the edges of an excavation must be marked with hazard
warning lights, especially where they are close to public thoroughfares.
Where excavation work is carried out on the roads, all necessary and appropriate barricades and
warning notices must be erected to prevent an accident or injury
Where vehicles are used for tipping materials into an excavation, safety measures such as well
anchored stop blocks must be used to prevent the vehicle overrunning the edge. It is
recommended that excavated material is utilised to form a bund wall.
These must be placed at a sufficient distance from the edge to avoid the danger of it breaking
away under the weight of vehicles.
Excavations must be inspected by an experienced and competent person, before work starts, at
least once a day, and before each shift.
Walkways or bridges used to cross excavations must be designed and equipped with standard
guardrails and be of non-slip material.
Access to excavations must be via a controlled method, such as a priority step system or an
equivalent access system.
All excavations must be guarded to prevent persons and vehicles from falling into them. Cones,
Netlon, Hazard Warning tape/rope are not acceptable means of edge protection
All barriers shall be at least 1m away from the edge of the excavation
Where vehicles are required to reverse to the excavation for purposes of tipping, secured stop
blocks of sufficient strength and size must be positioned to prevent the vehicle from running over
the edge. The stop blocks must also be positioned so that the edge of the excavation will not
collapse under the weight of the vehicle.
Sufficient lighting and reflective signage must be provided at all times.
Good ventilation must be provided and dependant on the location and depth of the excavation it
may be regarded as a confined space.
Testing for toxic fumes/gases shall be required for all excavations in the vicinity of live sewers.
Atmospheric testing will be required to confirm acceptable entry conditions. Atmospheric testing
shall only be carried out by a competent person and with calibrated equipment
Exhaust fumes from plant and generators can build up in excavations and trenches, therefore,
periodic atmosphere testing shall be carried out in trenches with restricted air movement such as
narrow or deep trenches or enclosed tunnels
Where supports, slopes or batters have been provided to ensure safe working conditions, a
maintenance programme is required to be put in place.
If benches are used for access purposes the contractor shall ensure that suitable and sufficient
edge protection is installed (double guardrail) along the entire access route
The contractor shall, within 10 metres of a road, provide and maintain continuous hard barriers
(concrete jersey or water filled and interlocked or sand bunds) so as to prevent motorists driving
into said excavations
3.7.9 Piling
All piling works must be planned and carried out to reduce exposure of workers to falling into
openings and injury through contact with plant. Consequently, all piling operations must be under the
control of a competent person appointed by the contractor.
The piling contractor must produce and issue a detailed method statement and risk assessment
including proposed safe systems of work which must be approved by the SC prior to work
commencing onsite.
Prior to starting work, the contractor must conduct a search of existing drawings and physically on the
ground to ensure that all underground services in the area must be located and rendered safe.
Cranes and/or piling rigs must be selected and used in accordance with legal requirements. Records
of thorough examination must be held for all lifting appliances and gear. Such lifting appliances and
gears must be adequate for the job. Particular attention must be paid to the risk of damage to gear by
sharp edges.
Piling machine operators must be trained, competent, and must wear appropriate PPE.
A piling exclusion zone must be created before work commences. The exclusion zone must be clearly
marked with a high visibility barrier and warning signs and be clearly indicated on a plan in the
method statement.
When splitting bundles of sheet piles, chocks must be used. Piles must not be stacked too high or in a
cantilever position. Spacers and chocks must be used where necessary.
Spoil from boreholes must be kept clear of access to the borehole which, after completion, must be
fitted with a cover or other suitable protection. As an alternative to a cover, it is common practice to
back fill or to leave the auger in the borehole.
Persons are not permitted to enter any borehole less than 750mm in diameter. Where it is necessary
for any person to enter a borehole, it will be considered a confined space and be subject to the
confined space requirement. It must be ensured that no toxic or flammable substance/gas is present
in the borehole and that the air is fit to breathe. Where necessary, a proper ventilation system or
suitable breathing apparatus must be provided. No person must remain in the hole for more than one
hour at a time.
Pile helmets or crowns must be well constructed, strong enough and free from defect. If packing or
spacers are needed, they must be drilled, tapped, and screwed to secure in place, and then welded.
Any access ramp used by piling rigs must be constructed from well compacted crushed brick/
concrete hard-core or similar material. Piling mats must be subject to temporary works design and
checking procedures. The maximum gradient permitted for the ramp is 1:12 and the minimum width is
to be the width of the rig plus 1.0m each side. The sides of the ramp must be battered to an angle of
30° to the horizontal.
Operations must be planned, where possible, to eliminate reversing. Where reversing cannot be
avoided, it must be carried out under the control of a trained banksmen.
Passengers must not be carried on items of plant except where the equipment has a
manufacturer’s fitted passenger seat.
Engines must be switched off when plant is not in use or left unattended.
Keys must be removed when the plant is not in use.
Where risk of rollover and falling objects is present, all mobile plant and equipment must be fitted
with manufacturer approved Roll Over Protections Systems (ROPS) and Falling Object
Protections Systems (FOPS).
Where risk of plant and equipment roll over is present, all mobile plant equipment must be fitted
with manufacturer approved seatbelts.
All enclosed cabs must be fitted with fully functioning air conditioning units.
No curtains/cardboard etc. may be placed to act as sunscreens.
All mobile plant shall carry a serviceable and fully functional fire extinguisher.
Fuel and oil spillages must be reported and cleaned up as soon as practicably possible.
Initial inspections must be carried out by a mechanic or other competent person.
All mobile plant and vehicles in use will be subject to weekly inspections and routine
maintenance.
Operators must carry out daily pre-use inspections.
Contractors must establish, implement, and document a maintenance schedule for all mobile
plant and vehicles.
Routine maintenance and repairs may be carried out by an in house plant department.
Records shall be maintained. Only manufacturer approved spare parts shall be used.
Mobile plant and vehicles supplied by subcontractors will be subject to the same requirements set
out in this standard.
(if used on
public roads)
48 monthly
third party test
48 monthly
third party test
components together with any structural ties, track, etc. and the correct functioning of the safe
load indicator.
Where there are two or more cranes on a site erected in positions where they could collide or
over-sail or where the crane jib could slew into a restricted zone, then a SIL 2 type anti-collision
prevention system must be used. This system must only be used as a backup to vigilant crane
drivers/banksmen with crash radios, who must be the first line of defence together with well-
coordinated and well managed lifts.
Exclusion zones must be implemented for loading and unloading zones, and must be clearly
signed and demarked with warning tape or hard barriers to prevent inadvertent access. Where
practically possible, slingers and signallers must ensure that general workers are moved from the
path of slung loads. All slingers and signallers will be issued a whistle for warning general workers
of lifting operations in progress.
