You are on page 1of 9

OTC 13177

Cantarell’s Akal C Complex: the World’s Largest Offshore Gas Treating


and Lift Gas Generation Platforms
Ron Kettles, Bechtel Corporation, J. C. Kuo, IPSI/Bechtel, and Javier Rubio, Petroleos Mexicano (Pemex)
Copyright 2001, Offshore Technology Conference
• modernize the existing facilities to improve operational
This paper was prepared for presentation at the 2001 Offshore Technology Conference held in Houston, safety and efficiency.
Texas, 30 April – 3 May 2001.
The program to do so has resulted in several major
This paper was selected for presentation by the OTC Program Committee following review of the
information contained in an abstract submitted by the author(s). Contents of the paper, as presented, concurrent, integrated projects of unprecedented size and
have not been reviewed by the Offshore Technology Conference and are subject to correction by the
author(s). The material, as presented, does not necessarily reflect any position of the Offshore
complexity, which together have created the largest offshore
Technology Conference or its officers. Electronic reproduction, distribution, or storage of any part of this expansion of its type in the world. Major components of the
paper for commercial purposes without the written consent of the Offshore Technology Conference is
prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; Cantarell project include:
illustrations may not be copied. The abstract must contain conspicuous acknowledgement of where and
by whom the paper was presented.
• modernize 39 existing platforms and constructing 26 new
main platforms to increase oil and gas production and
Abstract handling capacity,
Petróleos Mexicanos (Pemex) is undertaking a major upgrade and • developing two new complexes (Akal L and B),
expansion of the Cantarell oil field in the Gulf of Mexico in order • building a floating storage/offloading facility for oil
to increase crude oil production, reduce gas flaring, and improve production handling,
the reliability and operational safety of existing facilities. Within • building the largest nitrogen generation plant in the world to
the Cantarell Field, Akal C is the most important complex due to supply 1,200 million standard cubic feet per day (mmscf/d) of
its gas treating and compression capacities. nitrogen gas to pressurize the oil reservoir,
This paper outlines the design and construction challenges • laying more than 400 km of subsea pipelines to augment the
associated with the modernization and expansion of the Akal C existing 1,700 km network,
complex to meet the Cantarell project objectives. • increasing gas handling capacity,
• building offshore gas treating platforms to generate lift gas,
Introduction to Cantarell Oil Field • modernizing Akal C to increase its gas compression and
The Cantarell field, located about 80 kilometers (km) offshore of processing facilities to generate lift gas offshore, and
the Yucatan Peninsula in the Bay of Campeche, Mexico (see • modernizing the safety and control systems of all existing
Figure 1: Location of Cantarell Oil Field), is the largest oil field in platforms and complexes.
Mexico. The Cantarell field is composed of four major fields: To execute this massive program, projects were grouped in
Akal, Nohoch, Chac, and Kutz, in addition to the reserves in the two “plans,” with considerable integration and tie-in between the
newly discovered deeper Sihil Field. Cantarell’s largest reservoir, two. The Short-Term Plan focused on the most urgent upgrades of
the Akal field, is considered the sixth largest reservoir in the world. existing 20-year-old facilities (complexes Akal C, Akal-J, and
Since Cantarell’s initial discovery in 1976 and exploitation in Nohoch-A) and a new lift gas generation facility at Akal C to
1979, reservoir pressure has declined by more than 60 percent (see allow oil production to increase and allow gas flaring to decrease.
Figure 2: Reservoir Pressure and Oil Production Over Time), The Long-Term Plan focused on additional lift-gas
leading to numerous operational difficulties in sustaining the target production capacity and extensive new oil production facilities,
oil production rate, including falling well fluid levels and the including new production complexes at Akal B and L, and 10 new
increased need for lift gas. satellite wellhead platforms to enable substantially more
In addition to overcoming the impacts from falling reservoir oil production.
pressure, Pemex wanted to accomplish several key objectives: This paper focuses on the technical, construction, and
• increase the reserves, execution challenges associated with generating additional lift gas
• more than double oil production, to meet increased oil production goals, and upgrading and
• utilize all the produced gas by adding sufficient debottlenecking the offshore complex to increase operational
compression and process capacity, and efficiency and accommodate the increased production objectives
2 R. KETTLES, J.C. KUO, J. RUBIO OTC 13177

