Professional Documents
Culture Documents
HSEM3BTECHSTANDARD0719
SESSION – 1 100
Percentage of work done by A in a day = % = 12.5%
8
TIME AND WORK – I
100
Percentage of work done by B in a day = % = 20%
1. Ans: [a] 5
A can do the work in 12 days. B can do it in 15 days. So, the net work done in two days i.e. 1 cycle = 12.5%
+ 20% = 32.5%
C can do it in 20 days.
Working for 6 days i.e. 3 cycles, they complete 3 × 32.5%
So, the rate of work per day of A, B and C is, and = 97.5%
respectively.
2.5 1
Working together, the work they can complete in a day The remaining 2.5% will be completed by B in of
20 8
1 1 1 1 the day.
12 15 20 5 Therefore, the no. of days taken by them to complete the
1 1 1
For completing the full work, time 5 work by working alternately 6 6 days
1 8 8
5
Page 1 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
5. Ans: [c] Let the time taken by A and B to complete the job be
Given that A can complete 80% of a work in 20 days, A x hours
20 Then, time taken by A alone to complete the job = x + 8
will complete the entire work in 100 25 days. hours
80
1 1 1
Rate of work of A = and let rate of work of B be And time taken by B alone to complete the job = x + 4
25 b 2
hours.
We know that A has already completed 80% of the work
and now that the remaining 20% is done by A and B Work done per day for A and B working together
together in 3 days. 1 1
Let B take ‘b’ days to do the work doing it alone. x 8 x 41
1 2
Hence, his rate of work per day ∴ Time to complete the job for A and B working together
b
1 1 1 1
So, 3 3 (x 8) x 4
25 b 5 2
x (as assumed above)
1
1 (x 8) x 4
Therefore, b = 37 days. 2
2
1 1
Aliter: x2 12 x 36 2x2 12 x
2 2
From the question, it can be inferred that B saves 2 days
of A's work by working for 3 days. x2 36 x 6
A completes the work in 25 days. Time taken by A and B to complete the job together
So, 2 days of A's work = 3 days of B's work. = 6 days
3 75 1 9. Ans: [c]
25 days of A's work 25 37 days of B's
2 2 2 1
work. Time to fill up the tank = 12 hours ⇒ per hour
12
1 1
Thus, B alone would take 37 days. Time to fill up the tank with leakage = 24 hours ⇒ per
2 24
6. Ans: [c] hour
Page 2 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 3 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Thus, 1 hour work of leak = 6 hours work of inlet pipe = 6 Thus both the statements together are necessary to
× 180 = 1080 litres. answer the question.
Tank capacity = 5 hours work of leak = 1080 5= 5400
29. Ans: [e]
litres.
There is no sufficient information given about the rate of
25. Ans: [c] work of woman in both the statements, hence we cannot
A ---> (1st day) ---> 3 feet wall find the answer.
B ---> (2nd day) ---> 2 feet wall 30. Ans: [d]
C ----> (3rd day) ---> 4 feet wall (negative work) From statement I alone,
A + B – C = 3 + 2 – 4 = 1 1 feet in 3 days We can get the answer as 32 workers can complete the
So, in 15 days = 5 feet work in 10 days.
Remaining work is 5 feet Similarly from statement II alone, we get the same answer
16th day A will build 3 feet as 32 workers can complete the work in 10 days.
17th day B will build 2 feet So, both the statements are sufficient individually.
Hence, 15 + 1 + 1 = 17days to complete. 31. Ans: [b]
26. Ans: [a] Pump P3 has to open when the tank was filled half
X + Y + Z ---> days ---> 4 units according to the supervisor's plan. Therefore, calculate
the time taken by the pump 1 and pump 2 working
Y ---> 144 days ---> 1 unit
together in which half of the tank will be filled.
After 12 days, Y has fallen sick
Now part of the tank to be filled by P1 + P2 in one hour
X + 1 + Z ---> 4; X + Z ---> 3
1 1 5
For 12 days, 12 4 = 48 units = + =
8 2 24
Hence, 144 – 48 = 96 units to be completed by X. Therefore, the time in which half of the tank was to be
X + Z ---> 96/3 = 32 days
filled by both of them working together =
24 / 5 12
2 5
27. Ans: [a]
hours.
X members ---> 8 days
Now the pump P3 was to open.
