Professional Documents
Culture Documents
Bridge designers are essentially striving to achieve the same goals, namely: long-term serviceability, low
maintenance characteristics and economy of construction. While many recent developed techniques have been
mastered such as welding techniques, composite decks, etc., one important aspect of design -reduction or
elimination of expansion devices and associated bearings- is consistently overlooked or avoided by nearly all
bridge-design practitioners. Although the design shown in figure 1 works well in concept, experience shows that
the expansion joint/bearing detail can be significant post-
construction maintenance item and thus expense during the in-
service life of a bridge. Therefore, the concept was developed to
physically and structurally connect the superstructure and
abutments as shown in figure 2 to create what is refereed to as an
integral abutment bridge.
Fig. 3. Fig. 4.
Integral bridge; deflection caused by thermal action. Integral bridge; deflection caused by traffic loading.
Integral bridges accommodate superstructure movements without conventional expansion joints/bearings. With the
superstructure rigidly connected to the substructure and with flexible substructure piling, the superstructure is
permitted to expand and contract. Approach slabs, connected to the abutment and deck slab with reinforcement,
move with the superstructure. At its junction to the approach pavement, a sleeper slab may support the approach
slab. If a sleeper slab is not utilised, the superstructure movement is accommodated using flexible pavement joints.
As for retaining wall abutments, a reinforced concrete pile cap is considered to be the most practical means of
achieving this connection. An example of such a connection is given in figures 5 – 7.
Fig. 5. Fig. 6.
Built-in connection for high modulus pile retaining wall. Built-in connection for tubular column-pile.
Fig. 8. Example of accumulated dirt leading to failure of the elastomeric expansion joint.
Beside arguments summarised above, advantages from structural continuity between the deck and structural
elements, such as design efficiency, reduction of span length and sound emission, dynamic behaviour (passengers
comfort), damping capacity and aesthetics, are also becoming more popular using the integral concept. The choice
of type of bridge has been largely governed by overall first cost of bridges. For many years, this was a satisfactory
basis, but in recent years other factors have become increasingly important. These include: whole-life cost
inclusive of maintenance and road user delay; efficient use of energy and materials in construction; environmental
issues and sustainability. The record of durability has not been fully satisfactory. Bridges are usually critical
thoroughfares and often lack satisfactory alternative routes during repair work, especially estuarial crossings.
Traffic intensity and gross weights of trucks have increased significantly since the sixties when the current design
was largely developed. It is now recognised that the cost of disrupted traffic during repair and maintenance should
be considered. These have been evaluated as (almost) exceeding the cost of the repair itself. Although these costs
are not borne by bridge owners, they have considerable overall economic significance. Based on recent
experience, it is expected that integral bridges will be more efficient, especially in terms of whole-life cost and
sustainability. Because of the increasing interest in the use of integral bridges, for optimal design several questions
need to be answered, like:
main characteristics and current experience, experience abroad (England, United States, etc.), resulting
stresses due to creep, shrinkage, thermal action, etc., resulting deflection and rotation at the location of
structural continuity, limitation of span length for bridges (steel and concrete), several aspects of
construction, foundation stiffness (like soil characteristics) and junction between run-on slab and
highway itself (adjacent pavement).
Several international recommendations have been published, which form a basis for good design [1-4]. Valuable
information, mainly based on practical experience, exists on the relation between type of bridge (steel, composite
or concrete) and maximum span length [5]. Also, results have been published on skew integral bridges:
Following recommendations such as Highways Agency’s Standard BD 57, Design for durability “The majority of
bridges in the UK, with spans less than 60 m, should be designed as integral bridge”, is highly applicable to the
situation in The Netherlands, because approx. 70% of all bridges have a span length less than 60m.
For the classic concept of bridges in The Netherlands (concrete as well as steel bridges), a large majority of the
problems observed with expansion joints and bridge bearings can be attributed to corrosion, wear and lack of
(fatigue) strength. For a long period, 1975 – 1990, a planned routine inspection has been carried out on expansion
joints for medium movements. Several kinds of shortcomings were observed, which are classified in table 2.