for the Akal C complex which, when completed, will consist of 11 Option 1 was rejected because the Cantarell field lift gas
major platforms. system was not designed to handle highly corrosive sour gas.
Furthermore, the cost and safety considerations associated with
Generating Additional Lift Gas for Cantarell replacing the existing lift gas system and installing an additional
Lift gas is commonly used in the oil-producing industry to lift gas ring for sour gas was prohibitive.
facilitate oil extraction from the reservoir. Pressurized lift gas is The second option, to generate lift gas onshore and transport
injected into the extraction wells, where it mixes with the oil. The it offshore by subsea pipelines, was rejected because the existing
resulting mixture is lighter and therefore easier to lift. The onshore gas treating plants are located 160 km away from the
availability of lift gas at Cantarell is crucial for a sustained increase platforms. Two new costly pipelines and additional compressor
in oil production. and recompressor stations would have been needed, making this
There are about 205 production wells in the Cantarell field, option significantly more expensive.
producing between 4,000 and 16,000 barrels per day (bpd). Each The study concluded that the third option, to install the
well requires, on average, approximately 2.8 mmscf/d of lift gas. additional processing and compression facilities offshore, was the
The combined requirements of increasing reservoir pressure safest and most economical.
to maintain current production levels coupled with the increased
production objectives made the supply of lift gas the single most Location of New Lift-Gas Generation Facilities. The existing
crucial activity for a sustained increase in oil production for the Cantarell production facilities consisted of three main complexes:
Cantarell field. Akal C, Akal-J, and Nohoch-A.
Of these, the Akal C complex is the largest and accounts for
Existing Lift Gas Generation System. For the Cantarell field, the largest portion of oil and gas generated. The existing Akal C
most of the “sweet” lift gas was previously generated onshore. A complex had a capacity to compress 420 mmscf/d of gas, process
80-km-long pipeline supplied lift gas from an onshore natural gas 550,000 barrels per day (bpd) of oil, and accommodate
liquids (NGL) cryogenic recovery plant to the town of Atasta, 264 workers.
Mexico, where it was transported offshore in another 80-km-long The Akal C complex receives a two-phase oil/gas
subsea pipeline. hydrocarbon mixture from several remote wellhead platforms.
Some of the sour gas generated from oil field production was Numerous oil and gas pipelines enter or leave the complex.
sent onshore for gas conditioning and retail sale. However, some Because Akal C already had the capacity to handle a major
of the sour gas was flared at Akal C because the existing gas share of the total gas available for gas conditioning, it was decided
production facilities were not designed to handle either the that the new compression and process platforms for lift gas
increased need for lift gas to maintain the oil production or the generation would be installed as part of the Akal C complex.
additional gas quantities required to support the This configuration eliminates the need for subsea pipelines to
increased production. transmit the sour gas for gas conditioning to these new platforms.
This increase in gas handling requirements created an
overwhelming need to significantly increase the gas handling Lift Gas Generation Process. There are many different
(compression and process) capacity. combinations of treatment and refrigeration processes that can be
used to generate lift gas. The optimal process option, defined in the
Options to Generate Additional Lift Gas. A comprehensive study phase of the project (shown in Figure 3: Lift Gas
study was conducted to identify potential sources and the best Generation Process) generally consists of:
possible option for generating additional lift gas in order to meet • compressing the gas to between 1,100 and 1,200 psig
the increased oil production goals. Options studied included: • sweetening the gas and then partially cooling it,
1. continuing to use onshore-generated (sweet) lift gas,
• dehydrating the gas, by cooling it to 55oF in propane chillers,
transported offshore through the existing subsea lines, and
to remove the heavier hydrocarbon condensates,
using the sour gas generated offshore as supplemental lift gas,
• heating the gas by exchanging heat with gas from the
2. generating additional (sweet) lift gas onshore and transporting
sweetening unit, and
it through new onshore and subsea pipelines, or
3. installing additional platforms for treating the sour gas • feeding the heated gas to the lift gas ring, where it is injected
offshore. This would require sweetening and refrigerating the into the reservoir.
treated gas and meeting stringent hydrogen sulfide (H2S),
carbon dioxide (CO2), water, and hydrocarbon dew Conceptual Design and Project Execution. Lift gas
point specifications. generation plants of the size required for the oil production at
Key factors considered in these analyses included: objectives of Cantarell have been built onshore, but never
offshore. The construction strategy and logistics of building
• capital and operating costs associated with compression and
offshore, therefore, dictated the project’s conceptual design.
transportation of sour gas and lift gas,
There are typically two options by which major projects are
• costs associated with revamping the existing lift gas injection
installed and completed offshore: float-over, in which the unit is
system to handle sour gas, and
lowered into place from its transportation vessel, or heavy-lift, in
• safety risks associated with the use of sour gas as lift gas.
CANTARELL’S AKAL C COMPLEX: THE WORLD’S LARGEST OFFSHORE GAS TREATING
OTC 13177 AND LIFT GAS GENERATION PLATFORMS 3

