Professional Documents
Culture Documents
DETAILED ESTIMATE
GROUND FLOOR
S.No DESCRIPTION NOS L B D Quantity Unit
f for Lintels:
D1-Doors 3 2.300 0.230 0.150 0.24
D2-Doors 8 1.200 0.230 0.150 0.33
D3- Doors 5 1.050 0.115 0.150 0.09
W1-Windows 18 2.000 0.230 0.150 1.24
W2-Windows 6 1.500 0.230 0.150 0.31
W3-Window 1 2.700 0.230 0.150 0.09
W4-Window 2 1.500 0.230 0.150 0.10
KW2- Window 2 1.500 0.230 0.150 0.10
2.51
Add for variation 0.05
2.56
Say 2.60 cum
2 VRCC M25 Design Mix
Roof beams
RB-1(300x600) 1 3.230 0.300 0.475 0.46
RB-2(380x725) 1 613.630 0.380 0.600 139.91
Deduct for Columns: (Horizantal &
Vertical)
C1 2 -5 0.600 0.600 0.600 -2.16
C2 2 -5 0.450 0.450 0.600 -1.22
C3 2 -19 0.900 0.900 0.600 -18.47
C4 2 -12 0.450 0.900 0.600 -5.83
112.69
Add for variation 2.25
114.95
Say 115.00 cum
3 Roof Slab
i 125mm thick
514.00
524.28
Say 524.30 sqm
65.54 cum
43.15
Planter box walls beside entrance steps 1 11.430 3.775
47.79
Planter box walls beside entrance steps 1 12.660 3.775
Deductions:
Bed Blocks
D3- Doors -5 1.050 0.150 -0.79
Lintels
D3- Doors 6 -5 0.230 0.150 -1.04
Openings
D3- Doors -5 0.750 2.400 -9.00
271.55
Add for variation 5.43
276.98
Say 277.00 sqm
8 Platforms /Lofts
Kitchen 1 6.390 0.600 3.83
Café Service 1 2.630 0.600 1.58
Say 5.41 sqm
9 High Polished Granite (Platforms)
11 MILD STEEL
Platforms 5.41 3.000 Kgs/sqm 16.24
RBM walls 277.00 2.000 Kgs/sqm 554.00
570.24
Add for variation 11.40
581.64
Say 581.70
Say 0.58 MT
16 Skirting
Learning center 1 55.090 55.09
Kitchen 1 15.360 15.36
Cafeteria 1 37.300 37.30
Café service 1 12.620 12.62
Store room 1 8.880 8.88
Back office 1 11.740 11.74
140.99
Add for variation 2.82
143.81
Say 143.90 Rmt
19 Water Proofing
Toilet block -Gents 1 3.770 3.370 12.70
Toilet block - Ladies 1 3.370 2.880 9.71
say 22.41 sqm
20 Granite Clading
Learning center to Cafeteria 1 31.320 3.900 122.15
Learning center room side wall 1 9.940 3.900 38.77
Ladies toilet to Electrical ups room 1 14.520 3.900 56.63
Cafeteria wall 1 10.320 3.900 40.25
Elevator to store room wall 1 17.990 3.900 70.16
Elevator to Elevator wall 1 4.660 3.900 18.17
Staircase wall 1 1.580 3.900 6.16
Staircase wall 1 4.770 3.900 18.60
Staircase wall 1 6.050 3.900 23.60
Staircase wall 1 5.820 3.900 22.70
Electrical ups room 1 7.830 3.900 30.54
Deduction of Opening
W1-Windows -18 1.700 1.500 -45.90
W2-Windows -6 1.200 1.500 -10.80
W3-Window -1 2.400 1.500 -3.60
W4-Window -2 1.200 1.200 -2.88
Treads
Central staircase 23 1.500 0.300 10.35
Fire escape staircase 23 1.500 0.300 10.35
20.70 sqm
22 False Ceiling
Qnty Same as Ornamental Plastering
sqm
523.46
23 Non-Skid Flooring
Gents toilet 1 3.770 2.880 10.86
Ladies toilet 1 3.770 2.880 10.86
Say 22.15
24 Dadooing
Mens toilet 1 13.300 2.100 27.93
Ladies toilet 1 13.300 2.100 27.93
Ladies w/c room walls 1 4.400 2.100 9.24
Ladies w/c room walls 1 4.400 2.100 9.24
Ladies w/c room walls 1 4.400 2.100 9.24
Ladies w/c room walls 1 4.400 2.100 9.24
Gents w/c room wall 1 4.400 2.100 9.24
Deductions
D3 -5 0.750 2.100 7.88
109.94
Add for variation 2.20
112.13
Say 112.20
Windows
W1-Windows 18 1.700 1.500 45.90
W2-Windows 6 1.200 1.500 10.80
W3-Window 1 2.400 1.500 3.60
W4-Window 2 1.200 1.200 2.88
KW2- Window 2 1.200 0.900 2.16
Say 65.34 Sqm
30 SS railing
Staircase 1 13.080 0.900 11.77
2 8.200 0.900 14.76
Say 26.53 Sqm
31 Structural Glazing
W5-Fixed Glazing 1 2.400 3.900 9.36
W6-Fixed Glazing 1 4.730 3.900 18.45
V-Ventilators 2 1.200 0.600 1.44
29.25
Add for variation 0.58
29.83
Say 29.90 sqm
(Lead)
charges
(Lead)
(Lead) (Lead) for trucks
charges for
charges for charges for and
trucks and (Lead)
trucks and trucks and tippers for (Lead)
tippers per charges for
tippers for tippers for Cement/ charges for
cu.meter for trucks and
Earth / Sand Rubble/Size Steel/ trucks and
Sl No. Distance PCC slabs/ tippers per
/Gravel / stones/ Cut RCC tippers for
Shahabad cu.meter for
Murrum/ Stones/ poles/ AC Bricks
slabs/ CC & water/ 1000
Lime/ Surki/ Coarse & GI /1000 nos
Laterite litres
per aggregate sheets/
blocks/
cu.meter per cu.meter Packed
Wood/ cum
materials/
tonne
1 2 3 4 5 6 7 8
1 Lead up to 1 km 1 32.10 30.90 19.30 45.40 19.10 51.40
2 Lead up to 2 km 2 44.90 43.20 27.00 63.50 26.80 72.00
3 Lead up to 3 km 3 59.90 59.90 37.40 88.00 35.70 96.00
4 Lead up to 4 km 4 72.70 72.70 45.40 106.90 43.40 116.60
5 Lead up to 5 km 5 85.50 85.50 53.40 125.70 51.00 137.20
6 for Every km beyond 5 km up to 30 km 30 12.80 12.80 8.00 18.90 7.70 20.60
7 for Every km beyond 30 km 10000 10.70 10.70 6.70 15.70 6.40 17.10
Rubble/ size
Earth / Sand stone/ cut
/Gravel stone/
Cement in Steel in Bricks
Sl No. Description of item Murrum/ / Coarse
Rs/Tonne Rs/Tonne Rs/1000 Nos.
Surki/ Rs / aggregate,
cum Lime in
Rs/cum
1 Loading 21.50 43.00 71.00 85.10 59.20
D Allowances
1 Add for MA @ 25% 0.25
2 Overheads&Contractors Profit @13.615% 0.13615
Water charges (Rural -73, Urban - 98)
Type of Habitation 2 1 for Rural
2 for Urban
Common SoR 2014-15 Page-14
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
117 15mm Mineral Fiber sheet 600 x 600 34 TBSC-K.I-06 626.00 1 sqm
118 12mm Mineral Fiber sheet 600 x 600 34 TBSC-K.I-04 Deleted 1 sqm
119 12mm Thermocole sheet 35 TBSC-K.I-24 24.00 1 sqm
Cement Bonded Prelaminated
120 43 TBSC-K.IV-13 3490.00 1 sqm
Particle Board aluminum glazed partitions
Cement bonded Prelaminated particle board
121 43 TBSC-K.IV-13 3490.00 1 sqm
aluminium glazed partions
122 MDF Board Interior - BSL 18mm thick 29 TBSC-H.III-13 1100.00 1 sqm
12 mm - Mineral Fiber sheet 600 x 600
123 34 TBSC-K.I-04 Deleted 1 sqm
(Square / Tegular) Edge tiles
12 mm - Mineral Fiber sheet 600 x 600
124 34 TBSC-K.I-04 Deleted 1 sqm
(Square / Tegular) Edge tiles
129 Supply and fixing of UPVC openable doors 59 TBSC-L.III-12 7989.00 1 sqm
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
147 Dismantling
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
171 G.I ‘J’ bolts 8 mm Diameter 24 TBSC-D.VI-16 10.00 1 No.
172 GI washers 24 TBSC-D.VI-17 2.00 1 No.
173 Limpet washers (for scam & ‘J’ bolts) 24 TBSC-D.VI-18 2.00 1 No.
174 Bitumen washers 24 TBSC-D.VI-19 2.00 1 No.
156 White cement 105 TBSC-R.I-01 29.00 1 Kg
158 Power Drill - Hand Operated - Hire Charges 109 TBSC-S.I-03 121.00 1 hour
Reference
Material hire Labour
159 Hire charges for Access Scaffolding to SSR Unit
charges charges
page
A) Brick Masonry / Stone Maasonry
a) 1st floor 116 10.32 75.68 1 Sqm
b) 2nd floor 10.32 108.36 1 Sqm
c) 3rd floor 10.32 141.04 1 Sqm
d) 4th floor 10.32 173.72 1 Sqm
e) 5th floor 10.32 206.40 1 Sqm
f) 6th floor 10.32 239.08 1 Sqm
g) 7th floor 10.32 271.75 1 Sqm
h) 8th floor 10.32 304.43 1 Sqm
i) 9th floor 10.32 337.11 1 Sqm
j) 10th floor 10.32 369.79 1 Sqm
B) Plastering to walls
a) 1st floor 116 1.03 7.57 1 Sqm
b) 2nd floor 1.03 10.84 1 Sqm
c) 3rd floor 1.03 14.10 1 Sqm
d) 4th floor 1.03 17.37 1 Sqm
e) 5th floor 1.03 20.64 1 Sqm
f) 6th floor 1.03 23.91 1 Sqm
g) 7th floor 1.03 27.18 1 Sqm
h) 8th floor 1.03 30.44 1 Sqm
i) 9th floor 1.03 33.71 1 Sqm
161 HIRE CHARGES FOR CENTERING&SCAFFOLDING-centering using Steel scaffolding pipes , jack props , wallers , Foo
Common SoR 2014-15 Page-22
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
Reference Material hire
to SSR charges Labour charges
162 HIRE CHARGES FOR CENTERING & SCAFFOLDING -Unsupported height of 3.66M -centering using Steel scaffolding pipes , jac
plates etc.,
Reference Material hire
to SSR charges Labour charges
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
163
PVC Clamps PH-160 TBSP-H.II-61 18.00 1 Each
LABOUR CHARGES
Part-I Common
SKILLED SoR(I&CAD)
164
Bar bender 9 I-1 565.00 1 Each
165
Blacksmith 9 I-2 470.00 1 Each
166
Blaster 9 I-3 565.00 1 Each
167
Carpenter 9 I-4 565.00 1 Each
168
Work Inspector(Non technical) 9 I -10 565.00 1 Each
169
Mason / Brick layer 9 I -11 470.00 1 Each
170
Operator concrete mixer 9 I -16 470.00 1 Each
171 Operator Jackhammer / Pneumatic
tamper(skilled) 10 I - 23 470.00 1 Each
172
Painter 10 I - 35 540.00 1 Each
173
Plumber / Pipe fitter 10 I - 36 540.00 1 Each
SEMI SKILLED
173
Sprayer(semi skilled) 11 II - 1 420.00 1 Each
174
Carpenter 11 II - 4 440.00 1 Each
175
Plumber / Pipe fitter 11 II - 9 425.00 1 Each
175
Mason / Brick layer 12 II - 35 425.00 1 Each
176
Painter 12 II - 37 420.00 1 Each
UN SKILLED
Man Mazdoor / Woman Mazdoor
177
13 III - 3, 4 400.00 1 Each
Cost of Materials :
178
Binding wire 22 3 46.00 1 Kg
179
Detonator electric 22 21 8.00 1 No.
180
Sand (un-screened for concrete items) 22 27 600.00 1 Cum
181
Sand un-screened for filling 22 27 600.00 1 Cum
182
Sand(screened for mortar, plastering items) 22 28 800.00 1 Cum
183
Gravel / Quarry spall Sl.No. 90 Roads & Bridges 98.00 1 Cum
184
Roads & Bridges
Aggregates 6mm nominal size (HBG) Sl.No .25 SS item 33a 505.00 1 Cum
185 Aggregates 10mm nominal size (HBG) Sl.No.26 SS item 33b 657.00 1 Cum
186 Aggregates 13.20 / 12.50mm nominal size
(HBG) Sl.No.27 SS item 33c 781.00 1 Cum
187 Aggregates 20mm nominal size (HBG) Sl.No.28 SS item 33d 870.00 1 Cum
188 Aggregates 40mm nominal size (HBG) Sl.No.30 SS item 33f 505.00 1 Cum
189
Gelatin 80% 37 M - 104 73.00 1 Kg
190
Water charges(Urban) 240 M - 189(a) 98.00 1 KL
191
Water charges(Rural) 239 R&B 73.00 1 KL
Common SoR 2014-15 Page-24
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
192
PH Items
PVC pipes 110mm dia.(4.00Kgs/sq.cm) Table18 202.00 1 RM
193
MS Z Hold fasts - 300 mm long of 40 x 40 x 5
mm ISA 101 TBSC-P.IX-08 32.00 1 No.
Common SoR 2014-15 Page-25
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
194 Hire &
Crew
Machinery Charges Common SSR Fuel
charges
charges
a)
Air compressor 7 cmm ( diesel) 3 983.90 1 hour 222.10
b)
Batching plant 0.50 cum (6 cum/hour) 9 237.10 1 hour 359.40
c) Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 16 135.20 1 hour 231.40
d)
Jack hammer 39 19.90 1 hour 347.10
e)
Needle vibrator 40mm( petrol) 40 25.10 1 hour 166.60
f)
Shovel 0.85 cum 110hp 52 2542.1 1 hour 249.60
g) Lift charges of materials(Winch 35HP-
Electric) 66 341.70 1 hour 277.70
195
Seigniorage charges
i)
Coarse aggregate , stone 75.00 1 cum
ii)
Earth , Gravel 30.00 1 cum
ii)
Sand for mortar & filling 40.00 1 cum
iv)
Bricks 60.00 1000 Nos.
v)
Polished Shahabad/Tandur stone slbs 8.00 1 sqm
vi)
Black Kadapa slabs 8.00 1 sqm
vii)
Granite 32.73 1 sqm
196
Rough Stone (OTG) (Part II) Sl.No.1 152.00 1 cum
197 Roads &
Rough Stone (HBG) Sl.No.12 239.00 1 cum
Bridges
198 Drilling 20mm dia. Holes with pneumatic
2016-17
compressor Sl.No.140 133.00 1 RM
Reference
Sl. S.No./ Item
Items to SoR Rate Unit
No Code No.
page
14 Powder coated handles 100mm long 30.00 1 No.
15
Labour charges including cost of nails,
making holes to wall and in aluminium sheet
for expansion joint 25.00 1 No.