Fig. 9.
Left: example of an expansion joint (finger).
Middle: example of an expansion joint (asphalt plug).
Right: example of a steel bearing.
Simplified construction
The simple characteristics of integral bridges make
for rapid and economical construction. For
example, there is no need to construct cofferdams,
make footing excavations, place backfill, remove
cofferdams, prepare bridge seats, place bearings,
backwalls and deck joints.
Instead, integral construction for small span bridges
generally results in few placement days. After the
embankments, piles and pile caps have been placed
and deck stringers erected, deck slabs, continuity
connections, and approach slabs can follow in rapid
succession.
In extreme cases, some multi span bridges have been completed with just two concrete placement days; one for the
structure itself and one for the approach slabs. Like all other type of bridges, the construction of an integral bridge
is done in stages. An example is given in figure 11.
(1) (Sheet)piling
(2) Casting of cap beam
(3) (Bridge)deck
(4) Connection between sub-superstructure
(1) (2) (3) (5) Slab, soil excavation, etc.
Fig. 11.
Construction stages of an integral bridge.
(4) (5)
Design efficiency
Design efficiencies are achieved in:
Secondary effects
Like most of their jointed bridge counterparts, integral bridges are subjected to secondary effects due to shrinkage,
creep, thermal gradients, differential settlements and differential deflections. They are also subjected to passive
pressure effects when abutment backfill is compresses during superstructure elongation and to pavement relief
joint pressure when moisture and sustained high temperatures trigger pavement growth. The stress levels
generated by these secondary effects are generally understood but mostly not well quantified.
16.4 Limitations
Like any other type of design, the attributes of integral bridges are accompanied by some limitations.
Approach slabs
(Integral) bridges should be provided with approach slabs to prevent vehicular traffic from consolidating backfill
adjacent to abutments, to eliminate live load surcharging of backfill, to minimize the adverse effect of consolidated
backfill and approach embankments on movement of vehicular traffic adjacent to abutments and to prevent water
penetration. Because of the cyclic movement of integral bridges, approach slabs must be anchored to the bridge;
otherwise, continual bridge movement and joint infiltration will shift slabs toward flexible approach pavement,
away from abutments and off the approach slab seats.
As an indication:
- the length of an approach slab vary from a minimum of 3 m to a maximum that is based on the intercept
of a 1 on 1.5 line from the bottom of the abutment excavation to the top of the pavement.
- the end of the approach slab shall be parallel to the skew
- where warranted, as per the expansion provision as summarized below, to prevent the approach slab
from moving excessively, it should rest on a keyed sleeper slab.
- the approach slab shall be designed as a structural slab that is supported at each end.
For the integral bridge with a span length of approx. 70 m, constructed at Son A50, special attention has been paid
to optimal design of the adjacent pavement because of the (expected) increased length of the integral bridges
compared to all other existing integral bridges. A detailed research has been carried out, resulting in an improved
connection. The main characteristics of the new developed connection are:
- concrete approach slab 5000*350 mm2 supported by stabilized sand;
- concrete approach slab hinged connected to the bridge deck by stainless steel reinforcement ø25-420;
- for control of cracks, such as crack width criteria for concrete design, for a length of approx. 15 m
starting at the beginning of the concrete slab, asphalt-reinforcement glassgrid 8501 as illustrated in
figure 12 is being used. Because of the response to cyclic deck movements, especially those caused by
thermal actions, the fatigue strength is an important design criterion.
Fig. 12.
The use of asphalt-reinforcement
glassgrid 8501 for connecting the
bridge deck to the highway.
The real span lengths given depends on many factors, like type of material used for the superstructure (steel,
(prestressed) concrete, etc.), type of material used for the substructure (steel/concrete piles) and it’s bending
stiffness ‘EI’, construction stages, concrete time-dependence aspects like shrinkage and creep, backfill material,
etc.
Pile loading
One primary concern expressed about the construction of integral bridges with pile supported flexible abutments is
the design complexity on abutment pile flexural stresses.
