Timeline

Pre-Construction Period

Site Plan

TTD Perjanjian

Maks. 3 Hari Performance Security / Guarantor Bank Rp. 25 M

Maks. 7 Hari Contractor Documents

Maks. 7 Hari Review Developer

Maks. 60 Hari sejak TTD Perjanjian Mulai Pekerjaan

Construction Period

Milestone 1 : Advanced Payment Rp. 22.5 M / Guarantor Bank + Rp.


25 M (Rp. 50 M)

Milestone 2 : Pekerjaan Persiapan Rp. 18.75 M

Milestone 3 : Pekerjaan Tanah Rp. 18.75 M

(Pre-commissioning Test)

Milestone 4 : Pekerjaan Struktur Bawah Rp. 45 M

Milestone 5 : Pekerjaan Struktur Atas 10 Rp. 45 M

6 : Pekerjaan Struktur Atas 8 Rp. 45 M

7 : Pekerjaan Struktur Atas 8 Rp. 45 M

8 : Pekerjaan Struktur Atas 8 Rp. 45 M

Milestone 9 : Kelistrikan dan Plafond Rp. 45 M

(Commissioning Test)

Milestone 10 : Finishing Rp. 25 M

(Trial Operation)

Validation Completion (Completion Certificate) Rp. 50 M

Maintenance Period

Maintenance Period 2 Tahun (Maintenance Certificate) Rp. 50 M / Guarantor Bank Rp. 30 M