16 Providing specialized polysulphide sealant
treatment to the expansion joints 105 TBSC-Q.VII-07 675.00 1 RM
17 Labour charges for cup board shutters and
fixing fixtures 800.00 1 sqm
18 Cup board locks 100.00 1 No.
19
Al. lock with handle 55.00 1 No.
20 Cement Jally 50mm thick 402.00 1 Sqm
Common SoR 2014-15 Page-27
Common SoR 2014-15 Page-28
Steel scaffolding pipes , jack props , wallers , Foot plates , brackets , steel centering plates etc.,
Common SoR 2014-15 Page-29
1 Cum
.66M -centering using Steel scaffolding pipes , jack props , wallers , Foot plates , brackets , steel centering
plates etc.,
5th 6th
7th 8th 9th 10th 11th
Floor Floor
2153.0 2307.0 2461.0 2615.0 2768.0 2922.0 3076.0 1 Cum
2600.5
NAME OF THE WORK : Construction of IT -Tower including Innovation Hub in Khanapur(V) shivar, Dist. Nizamabad
LEAD CHART (COMMON SoR 2017-2018) (Cement & Steel - MAR, 2018 rates)
MA
Initial Blasting Crushing
Referenc Unloa
S.No./ Cost Charges charges( Convey- Seignor
Sl. Source of e to SSR Lead in ding
Description Item Unit excluding (as per R 25% over ance age Total
No. Materials page KM charg
Code No. seigniorage &B initial Charges charges
number es
charges Sl.No.36) cost) 25%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
Tipper hire charges per 5 Cum incl fuel & crew charges 924.10
Truck hire charges 10Ton incl fuel & crew charges 891.90
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
Khazipur Sand 27
9 Sand for filling 18 1 Cum 28.00 570.00 34.55 878.42
Quarry 273.87
10 2nd Class Bricks (23x11x7cm) local 14 TBSC-A.I-01 1000 Nos 15.00 5714.00 297.30 6011.30
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
Roads &
Aggregates 6mm nominal size Quarry at 13/0 Bridges
17 Sl.No .25 1 Cum 15.00 505.00 67.00 126.25 64.79 905.85
(HBG) Km Sircilla rd SS item
33a 142.82
Quarry at 13/0
18 RR Masonry Stone granite 22g 1 Cum 15.00 239.00 67.00 64.79 513.60
Km Sircilla rd
142.82
19 Gravel / Quarry spall Outskirt Sl.No. 90 34 1 Cum 15.00 98.00 25.92 266.73
142.82
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
GENERAL - ABSTRACT
CHIEF ENGINEER
NAME OF THE WORK : Construction of IT -Tower including Innovation Hub in
Khanapur(V) shivar, Dist. Nizamabad
SUMMARY
Sl.No. Description of Item Amount
9 VPCC (1:3:6)
a For Foundation
Alround the building for PCC Wall 1 254.500 0.305 0.600 46.57
Alround the Open to Sky 1 22.434 0.305 0.600 4.11
Alround the Cut Out 1 7.500 0.305 0.600 1.37
Alround the Duct at Stair case 1 8.000 0.305 0.600 1.46
Alround the PHC Duct 1 4.630 0.305 0.600 0.85
Alround the Lift- 1 & 2 2 8.000 0.305 0.600 2.93
Alround the Duct 1 8.000 0.305 0.600 1.46
Alround the Fire Duct 1 7.530 0.305 0.600 1.38
Alround the Ele Duct 1 6.000 0.305 0.600 1.10
Alround the Land scape 1 16.300 0.305 0.600 2.98
Alround the Ele. Duct 1 8.000 0.305 0.600 1.46
Alround the Fire duct 1 8.000 0.305 0.600 1.46
80.57
Say 81.00 Cum
b Pedestals
P 104 0.900 0.900 0.900 75.82
a GL to plinth level
C1 9 0.230 0.750 1.200 1.863
C2 7 0.300 0.450 1.200 1.134
C3 1 0.300 0.600 1.200 0.216
C4 22 0.380 0.680 1.200 6.822
C5 0.785 10 0.450 0.450 1.200 1.91
C6 15 0.450 0.750 1.200 6.075
C7 20 0.600 0.600 1.200 8.640
84 31.99
Say 32.00 Cum
16 Lintels
D1 9 1.960 0.225 0.175 0.695
D2 5 1.460 0.225 0.175 0.287
D3 6 1.360 0.225 0.175 0.321
Lift Opening 2 1.360 0.225 0.175 0.107
D3 7 1.210 0.100 0.150 0.127
1.54
Say 2.00 Cum
17 Sill Slabs
Ampitheatre back 1 3.970 0.225 0.050 0.04
Ampitheatre side 1 6.590 0.225 0.050 0.07
innovation hall 1 8.730 0.225 0.050 0.10
innovation hall 1 2.810 0.225 0.050 0.03
Skill development Class-1 1 4.780 0.225 0.050 0.05
Skill development Class-2 1 4.780 0.225 0.050 0.05
Faculty Room 1 1.180 0.225 0.050 0.01
out door Innovative group activities 1 18.390 0.225 0.050 0.21
learning centre /Innovative group activities 1 7.000 0.225 0.050 0.08
learning centre /Innovative group activities 2 5.710 0.225 0.050 0.13
External Staircase 1 3.000 0.225 0.050 0.03
learning centre /Innovative soft skills 1 8.500 0.225 0.050
training 0.10
learning centre /Innovative soft skills 2 6.000 0.225 0.050
training 0.14
Toilet block 1 5.500 0.225 0.050 0.06
Toilet block 1 4.040 0.225 0.050 0.05
Cafeteria 1 8.710 0.225 0.050 0.10
Cafeteria 1 5.940 0.225 0.050 0.07
Conference Room/Audio visual 1 5.520 0.225 0.050
Room/Lecture Hall 0.06
Conference Room/Audio visual 1 6.310 0.225 0.050
Room/Lecture Hall 0.07
Main Entrance lobby 1 2.500 0.225 0.050 0.03
Office 1 4.700 0.225 0.050 0.05
Skill development Class-1 1 3.780 0.225 0.050 0.04
Skill development Class-2 1 3.780 0.225 0.050 0.04
Faculty room 1 1.680 0.225 0.050 0.02
Main Door 1 5.580 0.225 0.050 0.06
Lobby near external staircase 1 4.460 0.225 0.050 0.05
Lobby near external staircase 1 4.660 0.225 0.050 0.05
1.803
Say 2.00 Cum
18 Platforms
Pantry 1 4.450 0.600 2.670
Cafeteria 1 8.200 0.600 4.920
Kitchen 1 5.700 0.600 3.420
G.Toilet 1 1.760 0.600 1.056
L.Toilet 1 1.760 0.600 1.056
24 HYSD STEEL
Column Footings 788.0 100.000 Kgs/Cum 78800.00
Pedestals 76.00 125.000 Kgs/Cum 9500.00
Columns 196.00 350.000 Kgs/Cum 68600.00
Plinth Beams 110.00 125.000 Kgs/Cum 13750.00
230mm thick Retaining wall 64.0 130.000 0.230 Kgs/Cum 1913.60
Roof Beams 173.0 350.000 Kgs/Cum 60550.00
Roof Slab 125 mm thick 108.0 100.000 0.125 Kgs/Cum 1350.00
Roof Slab 150 mm thick 909.0 100.000 0.150 Kgs/Cum 13635.00
175mm thick waist slab 63.00 100.000 0.175 Kgs/Cum 1102.50
175mm thick Roof slab 404.0 100.000 0.175 Kgs/Cum 7070.00
Lintels 2.00 100.000 Kgs/Cum 200.00
256471.100
Say 256.47 MT
25 Mild Steel
RBM 33.00 2.000 Kgs/Sqm 66.00
Platform 14.00 3.000 Kgs/Sqm 42.00
Loft 3.00 3.000 Kgs/Sqm 9.00
Sill slab 2.00 3.000 Kgs/Cum 6.00
31 Non-Skid Flooring
Gents Toilet
W.C 2 1.430 1.200 3.43
Infront of W.C 1 2.540 2.060 5.23
At Hand Wash 1 3.730 1.760 6.56
Janitor Room 1 2.000 2.400 4.80
Infront of Janitor Room 1 3.500 1.600 5.60
L. Toilet
W.C 4 1.430 1.200 6.86
Infront of W.C 1 1.500 2.540 3.81
At Hand Wash 1 3.000 1.760 5.28
PH Toilet 1 3.000 2.500 7.50
Faculty Room toilet 1 1.500 1.100 1.65
50.73
Say 51.00 Sqm
34 Granolithic flooring
Amphitheater 1 30.100 30.10
Say 31.00 Sqm
External cladding
S-W Right
Entry
Alco panel
verticals sides 2 3.750 3.000 22.500
verticals face 1 0.300 3.000 0.900
Ceiling 2 5.660 3.750 42.450
ceiling -face 1 5.660 0.300 1.698
ceiling -sides 1 3.750 0.300 1.125
Ampithere sides 1 5.870 5.000 29.350
Ampithere sides 1 6.630 5.000 33.150
Ampithere sides 1 6.630 5.000 33.150
Ampitheatre back 1 3.970 0.600 2.382
Ampitheatre side 1 6.590 0.600 3.954
innovation hall 1 8.960 0.600 5.376
innovation hall 2 2.510 0.600 3.012
Skill development Class-1 1 4.780 0.600 2.868
Skill development Class-2 1 4.780 0.600 2.868
Faculty Room 1 1.180 0.600 0.708
learning centre 1 7.000 0.600 4.200
learning centre 2 5.710 0.600 6.852
Staircase 1 3.000 0.600 1.800
learning centre 1 8.500 0.600 5.100
learning centre 2 6.000 0.600 7.200
Toilet block 1 10.230 0.600 6.138
Cafeteria 1 8.600 0.600 5.160
Conference Room 1 5.520 0.600 3.312
Conference Room 1 6.310 0.600 3.786
Main Entrance lobby 1 2.500 0.600 1.500
230.54
SAY 231.00 SQM
36 Dadooing
Gents Toilet
W.C 2 5.260 2.100 22.09
G.Toilet 1 16.000 2.100 33.60
Janitor Room 1 8.800 2.100 18.48
Infront of Janitor Room 1 10.200 2.100 21.42
Ded passage -1 2.000 2.100 -4.20
L. Toilet
W.C 4 5.260 2.100 44.18
L. Toilet 1 14.600 2.100 30.66
PH Toilet 1 11.000 2.100 23.10
Faculty Room toilet 1 5.200 2.100 10.92
Deductions
D3 -7 0.750 2.100 11.03
D2 -3 0.900 2.100 5.67
216.95
Say 217.00 Sqm
D
Cafeteria 1 2.250 2.600 5.85
Say 5.90 Sqm
D1- 1.5 x 2.6
Conference Hall/Audio Visual class Room
2
Learning center/ Innovative Soft skills 3
Office 1
Innovation Hall 1
Electrical Room 1
Windows
Ampitheatre back 1 3.970 4.100 16.277
Ampitheatre side 1 6.590 4.100 27.019
innovation hall 1 8.730 4.250 37.103
innovation hall 1 2.810 4.100 11.521
Skill development Class-1 1 4.780 4.100 19.598
Skill development Class-2 1 4.780 4.100 19.598
Faculty Room 1 1.180 4.100 4.838
out door Innovative group activities 1 18.390 4.100 75.399
learning centre /Innovative group activities 1 7.000 4.100 28.700
learning centre /Innovative group activities 2 5.710 4.100 46.822
External Staircase 1 3.000 5.000 15.000
learning centre /Innovative soft skills 1 8.500 4.100 34.850
training
learning centre /Innovative soft skills 2 6.000 4.100 49.200
training
Toilet block 1 5.500 1.200 6.600
Toilet block 1 4.040 1.200 4.848
Cafeteria 1 8.710 4.100 35.711
Cafeteria 1 5.940 4.100 24.354
Conference Room/Audio visual 1 5.520 4.100 22.632
Room/Lecture Hall
Conference Room/Audio visual 1 6.310 4.100 25.871
Room/Lecture Hall
Main Entrance lobby 1 2.500 4.100 10.250
Office 1 4.700 4.100 19.270
Skill development Class-1 1 3.780 4.100 15.498
Skill development Class-2 1 3.780 4.100 15.498
Faculty room 1 1.680 4.100 6.888
Main Door 1 5.580 4.250 23.715
Lobby near external staircase 1 4.460 4.100 18.286
Lobby near external staircase 1 4.660 4.100 19.106
634.45
51 SS railing
Staircase 3 3 5.412 1.000 48.71
3 1 0.400 1.000 1.20
at Main Entrance 1 2 3.780 1.000 7.56
Ramp at Main entrance 1 1 4.250 1.000 4.25
Ramp at Main entrance 1 1 1.150 1.000 1.15
Ramp at Main entrance 1 1 3.000 1.000 3.00
External staircase lobby 1 1 0.830 1.000 0.83
External staircase lobby 1 1 1.280 1.000 1.28
67.98
Say 68.00 Sqm
Fixed Partitions
Innovation Hall
Room-1 & 2 1.00 2 3.500 4.250 29.75
Room-3 & 4 1.00 2 2.650 4.250 22.53
52.28
Say 53.00 Sqm
52 MS Pergola
4" x 8" pergola & Elevation, power coated
at 1' 6" c/c of 5mm thick 22.26 Kg/RM
Front (South )
Entry
verticals 26 6.75 175.500
verticals 21 1.9 39.900
Horizontals 6 18.000 108.000
Horizontals 15 12.400 186.000
Total weight for all floors and all bloks 14 4 2 552 61824 Kgs
61.82 MT
Safety / Elevation members 4" x 8" of
5mm thick 22.26 Kg/RM
between blocks
Total area for all floors and all bloks 14 4 2 6.60 739.2
Say 740.000 Sqm
Safety / Elevation members 4" x 8" of
5mm thick 22.26 Kg/RM
between blocks
S&F windows
W3 2 1.200 1.200 2.88
Say 3.00 Sqm
11 White cement paint for ceiling
Same as ceiling plastering 83.02
Say 84.00 Sqm
12 Plastic emulsion Paint for Internal Wall
16 Impervious coat
Columns
un supported height up to 4.27 m
a Ground Floor 4.07 CUM 12296.26 50046.0
a) Roof beams
un supported height up to 4.27 m 3.52 CUM 11701.75 41190.0
5 Granolithic Concrete flooring 20 mm thick with (1:1:2), using 75.00 Sqm 364.97 27373.0
6mm to 12 mm size hard granite machine crushed metal and
screened sand laid over CC bed already laid or RCC roof slab,
in alternate panels of size not exceeding 1.50 m x 1.50 m,
using glass strips and finishing the top surface to required
smoothness and slopes and thread lining including cost of all
materials like cement, metal sand and water and overheads &
contractors profit complete for finished item of work. (APSS
No.701 & 710)
7 Supply & fixing of Rolling shutter made of 80 x 1.25 mm 6.30 SQM 4017.43 25310.0
machine rolled CRCA laths, interlocked together through their
entire length and jointed together at the ends by end-locks,
mounted on specially designed pipe shaft of 50mm dia
nominal bore MS B class pipe with brackets, plates, guide
channels, stoppers, bottom locking plates and arrangements
for inside & outside locking with push-pull operations including
cost of hood cover and springs complete, painted with one
coat of approved steel primer, locks, ball bearings, all
accessories etc., overheads & contractors profit complete for
finished item of work as per special spn: 1108
8 Supplying and fixing of Unplasticised Poly Vinyl Chloride 5.67 SQM 7242.96 41068.0
(UPVC) sliding windows two track sliding duly manufactured
using UPVC reinforced profiles of (62 mm x 60 mm)/(60 mm x
45 mm)/ (60 mm x 52 mm) x 2.0 mm for outer frames, (66 mm
x 38 mm)/(58 mm x 39 mm)/ (60 mm x 42 mm) x 2.0 mm for
sliding shutter frames capable of mounting single glazing
system, structurally reinforced with hot dip galvanized up to 50
microns of minimum thickness of 1.2 mm prefabricated &
welded through fusion welding the window sash shall be fitted
with 5 mm thick clear float glass of reputed make duly fixed
with TPV Gaskets/ EPDM weathering seal resistant
accessories like locking system 1 No., per set of sashes and
the system is to be installed at the site using anchor fasteners,
silicon rubber sealant, easy glazing/ deglazing at site etc.,
including cost and conveyance of all materials, accessories,
labour charges for transportation, erection at site with
templates for casement sizing, overheads and contractors
profit etc., complete for finished item of work
9 Supplying and fixing of MS Grill to windows using 25mm x 5.67 SQM 964.35 5468.0
6mm MS flat alround and 10mm MS square bars horizontally
at 125mm centre to centre and vertically at 30cm centre to
centre including fixing with 4 Nos of MS Z holdfasts (2 on
each side) duly making cutting brick masonry, fixing and
making to original surface neatly and painting grill with one
coat of red oxide primer including cost all taxes and
conveyance of all materials including cutting, bending, welding
including all operational charges and all labour charges etc.,
complete for finished item of work.