All mobile cranes must extend outriggers before commencing lifting operations. All crane warning
devices or lights must be in full working condition prior to commencing lifting operations.
Crane operators must not exceed the crane capacity and must immediately cease operations if
the automatic warning devices activate.
Grillages (crane mats) must be used on mobile crane outriggers to spread the load.
A copy of third-party inspection and test certificates must be maintained for all lifting equipment
and lifting accessories (lifting gear).
Lifting equipment and accessories (lifting gear) must be colour-coded on a monthly or quarterly
basis to ensure that only certified equipment is in use on-site. Coloured tags must only be
attached to equipment or accessories that have valid test or inspection certificate.
A permit-to-work system may be implemented for lifting operations if required by the employer.
This system will be detailed in project-specific health, safety, and environmental plans, and will be
included within relevant method statements provided by the contractors.
Unless specified, tower crane hoisting cables will be terminated on the jib using a wedge socket.
Note that the live and dead ends of the hoisting cable must not be clipped together.
The ‘X’ value is the minimum length of the dead end of the hoisting cable which must not be less
than 150 mm.
Shackles
Lifting Clutch
Chain Slings
Web Slings
Lifting Hooks
Plate Clamp
Beam Clamp
Suction Lifter
Forklift Hook Attachment
Pallet Lifter
Man Basket
C Hook (Formwork Lifter)
Tower Crane
Pre-use inspection (competent user) o r monthly
site inspection (competent person)
Annual inspection of equipment by third party or 6-
monthly inspection if used to lift person
48-monthly third-party test (proof load)
Crane Arm
Pre-use inspection (competent user) or monthly site
inspection (competent person)
Annual examination of equipment by third party
48-monthly third-party test (proof load)
Telescopic Handler
Pre-use inspection (competent user) or monthly site
inspection (competent person)
Annual examination of equipment by third party
48-monthly third-party test (proof load)
Forklift
Pre-use inspection (competent user) or monthly site
inspection (competent person)
Annual examination of equipment by third party
48-monthly third-party test (proof load)
Winch
Vacuum Lifter
Bottle Jacks
Hydraulic Jacks
3.9.12 Slingers
To safely plan and conduct all lifting operations, adequate number of competent operatives
(riggers/slingers) must be provided and each must have proof of competence.
Contractors must ensure that adequate slingers/signallers are appointed and that this is
communicated to all project stakeholders. It is recommended that operatives involved in lifting must
wear PPE that readily identifies their role (e.g. different coloured hard hat or hi-visibility clothing)
Contractors’ lifting supervisor must:
Ensure lifting operations only commence after the task lifting plan has been approved by the
project team and has been coordinated with other lifting operations.
Supervise lifting operations to ensure they are carried out in a safe manner fully in line with the
agreed lifting plan. Including supervision of crane drivers and slingers/signallers under their
control but in liaison with the appointed crane/lifting managers from other project stakeholders.
Ensure works are stopped if any deviation from the lifting plan is likely to occur.
Ensure that all relevant parties (crane operator, slingers/signallers etc.) are briefed and trained in
the requirements of the relevant lifting plan.
Liaise with the appointed person regarding methods and coordination.
The level of supervision required for each lift depends on the complexity of the risks associated with
the operation. Some lifts dependent on complexity and risk may require continuous supervision by the
crane supervisor at all times during the lift. Other repeated lifts of less complexity or risk, may only
require the crane supervisor to ensure the operation is set up correctly with all relevant parties
understanding the safe system of work/lifting plan and action to take if conditions/circumstance
change that may affect the lift. The lifting operation must be regularly monitored.
This role may be combined with other roles. However, they must have sufficient time to supervise all
lifts and slinger/signallers under their control and personally supervise at all times non-generic lifts
standard and complex lifts i.e. formwork table extraction from building etc.
Prior to works commencing all crane operators and slingers must have proof of competency as
prescribed in local laws and regulations and proof of competency must be conducted prior to
operators and slingers commencing on-site.
All projects will conduct periodic inspections of proof of competency to ensure that relevant
certificates/qualifications exist and are current.
Any slingers or operators without current proof of competency will be removed from site. Crane
operators working without proof of competence is a serious offence and any breach must be reported
to the local health and safety regulatory authority.
In all cases where a crane is in operation, there must be a trained slinger/signaller in attendance. All
slinger/signallers must hold a recognised qualification regarding lifting and slinging, or other approved
training.
All appointed slinger/signallers must wear high visibility vests/jackets or helmets that identify their role
on the project. Their duties include:
To follow directions given by the lifting Supervisor and or Appointed Person.
To ensure they are fully aware of the requirements of all relevant lifting plans and they follow
them.
Do not undertake any lifting activity they believe to be unsafe or does not conform to the agreed
lifting plan.
To immediately stop any lifting activity, they believe has or will become unsafe.
Immediately advise the crane supervisor of any changes in circumstance that increases risk or in
any way affects the lifting plan.
To sling and detach loads in line with industry best practice.
To give relevant signals to crane operators using the approved system of visual and radio signals.
Not to put themselves or others at risk.
All slinger signallers must have a current signaller’s certificate and adequate experience of the type of
loads they are expected to sling. Their competency must be checked via physical on-site
demonstration to the lifting manager/appointed person and they must be recorded as an ‘Appointed
Slinger’ prior to slinging any load.
On projects where more than one crane is in use there must be a daily coordination meeting including
operators and signallers. This meeting must be outlined in the project lifting plan.
Any outcomes from the meetings which alter the lifting strategy for the project (e.g. change in the
swing arc of a tower crane) must ensure that the project lifting plan is updated and changes
communicated to all project parties.
Lifting coordination must include input from the project delivery and/or logistics coordinators to ensure
that the lifting schedules compliment the ‘just in time’ delivery strategy.
A schedule of common lift recommended slinging methods is provided in Table 3-8.
Table 3-8. Recommended Slinging Methods
Man Baskets
Concrete Bucket
Stillages
Palletised Loads
Steel Sections/Beams
Tag Lines
Centre of Gravity
Skips
The adverse effects of the wind on the skips must be considered when they are being lifted.
The raising or lowering of the skips over roads or footpaths used by the public must be avoided. If
this is not possible, it must only be carried out during off-peak periods with special attention being
given at all times to excluding members of the public and site personnel from the area of activity.
This may require the erection of suitable and adequate barriers, fans and warning notices as well
as controlling the movement of pedestrian and vehicular traffic.
A competent person must check the underside of the skip to confirm the skip’s structural integrity
and its ability to contain any load.