End of each day 10 members leaving the job Obviously, part of the tank to be filled by all of them in one
The entire job completed in 12 days 1 1 1 1
hour = + − =
1st day, assume x men are working 8 12 8 12
So Therefore time to be taken by all of them to fill the
x + (x – 10) + (x – 20) + (x – 30) + .... + (x – 100) + (x – 110) 12
remaining half of the tank = = 6 hours
= 8x 2
12x – 660 = 8x Thus, total time in which the supervisor had to return
4x = 660 => x = 165 12 42
+6= hours
Initially 165 men started the work.
5 5
Now we just have to calculate the part of the tank filled by
28. Ans: [d] 42
all the pipes in hours.
x 5
Statement I gives machine X produces candles in 1
5 1 (24 / 5)
of the tank is filled by the pumps P1 + P2 in
minute. Here nothing is known about machine Y. 3 3
So, statement I alone is not sufficient to answer the 8
hours i.e. hours(from the above).
question. 5
x Remaining time in which all the pumps have to work
From statement II, machine X and Y produce candles in
2 42 8 34
together = − = hours.
1 minute. 5 5 5
Combining statements I and II together, we get, machine y Part of the tank to be filled by all the pumps working
x x 3x 34
produces candles in 1 minute. together in hours
2 5 10 5
1 34 17
10 = × =
x candles will be produced in minutes. 12 5 30
3
Page 4 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 5 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 6 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 7 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 8 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Hence, the ratio of times taken to complete the work by 50 men are sufficient to complete the remaining work.
the former and later groups is 31:13. Therefore, 50 labourers can be removed.
P, Q and S take 13 days.
71. Ans: [c]
66. Ans: [c] 1
Time taken to complete of the work = 5 days
A – 15days 4
B – 20 days Time taken to complete the work = 20 days
LCM – 60
Time taken to complete 10 times the work
A – 4 units
B – 3 units 20 10 200 days
1 day they work together = 7 units
72. Ans: [b]
4 days 28 units.
Work left is 32 units of 60 units.
1
Work done by A in 1 day
32 8 20
That is days. 1
60 15 Work done by B in 1 day
15
67. Ans: [a] Work done by both A and B in 1 day
Ratio of rates of working of A and B = 2:1
1 1 7 4
So, ratio of times taken = 1:2 8
1 20 15 60 7
B's 1 day's work = 4
12 A and B together will complete the work in 8 days
1 7
A's 1 day's work = (2 times of B's work)
6 73. Ans: [a]
1 1 3 1 1
(A + B)'s 1 day's work = Work done by Pinky and Neha in 1 day
6 12 12 4 10
So, A and B together can finish the work in 4 days. 1
Work done by Neha alone in 1 day
68. Ans: [c] 12
Let Ram under take a tour of x days. 1 1 1
Work done by Pinky alone in 1 day
360 10 12 60
Then, expenses for each day =
x Pinky alone will complete the work in 60 days.
360 360 74. Ans: [c]
3
x4 x 1
Work done by A in 1 day
x = 20 and − 24 24
Hence, x = 20 days 1
Work done by B in 1 day
69. Ans: [d] 6
(20 x 16) women can complete the work in 1 day. 1
Work done by C in 1 day
1 12
1 woman's 1 day's work =
320 1 1 1
Work done by A, B, C together in 1 day
(16 x 15) men can complete the work in 1 day. 24 6 12
1 7
1 man's 1 day's work =
240 24
1 1 The work will be completed by A, B and C together in
So, required ratio = :
240 320 24 3
1 1 days 3 days
: 7 7
3 4
= 4:3 (cross multiplied) 75. Ans: [c]
1
70. Ans: [a] Work done by the man in 1 day
15
3/4w = 3/5d * 100 …….... 1 (completed work)
1
1/4w = 2/5d * x …………...2 (Remaining work) Work done by his father in 1 day
Dividing 1 by 2, we get 20
3/1 = (3/2) * (100/x) 1
Work done by his son in 1 day
6x = 300 => x = 50. 25
Page 9 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Work done by all the three together in 1 day 79. Ans: [b]
1 1 1 47 Let the work be completed in x days.
15 20 25 300 x x 9
1
300 24 21
All the three will complete the work in days
47 7x 8x 72
1
= 6.4 days 168
15x 240 x 16 days
SESSION – 5
80. Ans: [c]
TIME AND WORK – V 12 monkeys eat 12 bananas in 12 minutes.
So, 1 monkey can eat 1 banana in 12 minutes.
76. Ans: [a] 4 monkeys can eat 4 bananas in 12 minutes.
Less bolts, less days (direct proportion)
Less hours, more days (indirect proportion) 81. Ans: [b]
Less men, more days (indirect proportion) Let the work be completed in x days.