10 Painting two coats with synthetic enamel paint Grade-II VOC 25.00 SQM 159.78 3994.0
(Volatile Organic Compound) content less than 50 grams/litre
over primer coat of red oxide to new iron work including cost
and conveyance of all materials to site, sales & other taxes,
incidental, operational and all labour charges etc., and
overheads & contractors profit ,all taxes except GST complete
for finished item of work in all floors. (SS No. 1201, 1212 &
1207).
11 Providing 110 mm Dia ISI marked PVC down water take pipes 5.00 RM 347.43 1737.0
with socket , 2.5mm thick 4.0 kg/sq.cm pressure of ISI marked
including cost of necessary PVC Bends, shoes, iron / PVC
clamps and all other accessories and fixing in position
including cost and conveyance of all materials, sales & all
taxes except GST on all materials to site, operational &
incidental charges including all labour charges for fixing at site
etc., and overheads & contractors profit etc., complete for
finished item of work. (APSS No. 1328).
12 Providing and Fixing M.S. Chequered Plates of approved 1131.00 Kg 100.89 114107.0
thickness with MS angles of approved sizes for cable trenches
and wherever required, at all levels, etc, complete, as per
standard specifications / approved detailed drawings including
cutting, welding, hoisting & including cost and conveyance of
all materials, all taxes except GST, labour charges for
fabrication erection at site work etc., complete and as directed
by engineer-in-charge.
193 530278.0
TP @ Excess 1.98% 10500
540778
b Pump Roof beams upto 3.66 mts level 2.73 CUM 11093.5
c Sump Roof Slab 150 mm thick upto an unsupported height 58.74 Sqm 1449.65
of 3.66 mts level
d Pump Room Roof Slab 125 mm thick upto an unsupported 56.78 Sqm 1327.01
height of 3.66 mts level
4 Providing impervious coat to exposed RCC roof slab 368.00 Sqm 160.15
surfaces of sump , sump side wall,sump bottom slab,in
side of septic tank , in sunken slabs etc. to required
slopes with CM (1:3) prop. using screened sand 12mm thick
mixed with integral cement water proofing liquid confirming
to IS: 2645-2003 manufactured by reputed manufacturers as
approved by Engineer-in-charge at 1 Kg per one bag of
cement, laid over roof slab when it is green, finished smooth
with a floating coat of neat cement and thread lining at
regular intervals of 45cmx45cm where ever necessary
including cost and conveyance of all materials like cement,
sand, water proofing compound, water etc., to site, including
seignorge charges, sales & other taxes except GST on all
materials and operational, incidental, and labour charges for
mixing mortar, laying, lift charges, rendering smooth and
thread lining, curing including rounding off junctions of wall
and slab etc., and overheads & contractors profit etc
complete for finished item of work. (APSS No. 901 & 903).
5 Providing impervious coat to exposed RCC roof slab 114.00 Sqm 473.57
surfaces to required slopes with CM (1:3) prop. using
screened sand 20mm thick (average) mixed with integral
cement water proofing liquid confirming to IS: 2645-2003
manufactured by reputed manufacturers as approved by
Engineer-in-charge at 0.40 litres per 10.00sqm of roof area,
laid over roof slab when it is green, finished smooth with a
floating coat of neat cement slurry and thread lining at
regular intervals of 45cmx45cm including cost and
conveyance of all materials like cement, sand, water
proofing compound, water etc., to site, including seigniorge
charges, sales & all other taxes except GSTon all materials
and operational, incidental, and labour charges for mixing
mortar, laying, lift charges, rendering smooth and thread
lining, curing including rounding off junctions of wall and slab
etc., and overheads & contractors profit complete for
finished item of work. (APSS No. 901 & 903).
#REF! Supply & fixing of Rolling shutter made of 80 x 1.25 mm 5.10 SQM 4017.43
machine rolled CRCA laths, interlocked together through
their entire length and jointed together at the ends by end-
locks, mounted on specially designed pipe shaft of 50mm
dia nominal bore MS B class pipe with brackets, plates,
guide channels, stoppers, bottom locking plates and
arrangements for inside & outside locking with push-pull
operations including cost of hood cover and springs
complete, painted with one coat of approved steel primer,
locks, ball bearings, all accessories etc., overheads &
contractors profit complete for finished item of work as per
special spn: 1108
#REF! Painting two coats with synthetic enamel paint Grade-II VOC 11.00 SQM 159.78
(Volatile Organic Compound) content less than 50
grams/litre over primer coat of red oxide to new iron work
including cost and conveyance of all materials to site, sales
& other taxes, incidental, operational and all labour charges
etc., and overheads & contractors profit ,all taxes except
GST complete for finished item of work in all floors. (SS No.
1201, 1212 & 1207).
#REF! Supply & application of one coat water based Cement Err:509 SQM 159.39
Primer of Interior Grade-1 and two coats of acrylic emulsion
paint interior grade having VOC (Volatile Organic
Compound) content less than 50 grams/ liter for internal
walls including cost and conveyance of all materials to site,
sales & other taxes except GST, incidental, operational and
all labour charges etc.,and overheads & contractors profit
etc.,complete for finished item of work in all floors.
#REF! Supplying and fixing stainless steel hand railing, balustrade 9.00 SQM 5079.25
etc using 304 grade stainless steel pipes of 50 mm dia
nominal bore for hand railing at 3'0" high from base leveland
40mm dia nominal bore for vertical supports placed at
5'0"c/c and two numbers 25mm dia nominal bore for
horizontal pipes placed below hand railing pipe as per the
approved drawing including cost and conveyance of all
materials to site, buffing charges, polishing charges all taxes
except GST, over heads & contractors profit etc complete
using pipes with minimum weight of 4.57kg/Rmt for 50mm
dia, 3.61kg /Rmt for 40mm dia and 2.46kg/Rmt for 25mmdia,
complete for finished item of work.
#REF! Supply and placing in postion water stopper 8 - 10 mm thick 201.00 RM 460.14
310 mm wide including cost and conveyance of all materials
to site and sales and other taxes except GST on all
materials to site etc., complete for finished item of work
TP @ Excess 1.98%
Amount
1317577
40510
30285
85152
75341
58934
53987
20489
1758
Err:509
45713
92488
Err:509
Err:509
Err:509
6 SS Railing
Ist Flight 1 2.040 1.000 2.04
IInd Flight 1 4.080 1.000 4.08
Midlanding 1 2.500 1.000 2.50
8.62
Say 9.000 SQM
2 Providing and fixing of Expansion joint filler board for buildings, 9.00 SQM 416.00 3744.0
columns, beams and slabs 25 mm thick including cost and
conveyance of all materials to site, all incidental, operational,
labour charges etc.overheads & contractors profit complete for
finished item of work as per approved drawing for all floors
7 39325.0
TP @ Excess 1.98% 779
40104
462.8
Say 463.00 RM
1 Coping
above compound wall 1 463.00 0.150 0.075 5.21
above brick pillars 93 0.45 0.230 0.075 0.72
Expansion joint pillasters top 30 0.45 0.230 0.075 0.23
6.16
Say 7.00 cum
2 Providing and fixing of Mastic pad
above P.B 30 1.80 0.15 8.10
SAY 9.00 SQM
3 Providing Plain Cement Concrete (1:3:6) mix using 20mm size 200.00 CUM 1 ONE CUM 3692.38
HBG crushed stone aggregate and fine aggregate conforming
to table 1000-2 of MoRT&H including cost, conveyance of all
materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other
incidental and operational charges of all T&P etc., complete
for finished item of work as per MoRT&H specification
1500,1700, 2100 (5th Revision) and as directed by the
Engineer-in-Charge for base coarse below CC Pavement
excluding GST.
5 Supply and fixing of High Performance expansion joint filler 653.00 RM 1 ONE RM 240.91
board conforming to M.O.S.T " Silfex" Cpcell HD-100 of 25mm
thick to a depth of 175mm for expansion joints including
hipping clearing the expansion joint groove and pouring
bitumen including heating, etc including cost and conveyance
of all materials to site, all labour charges, as per direction of
engineer in charge, complete for finished item of work,
excluding GST
5 Plain Cement Concrete(1:4:8) mix using 40mm size hard 15.00 CUM 1 ONE CUM 3045.37
broken granite metal including cost and conveyance of all
materials to site, seigniorage, machine mixing charges, labour
charges, placing in position, levelling, vibrating, curing, etc.
complete for finished item of work as directed by the
Engineer-in-charge, excluding GST and Seigniorage charges
as per technical specification clause No.2100 of Morth.
6 Supply and fixing of M20 Grade Pre-Cast cement concrete 667.00 RM 1 ONE RM 645.83
kerb stone of size 600MM x 150MM x 450MM including cost
and conveyance of all materials like cement, sand, Water,
Kerb etc, to site, loading, unloading, kerb stone transportation
charges, labour charges for fixing kerb stone true to
alignment, mixing charges, jointing to full depth and width with
CM (1:4) proportion, curing, including all hire and operational
charges of T&P, all labour charges, complete for finished item
of work,except GST
7 Painting two coats after filling the surface with synthetic 200.00 SQM 1 ONE SQM 80.94
enamel paint in all shades on new plastered concrete surface
as per Technical Specification 800 of MORT&H (5th Revision)
and as directed by the Engineer-in-Charge.
381337
738477
1504878
157312
45681
430771
16189
3661126
72490
3733616
Parking
SW -Side of building 1 64.980 64.98
NW -Side of building 1 8.12 8.12
NW -Side of building 1 19.47 19.47
NW -Side of building 1 11.34 11.34
NW -Side of building 1 14.93 14.93
Add for variations 11.88
130.72
Say 131.00 RM
5 Expansion Joint
for Longitudinal 1x1 1 268.000 268.00
6 Providing impervious coat to exposed RCC roof slab 490.00 Sqm 160.15 78472.0
surfaces of sump , sump side wall,sump bottom slab,in
side of septic tank , in sunken slabs etc. to required slopes
with CM (1:3) prop. using screened sand 12mm thick mixed
with integral cement water proofing liquid confirming to IS:
2645-2003 manufactured by reputed manufacturers as
approved by Engineer-in-charge at 1 Kg per one bag of
cement, laid over roof slab when it is green, finished smooth
with a floating coat of neat cement and thread lining at regular
intervals of 45cmx45cm where ever necessary including cost
and conveyance of all materials like cement, sand, water
proofing compound, water etc., to site, including seignorge
charges, sales & other taxes except GST on all materials and
operational, incidental, and labour charges for mixing mortar,
laying, lift charges, rendering smooth and thread lining, curing
including rounding off junctions of wall and slab etc., and
overheads & contractors profit etc complete for finished item of
work. (APSS No. 901 & 903).
7 Supplying , laying , aligning & jointing of RCC Hume Pipes of 411.00 RM 490.05 201411.0
200mm dia NP3 class including all necessary fixtures like
collars of respective diameter including cost and convenyance
of all materilas to site,sales and all other taxes except GST on
all materials etc. , lifting, placing and fixing in position for
finished item of work.
9 Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 25.00 Each 4966.52 124163.0
prop. Masonry. Inspection chamber up to 914.4 mm (3'0") and
fitted with 100 thick perforated slab. including cost and
conveyance of all materials and all labour charges, overheads
& contractors profit etc., all taxes, except GST, complete for
finished item of work for all floors for Catch basin.
813 1374979.0
TP @ Excess 1.98% 27225
1402204
8 Plinth protection
alround the bldg 1 78.98 1.000 78.983
alround the bldg 1 116.83 1.000 116.832
195.815
Say 196.00 Sqm
FGL- 101.30
near septic tank 99.843
near sump 99.880
near parking shed (Front
side) 100.347
near Main gate 100.276
400.346
average ground level 100.087
a 101.60mm dia upto 914.40mm (3') depth Rmt 100.00 Rmt 480.59 48059.15 100.00 480.59 48059.145 0.00
b 152.40mm dia upto 914.40mm (3') depth Rmt 250.00 Rmt 715.77 178943.63 250.00 715.77 178943.625 0.00
c 203.20mm dia upto 1524mm (5') depth Rmt 300.00 Rmt 989.87 296961.21 300.00 989.87 296961.20625 0.00
2 Supplying and fixing of SWG Gully traps 150mm x Each 10 Each 676.01 6760.09 10 676.01 6760.09 0.00
100mm of ISI make confirming to IS 651 & 4127
with C.I grating & constructing cement brick
masonry in CM (1:6) prop., intermediate chamber
and fitted with 304.8 mm X 288.6 mm (12"x9") C.I
Frame with hinged cover of standard make as
approved including cost and conveyance of all
materials to site, labour charges,, overheads &
contractors profit etc., all taxes, except GST
complete for finished item of work.