Skips must not be overfilled and where necessary must be suitably covered to prevent accidental
spillage of the contents or windblown debris/dust.
Training
Give operatives instruction on correct use of tools/equipment and safe methods of working.
Ensure risks of vibration exposure and control measures required, as well as effects of cold
weather and other factors, are made known to, and understood by, operatives. Employ a strategy
for the use of gloves, even though they do little to reduce vibration they can ease grip strength
and create warmth. Encourage employees to take active steps to keep their hands and
themselves warm. Provide good welfare facilities where operatives can get warm and dry their
hands. Encourage massaging/exercising/stretching of hands and fingers before and during work.
Consider running schemes to discourage smoking because of the detrimental effects in regards to
HAVS.
Reporting
Ensure operatives report symptoms of Vibration White Finger (VWF)/HAVS to immediate
Supervisor. A rule of thumb is to suspect any process that causes tingling or numbness after 5-10
minutes.
In the event of HAVS is being diagnosed via health screening, contractors and suppliers must:
remove employees from normal duties until a clinical diagnosis is obtained, look for alternative
works.
Contractors and suppliers must inform Expo 2020 of any suspected or confirmed cases of HAVS.
Figure 3-1. HAVS Exposure Table
What Good Looks Like – Use of Exposure tables when activities cannot be avoided
3.11 Scaffolding
3.11.1 Scaffold Selection
There are numerous types of scaffold commonly used in the construction industry and it is a
fundamental safety requirement that the selected scaffold be fit for purpose. There are many
factors that determine suitability, the most common are listed below:
Nature and duration of work planned
Height and loading
Access/egress
Weather and environmental aspects
Proximity of other hazards (lifting operations, overhead electrical services etc.)
Ground stability/stability of supporting structures
Once the factors are clearly determined, the selection of suitable scaffold can be made.
Any company involved in the erection, inspection and dismantling of scaffold must appoint a
competent scaffold supervisor who will oversee the erection and dismantling of the scaffold. This
supervisor will be responsible for daily scaffold inspection.
The competent scaffolding supervisor shall hold a valid third-party certificate for the design, erection
and inspection of scaffolding. Major projects may require more than one competent scaffolding
supervisor. No person shall erect, alter or dismantle any scaffolds unless they are trained and
competent to do so.
Note: The proprietary scaffold systems must not be mixed. For example, ‘Cup lock’ components
must not be mixed with ‘Kwikstage’ components. Only additional bracing tubes and raking tubes
may be utilized with proprietary scaffold systems.
Details of any system scaffolds intended to be utilised are to be issued to the employer/engineer for
review and approval.
Note: A competent ’scaffold controller/coordinator’ must be appointed to oversee the safe control of
all scaffolds.
Scaffolding that has been constructed in accordance with the planned design will be authorised for
use by displaying a notice at all access points detailing the following information:
The unique identification and location of the scaffolding
The name of the person making the check
The date that the check was completed
The intended loading capacity of the scaffold
Scaffold tags must be updated on a weekly basis (seven days) or when a scaffold is deemed unfit for
purpose through the daily inspection regime.
Ensure that the temporary works are designed, checked, certified and implemented in accordance
with the approved procedures, appropriate to the classification.
Classify and register all packages of temporary works in accordance with Section 4.1 and compile
the Temporary Works Register (TWR).
Prepare detailed design briefs for each item of temporary works when required by the temporary
works classification.
Ensure concept, design, risk assessment and checking are carried out in accordance with the
design brief.
Establish and implement an inspection regime for all temporary works with the temporary works
designer to ensure that they remain suitable and fit for purpose.
Submit checked temporary works design drawings and calculations for approval.
Produce method statements for the erection, use and dismantling of the temporary works.
Obtain any related licences and no objection certificates (NOCs), such as RTA and DEWA.
Inspect the completed temporary works to confirm when a structure can be loaded and unloaded.
Issue permits to load and unload.
Where appropriate, ensure that copies of the design, design check and test certificates as well as
permits to load/strike are issued and registered.
Ensure that loads from temporary works and temporary loads, such as plant and materials are
accepted by the permanent works designers.
Ensure that method statements for the erection, use and dismantling of the TW are prepared and
communicated to all those involved in the operation.
Appoint and liaise with the falsework coordinator as appropriate.
Appoint competent temporary works inspectors.
All electrical equipment used on the worksite will be manufactured in accordance with
internationally recognised standards and installed in accordance with BS 7671 or equivalent
international standard.
Cables, sockets, connectors and splitters and sockets will be of an industrial type. Domestic
type cabling, connectors and sockets are prohibited in construction areas. Jointing of all
electrical cables and wires shall be by means of proprietary terminations or
connectors/splitters.
Jointing of all electrical cables and wires shall be by means of proprietary terminations or
connectors.
The purpose of the test is to ensure that the appliance is maintained in good order throughout its
working life and that the inbuilt protection of the appliance protects the user. The inbuilt protection of
portable electrical apparatus is normally by means of insulation and earthing. The purpose of this
protection is to ensure that the user does not come into contact with any live parts.
All electrical equipment, tools, cables and electrical accessories shall be tested prior to first use,
after any substantial alteration or repair.
A monthly inspection of all hand held electrical tools, hand held electrical lighting, extension leads and
distribution boards shall be carried out on a monthly basis for hand held equipment.
A quarterly inspection electrically operated lifts, hoists and fixed lighting shall be carried out on a
monthly basis for hand held equipment, extension leads and distribution boards.
Contractor’s maintenance programs shall be under the supervision of the electrical coordinator.
Testing will be done by a competent electrician who will visually inspect all equipment, check the
earth continuity, the resistance of the earth and the insulation of the system.
A documented record of such inspections shall be made by the contractor, a copy of which will be
held onsite and made available to on request. It is recommended that the contractor responsible for
temporary distribution purchase a Portable Appliance Tester (PAT) to complete the above testing
requirements.
The term interior lighting covers those parts of structures which may not have cladding during
erection, but which will become interiors when the work is finished. Lighting including emergency
lighting must be provided to all areas of the site. The level of lighting to be provided must be
determined following a risk assessment as required by the safety management system and this will
depend on the security arrangements, hours to be worked, out of hours working and the local
environmental considerations.
The following safety lighting levels must be supplied on all sites, together with individual task lighting
as necessary. Safety lighting must be provided to all rooms, corridors and staircases.