If the pile supporting system utilizes the frictional forces between the piles and the soil, consideration should be
given to the effect of lateral displacement of the piles on the frictional resistance. As the piles will be moving
laterally with temperature variations and with traffic loading, a gap may be produced between the disturbed soil
and the pile. This may result in considerable decrease of the frictional resistance of the piles. Therefore, the pile
should be designed using the effective frictional pile length reduced by pile displacements.
60 anchoring
Fig. 13.
Integral - without additional
40 Number of (semi)integral
anchorings
bridges by span length in The
20 Semi-Integral - without Netherlands.
additional anchoring
0
0 20 40 60
length (m)
As illustrated in figure 14, most of the existing integral bridges are constructed using concrete only (incl. abutment
wall and pile support) and working integrally with the soils surrounding them. The inspection of integral bridges
looks very promising, because up to now nearly all bridges were found to be fully maintenance-free. For some
bridges, in spite of using a concrete approach slab, the solution without using an asphalt plug or one asphalt plug
joint at the beginning of this slab (bridge side) only results in pavement cracks. For all integral bridges, as shown
in figure 14, using an asphalt plug at both ends of the slab resulted in a maintenance-free solution.
Fig. 14.
Left: frequently used types of integral bridges.
Right: asphalt plug at both ends of an approach slab.
Many of the (semi) integral bridges are skew in plan, some even with a very large skew angle, like 40º. The effect
of high skew is to magnify the displacement at the acute corner of a wide bridge. As a design tool, a limit of
approx. 60º is used [5]. However, this limitation should be regarded as a warning, rather than an absolute
limitation. The results of an inventory on integral bridges in The Netherlands that are skew in plan is given in
figure 15. The alternatives used for foundation of integral bridges in The Netherlands can be summarized in the
categories as shown in figure 16. Compared to other countries, prestressed concrete piles are in comparison to
steel piles rather popular because of excellent load resistance (shaft friction and end-bearing) and relatively low
costs.
80 Integral
length (m)
60 Semi-Integral
40
20
0
1930 1940 1950 1960 1970 1980 1990 2000 2010 Fig. 15. Skew angle in relation to span
length and additional anchoring (sheet
year pile abutment).
banksea
t
combi- 4%
piles
concrete
21%
piles Non-integral bridges are almost always founded on concrete piles.
47%
sheet
piles
17% tubular
piles
11%
The largest integral bridge, recently finished at Son A50, has a total length of approx. 70 m. A view of the bridge
is given in figure 17. The bridge deck was constructed in situ using prestressed concrete. Instead of using a
concrete capping beam connection between deck and foundation, the frame abutment is fully integrally casted with
the deck, which implies that there are no construction joints. Some of the consequences of using such a method are
reduction of effectively prestressing and additional stresses caused by time dependent aspects, like shrinkage.
For the foundation, as illustrated in figure 17, because of criteria on axial load
resistance, deformation capacity needed for cyclic horizontal displacement,
costs, aesthetics and durability, steel combi-piles are used.
(a) ∆ 6EI∆
MT = 2 + M PASSIEF
L
6 EI∆
MB = 2 − M PASSIEF
MT L
An integral bridge will experience elongation and contraction due to
temperature variations during it’s service life. Thus, the earth pressure at
the abutments should be considered in correlation with temperature
L
actions.
EI Therefore, when the bridge contracts, an active earth pressure will be
developed behind the abutment. At rest earth pressure behind the
abutment is assumed when there is no horizontal displacement.
f
Fig. 20. Bending moments caused by horizontal displacement.
k
MB
When the bridge elongates due to an increase in temperature, the intensity
of passive earth pressure behind the abutment depends on the magnitude of the bridge displacement toward the
backfill soil. In addition to horizontal displacement caused by temperature variations, the concrete effects like
shrinkage, creep and prestress should taken into account. The horizontally soil-structure interaction is explained by
considering some results obtained from a case study on especially the forces and displacements of the abutment
concrete piles of a multi-span concrete integral bridge.