which the unit is lifted into place with large • 450 mmscf/d triethylene glycol (TEG) gas dehydration to
vessel-mounted cranes. reduce the gas water dew point,
Early in the project, designers recognized that, regardless of • 900 mmscf/d propane refrigeration to reduce the gas
installation technique, the new lift gas generation plant would need hydrocarbon dew point,
to be built in modules fabricated onshore and then shipped • 360 MMBtu/hr waste heat recovery unit for MDEA
offshore for installation. gas treating,
The transportation and installation limitations of these • 40 mmscf/d acid gas (33 percent H2S) incinerator, and
construction approaches dictated the size, weight, and weight • 80 mmscf/d acid gas (33 percent H2S) compression from
distribution of each module, which, in turn, dictated the layout and 6 psig to 135 psig
equipment configurations.
The heavy-lift method of installation was selected for its The propane refrigeration system consists of four parallel
inherent advantages in flexibility and its ability to complete the propane chillers, three propane compressors, one propane
installation in challenging sea-states. economizer, and one accumulator. Each propane chiller has a
Developing logical process equipment layouts so that each capacity of chilling 225 mmscf/d, and two propane compressors
module was light enough to lift into place was a major design can provide refrigeration for 750 mmscf/d of gas. Refrigeration
challenge. Structurally, each module needed to support its own units of this size have never been installed offshore.
weight and the weight of heavy process equipment. These new platforms are connected to the existing Akal C
This offshore facility also required many technical details that process complex in the Cantarell Field. Ancillary structures
are not typically included in an onshore lift gas generation plant. constructed at Akal C included:
For example, space was extremely limited. Among other things, • two new bridge supporting platforms,
this necessitated designing a blowcase closed drainage collection
• two interconnecting bridges,
system in lieu of the sub-cellar deck in which a sump tank could
• one flare bridge support structures,
be located.
• a flare bridge with three spans, and
New Platforms and Equipment. The new Akal C • a flare and flare structure.
compression platform consists of a booster compression system, Additionally, a new habitation platform and living quarters
a high-pressure compression system, a dehydration system, a module was constructed at Akal C, providing capacity to house an
condensate handling system, and a utility support system. The additional 250 workers.
platform has six levels encompassing 9,920 square meters (m2) of The new compression and process platforms will have the
deck area within a footprint of 90 meters (m) by 45 m. The highest capacity to handle 900 mmscf/d of gas, producing 730 mmscf/d of
point of the platform is 73 m above water line and the platform lift gas. When completed, the new offshore lift gas generation
topsides weight is 15,000 tons, making it the largest platform in platforms together with the upgrades to the existing facilities will
the Cantarell field. make Akal C the largest offshore complex in the world.
The new compression platform was installed in two primary
Debottlenecking and Revamping Existing Facilities
modules: a single-level lower module (see Figure 4: Compression
Revamping, upgrading, and debottlenecking of the existing
Platform Lower Module Lift-Off From Barge) and a four-story
process systems on Akal C, Akal-J, and Nohoch-A were required
upper module (see Figure 5: Compression Platform Upper
in order to meet the overall goals of increasing oil production and
Module Lowered Onto Lower Module), with four high-pressure
reducing gas flaring.
compressor modules.
This analysis was conducted across 75 platforms and
The new Akal C process platform consists of gas
associated pipelines to develop an optimal conceptual design basis,
sweetening units, the propane dew-point control refrigeration
while at the same time developing innovative conceptual
system, and additional utility support systems. It is built in three
approaches to the work.
levels encompassing 7,160 m2 of deck within a footprint of 82 m
The entire production and processing system was analyzed,
by 45 m. The highest point of the platform is at 64 m above water
system by system, to identify processes that were currently
line. It also weighs approximately 15,000 tons and was installed in
operating at full capacity and could benefit from refurbishment,
similarly sized two modules, lower (see Figure 6: Process
augmentation, or replacement by new ones with a higher capacity
Platform Lower Module During Onshore Fabrication) and upper
or installing new equipment to handle the additional oil and gas.
(see Figure 7: Process Platform Upper Module During Onshore
Concurrently, many new pipelines and several remote
Fabrication), and four air-cooler modules.
wellhead platforms were revamped with commensurate changes in
The new facilities include:
oil and gas production profiles. Tracking the oil and gas
• 484 mmscf/d high pressure compression from 125 psig to production schedules from each wellhead platform and managing
1,100–1,200 psig,
the logistics to ensure sufficient oil and gas handling capacity were
• 900 mmscf/d methyldiethanomoline (MDEA) gas treating to challenges.
reduce hydrogen sulfide (H2S) and carbon dioxide (CO2)
concentrations,
4 R. KETTLES, J.C. KUO, J. RUBIO OTC 13177