Safety Lighting
Stairs 20 10 At treads
Task Lighting
Bricklaying (except facings) 200 100 Task height
Emergency Lighting
All areas 5 5 Ground
Accommodation
Offices/First-aid Rooms 500 250 Desk height
The lock out/tag out system requires one or more padlocks fitted to the isolation switch with keys
being held by the operators/maintenance personnel. Their name(s) and reason for the lock-out is
written on the tags attached to the padlock. When the task is completed, the locks and tags are
removed and power can be restored.
Isolation shall provide positive protection and be achieved by the use of locking devices or the
establishment of a physical barrier or separation.
Any person working within an energized area shall ensure that the energy sources are positively
isolated.
Any isolation which requires transfer between shifts or different workgroups shall require the use
of an isolation permit.
All personnel who are required to perform isolations shall be trained and deemed competent
relevant to the level of competency required to perform their tasks.
Tags are essentially warning devices affixed to energy isolating devices, and do not provide the
physical restraint on those devices normally provided by a lock.
When a tag is attached, it is not to be removed except by the authorized person responsible for it,
and it is never to be bypassed, ignored, or otherwise defeated.
To be effective, tags must be legible and understandable by all employees whose work
operations are or may be in the area.
Tags and their means of attachment must be made of materials that will withstand the
environmental conditions encountered in the work place.
Tags may evoke a false sense of security, and their meaning needs to be understood as part of
the overall energy control programme.
Tags must be securely attached to energy-isolating devices so they cannot be inadvertently or
accidentally detached during use.
3.14 Access/Egress
3.14.1 General Access and Egress Paths
The provision of safe means of general access and egress is critical to the prevention of slip and trip
hazards on Expo 2020 sites. Through planning processes, the contractor will coordinate the allocation
of general access and egress routes on-site. All contractors have a significant role to play to ensure
that general site access and egress paths remain in a safe condition for use. These actions are as
follows:
All main access ways, emergency routes and passage ways (including basements and stairwells)
must be clearly lit, marked and kept free from obstructions and debris to reduce the risk of trips
and slips.
Any place where work is carried out must be safe and free of risks to health and safety at all
times. This includes access to and egress from the workplace and is particularly relevant to the
construction industry.
Access ways must be clearly delineated by marker barriers external to any building. Where
required within structures, pedestrian access ways must also be clearly defined to avoid persons
entering specific work areas.
Emergency routes must be clearly signed and marked so that any worker or visitor can readily
locate and follow the signs and lighting provided.
All access ways must not have debris and this must be checked on a daily basis. Any
obstructions must be cleared with immediate effect and not delayed until the end of a shift.
Emergency lighting must be best achieved by linking to the temporary lighting system with
strategically placed battery operated fluorescent tubes or bulkhead fittings providing a minimum
three-hour performance. Emergency lighting systems must be inspected weekly and the results
entered in a register. Action items must be distributed to the relevant management department.
Comply with all walkway signage at all times (including not obstructing signage with materials).
Do not store materials in designated general access and egress ways.
Do not work in designated common general access and egress ways (without prior permission
from Expo 2020).
Adequate fire extinguishers shall be provided for all fire hazard related site activities.
The workforce shall be adequately trained in the safe use of fire extinguishers.
All site storage and accommodation huts will be in accordance with the employer’s HSE
requirements and their provision on-site will only be with the permission of the employer/engineer.
A Hot Works Permit procedure shall be in force for all types of hot works such as burning,
welding, and abrasive wheel operations.
Contractors must ensure their own specific fire arrangements are provided within their safety
documentation submitted to Expo 2020.
Full screening to arc welding is required where controlled access to the welding area is not
possible by restricting access.
Electric arc welding leads and welding return cables are frequently dragged over rough surfaces.
Their insulation must, therefore, be suitable for resisting hard ware and must be examined frequently
for defects. The part of the cable which is connected to the electrode holder must be as flexible as
possible so as not to hamper the movement of the welder. The welding return must be of a section
not less than that of the welding lead.
Joints between cable sections must be made with properly constructed insulated cable couplings
adequately shrouded, so that live metal is not exposed if the parts of the connector are separated.
The welding return must be firmly connected to the metal on which welding is taking place, by means
of a well-constructed clamp.
3.15.3 Smoking
Smoking is prohibited within all enclosed areas and in the vicinity of combustible materials,
explosives, and highly flammable liquids/gases.
Smoking is a hazard with the potential to cause fires on-site. Smoking is not allowed at the following
locations:
In existing occupied buildings
At finishing stages of projects with a large amount of inflammable fittings installed
In offices, rest areas, mess facilities, toilets, and changing rooms
In high risk works
Smoking is allowed:
In the designated smoking areas near to (but not inside) canteen and offices
Designated smoking areas must be constructed of non-combustible materials and have sand buckets
or other suitable container available to allow cigarettes to be safely extinguished. Adequate signage
must be posted to all designated smoking points.
Note: Passive smoking is a risk to the health of other personnel. There must not be any designated
smoking areas in areas that could result in other personnel being subject to passive smoking.
of floor area. Extinguishers to temporary accommodation, stores, and facilities must be determined by
the fire risk assessment.
Fire point plans must be prepared and visible around the site. Include on these plans:
Alarm call point
One full set of extinguishers
Fire escape routes
Dry riser access points
Hydrants
Emergency assembly point
Fire point sign must be at a height readily seen above stored materials
Fire points must be conspicuously positioned, i.e. near exits
Adequate numbers of extinguishers must be provided throughout the site:
All personnel must be trained in their use
Extinguishers must be located in red boxes raised 500 mm above the floor level and marked
‘FIRE POINT’
Portable fire equipment must be serviced at least annually
Provision of equipment must be reviewed as works progress
Ride on plant must carry an appropriate fire extinguisher
Ensure that all firefighting equipment is checked and serviced and that Fire Exits and Escape
Routes are checked to ensure they are kept clear at all times
Ensure that nominated fire personnel are adequately trained and details recorded
Ensure emergency procedures are displayed and fire exit routes clearly marked
Arrange an establishment fire drill at least every six months
In the event of a fire or other emergency evacuation, to assume overall control of and evacuation
of the establishment, with Fire Marshals reporting to them at the assembly point
Liaise with the local Civil Defence requirement for carrying out mandatory Fire Risk Assessments
General Duties of Fire Warden
Enforce the requirements of the construction fire and emergency document
Ensure the fire escape routes are maintained daily
Conduct weekly checks of fire points and extinguishers, enter results in the fire register
Ensure fire brigade is directed to scene of incident
Assist in putting out of small fires (if safe to do so) with extinguishers provided
Assist where necessary to evacuate personnel
Ensure key personnel/emergency list updated
Assist the emergency services where required, giving information on LPG stores, high voltage
cable routes and other relevant information
Firefighting team – the firefighting team is there to:
Assist in putting out small fires with extinguishers (in addition to other personnel)
To support the fire warden in evacuation and control of workforce during a head count
Inspect and clear designated areas
Update equipment
Access locations and relevant construction processes
Ensure connections for civil defence satisfy mandatory requirements
All projects must ensure that access is provided to emergency services. Access must be clear and
well maintained and allow access to firefighting services such as hydrants and to first-aid or medical
rooms.