4 Constructing 904.0 mm (3’0”) dia brick masonry Each 10 Each 8317.75 83177.54 10 8317.75 83177.54 0.00
inspection chamber as per IS - 4111: Part-1:1986
with cement mortar (1:6) prop using 2nd Class Clay
Bricks of 225 mm thick from approved source having
a minimum crushing strength of 5 N/sq.mm
including plastering with cement mortar 1:3 prop; ½”
thick both inside and outside fitted with 20” dia RCC
manhole covers and frames including excavating
pits up to a depth of 904 mm (3'-0") in all sorts of
soils (exculding rock) and laying cement conrete
(1:4:8) 150 mm thick using 40 mm HBG Metal and
P.C.C. 1:2:4 benching and channel 100 mm thick as
per Standard specification and including cost and
conveyance of all materials like cement, sand,
bricks, water etc., to site, cost of seigniorage
charges on all materials and all incidental and
operational, labour charges like mixing cement
mortar, constructing masonry, lift charges, curing
etc., overheads & contractors profit etc.,all taxes,
except GST, complete for finished item of work as
per Standard specification.
6 Supplying and fixing of 4" (101.6mm) multi floor trap Each 150 Each 162.47 24370.42 150 162.47 24370.42 0.00
with jali - UPVC/SWR pipe fittings as per site
requirements with standard practice for all floors
including cost and conveyance of all materials to
site, labour charges, , overheads & contractors profit
etc., all taxes, except GST complete for finished
item of work.
9 Supplying and fixing of stainless steel sink of size Each 35 Each 5053.60 176875.83 35 5053.60 176875.83 0.00
508.00mm x 457.2mm x 203.20mm, 1mm thick of
Indian make fixed on cantilever brackets including
supply and fixing 32mm dia nominal size C.P. waste
coupling, 30 mm nominal size dia PVC flexible
waste pipe of 914.4 mm length of Ist quality
including chiselling brick masonry wall and making
good & restoring to original surfaces, including cost
and conveyance of all materials to site, labour
charges etc overheads & contractors profit etc., all
taxes, except GST complete for finished item of
work in all floors
11 Supplying and fixing TV shape mirror with plastic Each 35 Each 529.45 18530.61 35 529.45 18530.61 0.00
frame of size 609.6mm x 457.2mm, plywood back
with NP screws 1st quality including cost and
conveyance of all materials, labour charges, ,
overheads & contractors profit all taxes except GST,
complete for finished item of work in all floors.
12 Supplying and fixing of 25 mm nominal size dia and Each 35 Each 169.29 5925.02 35 169.29 5925.02 0.00
609.6mm long aluminium anodized towel rod with
brackets and aluminium screws including cost and
conveyance of all materials,labour charges, ,
overheads & contractors profit all taxes, except
GST, complete for finished item of work.
13 S&F of Chromium plated finish stainless steel body Each 35 Each 899.83 31494.08 35 899.83 31494.08 0.00
Toilet paper holder with 10 years warranty including
cost and conveyance of all materials,labour
charges, , overheads & contractors profit all taxes,
except GST, complete for finished item of work.
15 Supplying and fixing Chromium plated finish brass Each 50 Each 3325.23 166261.35 50 3325.23 166261.35 0.00
body quarter turn Bibcock cum Health Faucet with
1m long tube and wall hook with 7 - 10 years
warranty with necessary fittings etc., complete
including cost and conveyance of all materials,
labour charges, overheads & contractor profit etc.,
all taxes, except GST complete for finished item of
work in all floors.
16 Supplying and fixing white glazed flat back half stall Each 50 Each 3372.95 168647.27 50 3372.95 168647.27 0.00
urinals of size 590 mm x 375 mm x 390 mm 1st
quality conforming to IS:2556-1995 with standard
C.P. Spreader fixed with screws complete Indian
make (HSW/Parry/Neycer) as approved by
Engineer-in-charge, including supply and fixing 15
mm nominal size PVC connection with brass union
nut C.P coated, 15 mm brass body CP finish self
closing tap push type conforming to IS 1711, 30 mm
nominal size dia PVC flexible waste pipe of 914.4
mm length of Ist quality including cost and
conveyance of all materials to site, labour charges
overheads & contractors profit etc., all taxes, except
GST complete for finished item of work for all floors.
a) 15.90mm OD pipe Rmt 124.00 Rmt 160.20 19864.45 124 160.20 19864.45 0.00
b) 22.20mm OD pipe Rmt 525.00 Rmt 195.42 102594.35 525 195.42 102594.35 0.00
c) 28.60mm OD pipe Rmt 256.00 Rmt 234.05 59916.01 256 234.05 59916.01 0.00
d) 34.90mm OD pipe Rmt 42.00 Rmt 319.26 13408.84 42 319.26 13408.84 0.00
e) 41.30mm OD pipe Rmt 97.00 Rmt 395.38 38351.88 97 395.38 38351.88 0.00
f) 54.00mm OD pipe Rmt 312.00 Rmt 577.16 180075.23 312 577.16 180075.23 0.00
a) 25mm Nominal bore Each 3 Each 1271.35 3814.06 3 1271.35 3814.06 0.00
b) 32mm Nominal bore Each 3 Each 1931.46 5794.37 3 1931.46 5794.37 0.01
c) 40mm Nominal bore Each 3 Each 2609.74 7829.21 3 2609.74 7829.21 0.00
d) 50mm Nominal bore Each 3 Each 3823.14 11469.43 3 3823.14 11469.43 0.00
e) 65mm Nominal bore Each 1 Each 5903.44 5903.44 1 5903.44 5903.44 0.00
21 Supplying & fixing Bronze Horizontal Check (Non Each 1 Each 2250.71 2250.71 1 2250.71 2250.71 0.00
return) Valve as per IS-778 I-class heavy duty - 40
mm NB S including cost and conveyance of all
materials, labour charges, overheads & contractors
profit etc., all taxes, except GST, complete for
finished item of work.
a) 75mmdia Rmt 259.00 Rmt 190.31 49289.03 259 190.31 49289.03 0.00
b) 110mmdia Rmt 259.00 Rmt 277.98 71997.29 259 277.98 71997.29 0.00
23 Construction of Brick masonry support for CPVC Each 85 Each 86.35 7339.53 85 86.35 7339.53 0.00
pipe of size 304.80mm x 228.60mm x 228.60 mm
with Brick in CM (1:6) prop including plastering and
finishing with 12mm thick in CM (1:5) including cost
and conveyance of all materials and all labour
charges, overheads & contractors profit etc., all
taxes, except GST, complete for finished item of
work for all floors.
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.18
0.00
0.18
2 European EWC
Ground Floor 10 10
FIrst Floor 10 10
Second Floor 10 10
Third Floor 10 10
Fourth Floor 10 10
Say 50 Nos
4 Soap dish
Ground Floor 17 17
FIrst Floor 17 17
Second Floor 17 17
Third Floor 17 17
Fourth Floor 17 17
Say 85 Nos
5 Mirrors
Ground Floor 7 7
FIrst Floor 7 7
Second Floor 7 7
Third Floor 7 7
Fourth Floor 7 7
Say 35 Nos
8 Health faucet
Ground Floor 10 10
FIrst Floor 10 10
Second Floor 10 10
Third Floor 10 10
Fourth Floor 10 10
Say 50 Nos
9 Urinals
Ground Floor 10 10
FIrst Floor 10 10
Second Floor 10 10
Third Floor 10 10
Fourth Floor 10 10
Say 50 Nos
10 Morble Partitions
Ground Floor 10 10
FIrst Floor 10 10
Second Floor 10 10
Third Floor 10 10
Fourth Floor 10 10
Say 50 Nos
11 Sinks
Ground Floor 7 7
FIrst Floor 7 7
Second Floor 7 7
Third Floor 7 7
Fourth Floor 7 7
Say 35 Nos
3 Inspection Chambers
10
Say 10 Nos
2 CPVC PIPES
Raising main
Domestic water
a) 50.30 OD pipe 1 50.0 50.0 Rmt
b) 28.60 OD pipe (For Drinking) 1 30.0 30.0 Rmt
3 Non-Return valve@Sump
Domestic water 1 1 Nos
1 No. brass tower bolt 150 mm long, 2 Nos. 150mm 1.58 ONE Sqm 7706.56 12138
long brass handles ,1 No. of Heavy duty mortice lock
6/7 levers (IS:2209) with brass heavy handles and 1 No
of Rubber door stop bushes including supplying and
fixing 1.20mm thick PVC sheet to full height of the
shutter inside including labour charges for fixing the
frame in position, fixing the shutter to the frame etc.,
including overheads & contractors profit etc., all taxes
but excluding GST complete for finished item of work as
per APSS 1001 & 1002. (The vertical frame of door shall
be embedded in flooring for depth of not less than
10mm) ( 750mm x 2100mm )
4 Supplying and fixing of MS Grill to windows using 1.44 ONE SQM 964.35 1389
25mm x 6mm MS flat alround and 10mm MS square
bars horizontally at 125mm centre to centre and
vertically at 30cm centre to centre including fixing with 4
Nos of MS Z holdfasts (2 on each side) duly making
cutting brick masonry, fixing and making to original
surface neatly and painting grill with one coat of red
oxide primer including cost all taxes and conveyance of
all materials including cutting, bending, welding
including all operational charges and all labour charges
etc., complete for finished item of work.
For Wicket gates and Main Gates 1.64 ONE MT 127154.12 208533
Ceiling
Ground Floor : Err:509 ONE SQM 159.39 Err:509
11 Painting to new wood work and flush shutters with 1.58 ONE SQM 186.93 294
lappam finish , over a primary coat and painting two
coats of synthetic enamel paint Grade-I VOC (Volatile
Organic Compound) content less than 50 grams/litre of
approved shade including cost and conveyance of all
materials to site cost of primer coat and all labour
charges etc. complete including applying sand paper on
lappam coats for neat finish including sales & other
taxes on cost of all materials etc., and overheads &
contractors profit,all taxes except GST complete in all
floors (APSS No.1200, 1207 & 1211).
### Doors
i) Doors
D1 (0.9X2.10) 1 0.900 2.100 1.890
1.890 Sqm
Wicket Gate
80 X 80X 4 Box section @ 9.22 Kg/ Rmt 1 8.080 9.220 74.498 Kgs
- alround
25 X 25 X 2.6 Box section @ 1.69 Kg/ 20 2.668 1.690 90.178 Kgs
Rmt
25 X 25 X 2.6 Box section @ 1.69 Kg/ 2 1.368 1.690 4.624 Kgs
Rmt
1562.768 Kgs
Add Wastage @ 5% 78.138 Kgs
1640.906 Kgs
Say 1.640 MT
Amount
S.No Description of Work Quantity Unit Rate
(Rs.)
1 Supplying, laying, filling, jointing and testing SWG SP-1 pipe of ISI
mark conforming to ISI 651 & 4127 with air tight Cement joints in
CM (1.5:1) prop. including excavation of trenches and socket pits
in any soil (except rock requiring blasting) and refilling with
watering and tamping to the required slope including cost and
conveyance of all materials to site and all labour charges,
overheads & contractor profit etc., all taxes, except GST complete
for finished item of work (APSS NO 1301 & 1318)
a) 203.20mm dia upto 1524mm (5') depth 156.00 Rmt 989.87 154419.83
b) 254mm dia upto 1524.0mm (5') depth 92.00 Rmt 1442.06 132669.37
2 Manholes
3' depth 8 8 Nos
5'depth 3 3 Nos
2 Roof beams
Horizontal
M30-O30 (TYP) 5 8.960 0.380 0.600 10.214
Deduction of C6 -6 0.450 0.380 0.600 -0.616
Deduction of C7 -2 0.600 0.380 0.600 -0.274
M18 to SB beam 1 6.600 0.230 0.275 0.417
SB Beam to N15 (TYP) 2 2.540 0.230 0.300 0.351
M1-O1 (TYP) 5 9.330 0.380 0.600 10.636
Deduction of C7 -6 0.600 0.380 0.600 -0.821
Deduction of C1 -1 0.230 0.380 0.600 -0.052
O22-P22 (Duct Beam) 1 2.000 0.230 0.450 0.207
P27 - Y 27 & P24-Y24 2 11.300 0.300 0.425 2.882
Deduction of C4 -6 0.380 0.300 0.425 -0.291
Deduction of C4 -1 0.680 0.300 0.425 -0.087
Deduction of C1 -2 0.230 0.300 0.425 -0.059
Secondary beam 1 3.500 0.300 0.425 0.446
duct beams 1 2.000 0.230 0.325 0.150