Basics on geometry
A multi-span concrete integral bridge with a length of 80 m (25-30-25) is considered.
The geometrical basics are explained in figures 21 – 23.
80 m
25 m 30 m 25 m
4,5 m
0,6 2,3 2,3 2,3 2,3 2,3 2,3 0,6
15,0
7 concrete piles450 mm
Fig. 21.
Left: Geometry of the integral bridge.
Right: Schematic view of foundation (at abutment).
For the deck, in-situ concrete C55/65 is used and prefab prestressed concrete piles C45/55 constitute the
foundation. The concrete cross head beam / endscreen wall is casted together simultaneously with the bridge deck
at the same time.
field
15,0 m
0,25 m
0,25 m 0,72 m
0,22 m
2,5 m 10,0 m 2,5 m
At support
15,0 m
0,25 m
0,25 m 0,97 m
0,47 m
(1) (2) (3) (4)
2,5 m 10,0 m 2,5 m
Fig. 22.
Left: Cross sections of the bridge deck.
Right: Conceptual method about construction on site.
Fig. 23.
Left: Prestressing of the concrete deck.
Right: Bridge deck at pier location.
with
Ka = active side: earth pressure coefficient
Ko = at rest: earth pressure coefficient
Kp = passive side: earth pressure coefficient
C’ = effective stress cohesion strength [kPa]
δ = mobilised angle of wall friction [o ]
φ’ = effective stress angle of shearing resistance [o ]
Accurately determined soil properties, both local and adjacent to the construction site need to be obtained. For
defining the soil stiffness K [kN/m3 ], a certain scatter (upper and lower bound) on soil characteristics is taken into
Bridge Road
Cneter pile
Ground l. +4,0
sand 1 sand 2
talud 2:3
-1,6
wp -2,0
sand 1 sand 2
-3,0
peat 1 peat 2
-6,0
clay 1 clay 2
-9,2
clay 3 clay 3
-10,0
account so-called soft (low) and high stiffness. Also, the
sand 3 sand 3 stiffness depends on type of loading , like for example traffic
loading classified as short term loading and temperature
-15,0
actions classified as long term loading. Because of the
clay 3 clay 3 presence of a certain excavation level underneath the bridge,
-19,0
there exists a difference on soil stiffness for both sides of the
sand 4 sand 4 pile foundation( see figure 24). The result on soil stiffness
-20,0
Pile length 24 m coefficients are summarized in table 4.
Some results on rotation stiffness for lower and upper bound earth pressure coefficients are summarized in table 7.
In general, for all displacements considered (0, +12, -35 and –72 mm), the ratio on rotation stiffness for lower and
upper bound earth pressure coefficients is larger than 80%. Therefore, for the design an average value is used.
M; θ
Using a sign notation as explained in figure 25, the results on the relation between
F; ∆
- + horizontal displacement – bending moment – rotation stiffness are given in figure
26.
Displacement 0 mm
100000
Fig. 26. Relation between horizontal displacement
and rotation stiffness. 50000
0
-1000 -500 0 500 1000
moment (kNm)
horizontal force
100
(kN)
0
-100
-200
-100 -50 0 50
displacement (mm)
Fig. 27. Analytical results on the relation between displacement and horizontal force.
500
bending mmoment (kNm)
Fig. 28. Relation between bending moment and horizontal displacement for alternative analytical models.
As shown in figure 28, the relation between horizontal displacement and bending moment is rather linear.
Therefore, the magnitude of bending moment largely depends on the ‘EI’ value of the pile foundation instead of
soil stiffness. Considering the analytical model based on ALP, as shown in figure 29, the resistance by soil
stiffness for elongation of the bridge deck is much larger then for contraction.
Fig. 29. Analytical model based on APL: Relation between horizontal displacement and normal force.
Using the M-sheet analytical model, the results on load distribution for the three types of horizontal displacements
analyzed are given in table 8.