Access for emergency services must be part of the project logistics and traffic management plans.
Projects must also have periodic reviews with civil defence authorities to ensure that site fire
management and firefighting provisions are suitable and that all parties are familiar with the
requirements and capabilities of the other group. Where possible, civil defence must be used or
consulted for appropriate training and awareness for emergency response.
3.16.1 Planning
When planning work at height the hierarchy of controls must always be applied. See the Work at
Height (WAH) process and work equipment selection process charts below.
Contractors must produce a project specific fall prevention, and (where required) rescue plan for the
project.
Contractors must complete a project risk assessment including addressing work at height issues and
eliminating the reliance of harnesses as the primary and sole means of work at height protection.
Detailed Work Method Statements and Risk Assessments must be prepared for all Work at Height.
Use an existing safe place of work such as: Scaffolding, MEWP, and Mobile Tower
Select individual protection systems, such as fall restraint, fall arrest and rope access techniques
Key elements of this material and the issues arising in the Fall Prevention Plan will be provided to
assist in the induction, training and education of the workforce.
Each contractor is to be fully responsible for ensuring that all fall prevention material provided is
cascaded to any subcontractors employed onsite.
Random audits of any pre-qualification, tender, or service agreements with any sub-contractors will be
conducted to ensure that fall prevention materials are provided to all organisations working on the
project site.
Integrated Fall Prevention Programme
All projects where the design can be influenced shall identify risk, plan, manage and deliver, as per
the Fall Prevention process outlined below.
A design review must be conducted where an opportunity exists to influence design.
Integrated into this session shall be the identification of all work that will require tasks to be performed
at height. If reasonably possible, design change or alternative work methods shall be implemented to
totally eliminate the need to work at height.
Fall Prevention Plan
As part of the overall Project Health and Safety Plan, a Fall Prevention Plan shall be included within
the overall document. The plan will identify potential work at height risks and address the risks with
solutions based around either eliminating the need to work at height, or by providing suitable primary
(and in some cases secondary) fall prevention means.
The Fall Prevention Plan shall be reviewed and approved by the SC and the employer.
Method Statement (MS)
The contractor shall develop an MS for all work at height with adequate lead time and submit to the
relevant project party for review and approval. MS shall be reviewed by the employer and engineer to
verify that all planned solutions are compliant with the Fall Prevention Plan. If a safety harness is used
as the primary means of fall protection OR prevention, then a rescue plan shall be required to be
incorporated in the MS. All workers are to be inducted into their MS.
Supervision of Work
Supervision shall be provided for all work at height to ensure agreed methods are delivered as per
conditions of the MS. Supervision is to be provided by the contractor, and by any engineer as part of
any responsibility for overseeing compliance.
Daily checks of high risk activities
All work at height shall be considered a ‘High risk activity’. Any contractor’s supervisor in charge of a
high risk activity (shall maintain daily checks in conjunction with construction and H&S managers.
These checks must compare performance with the MS and the minimum standards in this document.
A record of regular inspections and supervision must be kept.
Weekly Compliance Reporting
All projects are to be reviewed on a weekly basis. This review is to be led by a senior member of the
project team and compare the project’s performance with minimum requirements. The results of the
review and any corrective actions shall be entered into online reporting system and reviewed at the
monthly project Safety Leadership Team (SLT) meeting.
Monthly Reporting
Contractors are to undertake detailed monthly compliance reporting to assess performance against
standards compliance including work at height. The results of the review and any corrective actions
shall be entered in the online reporting system and reviewed at the project H&S meetings and forums.
The advanced methods ensure protection at either 2 m or at full floor height. It must be in use for mid-
rise construction or on any building where, because of the nature of the work or the location of the
site, either site workers or the public at large are at significant risk. It must be used to eliminate fall of
person and fall of material risks at substantial heights where winds in particular present considerable
risk to the movement of persons or materials.
For all such buildings, the use of perimeter screens will be the default position when it comes to
standard setting and this option must be pursued before any other option is considered. Where this
method cannot be employed.
The SC H&S Manager must be notified and he must engage with the team to work out an alternate
type of advanced protection to ensure that a full-height or 2 m high protection is employed.
To meet the minimum requirement of standard perimeter protection, the edge protection will:
Be provided to a minimum height following local legislation (with a preferred minimum height of at
least 1000 mm) and incorporate a toe board with a minimum height of 150 mm capable of
preventing materials falling, with no gaps below.
Not have vertical gaps between any guardrails or toe board which exceed local legislation (with a
preferred minimum gap of 470 mm). There must be no gaps below toe boards.
Be of continuous construction and robust and not made of surplus steel or timber that is not fit for
purpose.
Where items of powered mobile equipment are likely to be used, have physical stops provided to
prevent the powered mobile equipment reaching the edge of the slab and/or impacting the edge
protection.
Be erected, maintained and dismantled by competent persons and be inspected prior to use and
after alteration, repair, maintenance, and adverse weather.
Be provided to a higher standard and include; vertical netting, mesh, brick guards or similar where
additional hazards are identified, e.g. adjacent public areas/project interfaces (walkways, roads,
and offices), specific work activities, or where this solution will be adopted above two floors.
All perimeter edges where a guard rail system is used are deemed incomplete unless the system
incorporates a top rail, mid rail and toe board. Where toe boards are not specifically prescribed in
local legislation, it is still perceived to be a component of a risk management based approach and
essential part of the collective measures to avoid the fall of materials in particular. Any other edge
protection system other than guard rails must ensure that appropriate elements are in place to ensure
that materials cannot fall as they can slide through or under the edge protection system element in
use.
Where there is a potential for materials to fall in excess of two metres, material protection to a
minimum height of 1000 mm must be provided and be capable of retaining the materials to be stored
and used. (Where materials are stacked higher than 1000 mm, guardrails and material guards will be
provided above the height of the materials to be stored).
A system is not complete if materials can fall from the perimeter or opening due to the absence of a
toe board or suitable element of the system in use that prevents materials falling from floor level.