Lift beam 1 2.000 0.230 0.450 0.207
O21 -Y 21 1 13.400 0.230 0.300 0.925
Deduction of C6 -2 0.450 0.230 0.300 -0.062
Deduction of C1 -2 0.230 0.230 0.300 -0.032
Deduction of C4 -1 0.680 0.230 0.300 -0.047
P20 - U 20 & P15 - U 15 2 5.230 0.230 0.600 1.443
N15 - P 15 1 4.000 0.230 0.625 0.575
W17 - Z 17 1 5.500 0.230 0.300 0.380
Deduction of C3 -1 0.600 0.230 0.300 -0.041
Deduction of C4 -1 0.380 0.230 0.300 -0.026
W17- U14 9(Curved Beam ) 1 4.600 0.230 0.450 0.476
U 14 - X 14 (Typical) 2 5.200 0.230 0.300 0.718
Deduction of C4 -2 0.380 0.230 0.300 -0.052
Deduction of C4 -1 0.680 0.230 0.300 -0.047
O 14 - U 14 1 7.700 0.230 0.325 0.576
Deduction of C7 -1 0.600 0.230 0.325 -0.045
Deduction of C1 -2 0.230 0.230 0.325 -0.034
O 12 - Q 12 1 4.230 0.230 0.325 0.316
Q12 - U 12 1 3.000 0.230 0.300 0.207
O8-Q8 1 4.700 0.230 0.300 0.324
Deduction of C1 -3 0.230 0.230 0.300 -0.048
Q5 - U5 1 3.000 0.230 0.300 0.207
Y21 - Z 21 (TYP) 2 2.000 0.230 0.450 0.414
Y20 - Z20 1 2.000 0.230 0.300 0.138
Y14 - Z 14 1 2.540 0.230 0.300 0.175
Z29 - a 29 (TYP) 7 9.000 0.380 0.600 14.364
Deduction of C6 -2 0.450 0.380 0.600 -0.205
Deduction of C7 -4 0.600 0.380 0.600 -0.547
3 Roof Slab
i Roof Slab 150mm thick
Area as Per CAD at W-Z grids 1 71.421 71.421
Area as per Cad at Central cut out 1 29.811 29.811
Central Cut out -1 19.634 -19.634
M30-O30 x M30 -M21 1 8.960 16.460 147.482
M14-O14 x M14-M1 1 9.110 16.230 147.855
N21-P21 x N21-N20 1 4.415 2.000 8.830
U24-Y24 x U24-U21 1 5.708 5.724 32.673
Z29-a29 x Z29-Z20 1 8.960 16.459 147.473
Z20-a20 x Z20- Up to duct 1 6.600 2.000 13.200
a20-a16 x a20- Up to Duct 1 2.130 3.985 8.488
Z4-a4 x Z4-Z3 1 8.960 3.654 32.740
a20-c20 x Cantilaver Slab 1 4.690 2.960 13.882
Columns projections
C4 4 0.150 0.680 0.408
C4 1 0.150 0.450 0.068
C4 2 0.450 0.380 0.342
C6 2 0.212 0.515 0.218
C6 2 0.219 0.750 0.329
C7 2 0.219 0.600 0.263
Over Stair case Beams
Pantry side Stair case 1 3.000 0.230 0.690
Pantry side Stair case 1 5.630 0.230 1.295
Pantry side Stair case 1 3.639 0.230 0.837
Stair case at PHC 1 5.495 0.230 1.264
Stair case at PHC 1 2.545 0.230 0.585
Right side Stair case 1 5.390 0.230 1.240
Right side Stair case 1 5.500 0.450 2.475
Right side Stair case 1 3.830 0.300 1.149
645.38
Say 646.00 Sqm
5 Platforms
G.Toilet 1 1.760 0.600 1.056
L.Toilet 1 1.760 0.600 1.056
Pantry 1 4.570 0.600 2.742
4.85
Say 5.00 Sqm
6 Loft
Janitor Room 1 1.000 2.100 2.100
Say 3.00 Sqm
Shear walls
Elevation Projection
Left side block
Left side 2 0.900 3.250 5.85
Front side 2 0.900 3.250 5.85
Right side block
Left side 2 0.900 3.250 5.85
Front side 2 0.900 3.250 5.85
Rear block
Left side 2 0.900 3.250 5.85
Right side 2 0.900 3.250 5.85
35.10
Say 36.00 Sqm
Horizontal
Gents Toilet WC wall (TYP) 2 1.430 2.400 6.86
L.Toilet WC Walls (TYP) 3 1.430 2.400 10.30
Vertical
Gents WC wall (TYP) 1 2.550 2.400 6.12
L.Toilet WC vertical Wall 1 2.470 2.400 5.93
L.Toilet WC vertical Wall 1 2.540 2.400 6.10
Platform walls 5 0.600 0.900 2.70
Central cut-out 1 15.700 1.000 15.70
Parapet wall 1 54.770 1.000 54.77
Parapet wall 1 27.260 1.000 27.26
Deductions
D3 -6 0.750 2.100 -9.45
Lintels
D3 -6 1.210 0.150 -1.09
11 HYSD STEEL
Columns 85.00 350.000 Kgs/Cum 29750.00
Roof Beams 131.00 350.000 Kgs/Cum 45850.00
Roof Slab 125mm thick 83.03 100.000 0.125 Kgs/Cum 1037.93
Roof Slab 150mm thick 646.00 100.000 0.150 Kgs/Cum 9690.00
175mm thick waist slab 52.56 100.000 0.175 Kgs/Cum 919.80
Roof Slab 175mm thick 302.27 100.000 0.175 Kgs/Cum 5289.75
230mm thick shear walls 35.10 130.000 0.230 Kgs/Cum 1049.49
Lintels 1.00 100.000 Kgs/Cum 100.00
93686.98
Say 93.69 MT
12 Mild Steel
RBM 125.20 2.000 Kgs/Sqm 250.39
Platform 4.85 3.000 Kgs/Sqm 14.56
Lofts 3.00 3.000 Kgs/Sqm 9.00
273.95
Say 0.30 MT
14 Ceiling plastering
Qty. same Vitrified tile flooring 649.00
Qty. same Waist slab area 53.00
17 Non-Skid Flooring
G.toilets 1 3.700 4.300 15.91
Janitor Room 1 2.000 2.400 4.80
L.Toilets 1 4.500 2.400 10.80
Entry of L.Toilet 1 3.000 1.700 5.10
Lobby before G.Toilet, Ante Room and
L.Toilet 1 3.540 1.600 5.66
21 Dadooing
Gents Toilet
W.C 2 5.260 2.100 22.09
G.Toilet 1 16.000 2.100 33.60
Janitor Room 1 8.800 2.100 18.48
Infront of Janitor Room 1 10.200 2.100 21.42
Ded passage -1 2.000 2.100 -4.20
L. Toilet
W.C 4 5.260 2.100 44.18
L. Toilet 1 14.600 2.100 30.66
PH Toilet 1 11.000 2.100 23.10
Deductions
D3 -6 0.750 2.100 9.45
D2 -3 0.900 2.100 5.67
204.46
Say 205.00 Sqm
22 Granite Clading
Lift 1 2.230 3.850 8.59
b Risers
Stair cases - 1,2,3 3 28 1.410 0.15 17.77
Say 18.00 Sqm
34 Glazings
South West Side Office Room
Office Room 1 1 8.550 3.100 26.51
Office Room 1 1 6.560 3.100 20.34
Office Room 1 1 2.710 3.100 8.40
Office Room 1 1 8.320 3.100 25.79
South East Side Office Room
Office Room 1 1 7.980 3.100 24.74
Office Room 1 1 6.980 3.100 21.64
Office Room 1 1 2.710 3.100 8.40
Office Room 1 1 7.920 3.100 24.55
Pantry 1 4.690 3.100 14.54
Meeting Room 1 2.540 3.100 7.87
North East Side Office Room
Office Room 1 1 5.710 3.100 17.70
Office Room 1 1 6.690 3.100 20.74
Office Room 1 1 2.700 3.100 8.37
Office Room 1 1 6.690 3.100 20.74
Office Room 1 1 3.020 3.100 9.36
External Staircase 1 3.000 3.100 9.30
North West Side Office Room
Office Room 1 1 7.330 3.100 22.72
Office Room 1 1 2.710 3.100 8.40
Office Room 1 1 7.560 3.100 23.44
Toilet block 1 5.500 1.200 6.60
Toilet block 1 4.040 1.200 4.85
GYM 1 9.000 2.950 26.55
Meeting Room 1 2.210 2.950 6.52
368.06
Say 369.00 Sqm
Fixed Partitions
Cabin -1 &2 4.00 2 3.000 3.250 78.00
Server 4.00 1 2.000 3.250 26.00
Coffee & Drinking water 4.00 1 2.000 3.250 26.00
130.00
Say 130.00 Sqm
36 Impervious coat
over entrance lobby 1 276.140 276.14
Ded opening -1 45.500 -45.50
230.64
Say 231.00 Sqm
37 Impervious coat forToilets
G.toilets 1 3.700 4.300 15.91
Janitor Room 1 2.000 2.400 4.80
L.Toilets 1 4.500 2.400 10.80
Entry of L.Toilet 1 3.000 1.700 5.10
Lobby before G.Toilet, Ante Room and
L.Toilet 1 3.540 1.600 5.66
PH Toilets 1 3.000 2.500 7.50
49.77
Say 50.00 Sqm
38 PVC Downtake pipes
6 5.900 35.40
Say 36.00 Rm
Cupboards
Store in Office-1,2,3 & 4 4 5.500 2.100 46.200
46.200
Say 47.000 Sqm
Toughned glass at Parapet of 2nd Floor
Main entrance - Landscape 1 39.430 39.430
above Pergola 1 37.880 37.880
77.310
Say 78.000 Sqm
2 Roof beams
Horizontal
M30-O30 (TYP) 5 8.960 0.380 0.600 10.214
Deduction of C6 -6 0.450 0.380 0.600 -0.616
Deduction of C7 -2 0.600 0.380 0.600 -0.274
M18 to SB beam 1 6.600 0.230 0.275 0.417
SB Beam to N15 (TYP) 2 2.540 0.230 0.300 0.351
M1-O1 (TYP) 5 9.330 0.380 0.600 10.636
Deduction of C7 -6 0.600 0.380 0.600 -0.821
Deduction of C1 -1 0.230 0.380 0.600 -0.052
O22-P22 (Duct Beam) 1 2.000 0.230 0.450 0.207
P27 - Y 27 & P24-Y24 2 11.300 0.300 0.425 2.882
Deduction of C4 -6 0.380 0.300 0.425 -0.291
Deduction of C4 -1 0.680 0.300 0.425 -0.087
Deduction of C1 -2 0.230 0.300 0.425 -0.059
Secondary beam 1 3.500 0.300 0.425 0.446
duct beams 1 2.000 0.230 0.325 0.150
Lift beam 1 2.000 0.230 0.450 0.207
O21 -Y 21 1 13.400 0.230 0.300 0.925
Deduction of C6 -2 0.450 0.230 0.300 -0.062
Deduction of C1 -2 0.230 0.230 0.300 -0.032
Deduction of C4 -1 0.680 0.230 0.300 -0.047
P20 - U 20 & P15 - U 15 2 5.230 0.230 0.600 1.443
N15 - P 15 1 4.000 0.230 0.625 0.575
W17 - Z 17 1 5.500 0.230 0.300 0.380
Deduction of C3 -1 0.600 0.230 0.300 -0.041
Deduction of C4 -1 0.380 0.230 0.300 -0.026
W17- U14 9(Curved Beam ) 1 4.600 0.230 0.450 0.476
U 14 - X 14 (Typical) 2 5.200 0.230 0.300 0.718
Deduction of C4 -2 0.380 0.230 0.300 -0.052
Deduction of C4 -1 0.680 0.230 0.300 -0.047
O 14 - U 14 1 7.700 0.230 0.325 0.576
Deduction of C7 -1 0.600 0.230 0.325 -0.045
Deduction of C1 -2 0.230 0.230 0.325 -0.034
O 12 - Q 12 1 4.230 0.230 0.325 0.316
Q12 - U 12 1 3.000 0.230 0.300 0.207
O8-Q8 1 4.700 0.230 0.300 0.324
Deduction of C1 -3 0.230 0.230 0.300 -0.048
Q5 - U5 1 3.000 0.230 0.300 0.207
Y21 - Z 21 (TYP) 2 2.000 0.230 0.450 0.414
Y20 - Z20 1 2.000 0.230 0.300 0.138
Y14 - Z 14 1 2.540 0.230 0.300 0.175
Z29 - a 29 (TYP) 7 9.000 0.380 0.600 14.364
Deduction of C6 -2 0.450 0.380 0.600 -0.205
Deduction of C7 -4 0.600 0.380 0.600 -0.547
3 Roof Slab
i Roof Slab 150mm thick
Area as Per CAD at W-Z grids 1 71.421 71.421
Area as per Cad at Central cut out 1 29.811 29.811
Central Cut out -1 19.634 -19.634
M30-O30 x M30 -M21 1 8.960 16.460 147.482
M14-O14 x M14-M1 1 9.110 16.230 147.855
N21-P21 x N21-N20 1 4.415 2.000 8.830
U24-Y24 x U24-U21 1 5.708 5.724 32.673
Z29-a29 x Z29-Z20 1 8.960 16.459 147.473
Z20-a20 x Z20- Up to duct 1 6.600 2.000 13.200
a20-a16 x a20- Up to Duct 1 2.130 3.985 8.488
Z4-a4 x Z4-Z3 1 8.960 3.654 32.740
a20-c20 x Cantilaver Slab 1 4.690 2.960 13.882
Columns projections
C4 4 0.150 0.680 0.408
C4 1 0.150 0.450 0.068
C4 2 0.450 0.380 0.342
C6 2 0.212 0.515 0.218
C6 2 0.219 0.750 0.329
C7 2 0.219 0.600 0.263
Over Stair case Beams
Pantry side Stair case 1 3.000 0.230 0.690
Pantry side Stair case 1 5.630 0.230 1.295
Pantry side Stair case 1 3.639 0.230 0.837
Stair case at PHC 1 5.495 0.230 1.264
Stair case at PHC 1 2.545 0.230 0.585
Right side Stair case 1 5.390 0.230 1.240
Right side Stair case 1 5.500 0.450 2.475
Right side Stair case 1 3.830 0.300 1.149
645.38
Say 646.00 Sqm
Horizontal
Gents Toilet WC wall (TYP) 2 1.430 2.400 6.86
L.Toilet WC Walls (TYP) 3 1.430 2.400 10.30
Vertical
Gents WC wall (TYP) 1 2.550 2.400 6.12
L.Toilet WC vertical Wall 1 2.470 2.400 5.93
L.Toilet WC vertical Wall 1 2.540 2.400 6.10
Platform walls 5 0.600 0.900 2.70
Central cut-out 1 15.700 1.000 15.70
Deductions
D3 -6 0.750 2.100 -9.45
Lintels
D3 -6 1.210 0.150 -1.09
43.17
11 HYSD STEEL
Columns 85.00 350.000 Kgs/Cum 29750.00
Roof Beams 131.00 350.000 Kgs/Cum 45850.00
Roof Slab 125mm thick 83.03 100.000 0.125 Kgs/Cum 1037.93
Roof Slab 150mm thick 646.00 100.000 0.150 Kgs/Cum 9690.00
175mm thick waist slab 53.00 100.000 0.175 Kgs/Cum 927.50
Roof Slab 175mm thick 303.00 100.000 0.175 Kgs/Cum 5302.50
230mm thick shear walls 35.10 130.000 0.230 Kgs/Cum 1049.49
Lintels 1.00 100.000 Kgs/Cum 100.00
93707.42
Say 93.71 MT
12 Mild Steel
RBM 44.00 2.000Kgs/Sqm 88.00
Platform 4.85 3.000Kgs/Sqm 14.56
Lofts 3.00 3.000Kgs/Sqm 9.00
111.56
Say 0.20 MT
14 Ceiling plastering
Qty. same Vitrified tile flooring 649.00
Qty. same Waist slab area 53.00
16 Non-Skid Flooring
G.toilets 1 3.700 4.300 15.91
Janitor Room 1 2.000 2.400 4.80
L.Toilets 1 4.500 2.400 10.80
Entry of L.Toilet 1 3.000 1.700 5.10
Lobby before G.Toilet, Ante Room and
L.Toilet 1 3.540 1.600 5.66
20 Dadooing
Gents Toilet
W.C 2 5.260 2.100 22.09
G.Toilet 1 16.000 2.100 33.60
Janitor Room 1 8.800 2.100 18.48
Infront of Janitor Room 1 10.200 2.100 21.42
Ded passage -1 2.000 2.100 -4.20
L. Toilet
W.C 4 5.260 2.100 44.18
L. Toilet 1 14.600 2.100 30.66
PH Toilet 1 11.000 2.100 23.10
Deductions
D3 -6 0.750 2.100 9.45