Let the required number of days be x. x x 5 x 7
1
men 2:1 20 25 10
5x 4 x 5 10 x 7
bolts 2000 :1000 ::2: x
1
hours 2:1 100
2 1000 2 5x 4x 20 10x 70
x 2 4days 1
1 2000 1 100
19x 100 90 190
77. Ans: [c]
x 10days
1
(A + B)’s 1 day’s work
12 82. Ans: [c]
1 1 1 7
(B + C)’s 1 day’s work Part of work completed in the first 2 days
15 18 24 72
1 th
(C + A)’s 1 day’s work 7
20 In 2 10 20 days 10 of the total work is
72
1 1 1
2(A + B + C)’s 1 day’s work completed.
12 15 20
48 1 35 th
of the total work is completed.
240 5 36
1 35 1
(A + B + C)’s 1 day’s work Remaining work 1
10 36 36
th
So A, B, C together will complete the work in 10 days. 1
On the 21st day A works and he can complete of
78. Ans: [b]
36
Page 10 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 11 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 12 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
SESSION – 6 LT2
20 100
25 / 2
TIME, SPEED & DISTANCE - I
25 LT2
100
1. Ans: [c] 2 20
Average speed = 50 kmph LT2 = 150 m
Average speed = Total distance/Total time.
5. Ans: [b]
50 d1 d2 d
t1 t2
20
4
50 d1 d2 t
60
d1 d2
30 90 d
25
d1 d2 2
50 d1 d2 t
30 90 60
Page 13 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 14 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
TIME, SPEED & DISTANCE - II Now, time taken = D/S = (250/125) = 2 hours
Hence 2 hours after 10 a.m., i.e. by 12 noon they will meet.
21. Ans: [d]
Given: 28. Ans: [d]
9/Su + 27/Sd = 170 --------- (i) (1/Su = x, 1/Sd = y) Using statement I alone, S1 = 30 km/h and S2 = 50 km/h
9/Sd + 27/Su = 270 ---------(ii) Since time is constant, the average speed is given by,
Solving (i) and (ii) y = 10/3 AS = (S1 + S2)/2 (arithmetic mean). Therefore statement I
Sd = 3/10 => 3 km in 10 mins so 18 kmph alone gives the answer.
22. Ans: [b] Using Statement II alone, S1 = 50 km/h and S2 = 60 km/h
Time taken to cross 1st bridge = 200 + length of train Since distance is constant in this case, statement II alone
(L)/speed(s) gives the answer because average speed is given by
=> 200 + L = 25s --- (i) Harmonic Mean,
Time taken to cross the 2nd bridge = 100 + length of train H.M = {(2 S1 S2)/(S1 + S2)}. I and II individually gives
(L)/speed(s) us the answer. So, the answer is option (d).
=> 100 + L = 15s --- (ii)
Equating (i) and (ii) speed = 10 mps 29. Ans: [c]
The auto covers half the distance in double the time. So,
23. Ans: [c]
its speed must be a fourth of the bus speed i.e. the ratio
Statements I and II give the details of length of train, time is 4:1.
taken, speed and direction of bird. Hence the time speed
of the train could be calculated. 30. Ans: [c]
If d is the distance, then {(d/80) – (d/90)} = 1; d = 720 km
24. Ans: [a]
Statement I gives the ratio of downstream and upstream 31. Ans: [d]
as 8:6. Using statement I alone
According to II, distance covered does not give Time (T) = 10 seconds,
information about the speeds. Distance (D) = (100 + 120) m
25. Ans: [b] Let S1 be the speed of the longer train and S2 be the
When the travelling distances are same for various speed of the shorter train, then Speed (S) = S1 S2
portions (i.e. 100 m), the average speed is equal to the
[Both the trains are moving in the opposite direction.]
harmonic mean of speeds. Harmonic seed of 3, 2 and 1 is
not 2. Therefore the answer is invalid. Dist(D)
Speed (S) =
Time(T)
26. Ans: [b]
Between the two poles there is only one gap or one 100 120
S1 S2 =
interval. So, for 12 poles there are 11 gaps. It is given that 10
the car takes 22 seconds to cross those 11 gaps. Using statement I alone, the sum of the speeds of the two
Hence the time taken to cross each gap = 22/11 trains can be determined.
