Professional Documents
Culture Documents
net/publication/316364775
CITATIONS READS
0 650
4 authors:
Some of the authors of this publication are also working on these related projects:
IEEE Aswan International Workshop on Computational Methods in Power Systems (CMPS 2018) View project
All content following this page was uploaded by Ziad M. Ali on 22 April 2017.
Abstract_ Due to the frequently increasing in loads, the solve this problem without any change in the existing
generated power must be upgraded to match this increasing, protection relay scope in the power system.
consequently a new short-circuit level will be developed
based on the value of the generation system upgraded, this This work illustrates in details a realistic example of
raising on short-circuit current level could be extremely power plant consists of three generators and needed to add a
harmful on the protective equipment. To overcome the new generator as per loading increases therefor Fault
problem of the new S.C. level a new approach can be Current Limiter are being uses to maintain short circuit
achieved by using the fault current limiter (FCL) which level, SVC will also be used as the voltage drops on the 3.3
consider the most economical and practical solution. This KV switchgear Bus Bar due to using of the FCL .
paper investigates a realistic power plant system @ Khalda II. Fault Current Limiter (FCL).
Petroleum Company (KPC), which located at Egypt western
desert. The main target is to add a new 7 MW Generator to FCL is a nonlinear devices works on decreasing the
an existing 14 MW power plant drawn by three Generators amount of the fault current cause it has a high impedance
therefor a short-circuit study will be calculated after and that can be added to the electric circuit when fault take
before adding the new Generator. An adequate FCL will be place. Some of FLC has low impedance at the normal
selected to maintain the short-circuit within the previous operation change to high impedance device extremely fast
levels, on the other hand the S.V.C. will be used to once the faults happened, and before a circuit breaker take
maintain the voltage level likewise the existing by carrying action to trip a few milliseconds later. The common
out the Load Flow analysis after adding the FCL, all condition that for different current limiters is the operation
operations will be executed using ETAP 12.6 software. should be at the distribution voltage level [1], and the FLC
could be classified into two main types as following:
Keywords— Fault current limiter, Short Circuit, Load A. Passive Limiters:
Flow, SVC, ETAP 12.6.
It is permanently connected in series with the circuit of the
I. INTRODUCTION power system so no need to turn on or using an external
Catastrophically damage for all components of the signal to control its operation, the series inductors and
power system will be occurs due to frequently increasing of superconducting fault current limiters are considered
loads which demanding increasing in system generation in passive devices[2-4], Reactors are counted as the most
the power plant so an increasing in the short circuit level common passive limiter and flexible to be connected
may exceed the equipment breaking capacity. anywhere in the distribution circuit. They are a linear
inductive reactance; arithmetically the impedance will be
By using larger stepper transformer, the level of the voltage
added to the system to reduce of the fault currents, a voltage
will be increase and so adequate the S.C. level and this will
regulation carried out to maintain the distribution system
grantee the safety conditions for the equipment of the
voltage within the limits, due to voltage drop, which exists
system, or by readjusting the existing protection scope to be
due to the current flow through the reactors, are in the same
matches with the new S.C. level. Actually, both solutions
quadrature with the load voltage. The case under study with
will be expensive to carry out because of the high equipment
this type of FCL will be investigated in this work.
fees, so an economical and a practical solution is needed to
B. Solid State Limiters(SSL) feeders from the 4 generators to the two main bus bars
feeding the 11 KV switchgear, when the coupler will
During the fault case and after a few milliseconds of its maintain always closed the operation of adding new
action the solid state devices inserted by electronic switches generator of 10 MW will be implemented as per the
to increase the system impedance and to limit fault currents. following steps:
[5]. SSL is categorized into two main types: The resonance
based devices and the impedance switched bypass limiters. A- Calculate the short circuit values on the main four
The operation of resonance-based devices is based on that buses and at the far end, six buses are depicted in table
during the fault the voltage sags will be happened and will (1), from the table (1). The Max. Values of S.C. are
have a direct effect on the fault current values [6, 7]. 7.749 KA at BUS 1 & 2. these values should be
The impedance switched bypass limiters connected in series adequate to the breaking capacity of the protective
with the main distribution line, a pair of GTO are shunted devices such as the CB, CT and PT.
with it to operate during the voltage alternate half cycles to
create a new path of low impedance. The GTO switches are Table (1) Short-Circuit Summary
closed due to the fault and a large impedance will be
appeared and so limiting the current, but there are some 3 PHASE LINE TO
disadvantages due to switching power loss and its reliability FAULTS GROUND FAULT
cause the switching times effects are under search and study Bus No. Voltage (KA) (KA)
to enhance [8-9]. (KV)
1 11.000 7.749 3.331
III. SHORT CIRCUIT STUDY. 2 11.000 7.749 3.331
A short circuit study is modeled to get the values of the Max. 21 3.300 7.167 1.303
and Min., a new generator or Fault Current limiter is added
31 3.300 7.167 1.303
and so the study will be updated and repeat the adding
process until optimize the best efficient limiter which will 33 3.300 7.167 1.303
contribute on limiting the fault current to the same values 36 3.300 7.167 1.303
before adding the new generator. 38 3.300 7.686 0.813
All S.C. calculations were carried by using ETAP 12.6 40 3.300 7.686 0.813
based on IEC 60909 [10-13], the associated standards 42 3.300 7.686 0.813
classify short circuit currents according to their magnitudes 48 3.300 7.686 0.813
(maximum and minimum) and classify the fault distances
from the generator (far and near). Maximum short circuit
B- Calculate the short circuit values for the previous
currents determine equipment ratings, while minimum
buses after adding the new 7 MW generator which
currents dictate protective device settings. Near-to-generator
will certainly as a result on increasing the Max.
and far-from-generator classifications determine which of
Fault current as shown in table (2).
the AC components decrease in the calculation.
Table (2) Short-Circuit Summary
3 PHASE LINE TO
FAULTS GROUND
Bus No. Voltage (KA) FAULT
(KV) (KA)
1 11.000 7.403 3.230
2 11.000 7.403 3.230
21 3.300 7.106 1.299
31 3.300 7.106 1.299
33 3.300 7.106 1.299
36 3.300 7.106 1.299
38 3.300 7.624 0.812
40 3.300 7.624 0.812
42 3.300 7.624 0.812
48 3.300 76.24 0.812