D2 -3 0.900 2.100 5.67
204.46
Say 205.00 Sqm
21 Granite Clading
Glazing
South West Side Office Room
Office Room 1 1 8.550 3.100 26.51
Office Room 1 1 6.560 3.100 20.34
Office Room 1 1 2.710 3.100 8.40
Office Room 1 1 8.320 3.100 25.79
South East Side Office Room
Office Room 1 1 7.980 3.100 24.74
Office Room 1 1 6.980 3.100 21.64
Office Room 1 1 2.710 3.100 8.40
Office Room 1 1 7.920 3.100 24.55
Pantry 1 4.690 3.100 14.54
Meeting Room 1 2.540 3.100 7.87
North East Side Office Room
Office Room 1 1 5.710 3.100 17.70
Office Room 1 1 6.690 3.100 20.74
Office Room 1 1 2.700 3.100 8.37
Office Room 1 1 6.690 3.100 20.74
Office Room 1 1 3.020 3.100 9.36
External Staircase 1 3.000 3.100 9.30
North West Side Office Room
Office Room 1 1 7.330 3.100 22.72
Office Room 1 1 2.710 3.100 8.40
Office Room 1 1 7.560 3.100 23.44
Toilet block 1 5.500 1.200 6.60
Toilet block 1 4.040 1.200 4.85
Board Room 1 9.000 3.100 27.90
Meeting Room 1 2.210 3.100 6.85
369.75
Say 370.00 Sqm
33 SS railing
Staircase 3 2 4.652 1.000 27.91
3 1 0.400 1.000 1.20
Central cut-out 1 15.700 1.000 15.70
cut-out below land scape 1 9.550 1.000 9.55
External staircase lobby 1 6.960 1.000 6.96
61.32
Say 62.00 Sqm
Fixed Partitions
Cabin -1 &2 4.00 2 3.000 3.250 78.00
Server 4.00 1 2.000 3.250 26.00
Coffee & Drinking water 4.00 1 2.000 3.250 26.00
130.00
Say 130.00 Sqm
2 Roof beams
Horizontal
M30-O30 (TYP) 5 8.960 0.380 0.600 10.214
Deduction of C6 -6 0.450 0.380 0.600 -0.616
Deduction of C7 -2 0.600 0.380 0.600 -0.274
M18 to SB beam 1 6.600 0.230 0.275 0.417
SB Beam to N15 (TYP) 2 2.540 0.230 0.300 0.351
M1-O1 (TYP) 5 9.330 0.380 0.600 10.636
Deduction of C7 -6 0.600 0.380 0.600 -0.821
Deduction of C1 -1 0.230 0.380 0.600 -0.052
O22-P22 (Duct Beam) 1 2.000 0.230 0.450 0.207
P27 - Y 27 & P24-Y24 2 11.300 0.300 0.425 2.882
Deduction of C4 -6 0.380 0.300 0.425 -0.291
Deduction of C4 -1 0.680 0.300 0.425 -0.087
Deduction of C1 -2 0.230 0.300 0.425 -0.059
Secondary beam 1 3.500 0.300 0.425 0.446
duct beams 1 2.000 0.230 0.325 0.150
Lift beam 1 2.000 0.230 0.450 0.207
O21 -Y 21 1 13.400 0.230 0.300 0.925
Deduction of C6 -2 0.450 0.230 0.300 -0.062
Deduction of C1 -2 0.230 0.230 0.300 -0.032
Deduction of C4 -1 0.680 0.230 0.300 -0.047
P20 - U 20 & P15 - U 15 2 5.230 0.230 0.600 1.443
N15 - P 15 1 4.000 0.230 0.625 0.575
W17 - Z 17 1 5.500 0.230 0.300 0.380
Deduction of C3 -1 0.600 0.230 0.300 -0.041
Deduction of C4 -1 0.380 0.230 0.300 -0.026
W17- U14 9(Curved Beam ) 1 4.600 0.230 0.450 0.476
U 14 - X 14 (Typical) 2 5.200 0.230 0.300 0.718
Deduction of C4 -2 0.380 0.230 0.300 -0.052
Deduction of C4 -1 0.680 0.230 0.300 -0.047
O 14 - U 14 1 7.700 0.230 0.325 0.576
Deduction of C7 -1 0.600 0.230 0.325 -0.045
Deduction of C1 -2 0.230 0.230 0.325 -0.034
O 12 - Q 12 1 4.230 0.230 0.325 0.316
Q12 - U 12 1 3.000 0.230 0.300 0.207
O8-Q8 1 4.700 0.230 0.300 0.324
Deduction of C1 -3 0.230 0.230 0.300 -0.048
Q5 - U5 1 3.000 0.230 0.300 0.207
Y21 - Z 21 (TYP) 2 2.000 0.230 0.450 0.414
Y20 - Z20 1 2.000 0.230 0.300 0.138
Y14 - Z 14 1 2.540 0.230 0.300 0.175
Z29 - a 29 (TYP) 7 9.000 0.380 0.600 14.364
Deduction of C6 -2 0.450 0.380 0.600 -0.205
Deduction of C7 -4 0.600 0.380 0.600 -0.547
3 Roof Slab
i Roof Slab 150mm thick
Area as Per CAD at W-Z grids 1 71.421 71.421
Area as per Cad at Central cut out 1 29.811 29.811
Central Cut out -1 19.634 -19.634
M30-O30 x M30 -M21 1 8.960 16.460 147.482
M14-O14 x M14-M1 1 9.110 16.230 147.855
N21-P21 x N21-N20 1 4.415 2.000 8.830
U24-Y24 x U24-U21 1 5.708 5.724 32.673
Z29-a29 x Z29-Z20 1 8.960 16.459 147.473
Z20-a20 x Z20- Up to duct 1 6.600 2.000 13.200
a20-a16 x a20- Up to Duct 1 2.130 3.985 8.488
Z4-a4 x Z4-Z3 1 8.960 3.654 32.740
a20-c20 x Cantilaver Slab 1 4.690 2.960 13.882
Columns projections
C4 4 0.150 0.680 0.408
C4 1 0.150 0.450 0.068
C4 2 0.450 0.380 0.342
C6 2 0.212 0.515 0.218
C6 2 0.219 0.750 0.329
C7 2 0.219 0.600 0.263
Over Stair case Beams
Pantry side Stair case 1 3.000 0.230 0.690
Pantry side Stair case 1 5.630 0.230 1.295
Pantry side Stair case 1 3.639 0.230 0.837
Stair case at PHC 1 5.495 0.230 1.264
Stair case at PHC 1 2.545 0.230 0.585
Right side Stair case 1 5.390 0.230 1.240
Right side Stair case 1 5.500 0.450 2.475
Right side Stair case 1 3.830 0.300 1.149
645.38
Say 646.00 Sqm
5 Platforms
G.Toilet 1 1.760 0.600 1.056
L.Toilet 1 1.760 0.600 1.056
Pantry 1 4.570 0.600 2.742
4.85
Say 5.00 Sqm
6 Loft
Janitor Room 1 1.000 2.100 2.100
Say 3.00 Sqm
7 225 mm thick Fly ash block Block masonry
columns inner to inner
Horizontals
Office Entry Walls (TYP) clear 4 8.280 0.225 3.250 24.219
Office back side (TYP) 4 7.760 0.225 3.250 22.698
Duct wall (TYP) 1 2.000 0.225 3.550 1.598
Duct wall (TYP) 1 1.600 0.225 3.550 1.278
Janitor Horizontal wall 1 3.500 0.225 3.400 2.678
Gents Toilet wall 1 3.000 0.225 3.550 2.396
Lift wall (TYP) 4 2.000 0.225 3.550 6.390
AHU horizontal walls (TYP) 2 3.000 0.225 3.550 4.793
Toilets External walls (TYP) 1 11.300 0.225 3.400 8.645
Ded for col -3 0.380 0.225 3.400 -0.872
Ded for col -1 0.680 0.225 3.400 -0.520
Fire duct & Duct (TYP) 3 2.000 0.225 3.550 4.793
Ele Duct (TYP) 2 1.000 0.225 3.550 1.598
Stair case Lobby Wall 1 4.470 0.225 1.000 1.006
Stair case Back side wall 1 3.000 0.225 3.550 2.396
Pantry Cross wall 1 4.600 0.225 3.400 3.519
Pantry inside wall 1 4.480 0.225 3.550 3.578
Pantry wall external 1 4.690 0.225 3.550 3.746
Stair case Back side wall 1 3.000 0.225 3.550 2.396
Lift & Duct Walls (TYP) 5 2.000 0.225 3.550 7.988
Infront of Lift wall 1 2.230 0.225 3.550 1.781
Meeting Room 3 2.500 0.225 3.550 5.991
Verticals
Office- 1,2,3,4 8 16.460 0.225 3.525 104.44
Ded for col -24 0.750 0.225 3.525 -14.276
Ded for col -8 0.600 0.225 3.525 -3.807
Middle Stair case long walls 2 5.960 0.225 3.250 8.717
Ded for col -4 0.680 0.225 3.250 -1.989
Ext Stair case long walls 2 5.730 0.225 3.400 8.767
Ded for col -4 0.750 0.225 3.400 -2.295
Ext Stair case lobby wall 1 2.500 0.225 1.000 0.563
Stair case long walls 2 5.860 0.225 3.550 9.361
Ded for col -4 0.750 0.225 3.550 -2.396
Pantry short wall 1 2.000 0.225 3.550 1.598
Toilet walls 2 4.540 0.225 3.250 6.640
11 HYSD STEEL
Columns 85.00 350.000 Kgs/Cum 29750.00
Roof Beams 131.00 350.000 Kgs/Cum 45850.00
Roof Slab 125mm thick 84.00 100.000 0.125 Kgs/Cum 1050.00
Roof Slab 150mm thick 646.00 100.000 0.150 Kgs/Cum 9690.00
175mm thick waist slab 53.00 100.000 0.175 Kgs/Cum 927.50
Roof Slab 175mm thick 303.00 100.000 0.175 Kgs/Cum 5302.50
230mm thick shear walls 35.10 130.000 0.230 Kgs/Cum 1049.49
Lintels 1.00 100.000 Kgs/Cum 100.00
93719
Say 93.72 MT
12 Mild Steel
RBM 44.00 2.000Kgs/Sqm 88.00
Platform 4.85 3.000Kgs/Sqm 14.56
Loft 2.10 3.000Kgs/Sqm 6.30
108.86
Say 0.20 MT
14 Ceiling plastering
Qty. same Vitrified tile flooring 609.00
Qty. same Waist slab area 53.00
Qty. same Polished granite flooring 171.00
Qty. same Non- Skid flooring 50.00
883.00
Say 883.00 Sqm
20 Dadooing
Gents Toilet
W.C 2 5.260 2.100 22.09
G.Toilet 1 16.000 2.100 33.60
Janitor Room 1 8.800 2.100 18.48
Infront of Janitor Room 1 10.200 2.100 21.42
Ded passage -1 2.000 2.100 -4.20
L. Toilet
W.C 4 5.260 2.100 44.18
L. Toilet 1 14.600 2.100 30.66
PH Toilet 1 11.000 2.100 23.10
21 Granite Clading
Lift 1 2.230 3.850 8.59
Fire duct (L-shape) 1 4.230 3.850 16.29
Deduction of Opening -1 0.900 2.100 -1.89
22.98
Say 23.00 Sqm
22 Polished Granite slabs
a Treads
Stair cases - 1,2,3 3 26 1.410 0.30 32.99
Say 33.00 Sqm
b Risers
Stair cases - 1,2,3 3 28 1.410 0.15 17.77
Say 18.00 Sqm
23 Polished Granite slabs
Qty same as platforms 4.854
Say 5.00 Sqm
High Polished granite stone for Sill Slabs
South West Side Office Room
Office Room 1 1 8.550 0.225 1.92
Office Room 1 1 6.560 0.225 1.48
Office Room 1 1 2.710 0.225 0.61
Office Room 1 1 8.320 0.225 1.87
South East Side Office Room
Office Room 1 1 7.980 0.225 1.80
Office Room 1 1 6.980 0.225 1.57
Office Room 1 1 2.710 0.225 0.61
Office Room 1 1 7.920 0.225 1.78
Pantry 1 4.690 0.225 1.06
Meeting Room 1 2.540 0.225 0.57
North East Side Office Room
Office Room 1 1 5.710 0.225 1.28
Office Room 1 1 6.690 0.225 1.51
Office Room 1 1 2.700 0.225 0.61
Office Room 1 1 6.690 0.225 1.51
Office Room 1 1 3.020 0.225 0.68
External Staircase 1 3.000 0.225 0.68
North West Side Office Room
Office Room 1 1 7.330 0.225 1.65
Office Room 1 1 2.710 0.225 0.61
Office Room 1 1 7.560 0.225 1.70
Toilet block 1 5.500 0.225 1.24
Toilet block 1 4.040 0.225 0.91
Meeting Room 1 2.170 3.100 6.73
Meeting Room 1 2.210 3.100 6.85
39.21
Say 40.00 Sqm
24 White cement paint for ceiling
Same as ceiling plastering 883.00
883.00
Say 883.00 Sqm
27 False Ceiling
Office Room 4 8.500 16.000 544.00
AHU 1 3.000 5.500 16.50
Meeting Room 1 2.500 3.500 8.75
Pantry 1 30.000 30.00
Meeting Room 1 2.570 3.500 9.00
Lobby 1 117.580 117.58
Ded cut-out portion in lobby -1 19.630 -19.63
Lobby before PH Toilet and AHU Room 1 2.000 5.940 11.88
Passage from Fire duct to staircase 1 15.640 1.870 29.25
before Meeting Room 1 2.340 1.120 2.62
before Office Room 1 2.250 1.120 2.52
before Lift 1 2.220 2.000 4.44
G.toilets 1 3.700 4.300 15.91
Janitor Room 1 2.000 2.400 4.80
L.Toilets 1 4.500 2.400 10.80
Entry of L.Toilet 1 3.000 1.700 5.10
Lobby before G.Toilet, Ante Room and L.Toilet 1 3.540 1.600 5.66
PH Toilets 1 3.000 2.500 7.50
806.68
Say 807.00 Sqm
i Armstrong false ceiling
50% of above quantity 403.34
Say 404.00 Sqm
Glazing
South West Side Office Room
Office Room 1 1 8.550 3.100 26.51
Office Room 1 1 6.560 3.100 20.34
Office Room 1 1 2.710 3.100 8.40
Office Room 1 1 8.320 3.100 25.79
South East Side Office Room
Office Room 1 1 7.980 3.100 24.74
Office Room 1 1 6.980 3.100 21.64
Office Room 1 1 2.710 3.100 8.40
Office Room 1 1 7.920 3.100 24.55
Pantry 1 4.690 3.100 14.54
Meeting Room 1 2.540 3.100 7.87
North East Side Office Room
Office Room 1 1 5.710 3.100 17.70
Office Room 1 1 6.690 3.100 20.74
Office Room 1 1 2.700 3.100 8.37
Office Room 1 1 6.690 3.100 20.74
Office Room 1 1 3.020 3.100 9.36
External Staircase 1 3.000 3.100 9.30
North West Side Office Room
Office Room 1 1 7.330 3.100 22.72
Office Room 1 1 2.710 3.100 8.40
Office Room 1 1 7.560 3.100 23.44
Toilet block 1 5.500 1.200 6.60
Toilet block 1 4.040 1.200 4.85
Meeting Room 1 2.170 3.100 6.73
Meeting Room 1 2.210 3.100 6.85
348.57
Say 349.00 Sqm
Fixed Partitions
Cabin -1 &2 4.00 2 3.000 3.250 78.00
Server 4.00 1 2.000 3.250 26.00
Coffee & Drinking water 4.00 1 2.000 3.250 26.00
130.00
Say 130.00 Sqm
Bricks 0 60 0.00
NAME OF THE WORK :- Sump , Compound wall , security Room & Substation and supplemtal bldg
River
S.No Item Quantity Total Metal Gravel
Sand
gravel 0 30 0.00
14142.28
Seignorage charges
Brick
8842.2
8842.24
SUPPLEMENTAL D A T A (SoR 2017-18)
NAME OF THE WORK : Construction of IT -Tower including Innovation Hub in Khanapur(V) shivar, Dist.