Hierarchy of Preferred Edge Protection Methods (decreasing level of protection against the fall
of persons or materials)
Advanced - Perimeter Screens (full height, multiple floors)
Advanced - Perimeter Scaffold (full height netted proprietary system)
Advanced - Edge protection system 2 m+ or full floor height (meshed or netted)
Advanced - Full height vertical netting with proprietary edge protection (1.1 m)
Standard - Three element systems (perimeter rails with toe board) with netting or mesh
Standard - Three element system (perimeter rails with toe board) without net
Standard -Vertical reinforcement bar cast in situ with toe board added
Where roof sheeting is to be placed on the final level the perimeter of the roof must be protected
using a suitable and sufficient edge protection.
Safe procedures documented in the MS are to ensure that lifting loads over personnel or working
below suspended loads is avoided
Harness Permit to Work required if the need to use a safety harness as primary fall protection
cannot be avoided.
Note: Anchorage and life line systems shall be prefabricated and/or installed on the ground prior to
lifting or installed from a mechanical elevated work platform (MEWP).
The full height protection is to remain in place until the permanent doors are installed and
secured.
The lift stops will be installed first.
Protective measures for all openings are only removed when work is actually taking place in or
around the opening and effective safety measures are employed to prevent falls of those working on
them.
All loading platforms must be approved and signed off for use by a competent engineer before
installation to check that they are a robust design and that they can be safely and securely
located in the chosen locations by confirming structural integrity, installation and jacking
arrangements.
All loading platforms must be checked prior to installation and then weekly by an approved
supervisor to ensure adequate edge protection is fitted, smooth surfaces to facilitate the
movement of trolleys is provided and maintained, and to check that operatives are aware of safe
work procedures and are using the platform correctly.
Loading platforms and cranage must be arranged so that loads can be picked without the need
for the guarding to be removed from the end of the platform;
Systems of work on the loading platforms must not rely on the use of harnesses to prevent persons
falling – except for specific/unusual operations which have been risk assessed and detailed in a
Method Statement, are undertaken by trained operatives and carefully supervised
identified in the risk assessment and method statement and to ensure that the tool tethering policy
is complied with on completion of the task to which the dispensation relates.
Contractors have a responsibility to provide safe working conditions and a safe working environment
for their employees. This includes the provision of general and task specific personal protective
equipment for all employees. Risk management strategies must be in place to prevent incidents and
accidents at the work place.
Contractors staff must be trained, licensed (where applicable) and competent in the nature of work
and brief their employees before starting work of the risks and dangers involved in the profession they
are engaging in, such as fire, machinery risk, risk from vapour or dust of toxic substances, danger of
falling and relevant occupational diseases etc. Suitable Training must be given to all staff involved in
any potentially dangerous/hazardous operation/activity and such training shall be ongoing/periodic.
Contractors must also have strategies in place to deal with employees exposed to extreme
temperatures, confined spaces, noise, electric shock and work at height.
Contractors must provide warning signs in all potentially dangerous areas, such as chemical/ gas
cylinder storage areas, machinery, drills etc. Lessees must provide safety signs for protective clothing
as per working hazard, such as ‘WEAR SAFETY GEAR’ for noisy areas, ‘WEAR MASK’ for dusty
operational areas, in addition to other signs like ‘NO SMOKING’, FLAMMABLE STORAGE AREA’ etc.
All chemicals and hazardous materials stored on a project site must be stored in accordance with the
guidance contained in the supporting Material Safety Data Sheet (MSDS).
Material Safety Data Sheets must be kept both in a central file, displayed in the vicinity of the stored
chemical or hazardous substance and a full set kept at the First-aid Room/Medical centre.
A Material Safety Data Sheet provides information about the following:
Product Information
Hazardous ingredients
Physical data
Fire and explosion data
Reactivity data
Toxicological properties
Preventative measures
First-aid measures
3.19 PPE
3.19.1 General Requirements
All workers and visitors exposed to construction operations must wear five point PPE; Hard Hat,
Safety footwear, High Visibility clothing, and Eye Protection and gloves. The items must fit the
individual and be in good condition. All workers are also required to wear coveralls.
Adequate supplies of personal protective equipment must be available to protect both workers and
visitors. Their items of task specific Personal Protective Equipment (PPE) must be identified in risk
assessments and PPE provided on an as needs basis.
All PPE items must have the CE mark (the recognised mark for PPE tested and approved to
International Standards). Hard hats must be compliant with EN 397 or equivalent standard.
This standard is to be fully enforced and any person not in compliance with this element will be asked
to immediately rectify any missing elements of PPE. Failure to do so will result in exclusion from the
project.
All project stakeholders are to ensure that they have a suitable amount of PPE available to cater for
the workforce and for visitors.
Key personnel must be easily distinguished by visual markings, such as specific colours of helmets or
clothing for supervisors, safety professionals, slingers, and medics.
PPE risk assessments must be completed for all working tasks. Where specialist PPE is required,
employers must undertake an assessment of the type of PPE to be used taking into account the
following:
The environment where the PPE is to be used
The risks involved with the operation
The operatives using the PPE
Whether specialist training is required for the fitting/use of the PPE
Rescue/emergency procedures
The equipment has been regularly inspected and is in good working order
Maintaining cleanliness of public interface areas including adjacent operational areas (dust/dirt
caused from construction activities), head of stand areas, airside roads, areas within the terminal
and pier open to the public.
The team will be required on a daily basis to liaise with all the various trades to ensure the smooth
flow of all materials to a designated point of use. The point of use will be defined as an area close
to where the materials will actually be installed. The materials to be handled will be defined on a
matrix developed by the construction management team.
All equipment and materials shall be delivered directly to the contractor’s lay down/staging areas for
each main construction zone. A strict procedure shall be enforced such to avoid double handling and
that equipment and material deliveries are planned in advance.
Do not consume food on the site, unless it is within designated facilities provided.
Do not attend site under the influence of alcohol or drugs.
Do not smoke onsite except within authorised areas.
Do not remove or tamper with anything provided in the interest of health and safety
Do not remove any guardrail or cover to any hole unless you have been given express permission
from your supervisor. ensure protection measures are replaced on completion of your work
activities
Do not undertake any work unless your supervisor has briefed you on the key aspects of the safe
system of work.
Do not operate any plant, machinery, tools or equipment that you are not trained or authorized to
use.
Do not burn any materials onsite.
Do not indulge in horseplay whilst onsite.
Do not use radios, Walkman, msp3 players, iPod or similar on the construction site
Do not use any hand held device whilst driving onsite.
Do not stop on vehicle access roads.
Do not overtake unless it is safe to do so.
3.22.2 Introduction
The level of detail in the HSP must be proportionate to the scope of the project and the risks arising
from the construction activity.
Information must be project-specific.
Persons preparing, completing, reviewing and amending the HSP must be competent to do so and
must have the prerequisite knowledge, skills, awareness and training.