Existing Akal C Facilities. Revamping an existing platform coolers on the compressor discharge were revamped to increase
involves understanding the existing systems and identifying the cooling capacity and to eliminate potential foaming problems in
best modification strategy that will not hinder ongoing production. the dehydration contactor.
Akal C is a full processing complex (see Figure 8: Pre-Expansion
Akal C Platforms and Facilities) consisting of: Sour Gas Injection Systems and Flares. New injection
• three production platforms, compressors were added to increase the reservoir pressure
• one booster and gas injection compressor platform, until nitrogen injection could begin, to decrease gas flaring,
• one pipeline tie-in platform, and to help dispose of the acid gas produced from the new gas
• one high-pressure compressor and dehydration platform, and sweetening plant. To ensure safe operations of these
• two living quarters platforms compressors, a new 18-inch flare header was installed and tied
The existing production system consists of first-stage and into the existing flare system.
second-stage separators, vapor recovery compressors, booster
compressors, high-pressure compressors, a gas dehydration unit, a Sour Water Treatment Systems. The existing sour water
water treatment system, a condensate handling system, and oil treatment system was relocated and replaced by a new larger water
pipelines from remote first-stage separators, gas pipelines from treatment system with a capacity of 3,000 bpd. This new water
remote first-stage separators. treatment system will provide sufficient water treatment capacity
for existing and future platforms.
Debottlenecking Activities. The capacity of the following
process systems was increased or modified: Safety Systems. New gas and fire detection systems and
• oil/gas separation systems, emergency shutdown systems were designed and are being
installed to bring the exiting platforms into compliance with
• compression systems,
current international standards.
• dehydration systems,
• sour gas injection systems and flares,
System Controls. The existing pneumatic control systems,
• sour water treatment systems, typical of all existing Cantarell facilities, were modified so that all
• safety systems, and the system controls could be changed to distributed control
• process system controls. systems (DCS).
Complex tie-ins and integration between the existing
platforms and future platforms were designed and constructed. To provide new control capability to the existing pneumatic
The new system was scheduled to be commissioned in stages. level and pressure control loops on both the first-stage and second-
To accommodate the staged commissioning and to minimize stage separators, an electronic level-indicating transmitter,
shut downs, various operating modes for the new systems were electronic pressure-indicating transmitter, electronic to pneumatic
identified in order to determine the location and size of tie-ins. The transducers, three-way solenoid valves, and a common local
Cantarell field remained fully operational throughout digital recorder were installed.
debottlenecking activities.
Complex Project Execution
Oil/Gas Separation Systems. First-stage separators were The magnitude, complexity, and urgency of the program were the
installed on the remote platforms that feed Akal C, new lines were determining factors in developing the strategy of executing the
laid to transport the oil and gas in separated lines, and the second- program through multiple concurrent integrated projects.
stage separators at Akal C were replace by larger separators. This In order to accommodate the fast-track nature of the program,
reduced the excessive pressure drop on the pipelines and increased Pemex established an integrated Project Management Team
oil and gas production. (PMT) to develop conceptual engineering and oversee the
development and implementation of the contracting program to
Compression Systems. Increasing oil production results in an execute these projects.
increase in gas production. Therefore, the gas handling capacity of In order to accommodate the fast-track nature of the project,
the existing Akal C complex had to be increased, with the goal of Pemex adopted an engineering-procurement-construction (EPC)
decreasing gas flaring. execution strategy, in which the EPC contractors are responsible
The existing high-pressure compressors and dehydration for detailed engineering, selected procurement, and all fabrication,
system were refurbished, and three new 150 mmscf/d injection hook-up, and commissioning.
compressors were installed to inject the gas into the reservoir.
The gas header sizes and capacity of the associated Contracting Strategy. Pemex adopted an engineering-
condensate and sour water treatment systems were also increased procurement-construction (EPC) execution strategy, in which the
in order to integrate with new lift-gas process systems to be EPC contractors are individually responsible for detailed
installed on the new platforms. engineering, selected procurement, and all fabrication, installation,
hook-up, and commissioning of their respective projects
Dehydration Systems. The existing dehydration system was and contracts.
refurbished to increase its gas handling capacity. Additionally, the
CANTARELL’S AKAL C COMPLEX: THE WORLD’S LARGEST OFFSHORE GAS TREATING
OTC 13177 AND LIFT GAS GENERATION PLATFORMS 5