= 2 seconds Using statement II alone:
We have to find the time taken by the car to reach the 20th Time (T) = 50 seconds
pole (19 gaps), which is given by Distance (D) = (100 + 120) m
Time taken = 2 19 = 38 seconds Let S1 be the speed of the faster train and S2 be the
speed of the slower train which is given as 50 km/h.
Page 15 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Then Speed (S) = (S1 S2 ) [Both the trains are moving in Speed of each train
Page 16 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
SESSION – 8 Solutions for Q45 and Q46: Let the trains meet at point P
Distance travelled by train that started from station X
TIME, SPEED & DISTANCE - III
= 72 * 4.5 = 324 km
41. Ans: [b] So XP = 324 km
Let the distance be x km. Then, (time taken to walk x km) Distance travelled by train that started from station Y
+ (Time taken to ride x km) = 23/4 hrs. = 90 * 2.5 = 225 km
⇔ (Time taken to walk 2x km) + (Tie taken to ride 2x km) So YP = 225 km
= 23/2 hrs. But, time taken to ride 2x km = 15/4 hrs.
Total Distance = XY = XP + YP = 549 km
∴ Time taken to walk 2x km [23/2 - 15/4] hrs = 31/4 hrs
= 7 hrs 45 min. 45. Ans: [a]
Let the speed b reduced by x km/hr.
42. Ans: [b]
Total Distance will remain same
Let the required speed be y km/hr.
So, 72 * 3 + (72 – x) * 4.5+ 90 + (90 – x)4.5 = 549
Then, (2 x 64) x [ y/(64 + y)] = 56
This gives x = 54 km/hr
⇒ 128y = 64 x 56 + 56y
So new speeds of the trains that started from station X & Y
∴ y= (64 x 56)/72
r respectively 18 & 36 km/hr
= 49.77 km/hr.
46. Ans: [d]
43. Ans: [a]
Let x hours b the time taken after signal problem occurs
Let the usual speed of the aircraft be 'x' km/hr
(i.e. at 1.00 p.m.).
So, the reduced speed will be (x – 100) km/hr
Now the speeds of trains after signal problem occurs is 18
Time taken to reach the destination at usual speed
& 36 km/hr (as derived above)
T1 = (3000/x) hr
Again, Total Distance will remain same
Time taken to reach the destination at reduced speed
So, 72 * 4 + 18 * x + 90 * 2 + 36 * x = 549
T2 = (3000/x – 100) hr
x = 1.5 hours
Given: T2 - T1 = 1 hr
So, the two trains cross each other 1.5 hours after signal
(3000/x – 100) hr – (3000/x) hr = 1 hr
problem occurs i.e. at 2:30 p.m.
⇒ (3000x – 3000x + 300000)/(x)(x – 100) = 1 hr
47. Ans: [b]
⇒ x² – 100x – 300000 = 0
⇒ x² – 600x + 500x – 300000 = 0 A goes up at the rate of 34 floors/min or, 17 Floors/30
seconds.
⇒ x(x – 600) + 500(x – 600) = 0
B comes down at the rate of 36 floors /min or, 18
⇒ (x - 600)(x + 500) = 0
Floors/30 seconds.
⇒ x = 600 or x = – 500
Lets see where they would be after 30 seconds each:
Speed cannot be negative.
For A:
Hence x = 600 km/hr is correct speed.
9 + 17 = 26th Floor.
Original duration of flight = 3000/600 = 5 hours
For B:
44. Ans: [b] 44 – 18 = 26th Floor.
Let x be the upstream speed, then the downstream speed So they will meet at 26th floor.
will be (x + 3)
48. Ans: [a]
3 3
0
x x 3 Rate of stream = 1.5 km/hr
Let speed of man in still water = x km/hr and Distance = d
x2 x 3 0
Upstream speed = (x – 1.5) km/hr Downstream speed
1 13 = (x + 1.5) km/hr
x
2 Given, 2d/(x + 1.5) = d/(x – 1.5) => 2x – 3 = x + 1.5
1 3.6 x = 4.5 km/hr
1.3 km/h
2
(x 3) 4.3 km/h 49. Ans: [c]
While A runs 600 m, B runs (600 – 60) = 540 metre
Page 17 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
While A runs 400 m, B runs (540/600) × 400 = 360 Speed downstream = 12 km/hr
metre Speed upstream = 8 km/hr
While B runs 500 m, C runs (500 – 50) = 450 metre 12 8
Hence, speed of the current 2 km / hr
While B runs 360 m, C runs (450/500) × 360 = 324 2
metre
53. Ans: [d]
i.e., When A runs 400 metre, B runs 360 metre and C runs
Let the speed of Ravi be y km/hr and the speed of Kunal
324 metre.
