Load Distribution And Total Load ·on Different BURs

SN Condition Aux. M/C in service Load (KW) Remarks


1 All three BUR1 OCB112 25+25=50 -
BURs in BUR2 TM Blower%, 25+25+11+11 +4.7 BUR2 works at 47
service Converter Pump +4.7=81.4 Hz and when TM
%, Transformer required then work
Pump% at 50 Hz
BUR3 Compressor %, 15+15+3+3+5=41 BUR3 works at 50
T M scavenger Hz
Blower%,
Battery Charger
2 BUR1 got BUR1 NIL 0 ****
isolated BUR2 OCB%, TM· 25+25+25+25+3+3 BUR 2 works at 24,
blower%, TM =106 37Hz
'scavenger
·Blower%
BUR3 Compressor%, 15+15+11+11+4.7. BUR3 works at 50
Converter Pump +4. 7 +5=66.4 HZ
%, Transformer
pump%,
Charger .

3 BUR2 got BUR1 OCB %, TM 25+25+25+25+3+3 BUR 1 works at 24,


isolated blower%, TM =106 37Hz
scavenger
Blower%
BUR2. NIL 0 . ****
BUR3 Compressor %, 15+ 15+ 11 +11 +4. 7 BUR3 works at 50
Converter Pump +4.7+5=66.4 HZ
%, Transformer
pump%.
Charger
4 BUR3 got BUR1 OCB%, TM 25+25+25+25+3+3 BUR 1 works at 24,
isolated blower% ,TM =106 37Hz
scavenger
Blower%
BUR2 Compressor %, 15+15+11 +11 +4.7 BUR2 works at 50
Converter Pump +4. 7 +5=66.4 HZ
%, Transformer
pump%,
Charger
BUR3 Nil 0 ****