Construction stage Horiz. displa. [mm] Moment [kNm] Horiz. Force [kN]
umin umax Mmin Mmax Fh;min Fh;max
When using a steel pile foundation, a corrosion loss allowance needs to be taken into account. The redistribution
of earth pressure that occurs as a result of the increased flexure of a corroded section can be significant. Therefore,
the end-of-life condition can be a critical design situation of the pile section.
The reduced (corroded) section properties can be obtained from text books. For example the sacrificial
thicknesses, for one side of the pile only with a design life of 120 years, for piling according to BD 42 is equal to:
aspects incl. prestress are presented. The influences of the consequences using various concrete strength classes
and building sequences are included.
The temperature distribution within an individual element may be split into the following four essential constituent
components, as illustrated in figure 30.
a) uniform temperature component, ∆TN
b) linearly varying temperature component about
the z-z axis, ∆TMz
c) linearly varying temperature component about
the y-y axis, ∆TMy
d) non-linear temperature component, ∆TE
For bridges, all representative values of thermal actions should be assessed by the uniform temperature component
∆TN and the linear temperature component ∆TMy,z. In cases where non-linear distributions need to be considered in
detail, appropriate temperature differences ∆TE should be applied.
For different values on the design life (R), the modified T max
and Tmin can be taken from figure 32.
The characteristic value of the maximum contraction and maximum expansion range of uniform bridge
temperature component, ∆TN should be taken as
∆TN,con = Te,min - T0
∆TN,exp = Te,max - T0
with T0 = initial temperature when the structural element is restrained. If no other provision is required, the range
of movement for design shall be taken as the appropriate value obtained from
∆TN,con = ∆TN,con - 20o C
∆TN,exp = ∆TN,exp + 20o C
multiplied by partial factor for ULS or SLS respectively (according to EN 1990). However, if the temperature at
which the bridge restraining is set is known, the higher ranges may be reduced by 10o C.
In particular cases, for example when the orientation or configuration of the bridge results in one side being far
more exposed to sunlight than the other side, a horizontal temperature difference component ∆TMz may need to be
considered. In such cases, if no other information is available and no indications of higher values exist, 5°C may
be taken as a linear temperature difference between the outer edges of the bridge independent of the width of the
bridge.
Surfaci Negative
ng Positive temp. temp.
thicknes difference difference
s profile [o C] profile [o C]
[mm]
T1 T2 T3 T4 T1
unsurfa 30 16 6 3 8
ced 27 15 9 5 6
20 24 14 8 4 6
40
Fig. 33. Temperature differences for bridge decks – type 1: Steel decks.
or
( )
ε cs t − t s = ε cso ⋅ β s t − t s ( ) ε cso = ε s ( f cm )∗ β RH (notional shrinkage coefficient)
a f a fc
β s t − t s = t − t s / 0,035 ⋅ h02 + t − t s h 0 ,5
(description of the development of shrinkage with time)
a
ε s ( f cm ) = 160 + β sc ∗ 90 − fcm ∗10 f −6
(factor to allow for the effect of concrete strength on shrinkage)
F RH I 3
β sRH =1−
H 100 K (coefficient to allow for the effect of relative humidity on the notional shrinkage
coefficient)
β RH = −1.55 * β sRH for 40% ≤ RH < 99% (stored in air)
b. Creep
According to appendix A1.1.2 of the ENV 1992-1-1:1991, the creep coefficient may be calculated from
a f a f
φ t , t0 = φ 0 ⋅ β c t − t0 (creep coefficient)
φ 0 = φ RH ⋅ βa f f ⋅ βat f
cm 0 (notional creep coefficient)
φ RH = 1 + (1 − RH / 100) / 010
. ∗ 3 h0 c h (effect of relative humidity on the notional creep coefficient)
a f
β fcm = 16.8 / f cm (effect of concrete strength on the notional creep coefficient)
β c ( t − to ) = ( t − t o ) / (β H + t − to )
0 ,3
(coefficient of the development of creep with time)
and
n
t0 = t 0 ,T ⋅ 9 / 2 + t 0 ,T a f 1 ,2
+1 s α
≥ 0,5
( the influence of type of cement taken into account)
(α = power which depends on type of cement)
c. Prestress
−3 (prestressing of the cross section)
Fs = ∑ σ s ∗ As ∗10
Fs (concrete stress caused by prestressing)
3
σb = ∗10
Ab
σb
ε bcreep =
Ec 28 (concrete strain caused by prestressing)
Considering a range of concrete strength classes, results in deck dimensions by means of construction depth, etc.
