DETAIL OF MEASUREMENT(A1 TOWER )

EVEREST ENCLAVE,SEC-18 ,GROUP HOUSING VRINDAVAN SCHEME,LUCKNOW

Vascon Engineers Ltd


AREA STATEMENT - INTERNAL PAINTING
A1 TOWER
S.N. ITEM NO. L B H AREA UNIT
1 Finishing wall with Acrylic Smooth Paint
AT FIRST FLOOR
CORRIDOR AREA
STAIR SIDE WALL - (Y-13-Y-24)/X-12 1 12.88 2.850 36.71
DEDUCTION
D3 2 1.20 2.100 -5.04
STAIR CASE ENTRY /EXIT OPENING 1 1.500 2.100 -3.15
RAILING 1 2.820 2.100 -5.92
SIDE WALL FLAT ENTRY 2 0.490 2.850 2.79

LIFT SIDE WALL - (Y-13-Y-24)/X-15 1 12.88 2.875 37.03


DEDUCTION
D3 2 1.20 2.100 -5.04
STAIR CASE ENTRY /EXIT OPENING 1 1.500 2.100 -3.15
RAILING 1 1.330 2.100 -2.79
LIFT WALL 1 4.69 2.850 -13.37

LEFT/RIGHT SIDE COORIDOOR 2 4.065 2.850 23.17


DEDUCTION
FIRE DUCT 2 0.75 1.750 2.100 -5.51
IV DUCT 2 0.750 1.170 -1.76
CEILING COORIDOR AREA 1 12.880 3.650 47.01
CEILING NEAR FLAT ENTRY AREA 1 1.630 0.490 0.80
CEILING NEAR FLAT ENTRY AREA 1 2.435 0.490 1.19
STAIR CASE FRONT
INTERNAL WALL 1 17.860 2.850 50.90
CEILING LANDING 2 3.230 1.500 9.69
CEILING WAIST SLAB 2 3.020 1.500 9.06
DEDUCTION
STAIR CASE ENTRY /EXIT OPENING 1 1.500 2.100 -3.15
RAILING 1 1.500 2.850 -4.28
STAIR CASE LIFT SIDE
INTERNAL WALL 1 15.700 2.850 44.75
CEILING LANDING 2 2.650 1.250 6.63
CEILING WAIST SLAB 2 2.500 1.250 6.25
DEDUCTION
STAIR CASE ENTRY /EXIT OPENING 1 1.500 2.100 -3.15
RAILING 1 2.650 2.100 -5.57
Total 165.19 SQM
G.Total 165.19 SQM
DETAIL OF MEASUREMENT(B1 TOWER )
EVEREST ENCLAVE,SEC-18 ,GROUP HOUSING VRINDAVAN SCHEME,LUCKNOW

Vascon Engineers Ltd


AREA STATEMENT - INTERNAL PAINTING
B1 TOWER
S.N. ITEM NO. L B H AREA UNIT
1 Finishing wall with Acrylic Smooth Paint
AT FIRST FLOOR
CORRIDOR AREA
STAIR SIDE WALL - (C-9-Y-20)/A-13 1 12.87 2.850 36.68
DEDUCTION
D3 2 1.20 2.100 -5.04
STAIR CASE ENTRY /EXIT OPENING 1 1.500 2.100 -3.15
RAILING 1 2.820 2.100 -5.92
SIDE WALL FLAT ENTRY 2 0.490 2.850 2.79

LIFT SIDE WALL - (C-9-Y-20)/A-11 1 12.87 2.875 37.00


DEDUCTION
D3 2 1.20 2.100 -5.04
STAIR CASE ENTRY /EXIT OPENING 1 1.500 2.100 -3.15
RAILING 1 1.330 2.100 -2.79
LIFT WALL 1 4.69 2.850 -13.37

LEFT/RIGHT SIDE COORIDOOR 2 4.065 2.850 23.17


DEDUCTION
FIRE DUCT 2 0.75 1.750 2.100 -5.51
IV DUCT 2 0.750 1.170 -1.76
CEILING COORIDOR AREA 1 12.880 3.650 47.01
CEILING NEAR FLAT ENTRY AREA 1 1.630 0.490 0.80
CEILING NEAR FLAT ENTRY AREA 1 2.435 0.490 1.19
STAIR CASE FRONT
INTERNAL WALL 1 17.860 2.850 50.90
CEILING LANDING 2 3.230 1.500 9.69
CEILING WAIST SLAB 2 3.020 1.500 9.06
DEDUCTION
STAIR CASE ENTRY /EXIT OPENING 1 1.500 2.100 -3.15
RAILING 1 1.500 2.850 -4.28
STAIR CASE LIFT SIDE
INTERNAL WALL 1 15.700 2.850 44.75
CEILING LANDING 2 2.650 1.250 6.63
CEILING WAIST SLAB 2 2.500 1.250 6.25
DEDUCTION
STAIR CASE ENTRY /EXIT OPENING 1 1.500 2.100 -3.15
RAILING 1 2.650 2.100 -5.57
Total 165.13 SQM
G.Total 165.13 SQM