Project Location
Insert a map showing the location of the project.
Existing Pre-construction Information
Include any pre-construction information obtained from and/or issued by the employer/engineer,
such as:
Existing Environment
Surrounding Land Uses
Site Structures
Ground Conditions
Ground Investigation results
Existing Services
Services within the site
Existing Traffic systems
Responsibilities
Include specific personal responsibilities
Onsite Safety and Health Coordination Roles
Key project health and safety coordination roles are allocated to members of the project
management team.
Each coordinator has a duty to coordinate the health and safety information and requirements
with their specific role.
These key roles include (but are not limited to) the following:
Fire Safety coordinator
Scaffold coordinator
Temporary Works Coordinator
Temporary Works Inspector
COSHH coordinator
Permit to Work coordinator
Traffic Management coordinator
Appointed Person (lifting ops)
Lifting Supervisor
Excavation coordinator
Electrical duty holder
Plant manager/supervisor
Project Health and Safety Goals
Describe and define corporate and project specific HS goals and objectives
Goals must be measurable, wherever practicable and the arrangements for monitoring and
reviewing the Health and Safety performance provided in the HSP must be followed.
Health and Safety Goals
Examples of health and safety goals are listed in Table 3-11.
2 Prompt reporting of SNMI and incidents to next Ops and H&S Manager within
management tier one hour
4 All issues raised and closed out within seven days 100%
5 Audit programme with visible input Cr360 from all the Number of Audits and items
project Management Teams logged onto Cr360 by each
Project team member.
Performance Management
Regular liaison between parties onsite
Include arrangements for liaison with Client, Engineer, parties affected by our works. Explain how
we will liaise with the key parties.
Consultation of the workforce
Identify how the workforce are consulted on matters relating to health and safety
The exchange of Design Element Information between the Client, Designers, Contractors
Describe the process
Handling Design or Scope Changes
Describe the process
The Selection and Control of Contractors
Describe how subcontractors are assessed and selected.
First-Aid
Each contractor shall have a trained first-aiders/nurses/medics whilst works are being undertaken
onsite. Arrangements can be made where low numbers are concerned a shared first-aider may
be appropriate e.g. weekend, out of hours’ work. Describe the specific arrangements
Reporting and Investigation of Accidents and Incidents (including near misses)
Refer to the employer’s HSE Requirements
Risk Assessment and Safe Systems of Work
Refer to employer’s HSE Requirements
Refer to (HSP Template).
No mobilisation or construction activities must commence until the occupational health and safety
hazards have been identified and the risks arising from these hazardous have been evaluated.
The Risk Assessment is a process of evaluating risks (the likelihood of an occurrence of a
hazardous event plus the severity of injury or ill health arising out of that occurrence). It must
cover all routine and non-routine construction-related activities.
The Risk Assessment process must take into account the adequacy of any existing controls.
When determining controls or making changes to existing controls, consideration must be given to
reducing the risks according to the following hierarchy (the principles of prevention):
Elimination
Substitution
Engineering controls
Signage/warnings, and/or administrative controls
Personal protective equipment
Risk Assessments are used as the basis for preparing Method Statements. Risk Assessments
and Method Statements must be specific to the project or task; not generic.
Contractors must provide both Schedules and Registers for their own Risk Assessments and
Method Statements, along with the associated documents.
Allow for proper planning and adequate time resource to ensure that the correct Method
Statement documentation is in place prior to construction activities commencing.
No construction activities must commence until both the SC Project Manager and the SC
Construction Manager have approved the Method Statement and signed it off as a Category ‘A’
rating. The approved document must then be uploaded on Aconex, which is the employer’s
EDMS.
Where the SC rate a Method Statement with a Category ‘B’ rating, it must be returned to the
Contractor for amendment and reissue. Construction activities must not commence against
Method Statements where a Category ‘B’ rating is scored. Method Statements with a Category ‘C’
rating must be rejected.
Site Rules (including drug and alcohol policy)
Refer to Key Health and Safety Rules
Rules must be reasonable and properly communicated.
Fire and Emergency procedures
Identify foreseeable emergency situations that may arise, such as fires, explosions, failure of
critical equipment, loss of utility supply, flooding, environmental emergency, release of hazardous
materials/gases, severe weather, traffic accidents, and civil disturbance.
Coordinate emergency response procedures with the employer, contractors and other interested
parties.
Where external services are needed for emergency response, pre-approved arrangements need
to be put in place.
Fire safety plan required to be developed for works and site facilities.
No construction activity must commence where there are unstable structures until a structural
engineer has provided formal written advices. This includes demolition or dismantling works.
5. Preventing falls
Refer to (Work at Height Guidance)
6. Work with or near fragile materials
Refer to (Work at Height Guidance)
7. Control of lifting operations
Refer to (Project Lifting Plan)
Refer to (Lifting Manager Checklist)
The Maintenance of Plant and Equipment
Each trade will be expected to keep a schedule for all plant and equipment. All plant and equipment
will be checked daily by the operator and a record of the checks kept by the trade. Refer to Appendix
C - Key health and safety standards.
Work on excavations and work where there are poor ground conditions
Poor ground conditions may affect the safe use of plant or the safety of the ground works
Temporary Works Coordinator must be consulted. A structural engineer must sign-off
Drawings for excavations in poor ground conditions
Work on wells, underground earthworks and tunnels
Working on wells, underground earthworks and tunnels is not a routine occurrence. Seek advices
from H&S Department
Work on or near water where there is a risk of drowning
Work involving diving
Working involving diving is not a routine occurrence. Seek advice from H&S department
Work in a caisson or compressed air working
Work in a caisson and/or compressed air working are routine occurrences. Seek advice from H&S
department
Work involving explosives
Working with explosives is not a routine occurrence. Seek advice from H&S department
Traffic routes and segregation of vehicles and pedestrians
A detailed Traffic and Logistics Plan will be developed. The plans will show access routes to the site
for deliveries, safe pedestrian routes onto the site, proposed storage areas (including waste areas)
and emergency escape routes. Where there is an interface between the traffic and a pedestrian
crossing there will need to be traffic control signage, a banksman, etc. to minimise the likelihood of an
incident.
8. Storage of materials (particularly hazardous materials) and work equipment.
Identify on the Traffic Management and Logistics Plan where the storage areas are, how to access
them and ensure they are clearly marked onsite.
9. Any other significant Safety risks.
Health Risks
The removal of asbestos
We must ensure that we have reviewed the pre-construction Information and made all reasonable
enquires regarding the presence of asbestos in the areas we intend to operate in. A survey is advised
in most situations where a presence of asbestos is suspected or identified.