are summarised in table 11.
concrete deck, in case of a bridge length of 90m (h=680mm), the following general input parameters have been
used (displacements are given per abutment and considered to be equal for both bridge deck ends):
Yearly (uniform) ∆TN,con = -∆TN,exp = -35 o C which results in ∆l = ± 15.75mm.
Daily (linear) ∆TM,con = -6,5 o C which results in ∆l = -0.6mm
∆TM,exp = 15 o C which results in ∆l = 1.5mm.
Some results are shown in figure 34, and the main conclusions obtained are:
- the maximum elongation (+ sign) is slightly larger than the minimum contraction (- sign)
- the displacement caused by the linear bridge temperature component is found to be small and therefore this
thermal action can be neglected in case of fatigue analysis for e.g. the deck-abutment connection
- displacements are largely depending on the type of deck used (concrete deck versus composite deck)
- the influence of type of concrete strength class used on the displacement is negligible
- the differences in displacements between in situ and prefab concrete bridge deck can be neglected.
60
in situ C55/65: uniform minium
50
in situ C55/65: uniform maximum
]
40
in situ C55/65: linear minimum
bridge end displacement [mm]
Fig. 34. Bridge deck end displacement [mm] per abutment (char. value) caused by thermal actions according
to [10].
0.0
20 40 60 80 100 120 140 160 180
]
-10.0
bridge end displacement [mm]
-40.0
Fig. 35.
-50.0
Bridge deck end displacement
bridge length [m]
[mm] per abutment caused by
adiabatic shrinkage.
the shrinkage hardening takes place during the first 3 days (approx. 80%), and therefore in case of the restrained
condition (fixed connection bridge deck – abutment), the following factor on shrinkage is taken into account:
C35/45: ε = 0.015% (= 15o C) and C55/65: ε = 0.025% (= 25o C). Some results on displacements are shown in
figure 36 and the main conclusions obtained are identical to the conclusions given in case of adiabatic shrinkage.
Fig. 36.
-30
Bridge deck end displacement [mm] per
bridge length [m]
abutment caused by shrinkage hardening.
0.0
20 40 60 80 100 120 140 160 180
-5.0
bridge end displacement [mm] .
-10.0
-30.0
-35.0
-40.0
bridge length [m]
Fig. 37.
Bridge deck end displacement [mm] per abutment caused by (normal) shrinkage.
0.0
20.0 40.0 60.0 80.0 100.0 120.0 140.0 160.0 180.0
-10.0
-20.0
bridge end displacement [mm] .
-80.0
-90.0
-100.0
bridge length [m]
Fig. 38. Bridge deck end displacement [mm] per abutment caused by creep and prestress.
As an example: in situ concrete deck C35/45 results for a bridge length of 90 m into a total displacement per
abutment of –85.4mm. For the total bridge deck length a value of (2*-85.4)/90 = –1.90 mm/m’ is obtained.
40.0
20.0
0.0
20.0 40.0 60.0 80.0 100.0 120.0 140.0 160.0 180.0
-20.0
.
For a bridge length of 90m and a period of 75 years, results of the individual contribution of temperature and
concrete time dependency actions on the bridge end displacement are shown in figures 40-42.
creep
20% 29% prestress
adiabatic shrinkage
0% creep
prestress
47% adiabatic shrinkage
53% hardening shrinkage
(normal) shrinkage
minimum temperature
Fig. 41. Prefab concrete deck C45/55: contribution of actions on
bridge end displacement (total contraction = -43.5mm).
