Professional Documents
Culture Documents
Second Moplah Uprising (1921) - Malabar Movements
Second Moplah Uprising (1921) - Malabar Movements
Reasons:
o Tipping point: Police raided a mosque to arrest a Khilafat leader Ali Musaliar.
o Farmers attacked police stations, public offices and houses, land records of
zamindars and moneylenders under the leadership of Kunhammed Haji.
o For months, British government lost control over Ernad and Walluvanad taluks for
several months.
o This movement was termed as Anti-British, Anti-Zamindars and, to some extent, as
anti-Hindu.
o Podanur Blackhole: British put 66 Moplah prisoners into a railway wagon and
completely shut it down. They all died of asphyxiation.
o Result: Hundreds of Moplah lost lives- as a result they were completely demoralized
and didn’t join in any future freedom struggles or even communist movements post
independence.
Other Awards
The approximate estimate is prepared from the practical knowledge and cost of similar works. The
estimate is accompanied by a report duly explaining necessity and utility of the project and with a site or
layout plan. A percentage 5 to 10% is allowed for contingencies.
The following are the methods used for preparation of approximate construction cost estimates:
The cost of construction is determined by multiplying plinth area with plinth area rate. The area is
obtained by multiplying length and breadth (outer dimensions of building)
In fixing the plinth area rate, careful observation and necessary enquiries are made in respect of quality
and quantity aspect of materials and labour, type of foundation, height of building, roof, wood work,
fixtures, number of storeys etc.
As per IS 3861-1966, the following areas include while calculating the plinth area of building:
Types of Estimates:
Internal shafts of sanitary installations not exceeding 2.0 sqm, lifts, air-conditioning ducts etc.,
Area of barsati at terrace level: Barsati means any covered space open on one side, constructed on one
side, constructed on terraced roof which is used as shelter during rainy season.
Area of lofts.
Unenclosed balconies.
This method is generally used for multi-storeyed buildings. It is more accurate that the other two
methods viz., plinth area method and unit base method.
The cost of a structure is calculated approximately as the total cubical contents (Volume of buildings)
multiplied by Local Cubic Rate. The volume of building is obtained by Length x breadth x depth or height.
The length and breadth are measured out to out of walls excluding the plinth offset. The cost of string
course, cornice, corbelling etc., is neglected.
According to this method the cost of structure is determined by multiplying the total number of units
with unit rate of each item. In case schools and colleges, the unit considered to be as ‘one student’ and
in case of hospital, the unit is ‘one bed’.
The unit rate is calculated by dividing the actual expenditure incurred or cost of similar building in the
nearby locality by the number of units.
The quantities are calculated by multiplying the values that are in numbers
column to Depth column as shown below:
Details of measurements form
ii) Location of site: The site of work is selected, such that it should reduce
damage or in transit during loading, unloading, stocking of materials.
iii) Local labour charges: The skill, suitability and wages of local labores are
considered while preparing the detailed estimate.
ii) Cost of labour: The exact number of labourers required for unit of work
and the multiplied by the wages/ day to get of labour for unit item work.
iii) Cost of equipment (T&P): Some works need special type of equipment,
tools and plant. In such case, an amount of 1 to 2% of estimated cost is
provided.
The building cost estimates can be classified in many ways. The three major
and significant ways in which the building cost estimates can be classified
are:
This base for the cost estimation is either meter square of the constructed
building or based on the number of units like the number of cars in the
parking lot or the number of students in the high school or the number of
beds in a hospital.
The stochastic approach makes use of many variables which are considered
as parameters for the cost estimation as given by the experienced
estimators. These variables in most of the cases will not be well defined.
When dealing with various types of building estimates, the owner or the
contractor must relate the work to the “expected accuracy range”. This
accuracy is expressed either positively or negatively with an estimated
future cost.
The table-1 shows the various expected accuracy for different cost
estimates.
Table.1: Classification of Building Cost Estimates with Respective Expected Accuracy
Range (%)
It is observed that the total project cost is higher when compared to the
engineering and the project cost. This is because the project cost also
includes the cost that are used for the acquisition of the land, to study the
environment, the cost of financing and the market study.
To control the cost, the scope and the schedule of the project is to focus on
control of the design process. This is one of the critical element that must be
taken control off to reduce the project cost.
Any sort of failure in the control and the management of the design process
results in the delays and the increased construction cost of the project.
The design phase requires the submittals of the design review and the status
drawings. These are issued at required intervals. The project beginning must
have a clear idea on how many project submittals are essential and must be
prepared.
This must be clearly planned by the manager. These frequencies are mainly
at the 30, 60…. The frequency of the design review will change with the
complexity of the project.
The first engineering estimate has 30% of the design submittals that is
based on the drawings. This level helps the estimator to develop the work
quantities and the actual unit price.
The second engineering estimate have 60% of the submittals that will serve
the following:
The complete set of bid documents conforms to 90% submittals. This is the
last review chance and the owner should analyze completely that all his
requirements are met and achieved.
The unit cost method of estimation can be used for project design estimates
as well as for bid estimates.
During the preliminery cost estimate, as cost details of every minute elements
are not of much importance, the project is divided into major components
and cost estimate of these major units are calcualted based on the past
project experiences. The cost of euipments if any is also included. For
example, estimating the cost of entire floor based on its area.
During detailed Cost estimates, the project is divided into components of various
major systams and cost of each components is estimated to calculate project
cost. For example, cost of installation of any equipment, cost of beams,
columns or walls etc.
During Engineer’s cost estimates, each of the components of the major systems
of the project is divided into various components that contributes to the cost
of the major systems.
For example, for cost estimation of an RCC column, the components are
concrete, which is also divided into cement, sand and aggregates,
reinforcement steel, formworks etc. The unit cost of each of these materials
are considered by calculating the cost of an RCC column.
For bid estimates, the unit cost method of estimation can also be used even
though the contractor divides the project into different levels in a hierarchy
as follows:
1. Subcontractor Quotations: The general contractor of the construction project may get
quotations for various items from the subcontractors. The rates prescribed by the
subcontractors for various items of the projects can be used for the total
construction cost etimate for the project. However, the reliability of accuracy of the
cost depends on the method of cost estimates selected by the subcontractor.
2. Quantity Takeoffs: The division of a construction project into various items of
quantities that are measured from the engineer’s plan will result in a procedure
similar to that adopted for a detailed estimate or an engineer’s estimate by the
design professional. The levels of detail may vary according to the desire of the
general contractor and the availability of cost data.
3. Construction Procedures: If the construction procedure of a proposed project is used as
the basis of a cost estimate, the project may be decomposed into items such as
labor, material and equipment needed to perform various tasks in the projects.
Formula for Unit Cost Method
Suppose that a construction project is divided into “n” elements for cost
estimation. Let “Qi” be the quantity of the ith element and ui be the
corresponding unit cost. Then, the total cost of the project is given by:
where n is the number of units. The unit cost of element ui is estimated
based on the method of construction, technology used, type of materials
used etc.
Factored Unit Cost Estimate Formula
Sometimes during the cost estimate, there can be some of the minute
components which may not have been considered or there can be some
variations w.r.t time. In such cases, the cost of units are factored as an
allowance for variations or the elements not considered in the estimates.
The formula for factored unit cost estimation is as follows:
Note that WiLi yields the labor cost per unit of Qi, or the labor unit cost of
task i. Consequently, the units for all terms in Equation above are
consistent.