Professional Documents
Culture Documents
Bhel Report
Bhel Report
JUHI NAGPAL
B.Tech. 3rd year
Electrical and Electronics Engineering
AKGEC, GHAZIABAD.
TABLE OF CONTENTS
CONCLUSION
CHAPTER 1
INTRODUCTION ON BHEL
-
BHEL HARIDWAR
At the foothills of the majestic Himalayas, on the bank of the Holy Ganges in Ranipur,
Uttarakhand is located Heavy electrical equipment plant (HEEP) of B.H.E.L.
BHEL has turnkey capabalities for executing power projectors from concept to
commissioning. it possesses the technology and capability to produce thermal power
plant equipment upto 1000MW rating and gas turbine generator sets upto a unit rating of
240MW.Cogeration and combine cycle plants have been introduced to achieve higher
plant efficiencies. To make efficient use of the higher ash content crash coil
manufacturers 235MW nuclear turbine generator sets and has commenced the
generation of 500 MW nuclear turbine generator head discharge combinations are also
engineered and manufactured is equally competitive.
TRANSMISSION-
BHEL also supplies a wide range of transmission products and systems upto 400kV class.
These include high voltage power, distribution transformers, instrument transformers,
dry type transformer,SF6 switch gear, capacitor and insulator,etc.Series and shunt
compensation systems have been also developed and introduced to minimize
transmission losses.
TRANSPORTATION-
A high percentage of trains operated by the Indian Railways are equipped with BHEL’s
traction and control equipment including the metro at Calcutta and Delhi.the company
supplies broad gauge.
INTERNATIONAL OPERATIONS-
B.H.E.L.’s product series and projects have been exported to countries ranging from
United states in the west and New Zealand in the east and for India over 3000MW.a
few notable ones are a 15o MW gas turbine to Germany ,utility boiler and open cycle
gas turbine plant to Malaysia, Tripoli west, power station in Libya and Turkey .in Cyprus,
hydro generator to New Zealand and hydro power plant to Thailand, Oman, Greece
and Egypt.
CHAPTER 2
CIM SHOP (BLOCK – IV)
BAY-1: Bar winding shop: Manufacturing of stator winding bars of generator, Micalastic
Tank & Oven
BAY-2: Heavy duty generator stator bars with New CNC M/c No, 3-464 i.e. Roebel bar
centre, TIG Welding
BAY-3: Insulation detail shop: Manufacturing of hard insulation & machining of hares
insulation part (Glass textolite) such as packing, washer, insulation box, wedges etc. &
CNC Taping Machine
Bar Shop: This shop is meant for manufacturing of stator winding coils of generator that
may be turbo-generator or hydro-generator.
Why do we call it bar: It is quite difficult (rather impossible) to manufacture, handle and
wind the coil in stator slot of generator of higher generation capacity because of its
bigger size and heavy weight. That is why we make coil in two parts. One part is Bottom
part of coil called bottom or tower bar and other part of coil is called top bar or upper
bar.
TYPES OF GENERATORS:
The generator may be classified based upon the cooling system used in the generators
such as-THRI, TARI, THDI, THDD, THDF, THFF, THW.
T-> First alphabet signifies the type of generator i.e. turbo-generator or Hydro-generator.
H/A-> Second alphabet stands for the coding media used for the cooling of rotor i.e.
hydrogen gas or air.
R/D/F/I-> Third alphabet signifies the type of cooling or rotor e.g. radial, indirect, forced,
direct etc.
I/D/F-> Last alphabet stands for the type of cooling of stator e.g. indirect cooling, direct
cooling, forced cooling.
W-> Cooling media used for cooling of stator coil e.g. water.
TYPES OF INSULATION
Thermal classification depends upon the temperature withstand capability of the
insulation.
