Professional Documents
Culture Documents
Consulting services for Detailed Engineering Survey, Design and Cost Estimate
of
Dalchoki-Shanku-Ikudol-Majhkanda Road (Ch 0+000km to Ch 11+347Km)
SUBMITTED BY:
Summery of Cost
Item No. Description of Works Amount in NRs. % of Total Cost
1 GENERAL 2,339,308.14 0.73
2 SITE CLEARANCE 98,857.00 0.03
3 EARTHWORK 34,971,242.14 10.92
4 RETAINING AND BREAST WALL 10,893,407.43 3.40
CROSS DRAINAGE, SIDE DRAINAGE & MISCELLANEOUS
5 111,367,679.66 34.78
WORKS
6 PAVEMENT WORKS 148,942,007.87 46.52
7 ROAD FURNITURE AND TRAFFIC SAFETY MEASURES 11,311,604.45 3.53
8 DAY WORKS 276,830.00 0.09
9 Sub total with out Provisional Sums 317,861,628.56 100.00
10 Total cost with Provisional Sums 320,200,936.70
11 Contengency @ 4 % of 9 12,714,465.14
12 VAT @ 13 % of 9 41,322,011.71
13 Physical Contengency @ 10% of 10 32,020,093.67
14 Price Adjustement @ 10 % of 10 32,020,093.67
17 Grand Total Cost 438,277,600.89
Clearing and Grubbing Road Land ., Clearing and grubbing road land
including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees
girth up to 300 mm, removal of stumps of trees cut earlier and disposal of
2.01 201/ I,/(ii)/A&B unserviceable materials and stacking of serviceable Material to be used or m2 20,425.00 4.84 98,857.00
auctioned, up to a lead of 30 meters including removal and disposal of top
organic soil not exceeding 150 mm in thickness., By Mechanical Means, In area
of light jungle (less than 15 number per 100 sqm )
Sub-Total 98,857.00
Part 3: EARTHWORK
Road way excavation in all type of soil including disposal all complete as per
905/ 9.1/ I.II,IV/ A
3.01 specification. [Manual 10% and Machine 90%], all complete as per specification m3 127,279.00 113.91 14,497,990.69
&B
and Engineer's instruction. (SS 905)
Sub-Total 34,971,242.14
Part 4: RETAINING AND BREAST WALL
Providing and Laying Gabion structure for retaining earth with diaphragm
including rolling, cutting weaving, placing, laying sides and diaphragms with
4.032401,2402/24.2, A/24.3/24.4
binding wire and filling boulder all complete as per drawing and technical m3 1,299.46 4,993.70 6,489,113.45
specification. Heavy zinc coated Hexagonal mesh type 100 mm x 120 mm, mesh
wire 3mm, selvage wire 3.9 mm, lacing wire 2.4 mm
Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing
4.04 2401/24.1/ A/I and Specifications, 60% M 15 concrete and 40% boulders/stones, using m3 0.00 9,854.80 -
Mechanical Aids
Laying and fixing of Geo-Textile all complete as per specification., Providing 2
4.08 1804,1805/18.1/ a m 621.21 112.70 70,010.25
and laying of a geotextile filter between pitching and embankment slopes as per
Sub-Total 10,893,407.43
Bill of Quantities
Dalchoki-Shanku-Ikudol-Majhkanda Road (Ch 0+000km to Ch 11+347Km)
Providing and Laying Gabion structure for retaining earth with diaphragm
including rolling, cutting weaving, placing, laying sides and diaphragms with
2401,2402/24.2,
5.03 binding wire and filling boulder all complete as per drawing and technical m3 20.00 4,993.70 99,874.00
A/24.3/24.4
specification. Heavy zinc coated Hexagonal mesh type 100 mm x 120 mm, mesh
wire 3mm, selvage wire 3.9 mm, lacing wire 2.4 mm
Providing and laying Stone Masonry work in cement mortar 1:4 in structure
5.04 2606/26.5/B m3 9,371.00 10,772.20 100,946,286.20
complete as per Drawing and Technical, Coursed rubble Masonry (first sort )
Sub-Total 111,367,679.66
Part 6: PAVEMENT WORKS
Sub grade construction and preparation of formation in cutting and filling in all
1003/10.4/ Case-I, types of soil including rocks with disposal of unusable material at specified
6.01 m3 5,876.47 78.64 462,141.71
Case- II location, levelling and compaction as per specification and instruction of
engineer all complete.