Dealing with contaminated land
(Environmental Management Plan).
Manual handling
(Trades must include a manual handling risk assessment with their method statements)
Use of hazardous substances, particularly where there is a need for health monitoring
(Trades must include a COSHH assessment with their method statements)
Reducing noise and vibration
(Trades must include noise and vibration risk assessment with their method statements)
Work with ionising radiation
Working with ionising radiation is not a routine occurrence. Seek advice from H&S Department.
Exposure to Heat and UV radiation (from the sun)
Exposure to the sun causes sun burns and over time, repeated exposure may cause skin cancer.
Shorts are not permitted on any engineering project/site and will be one of the site rules.
Excessive exposure when working in the sun can cause dehydration, fatigue and heat
exhaustion. Arrange for suitable breaks and drinking water in easily accessible locations.
Any other significant health risks
Non-routine health risks must be referred to the H&S department
1 (a) Scope
Provide a clearly defined description of the work to be undertaken, identifying the trade
contractor, subcontractors, and the exact location of the works intended.
Reference clearly any other safety procedure, document or method statement associated with
the intended work (e.g. lifting plans if required).
1 (b) Methodology
Provide an organisation diagram identifying the composition of your site management and
supervisory team tasked with supervising your various site operations
Provide a summary CV for your key managers/supervisors
Experience
Qualifications where relevant
Safety training courses attended
Clearly identify the key Health and Safety duties of your management and supervisory staff.
Clearly outline the persons onsite who will be competent to provide first aid.
Clearly outline persons within the organisation that must be contacted in the case of an
emergency situation.
For contractors submitting more than one method statement this section does not have to be repeated where
unnecessary – simply insert a copy of organisation diagram from your original Health and Safety method
statement.
Information contained within this section must be included in Section 5 of operative task briefing sheets.
4. Access/Egress
Clearly identify the safe means of access and egress to the workplace
Will general access/egress routes be blocked as a result of the work?
If so, define the alternative arrangements which will be provided to maintain emergency
escape routes
Define the actual access used at the workface
Provide a diagram illustrating access and egress paths to the working area and within the working
area.
5. Lighting
Clearly identify your arrangements for ensuring your place(s) of work are provided with adequate
illumination.
Workplace ‘task lighting’ and ‘specific access route lighting’
‘Intrinsically safe’ lighting requirements where applicable
Provide a reference to the lux level required for the task, showing consideration for the
complexity of the task.
‘General access lighting’ and ‘emergency lighting’ will be provided by the Principal Contributor.
9. Waste Management
Clearly identify your arrangements for controlling your waste products at the workplace.
Keeping the workplace clean and tidy
Minimising the volume of the waste created by your work activities
Segregating ‘hazardous wastes (i.e. special waste) from ‘non-hazardous wastes’ for final
disposal from site.
The project will implement a specific waste management system for the collection of waste materials from the
workplace to be taken to final disposal from the site.
Identify any work activities which will require special control measures (such as permit to work
systems, specialist training, and specialist equipment) to be implemented to ensure the adequate
protection of employees and/or others against risk of injury.
Examples
Asbestos removal works
Work on or near electrical systems
Reduce
Accept
Transfer
Maintaining Records
It is important to maintain records of risk assessments that have been undertaken for the following
reasons:
They are useful for mitigation (i.e. audit trail of Health and Safety compliance) if
questioned/investigated by enforcement authorities.
They are usually necessary to supporting/producing Health and Safety Method Statements.
The particular work Inspecting the roof of a building for works to be undertaken by a
operations being contractor
carried out by Witnessing the commissioning/test procedures undertaken on
company employees plant or machinery (e.g. lift machinery)
Carrying out electrical tests/checks to plant or equipment
Moving equipment/furniture during office relocation/refurbishment
Supervising concrete breaking out works in an enclosed area
Supervising works which involve the application of hazardous
substances (e.g. epoxy resins for floor laying)
The risk which still exists Risk of falling still exists if guardrails not secured adequately
after all known control and maintained
measures are Risk of contact with moving machinery still exists as guards
implemented have to be removed for test procedures while machinery in
operation
Risk of electric shock still exists if personnel are not
competent and trained
Risk of muscular/skeletal damage still exists if personnel are
not adequately trained
Risk of noise exposure still exists if the correct type of
hearing protectors are not provided
Risk of exposure to harmful substances still exists if the
correct type of RPE is not provided
Accident Probability
Likelihood that the hazard will Very Likely Very likely that hazard will be realised
be realised into an accident into an accident event
event
Accident Severity
Likely consequences to Very Serious Fatal or permanently/long term
persons who may be exposed incapacitating injuries
to the accident event
Management plan structured 9 High Further action must be taken with regard
to address the accident risk to reducing the accident risk factor (i.e.
6
factors in order of priority. further control measures).
Accident Probability
success and integrity and the expression. This may include a divisional director where the division is
equivalent to an entity of substance or a leader of an entity.
Directors who carry out day to day management of work activities must also comply with the Expo
2020 Managers Training Standard.
Training Standard
Directors must be able to demonstrate they have sufficient knowledge of health and safety.
Directors must be able to demonstrate that they have met the training standard.
Suitable Courses
The employer recognises the following courses as being suitable and meeting the required standard:
IOSH Directing Safely (one day)
IOSH Managing Safety for Senior Executives (one day)
Comparable internally developed training may be recognised where the employer has demonstrated
that the training course has content and outcomes at least equivalent to these course types.
Duration
The course duration must be no less than one day.
Assessment
Courses must incorporate a form of assessment.
Certification
Directors must be in possession of a certificate that details the training provider, date awarded, course
title and confirmation stating whether or not the delegate has passed the examination.
Refresher Training
Directors must attend refresher courses as defined by the training provider. This must not exceed five
yearly intervals. If a refresher course is not available, the original course or similar must be resat at
five yearly intervals.
Duration
The course duration must be no less than four days.
Assessment
Courses must incorporate a form of assessment.
Certification
Managers must be in possession of a certificate that details the training provider, date awarded,
course title and confirmation stating whether or not the delegate has passed the examination.
Refresher Training
Managers must attend refresher courses as defined by the training provider. This must not exceed
five yearly intervals. If a refresher course is not available, the original course or similar must be resat
at five yearly intervals.
Refresher Training
Supervisors must attend refresher courses as defined by the training provider. This must not exceed
five yearly intervals. If a refresher course is not available, the original course or similar must be resat
at five yearly intervals.
Expo 2020 Programme Office
Expo 2020 Dubai Site
Jebel Ali-Lehbab Road
PO Box 2020
Dubai, UAE