The projects were competitively bid nationally and and priorities of an operating field. The safety of workers and
internationally under the Mexican Public Works Law on a fixed assets during construction, commissioning, and operation was a
‘unit rate by system’ compensation methodology, with associated top priority.
penalties for schedule delay. A total of 39 EPC contracts were The PMT was therefore also responsible for ensuring that
executed for the Cantarell project overall, including four schedule targets were aligned and persistently coordinated and that
specifically associated with lift gas generation and debottlenecking consistent and acceptable design standards, construction, quality
activities described in this technical paper. control, and construction safety policies, procedures, and
Pemex’s intent was to maximize the use of in-country EPC initiatives were delivered across the project. Extensive support
contractors to build the Short Term expansion projects. Therefore, and training was provided by the PMT to project contractors to
with the exception of six larger-scale EPCs, the contracts were develop effective project safety, quality, and project control work
awarded to Mexican contractors. The 10 larger-scale EPC processes, systems, and procedures.
contracts, two of which are specifically related to Akal C, were
tendered to international firms aligned with Mexican partners Project Achievements
or subcontractors. The PMT, including Pemex and its construction management
consultant, designed, procured, and installed the largest offshore
EPC Execution Challenges. EPC approaches are becoming lift gas capacity in the world at Akal C, five times larger than
commonplace in many parts of the world. However, because this any offshore lift gas generating plant.
project was unprecedented in size and complexity, particularly in Cantarell produced approximately 1.1 million barrels of oil
Mexico, many of the in-country and local engineering and per day in 1996. Debottlenecking modifications, completed under
construction contractors had little experience – prior to the the Short Term Plan, have allowed an increase in oil production of
Cantarell Project – in the work processes associated with this type over 25 percent, to around 1.4 million bpd.
of coordinated EPC approach. This year, the nitrogen injection platform (presented in a
Among the many design and construction challenges was the separate technical paper) will increase oil recovery by
extensive coordination required during both design and approximately 20 percent of the original oil in place.
construction phases between the short-term and the When the new Akal C lift gas generating facilities are put into
long-term projects. operation, they will allow oil production to increase an additional
Careful attention to technical process-related detail, along 50 percent, and will allow a 55 percent reduction in gas flaring.
with production capacity and schedules, was required to ensure a With an anticipated oil production capacity of approximately 2.2
fully operational and safe facility through all phases of project million bpd in 2002, Cantarell production will be equivalent to the
execution. Innovative and cost-effective shutdown execution combined oil production from the 25 largest fields in the
scopes and schedules were developed to ensure that production United States.
downtimes were minimized. In addition to significant economic benefits, the Cantarell
Maintaining effective communications and logistics field will meet the strictest international safety and
throughout a program that is being executed simultaneously in environmental standards.
multiple locations and countries is a fundamental element,
particularly given the impacts of weather and sea state conditions

Figure 1―Location of Cantarell Oil Field


6 R. KETTLES, J.C. KUO, J. RUBIO OTC 13177

Figure 2―Reservoir Pressure and Oil Production Over Time

Figure 3―Lift Gas Generation Process


CANTARELL’S AKAL C COMPLEX: THE WORLD’S LARGEST OFFSHORE GAS TREATING
OTC 13177 AND LIFT GAS GENERATION PLATFORMS 7

Figure 4―Compression Platform Lower Module Liftoff From Barge

Figure 5―Compression Platform Upper Module Lowered Onto Lower Module


8 R. KETTLES, J.C. KUO, J. RUBIO OTC 13177

Figure 6―Process Platform Lower Module During Onshore Fabrication

Figure 7―Process Platform Upper Module During Onshore Fabrication


CANTARELL’S AKAL C COMPLEX: THE WORLD’S LARGEST OFFSHORE GAS TREATING
OTC 13177 AND LIFT GAS GENERATION PLATFORMS 9

Figure 8―Preexpansion Akal C Platforms and Facilities

You might also like