be x km/yr. [x > y]
Hence, A beats C by (400 – 324) = 76 metre in a race of
The relative speed of Kunal with respect to Ravi is (x – y)
400 m
km/hr = (x – 4) km/hr
50. Ans: [c] Ravi’s speed for the 45 minutes is 4 km/hr.
(speed of wind)/(speed of car) = (Time utilised)/(time Distance walked by Ravi in 45 min
saved)
3
⇒ 332/x = 332/28 = 4 3 km
4
∴ x = 28 m/s Kunal covers this distance of 3 km at the relative speed of
51. Ans: [c] (x – y) km/hr or (x – 4) km/hr.
Page 18 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
+ Sr = ⁄ ....(2) 2x =
Page 19 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 20 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
When A has run 100 yards, C has run only When B covers 395 m, C covers
( ) yards. 396
395 391.05
Therefore, A wins by 13.6 yards. 400
When A covers 400 m, B covers 391.05 m
75. Ans: [b]
When D covers 400 m, C covers 384 m
In a 1000 metre race, A gives B a start of 100 m or 15
When C covers 391.05 m, D covers 407.3 m
seconds.
When A covers 400 m, D covers 407.3 m
This essentially means that B takes 15 seconds to run 100 m.
When D covers 400 m, A covers 392.8 m
Therefore, time taken by B to run the stretch of
D wins by 7.2 m, when D and A run the race.
( )
80. Ans: [d]
As A takes 15 seconds less than B, time taken by A to run
the 1000m = 150 – 15 = 135 seconds After the start the end of every 200 m of A they would
have met thrice and both would be at the starting point
76. Ans: [b] again. Hence at the end of the 1000 m race they would
Let 1, 2, 3, 4, .. are in AP 2 = x + d, 3 = x + 2d… and so on… 1000
have met 3 = 15 times
Let assume 1(variable) = x 200
Given time taken by 26 to meet 1 for the first time is 20 sec
SESSION – 10
i.e = 20
d = 0.5 m/sec TIME, SPEED & DISTANCE - V
Time taken by 13 = x + 12d is 52 minutes and 5 seconds 81. Ans: [d]
i.e ( ) = 3125 By the time a covers 1000 m, B has covered 900 m.
x = 0.8 m/sec By the time B covers 900 m.
Time taken by all of them to meet for the first time at the By the time B covers 1000 m, C has covered 850 m, C will
starting point is cover
[ ] 850
900 765 m
( ( ))
1000
( ) A beats C by 235 m
Page 21 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 22 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 23 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 24 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 25 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 26 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
1 120 111
Error percentage 100 25% Percentage of extra money paid 100
4 111
E = KW 8.1%
25% K 5 kg
36. Ans: [d]
K 5 CP Rs.20
Now the displayed weight is 10. MP = 25% above the CP
E = 5 weight 25% of CP 5
E = 5 10 kg So MP = Rs.25
The error = 50% Given that we have two successive discounts
The actual weight 100 x 100 x
100 100 25 20.25
100% 50% Error = 10 kg
150% 10 kg ‘x’ be the discount percentage.
x = 10%
100 20 Instead of decreasing he is going to increase it.
100% 10 kg
150 3 MP Rs.25
Assume 10% discount (But we have to add)
CP of 1 kg = 10 kg 10% of 2.5 = 2.5 25 2.5 27.5
20 200 Again 10% 10% of 27.5 = 2.75
CP of kg Rs.
3 3 Add 27.5 + 2.75 = 30.25
SP of 10 kg = 100 (10% of 100) = Rs.90 We know that CP = 20. So profit = 10.25
200 For initial case SP 20.25 CP 20 Profit = 0.25
90
P% 3 100 35% We require 10 is what percent of 0.25
200 x
3 0.25 10
100
34. Ans: [a] 10100
x 4000%
He sells a part of the packet at a profit of 30% 0.25
So SP of that part = 130% CP
On the remaining part, he incurs a loss of 10% 37. Ans: [c]
So SP of that part = 90% CP SP1 800 SP2 275
Total profit is 10% 110% CP SP1 SP2 525
Going with allegation
SP1 800 CP P … (1)
130 90
SP2 275 CP L … (2)
110
Given that P = 20 L, use this in (1)
20 20
SP1 800 CP 20L
Equal ratio 50 pens should be splited into two equal
SP2 275 CP L
parts The no. of pens he sold at profit = 25 pens.