Nizamabad
CEMENT MORTAR PER CUM CM (1:2) CM (1:3) CM (1:4) CM (1:5) CM (1:6) CM (1:8)
Cost of Sand for mortar & Plastering
( 1.05 cum ) 1121.84 1121.84 1121.84 1121.84 1121.84 1121.84
Cost of cement 3384.00 2256.00 1692.00 1353.60 1128.00 846.00
Mazdoor ( Unskilled ) for mixing
mortar ( 0.20 Nos.) 80.00 80.00 80.00 80.00 80.00 80.00
DATA
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
1 S1 Clearing Juliflora (Prosafis) jungle including up-rooting and removing of Juliflora stumps including
all labour charges.
Basic rate as per item No.112.d 1.00 SQM 3.50 1.00 SQM 3.50
Overheads&Contractors Profit @13. 0.13615 3.50 0.48
3.98
Add T.P @ 1.98% Exess 0.08
/1Sqm 4.06
2 S2 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and
depositing on bank for all lifts and with an initial lead of 10m and 3m to 6m depth including all
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads &
contractors profit complete for finished item of work excluding dewatering charges etc., as per SS 20
B(APSS 308)
(BLKD-CSTN-2-3)
Ordinary Soil - Mechanical Means up to 3m to 6m
depth
TSIIC-NIZAMABAD Civil Data 246 of 627
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Unit : 1 cum
Taking output : 210.00 cum
a) Labour
Mazdoor ( Unskilled) 8.32 Nos. 400.00 1 No. 3328.00
Add for MA @ 25% 0.25 3328.00 832.00
b) Machinery
Hydraulic Excavator 6.00 hours 2821.50 1 Hour 16929.00
21089.00
c&d)
Overheads&Contractors Profit @13. 0.13615 21089.00 2871.27
Cost for 210 cum ( a+b+c+d) 23960.27
Rate per 1 cum (a+b+c+d) / 210 114.10
Add T.P @ 1.98% Exess 2.26
/1Cum 116.36
3 S3 Brick masonry for panel walls in superstructure with CM (1:6) prop: (Cement : Screened sand) using
common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or traditional size 23 x
11 x 7 cms from approved source having minimum crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks, water etc., to site, including sales & other
taxes on all materials and such as labour charges, like mixing cement mortar, scaffolding charges,
constructing masonry, lift charges, curing, etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 501 & 504).
(BLD-CSTN-5-4)
Unit : 1cum
A.MATERIALS :
Cement 48.00 Kgs 4700.00 1000 Kgs 225.60
Common burnt clay bricks
23x11x7cms 512 Nos 6011.30 1000 Nos 3077.79
Fine aggregate ( Sand ) 0.20 cu.m. 1068.42 1 cu.m. 213.68
B.LABOUR :
1st class mason 0.24 Nos. 470.00 1 Each 112.80
2nd class mason 0.56 Nos. 425.00 1 Each 238.00
Mazdoor (Unskilled) 1.89 Nos. 400.00 1 Each 756.00
Add for MA @ 25% 0.25 1106.80 276.70
water charges @ 1% 0.01 4900.57 49.01
Rate per 1 cum 4949.58
a Up to basement
Rate as worked out above 1.00 Cum 4949.58 1 Cum 4949.58
Overheads&Contractors Profit 0.14 4949.58
@13.615% 673.88
Rate per 1 cum 5623.46
Say 5623
b) Superstructure :
Rate for other Floors FF SF TF 4F 5F 6F
Rate as worked out above 4949.58 4949.58 4949.58 4949.58 4949.58 4949.58
Hire charges for Access Scaffolding
44.87 44.87 44.87 44.87 44.87 44.87
Labour charges for scaffolding 329.04 471.13 613.22 755.30 897.39 1039.48
Add for MA @ 25% 82.26 117.78 153.31 188.83 224.35 259.87
Lift charges ( Page 131 of Std. 0.00 110.68 221.36 332.04 442.72 553.40
Data )
Add for MA @ 25% 0.00 27.67 55.34 83.01 110.68 138.35
4 S4 Reinforced cement concrete (1:5:10) proportion (Cement: fine aggregates: coarse aggregate) using
40mm size (SS5) hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water etc., to site
including centering using Casurina Ballies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates
etc., shuttering, machine mixing, laying concrete, lifting concrete manually , curing etc., and overheads &
contractors profit complete as per drawings but excluding cost of steel and it's fabrication charges for
finished item of work (APSS NO. 402 & 403) for Dummy columns.
(BLDS-CSTN-3-13)
Unit: 1 Cum
A.MATERIALS :
Cement 129.60 Kgs 4700.00 1000 Kgs 609.12
40mm HBG metal 0.90 Cum 905.85 1 Cum 815.27
Sand 0.45 Cum 878.42 1 Cum 395.29
B.LABOUR :
1st class Mason 0.1670 Nos 470.00 1 Each 78.49
2nd class Mason 0.167 Nos 425.00 1 Each 70.98
Mazdoor (both men&women) 4.70 Nos 400.00 1 Each 1880.00
Add for MA @ 25% 0.25 2029.47 507.37
C.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 1.00
cum)capacity hours 135.20 1 hour 135.20
Crew Charges 1.00 hours 231.40 1 hour 231.40
Add MA on crew charges 0.25 231.40 57.85
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 4898.56
a) COLUMNS :
un supported height up to 3.66 m
Rate for other Floors TF 4F 5F
Rate as above 4898.56 4898.56 4898.56
Hire charges of centering and
scaffolding 238.00 238.00 238.00
Labour charges 2175.00 2342.00 2510.00
Add for MA @ 25% 543.75 585.50 627.50
Lift charges of materials(Winch
35HP- Electric)
501.03 546.58 592.13
Crew charges 407.19 444.21 481.23
Add for MA @ 25% 101.80 111.05 120.31
Rate per 1 cum
8865.3 9165.90 9467.72
Overheads&Contractors Profit 1207.01 1247.94 1289.03
@13.615%
Rate per 1cum 10072.3 10413.84 10756.75
Say 10072.34 10413.84 10756.75
Add T.P @ 1.98% Exess 199.43 206.19 212.98
10271.77 10620.03 10969.73
5 S5 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with minimum
cement content of 400 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size
graded machine crushed hard granite metal(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
Part 8) from approved quarry including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and seignorge charges,sales & other taxes on all materials ,
centering using Steel scaffolding pipes , jack props , wallers , Foot plates , brackets , steel
centering plates etc., including all operational, incidental and labour charges such as weigh batching,
machine mixing, lifting of concrete mechanically, laying concrete, curing , overheads & contractors
profit ,all taxes except GST etc., complete but excluding cost of steel and its fabrication charges for finished
item of work (APSS No. 402)
(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 400.00 Kgs 4700.00 1000 Kgs 1880.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.067 Nos 470.00 1 Each 31.49
2nd class Mason 0.133 Nos 425.00 1 Each 56.53
Mazdoor (both men&women) 3.077 Nos 400.00 1 Each 1230.80
Add for MA @ 25% 0.25 1318.82 329.70
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 237.10 1 hour 73.03
Crew charges 0.308 hours 359.40 1 hour 110.70
Needle vibrator 40mm ( petrol ) 0.308 hours 25.10 1 hour 7.73
Crew charges 0.000 hours 166.60 1 hour 0.00
Add MA on crew charges 0.25 110.70 27.67
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 5224.50
6 S25Aun supported height up to 4.27 m
Rate for other Floors GF FF SF TF 4F 5F
Rate as above 5224.50 5224.50 5224.50 5224.50 5224.50 5224.50
Hire charges of centering and
scaffolding 2085.00 2085.00 2085.00 2085.00 2085.00 2085.00
Extra staging (Hire) 347.49 347.49 347.49 347.49 347.49 347.49
Labour , lift charges for scaffolding 1812.00 1993.00 2174.00 2356.00 2537.00 2718.00
Extra staging (Labour) 301.99 332.15 362.32 392.65 422.82 452.98
B) RCC SLABS :
a) Roof Slabs 115mm thick :
un supported height up to 3.66 m
Rate for Design mix M30 0.115 Cum 5224.50 1 Cum 600.82
Say 1241.89
(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 400.00 Kgs 4700.00 1000 Kgs 1880.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.167 Nos 470.00 1 Each 78.49
2nd class Mason 0.167 Nos 425.00 1 Each 70.98
Mazdoor (both men&women) 5.60 Nos 400.00 1 Each 2240.00
(BLD-CSTN-5-12)
Unit - 10sqm
A.MATERIALS :
Flyash lime solid blocks 247.00 Nos. 11297.30 1000 Nos. 2790.43
Cement Mortar (1:4) 0.10 cu.m. 2913.84 1 cu.m. 291.38
B.LABOUR :
1st class mason 0.60 Nos. 470.00 1 Each 282.00
2nd class mason 0.60 Nos. 425.00 1 Each 255.00
Mazdoor (Unskilled) 2.75 Nos. 400.00 1 Each 1100.00
Add for MA @ 25% 0.25 1637.00 409.25
Rate per 10 sqm 5128.07
Rate per 1 sqm 512.81
Internal walls :
Rate for other Floors GF FF SF TF 4F 5F
Rate as worked out above 512.81 512.81 512.81 512.81 512.81 512.81
Hire charges for Access Scaffolding
10.32 10.32 10.32 10.32 10.32 10.32
Labour charges for scaffolding 75.68 108.36 141.04 173.72 206.40 239.08
Add for MA @ 25% 18.92 27.09 35.26 43.43 51.60 59.77
Lift charges ( Page 131 of Std. 0.00 16.37 32.74 49.11 65.48 81.85
Data )
Add for MA @ 25% 0.00 4.09 8.19 12.28 16.37 20.46
Rate per 1 sqm 617.73 679.04 740.36 801.67 862.98 924.29
Overheads&Contractors Profit
@13.615%
84.1 92.45 100.8 109.15 117.49 125.84
Rate per 1 sqm 701.83 771.49 841.16 910.82 980.47 1050.13
Say 701.83 771.49 841.16 910.82 980.47 1050.13
Add T.P @ 1.98% Exess 19.41 20.79
999.88 1070.93
8 S18 Supplying and fixing of Glass with stainless steel ( grade 304 ) hand railing of 1.025 mts as per
approved drawing with top rail of 50 x 50 mm SS Box and 2mm thick medium class and vertical posts of
50 x 25mm SS Box and 2.0mm thick medium class and horizontals of 25 x 25mm SS Box and 2.0mm
thick medium class and providing and fixing of 12mm thick toughened glass fixed with base plate of 75mm
dia using bonding agent and anchor fastner and welding, drilling of 20mm dia holes with pneumatic
compressor for fixing railing, buffing, polishing all members of the railing thouroughly , lacquer finishing to
present seamless finish including cost and conveyance of all materials, electrodes, welding charges, cost of
all consumables, labour charges , overheads & contractors profit,all taxes except GST for finished item of
work.
For a length of 6.4 M. 6.560 Sqm
Top- 50 X 50 x 2.0mm Box section
(6.42x 3.00 Kgs/RM)
19.26 RM
Verticals- 50 X 25 x 2.0mm Box 17.39 Kgs
section (8 x 0.975x 2.23 Kgs/RM)
Horizontals- 25 X 25 x 2.0mm Box 50.75 Kgs
section - 6.42-3*0.45=5.07RM (7 x
5.07 x 1.43 Kgs/RM)
87.40 Kgs
Glass 1.32 Sqm
/1Sqm 11960.96
9 S21 Providing and applying Exterior grade Texture ready mixed plaster made with natural minerals - granite
flakes/ marble flakes/ powder, sand and other carefully selected and sieved minerals in an acrylic binding
medium of average 2 to 3 mm thickness over plastered surface to prepare the surface even and smooth
after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, applying
emery paper, Sand the surface, clean & wipe off loose dust, applying putty/ texture paint filler by putty knife
/ muslin pad, air dry for 2 - 3 hrs for the surface preparation including cost and conveyance of all
materials to work site and all operational, incidental, labour charges, scaffolding charges, overheads and
contractors profit etc., complete for finished item of work in all floors for external walls
Rate as per per Lowest Quotation 1.00 SQM 15607.80 1.00 SQM 15607.80
Transporation charges @ 1% 0.01 15607.80 156.08
Hire charges for Access Scaffolding 1.00 SQM 1.00 SQM 1.03
1.03
Labour charges for scaffolding 1.00 SQM 10.84 1.00 SQM 10.84
Rate per 1 Sqm 15775.75
OH & CP 0.1 15775.75 1577.57
17353.32
Say 17353.32
Add T.P @ 1.98% Exess 343.60
(BLD-CSTN-3-15)
a) COLUMNS :
un supported height up to 4.27 m
Rate for other Floors GF FF SF TF 4F 5F
Rate as above 7258.59 7258.59 7258.59 7258.59 7258.59 7258.59
Hire charges of centering and
scaffolding 355.00 355.00 355.00 355.00 355.00 355.00
Extra staging (Hire) 59.16 59.16 59.16 59.16 59.16 59.16
Labour charges 2160.00 2376.00 2592.00 2808.00 3024.00 3240.00
Extra staging (Labour) 359.99 395.98 431.98 467.98 503.98 539.98
Add for MA @ 25% 630.00 693.00 756.00 819.00 882.00 945.00
Lift charges of materials(Winch
35HP- Electric) 0.00 455.49 501.03 546.58 592.13 637.68
Crew charges 0.00 370.17 407.19 444.21 481.23 518.24
Add for MA @ 25% 0.00 92.54 101.80 111.05 120.31 129.56
Rate per 1 cum 10822.74 12055.93 12462.75 12869.6 13276.39 13683.21
Overheads&Contractors Profit
@13.615% 1473.52 1641.41 1696.80 1752.19 1807.58 1862.97
Rate per 1cum 12296.26 13697.34 14159.55 14621.8 15083.97 15546.18
Say 12296.26 13697.34 14159.55 14621.76 15083.97 15546.18
Add T.P @ 1.98% Exess 243.47 271.21 280.36 289.51 298.66 307.81
12539.73 13968.55 14439.91 14911.27 15382.63 15854.00
12 S24bSupply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with minimum
cement content of 400 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size
graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
Part 8) from approved quarry including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and seignorge charges,sales & other taxes on all materials,
centering using Steel scaffolding pipes , jack props , wallers , Foot plates , brackets , steel
centering plates etc., including all operational, incidental and labour charges such as weigh batching,
machine mixing, lifting of concrete mechanically, laying concrete, curing , overheads & contractors
profit,all taxes except GST etc., complete but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402)
(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 400.00 Kgs 4700.00 1000 Kgs 1880.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.167 Nos 470.00 1 Each 78.49
2nd class Mason 0.167 Nos 425.00 1 Each 70.98
S25
(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 400.00 Kgs 4700.00 1000 Kgs 1880.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.067 Nos 470.00 1 Each 31.49
2nd class Mason 0.133 Nos 425.00 1 Each 56.53
Mazdoor (both men&women) 3.077 Nos 400.00 1 Each 1230.80
Add for MA @ 25% 0.25 1318.82 329.70
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 237.10 1 hour 73.03
B) RCC SLABS :
a) Roof Slabs 150mm thick :
S25bun supported height up to 4.27 m
Rate for Design mix M30 0.150 Cum 5224.50 1 Cum 783.68
14 S26 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using WEIGH BATCHER with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including seigniorage charges,sales & other taxes except GST on all
materials, centering using Steel scaffolding pipes , jack props , wallers , Foot plates , brackets , steel
centering plates etc., for 60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick at free end with an
average thickness of 6.25cm including all operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete mechanically, laying concrete, curing, overheads &
contractors profit etc., complete but excluding cost of steel and its fabrication for finished item of work
(APSS No. 402, 403 & 903)
(BLD-CSTN-3-16)
A.MATERIALS :
Cement 380.00 Kgs 4700.00 1000 Kgs 1786.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.067 Nos 470.00 1 Each 31.49
2nd class Mason 0.133 Nos 425.00 1 Each 56.53
Mazdoor (both men&women) 3.077 Nos 400.00 1 Each 1230.80
Add for MA @ 25% 0.25 1318.82 329.70
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 237.10 1 hour 73.03
Crew charges 0.308 hours 359.40 1 hour 110.70
Add MA on crew charges 0.25 110.70 27.67
Water(including for curing) 1.20 kl 103.00 1 kl 123.60
Rate per 1 cum 5128.77
(BLD-CSTN-8-11)
Unit : 10 sqm
A.MATERIALS :
Rabbit wire mesh 13.30 sqm 17.00 1 sqm 226.10
Cement for base coat and 240.00 Kgs 4700.00 1000 Kgs 1128.00
plastering
Cement for lumps 50.00 Kgs 4700.00 1000 Kgs 235.00
Fine aggregate (Sand) 0.50 Cum 1068.42 1 Cum 534.21
Excluding HYSD steel/mild steel &
binding wire
B.LABOUR :
1st Class Mason 8.00 Nos. 470.00 1 Each 3760.00
Operator concrete mixer 1.00 Nos. 470.00 1 Each 470.00
Mazdoor (Unskilled) 10.00 Nos. 400.00 1 Each 4000.00
Add for MA @ 25% 0.25 8230.00 2057.50
C.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 2.00 hour 135.20 1 hour 270.40
cum)capacity
Crew Charges 2.00 hour 231.40 1 hour 462.80
Add for MA @ 25% 0.25 462.80 115.70
water charges @ 1% 0.01 13259.71 132.60
Rate per 10 Sqm 13392.31
Rate per 1 Sqm 1339.23
17 S31 Providing and Fixing M.S. Chequered Plates of approved thickness with MS angles of approved sizes
for cable trenches and wherever required, at all levels, etc, complete, as per standard specifications /
approved detailed drawings including cutting, welding, hoisting & including cost and conveyance of all
materials, all taxes except GST, labour charges for fabrication erection at site work etc., complete and as
directed by engineer-in-charge.