Providing and laying granular sub-base on prepared surface, mixing at OMC,
6.02 1201/12.1/A and compacting to achieve the desired density, complete as per Drawing and m3 12,061.00 2,222.62 26,807,019.82
Technical Specifications., By Mechanical means
Providing and laying Crusher Run Macadam on a prepared surface, spreading
6.03 1204/12.7/A and mixing , watering and compacting to form a layer of sub-base/Base course m3 6,001.00 4,192.80 25,160,992.80
as per Drawing and Technical Specifications., By Mix in Place Method
Tack Coat, Tack coat with Bitumen By Mechanical Means, Providing and
6.05 1302/13.2/A applying tack coat with hot Bitumen at specified rate on the prepared non- lit 27,423.52 100.93 2,767,856.25
bituminous surfaces including cleaning as per Technical Speciation .
Providing and Laying open graded premix carpet of 20mm thickness composed
6.06 1311/13.9/B/(i) of 13.2mm to 5.6mm aggregates as wearing course on a previously prepared m3 783.53 12,652.38 9,913,509.82
base as per drawing and Technical Specification Mechanical Means
6.07 Rigid Pavement m3 6,678.22 11,912.21 79,552,359.07
Sub-Total 148,942,007.87
Part 7: ROAD FURNITURE AND TRAFFIC SAFETY MEASURES
Supply and erecting Retro Reflective Traffic Sign in place including 50mm dia.
Steel tube, 2mm thick steel plates, cement concrete, painting, writing and
7.01 1501/15.2 supporting steel angle nut and bolt etc. all complete, as per drawings, No 1,084.00 7,671.34 8,315,732.56
specification (SS/SP-1501) and instruction of Engineer. 75 cm dia Circular, 75
cm equilateral triangle and 75cm x 60 cm rectangular shaped sign ( single post )
Metal Beam Crash Barrier, Type - A, "W" : Metal Beam Crash Barrier,
Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC
7.03 1509/15.14/A series channel vertical post, 150 x 75 x 5 mm spaced 2 m center to center, 1.8 m m 200.00 8,196.52 1,639,304.00
high, 1.1 m below ground/road level metal beam rail to be fixed on the vertical
post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete
as per Drawing and Technical Specifications.
Sub-Total 11,311,604.45
Part 8: DAY WORKS
Work shall only be executed as Day works only under the written instructions of
the Engineer.
Labour (the rates inserted shall include all costs of labour such as
8.01 SP insurance, accomodation, travelling, hand tools, supervision, overhead and
profit)
8.01 a) Foreman / Supervisor md 10.00 700.00 7,000.00
8.01 b) Skilled labor (Mason, Carpenter, mechanics etc.) md 10.00 953.00 9,530.00
8.01 c) General labor (Unskilled, helpers, assistant operators etc.)) md 20.00 700.00 14,000.00
8.02 Equipment
8.02 a) Concrete mixer (0.40 m3 capacity) hr 10.00 1,325.00 13,250.00
8.02 b) Concrete vibrator hr 10.00 355.00 3,550.00
8.02 c) Mini Dumper hr 50.00 725.00 36,250.00
8.02 d) Tipper hr 50.00 1,737.50 86,875.00
8.02 e) Water Browser hr 50.00 1,017.50 50,875.00
8.02 f) Motor Grader hr 10.00 2,475.00 24,750.00
8.02 g) Excavator hr 10.00 3,075.00 30,750.00
Sub-Total 276,830.00