525 21L
35. Ans: [c]
L 25
Let us assume
Cost price of sofa = Rs.100 If L 25, CP 300
Cost price of table Given that center table cost 40% as We need a profit of 25%.
much as sofa. 25% of 300 = 75
Rs.40 So SP should be Rs.375
Actual Bargain New rate 38. Ans: [d]
Sofa =25% sofa Rs.75 Rs.90 Initial case Second case
Table = 10% discount 36 30 Cost price = CP Cost price = 90% of CP
111 120 Selling price = SP Selling price = 110% of SP
Profit = P Profit = double than earlier
Page 27 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 28 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 29 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 30 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
A + B + C = 252 x 38
Page 31 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
SESSION – 15 60
Number of sheets typed by C in 1 hr
9
AVERAGES – II
60 60 60
21. Ans: [b] Hence the required average 6 7 9
Let the number of ladies be x. 3
The total consumption for 8 males 15 8 120 kg. 60 53 530
The total consumption for x ladies 6 x 6 x kg. 3 126 63
1825 5x 10 x 5 x 6
Correct average Average of 7 numbers
36.5 7
50
7 x 21
25. Ans: [d] x 3
7
Since the month begins on a Sunday, there are 5 Sundays Hence, the average increases by 1.
in the month.
5 510 25 240 30. Ans: [c]
Required average
30 Let the average amount paid by all be Rs.x.
2550 6000 8550 Total amount paid by all = Rs.20x.
285 16 50 x 10 x 15 x 25 x 30 20 x
30 30
880 4 x 20 x 16 x 880
26. Ans: [b]
x Rs.55
60
Number of sheets typed by A in 1 hr Hence, total bill 20 x Rs.55 20 Rs.1100
6
60
Number of sheets typed by B in 1 hr
7
Page 32 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 33 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 34 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 35 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
15 x 20 x 25 15 The no. of persons in the group with the entry of the new
700 x 700 x
100 100 100 100 person = 16
15 New average weight of the group = 62.875 kg
2700 x
200 New total weight = 16 × 62.875 = 1006 kg
x 25 x 20 Thus, the weight of the new person = 1006 – 948.75
30700 x 45x
100 100 = 57.25 kg
x = Rs.280 Aliter
C.P of the 2nd pen = 700 – 280 = Rs.420 We know that when a new quantity x is added to a set of N
values with mean M and if the average decreases by μ,
15. Ans: [b]
then the added new quantity x = M – (N + 1) μ
Let the C.P. be Rs.100.
By this, weight of the new person = 63.25 – (16 × 0.375)
M.P. = Rs.125
= 57.25 kg
1
87
1 19. Ans: [a]
With discount of 12 %, S.P = 125 2 Rs.109.375
2 100
Let ‘x’ be the average runs till 16 innings.
Profit percent = 9.375%
Therefore, (16x + 87) /17 = x + 3
New S.P. for double the profit = 100 + 2 9.375
x + 3 => the new average after 17th innings has increased
= Rs.118.750
by 3 from the old average.
1
M.P with the same discount of 12 % Solving for x, we get x = 36.
2
Therefore, new average = 36 + 3 = 39
100
118.750
87.5 20. Ans: [c]
135.7 Average of 6 numbers = 30
Mark – up percent = 35.7% Therefore, total = 6 x 30 = 180.
Average of first four numbers is 25.
16. Ans: [b]
Hence, total of first 4 = 25 x 4 = 100
Let the total number of workers be x.
Average of last 3 = 35
Therefore, number of non-technician workers = x – 7
Hence, total of last 3 = 3 x 35 = 105
Now x × 1700 = 7 × 2000 + (x – 7) × 1560
1700x = 1560x + 3080 Total of first 4 and last 3 = 100 + 105 = 205
Page 36 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
Page 37 of 38
QUANTITATIVE ABILITY – SOLUTION
HSEM3BTECHSTANDARD0719
x 85 2 10
100
100 2 2000 x 6000
100 100 1.8% 100
x 85 112.5 112.5
8 10
100 100 2500 x 5000 2000 x 6000
100 100
12. Ans: [d] 2,50,000 + 8x – 40,000 = 2, 00, 000 + 10x – 60000
Let the price of the 1st and the 2nd book be Rs.130 and 70,000 = 2x
Rs.100 respectively.
35,000 = x
Taking into account the off reduction, sales tax etc., the
price of the books is worked out as follows. Required weekly sales = Rs.35,000
Page 38 of 38