0% 12% creep
6% prestress
6%
adiabatic shrinkage
hardening shrinkage
(normal) shrinkage
76%
minimum temperature Fig. 42. Composite deck C35/45/steel girders S355:
contribution of actions on bridge end displacement (total
contraction = - 31.3mm).
The development of the total bridge end displacement per abutment by time (0.15 – 75 years) is shown in figure
43. A gradient of the lines shown is caused by the concrete time dependency actions.
Some main conclusions obtained from figure 43 are:
- for a composite deck, the change in minimum and maximum bridge deck end displacement during
0.15 – 75 years is negligible
- for a prefab deck, the elongation of the bridge deck end displacement exists only in the first period.
At 75 years, contraction caused by concrete time dependency is larger than elongation caused by temperature.
- for a prefab deck as well as an in situ deck, the maximum and minimum displacements at 0.15 and 75 years
differ entirely.
40.0
20.0
in situ C35/45: total minimum
bridge end displacement [mm]
-40.0
prefab C45/55: total minimum
Fig. 43. Bridge length 90: development of bridge deck end displacement [mm] caused by temperature and
concrete time dependency actions (0.15 - 75 years: logarithmic scale).
Conclusions
The bridge end displacement (elongation and contraction) largely depends on the type of bridge deck alternative
used (in situ concrete deck, prefabricated concrete deck, composite deck) and time considered. Therefore, static
stress analyses need to be done considering t = ± 0 and t = design life.
For practical design, for the analyses of the total bridge deck elongation and contraction, the following starting
points can be used:
In case of a fully symmetric integral bridge (superstructure + substructure) 50% of the values given in table 3 can
be used for the analyses of bridge deck end displacement (per abutment).
Considering deck end displacement, caused by minimum temperature only, might underestimate the bridge deck
contraction largely. For example, the percentage of displacement caused by minimum temperature on the total
displacement (contraction) is approx.:
In case of a monolithic in situ prestressed concrete deck, the contribution of actions on the total bridge deck end
displacement (contraction) is approx.: creep 29%, prestress 15%, adiabatic shrinkage 13%, hardening shrinkage
8%, normal shrinkage 15% and temperature 20%.
REFERENCES
[1] http://www.fhwa.dot.gov
[2] C. Miki et al. Journal of Constructional Steel Research 58 (2002) 3-20.
[3] Pritchard, B., “Continuous and Integral bridges”, Proceedings of the Henderson Colloquium, E&FN
Spon, ISBN 0-419190309, London, 1993.
[4] Biddle, A.R., Iles, D.C. and Yandzio, E., “Integral Steel Bridges: Design Guidance”, P163: ISBN 1-
859420532, SCI, Berkshire, 1997.
[5] Burke, M.P., “The Genesis of Integral Bridges in Ohio”, Concrete International, July 1996, page 48-51.
[6] Angust, E.C. and Taylor, D.C., “Current Trends in Bridge Design – The Design of Integral Bridges”,
The Institution of Engineers in Ireland, January 1998.
[7] Greimann, L.F., Yang, P.S. and Wolde-Tinsae, A.M., “Non-linear Analysis of Integral Abutment
Bridges”, Journal of Structural Engineering, Vol. 112, No. 10, October 1986, page 2263-2280.
[8] Kamel, M.R., Benak, J.V., Tadros, M.K. and Jamshidi, M., “Application of Precast, Prestressed Concrete
Piles in Integral Abutment Bridges”, fourth International Bridge Engineering Conference, San
Francisco, California, Vol. 2., August 1995, pages 146-157.
[9] Integral bridges, thesis work Ir. A.T.G. Maijenburg, 2000.
[10] prEN 1991-1-5:2002; Eurocode 1 - Actions on structures, Part 1.5: General Actions – Thermal actions.
[11] ENV 1992-1-1:1991; Eurocode 2 - Design of concrete structures, Part 1: General rules and rules for
buildings.
[12] ENV 1994-2:1997; Eurocode 4 – Design of composite steel and concrete structures, Part 2: Composite
bridges.
[13] ENV 1992-2: 1995; Eurocode 2 – Design of concrete structures, Part 2: Concrete bridges.