1. The document provides calculations for trenching work including the number of excavators, manpower, equipment, and time required. It estimates the total trenching time will be 27 days.
2. It calculates the volume of trenches using the trapezoidal method. The trenches have varying dimensions and the total volume is estimated to be 67,205.94 cubic meters.
3. Based on an excavator capacity of 108 cubic meters per day, 3 excavators would take approximately 27 days to complete the trenching work.
1. The document provides calculations for trenching work including the number of excavators, manpower, equipment, and time required. It estimates the total trenching time will be 27 days.
2. It calculates the volume of trenches using the trapezoidal method. The trenches have varying dimensions and the total volume is estimated to be 67,205.94 cubic meters.
3. Based on an excavator capacity of 108 cubic meters per day, 3 excavators would take approximately 27 days to complete the trenching work.
1. The document provides calculations for trenching work including the number of excavators, manpower, equipment, and time required. It estimates the total trenching time will be 27 days.
2. It calculates the volume of trenches using the trapezoidal method. The trenches have varying dimensions and the total volume is estimated to be 67,205.94 cubic meters.
3. Based on an excavator capacity of 108 cubic meters per day, 3 excavators would take approximately 27 days to complete the trenching work.
owned owned 15,000,000.00 45,000,000.00 owned owned 50,000,000.00 300,000,000.00 Rp345,000,000.00 Rp345,000,000.00 Perhitungan: Panjang: 15000 m Lebar Galian: 1914 mm 1,914 m Tinggi Galian: 2614 mm 2,614 m Diagonal : 2689.4 mm 2,689 m Lebar bagian 1514 mm bawah
Luas Trapesium = Jumlah Sisi Sejajar x tinngi/2
4480396 mm² Volume Trapesium = L Trapesium x Panjang Volume Trapesium = 67205.94 mᶟ Kapasitas Excavator = 108 mᶟ/jam 1080 mᶟ/hari