TRANSPOSITION
ASSEMBLY OF
CONDUCTORS
CROSS OVER
INSULATION
I.S. TEST
FORMING
PICKLING
MOUNTING
BRAZING
REPICKLING
THERMAL SHOCK
TEST
REFORMING OF
OVERHANG PORTION
INSULATION ON CNC
MACHINE
IMPREGNATION
SURFACE FINISHING
OUTER CORONA
PROTECTION (OCP)
Upper Bar
2. Transposition
Transposition means changing/shifting of position of each conductor in active core
(slot) part. After cutting the required number of conductors, the conductors are
arranged on the comb in staggered manner and then bends are given to the
conductors with the help of bending die at required distance. Then the conductors are
taken out from the comb and die and placed with their ends in a line and transposition
is carried out. This process is repeated for making another half of the bar which would
be mirror image of the first half. The two halves of the bar are overlapped over each
other and a spacer is placed between the two -halves.
1. To reduce eddy current losses.
2. 2.Equalize the voltage generator
3. To minimize skin effect of ac current, small cross section of conductor is used and also
hollow conductors are used to effect cooling by D.M. water.
3. Crossover Insulation
The pre insulation of the copper conductor may get damaged due to mechanical
bending in die during transposition, hence the insulating spacers are provided at the
crossover portion of the conductors. A filler material (insulating putty or molding
micanite) is provided along the height of the bar to maintain the rectangular shape and
to cover the difference of level of conductors. To eliminate inter turn short at bends
during edges wise bending and leveling of bars in slots portion for proper stack
pressing.
4. Stack Consolidation
The core part of the bar stack is pressed in press (closed box) under pressure (varies from
product to product) and temperature of 1600 C for a given period. The consolidated
stack is withdrawn from the press and the dimensions are checked.
5. Inter Strand Short Test
The consolidated oar stack is tested for the short between any two conductors in the
bar, if found then it has to be rectified. This is done to ensure that no local current is
flowing due to short circuit between conductors. (300V A/C supply)
6. Forming
The straight bar stack is formed as per overhang profile (as per design), the overhang
portion is consolidated after forming.
7. Brazing of coil lugs
For water cooled generator bars, the electrical connection contact and water box for
inlet and outlet of water are brazed.
8. Thermal shock test
26 cycles of hot (800C) and cold (30°C) water are flown through the bar to ensure the
thermal expansion and contraction of the joints.
9. Helium leakage test
After thermal shock test bar is tested for any leakage with the help of helium gas.
10. Insulation
The bar is insulated with the given number of layers to build the wall thickness of
insulation subjected to the generating voltage of the machine.
RESIN SYSTEM:
a) Rich Resin or Thermo-reactive insulation system: In this type of insulation system the
bond content in resin 36-37%. The raw materials are ready to use and require
preservation and working on temperature 20-25':C. Its shelf life is one year when kept at
temperature 20 C which could be increased when kept at temperature of 5 C.
b) Poor resin or Micalastic insulation system: In this type of insulation the bond content
in the resin is 5-7% and insulating material is prepared with accelerator treatment. The
temperature control need not required. The insulating material is applied on job and
then the same is impregnated (fully dipped) in the resin.
TESTING
a) Tan∆ test:
This test is carried out to ensure the healthiness of dielectric (Insulation) i.e. dense or rare
and measured the capacitance loss. The capacitance of the bar is found and the angle
of deviation due to the impurity in the insulation is obtained from the formula
C4*R4*10-4 =tan∆
b) H.V. Test:
(High Voltage Test) each bar is tested momentary at high voltage increased gradually to
three times higher than rated voltage.
This training has proved to be quite faithful. This gave me, a chance to have an
encounter with such heavy machines like turbo generator (TG) 500MW.The architecture
of B.H.E.L. ,the way the various units are linked and the way the working of the whole
plant is controlled, makes the student realize that engineering is not just the structural
description but more of planning and management. It has provided an opportunity to
learn that optimization of technology used at proper place and time can save a lot of
labour.