S32
(BLD-CSTN-3-14)
FOUNDATIONS , PLINTH , PEDESTALS ( Below Plinth)
A.MATERIALS :
Cement 400.00 Kgs 4700.00 1000 Kgs 1880.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.133 Nos 470.00 1 Each 62.51
2nd class Mason 0.267 Nos 425.00 1 Each 113.48
Mazdoor (both men&women) 4.60 Nos 400.00 1 Each 1840.00
Add for MA @ 25% 0.25 2015.99 504.00
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 237.10 1 hour 316.05
Crew charges 1.333 hours 359.40 1 hour 479.08
Add MA on crew charges 0.25 479.08 119.77
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 6791.74
a Footings
Rate for Design mix M 30 1.00 Cum 6791.74 1 Cum 6791.74
Hire charges of centering and
scaffolding 1.00 Cum 288.00 1 Cum 288.00
Labour charges 1.00 Cum 601.00 1 Cum 601.00
19 S33 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with minimum
cement content of 400 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size
graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
Part 8) from approved quarry including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and seignorge charges,sales & other taxes on all materials,
centering using Steel scaffolding pipes , jack props , wallers , Foot plates , brackets , steel
centering plates etc., including all operational, incidental and labour charges such as weigh batching,
machine mixing, lifting of concrete mechanically, laying concrete, curing , overheads & contractors
profit,all taxes except GST etc., complete but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402)
(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 400.00 Kgs 4700.00 1000 Kgs 1880.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.167 Nos 470.00 1 Each 78.49
2nd class Mason 0.167 Nos 425.00 1 Each 70.98
Mazdoor (both men&women) 5.60 Nos 400.00 1 Each 2240.00
Add for MA @ 25% 0.25 2389.47 597.37
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 237.10 1 hour 316.05
Crew charges 1.333 hours 359.40 1 hour 479.08
Add MA on crew charges 0.25 479.08 119.77
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 7258.59
a) COLUMNS :
S34 un supported height up to 3.66 m
Rate for other Floors GF FF SF TF 4F 5F
Rate as above 7258.59 7258.59 7258.59 7258.59 7258.59 7258.59
Hire charges of centering and
scaffolding 355.00 355.00 355.00 355.00 355.00 355.00
Labour charges 2160.00 2376.00 2592.00 2808.00 3024.00 3240.00
Add for MA @ 25% 540.00 594.00 648.00 702.00 756.00 810.00
Lift charges of materials(Winch
35HP- Electric)
0.00 341.70 455.49 501.03 546.58 592.13
Crew charges 0.00 277.70 370.17 407.19 444.21 481.23
Add for MA @ 25% 0.00 69.43 92.54 101.80 111.05 120.31
Rate per 1 cum
10313.59 11272.42 11771.80 12133.6 12495.44 12857.26
Overheads&Contractors Profit 1404.20 1534.74 1602.73 1651.99 1701.25 1750.52
@13.615%
Rate per 1cum 11717.79 12807.16 13374.53 13785.6 14196.69 14607.78
Say 11717.79 12807.16 13374.53 13785.61 14196.69 14607.78
Add T.P @ 1.98% Exess 232.01 253.58 264.82 272.95 281.09 289.23
11949.80 13060.74 13639.34 14058.56 14477.78 14897.01
a) LINTELS :
Rate for other Floors GF FF SF TF 4F 5F
Rate as above 7258.59 7258.59 7258.59 7258.59 7258.59 7258.59
Hire charges of centering and
scaffolding 1180.00 1180.00 1180.00 1180.00 1180.00 1180.00
Labour charges 1538.00 1692.00 1846.00 1999.00 2153.00 2307.00
Add for MA @ 25% 384.50 423.00 461.50 499.75 538.25 576.75
Lift charges of materials(Winch
35HP- Electric) 0.00 341.70 455.49 501.03 546.58 592.13
Crew Charges 0.00 277.70 370.17 407.19 444.21 481.23
Add for MA @ 25% 0.00 69.43 92.54 101.80 111.05 120.31
Rate per 1 cum 10361.09 11242.42 11664.29 11947.4 12231.68 12516.01
Overheads&Contractors Profit 1410.66 1530.66 1588.09 1626.63 1665.34 1704.05
@13.615%
Rate per 1 cum 11771.75 12773.08 13252.38 13574.0 13897.02 14220.06
Say 11771.75 12773.08 13252.38 13574.00 13897.02 14220.06
20 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with minimum
cement content of 400 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size
graded machine crushed hard granite metal(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
Part 8) from approved quarry including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and seignorge charges,sales & other taxes on all materials ,
centering using Steel scaffolding pipes , jack props , wallers , Foot plates , brackets , steel
centering plates etc., including all operational, incidental and labour charges such as weigh batching,
machine mixing, lifting of concrete mechanically, laying concrete, curing , overheads & contractors
profit ,all taxes except GST etc., complete but excluding cost of steel and its fabrication charges for finished
item of work (APSS No. 402)
S34
(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 400.00 Kgs 4700.00 1000 Kgs 1880.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.067 Nos 470.00 1 Each 31.49
2nd class Mason 0.133 Nos 425.00 1 Each 56.53
Mazdoor (both men&women) 3.077 Nos 400.00 1 Each 1230.80
Add for MA @ 25% 0.25 1318.82 329.70
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 237.10 1 hour 73.03
Crew charges 0.308 hours 359.40 1 hour 110.70
Needle vibrator 40mm ( petrol ) 0.308 hours 25.10 1 hour 7.73
Crew charges 0.000 hours 166.60 1 hour 0.00
Add MA on crew charges 0.25 110.70 27.67
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 5224.50
A) BEAMS :
un supported height up to 3.66 m
Rate for other Floors GF FF SF TF 4F 5F
Rate as above 5224.50 5224.50 5224.50 5224.50 5224.50 5224.50
Hire charges of centering and
scaffolding 2085.00 2085.00 2085.00 2085.00 2085.00 2085.00
Labour , lift charges for scaffolding 1812.00 1993.00 2174.00 2356.00 2537.00 2718.00
Add for MA @ 25% 453.00 498.25 543.50 589.00 634.25 679.50
Lift charges of materials(Winch
35HP- Electric) 0.00 91.23 100.36 109.48 118.60 127.73
Crew charges 0.00 74.15 81.56 88.98 96.39 103.80
Add for MA @ 25% 0.00 18.54 20.39 22.24 24.10 25.95
Rate for 1 cum 9574.50 9984.67 10229.31 10475.20 10719.84 10964.48
Overheads&Contractors Profit 1303.57 1359.41 1392.72 1426.2 1459.51 1492.81
@13.615%
Rate per 1 cum 10878.07 11344.08 11622.03 11901.4 12179.35 12457.29
Say 10878.07 11344.08 11622.03 11901.40 12179.35 12457.29
Add T.P @ 1.98% Exess 215.39 224.61 230.12 235.65 241.15 246.65
11093.46 11568.69 11852.15 12137.05 12420.50 12703.95
B) RCC SLABS :
a) Roof Slabs 125mm thick :
un supported height up to 3.66 m
Rate for Design mix M30 0.125 Cum 5224.50 1 Cum 653.06
Overheads&Contractors Profit
@13.615% 181.56
Rate per 1 sqm 1515.11
Say 1515
(BLD-CSTN-10-25)
Unit : 10 sqm
A.MATERIALS :
Cost of CM(1:3) 0.15 Cum 3477.84 1 Cum 521.68
Impervious Water proof compound 0.29 Lts 191.00 1.00 Lts 55.39
B.LABOUR :
1st Class Mason 0.60 Nos. 470.00 1 Each 282.00
Mazdoor (Unskilled) 0.96 Nos. 400.00 1 Each 384.00
Add for MA @ 25% 0.25 666.00 166.50
Rate per 10 Sqm 1409.57
38 Supply and placing in postion water stopper 8 - 10 mm thick 310 mm wide including cost and conveyance
of all materials to site and sales and other taxes except GST on all materials to site etc., complete for
finished item of work
S38
Rate as per SoR 1.00 RM 405.00 1 RM 405.00
405.00
Overheads&Contractors Profit 0.13615 405.00
@13.615% 55.14
Rate per 1 sqm 460.14
Rate per 1 sqm Say 460.14
Add T.P @ 1.98% Exess 9.11
469.25
39 S39 Plain Cement Concrete M 20 nominal mix using WEIGH BATCHER / MIXER, 20mm size hard granite
machine crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concrete including cost and
conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site
including steel centering, shuttering, machine mixing, lift charges, laying concrete,vibrating, curing,
overheads & contrctors profit etc., complete for finished item of work for coping on top of compound
wall (APSS No. 402 & 403).
(BLD-CSTN-3-11)
Unit : 1 cum
A.MATERIALS :
Cement 330.00 Kgs 4700.00 1000 Kgs 1551.00
20mm HBG graded metal 0.90 Cum 1362.10 1 Cum 1225.89
Fine aggregate ( Sand ) 0.45 Cum 878.42 1 Cum 395.29
Water (including curing) 1.20 kl 103.00 1 kl 123.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 135.20 1 hour 135.20
Crew charges 1.00 hour 231.40 1 hour 231.40
Add MA on crew charges 0.25 231.40 57.85
C.LABOUR :
1st class mason 0.10 Nos. 470.00 1 Each 47.00
Mazdoor (unskilled) 1.39 Nos. 400.00 1 Each 556.00
Add for MA @ 25% 0.2500 603.00 150.75
4473.98
Overheads&Contractors Profit 0.13615 4473.98
@13.615% 609.13
Rate per 1 cum 5083.11
Say 5083.00
Add T.P @ 1.98% Exess 100.64
5183.64
40 Providing and fixing of Expansion joint filler board for buildings, columns, beams and slabs 25 mm
thick including cost and conveyance of all materials to site, all incidental, operational, labour charges
etc.overheads & contractors profit complete for finished item of work as per approved drawing for all floors
S40
Rate as per SSR 1.00 Sqm 366.00 1 Sqm 366.00
Overheads&Contractors Profit 0.14 366.00
@13.615% 49.83
Rate per 1 sqm 415.83
Say 416
Add T.P @ 1.98% Exess 8.24
424.24
1 S6 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with minimum
cement content of 400 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size
graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
Part 8) from approved quarry including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and seignorge charges,sales & other taxes on all materials,
centering using Steel scaffolding pipes , jack props , wallers , Foot plates , brackets , steel
centering plates etc., including all operational, incidental and labour charges such as weigh batching,
machine mixing, lifting of concrete mechanically, laying concrete, curing , overheads & contractors
profit,all taxes except GST etc., complete but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402)
(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 400.00 Kgs 4700.00 1000 Kgs 1880.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.167 Nos 470.00 1 Each 78.49
2nd class Mason 0.167 Nos 425.00 1 Each 70.98
Mazdoor (both men&women) 5.60 Nos 400.00 1 Each 2240.00
Add for MA @ 25% 0.25 2389.47 597.37
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 237.10 1 hour 316.05
Crew charges 1.333 hours 359.40 1 hour 479.08
Add MA on crew charges 0.25 479.08 119.77
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 7258.59
a) COLUMNS :
un supported height up to 3.66 m
Rate for other Floors GF FF SF TF 4F 5F
Rate as above 7258.59 7258.59 7258.59 7258.59 7258.59 7258.59
Hire charges of centering and
scaffolding 355.00 355.00 355.00 355.00 355.00 355.00
Labour charges 2160.00 2376.00 2592.00 2808.00 3024.00 3240.00
Add for MA @ 25% 540.00 594.00 648.00 702.00 756.00 810.00
Lift charges of materials(Winch
35HP- Electric)
0.00 341.70 455.49 501.03 546.58 592.13
Crew charges 0.00 277.70 370.17 407.19 444.21 481.23
Add for MA @ 25% 0.00 69.43 92.54 101.80 111.05 120.31
Rate per 1 cum
10313.59 11272.42 11771.80 12133.6 12495.44 12857.26
Overheads&Contractors Profit 1404.20 1534.74 1602.73 1651.99 1701.25 1750.52
@13.615%
Rate per 1cum 11717.79 12807.16 13374.53 13785.6 14196.69 14607.78
Say 11717.79 12807.16 13374.53 13785.61 14196.69 14607.78
Add T.P @ 1.98% Exess 232.01 253.58 264.82 272.95 281.09 289.23
11949.80 13060.74 13639.34 14058.56 14477.78 14897.01
un supported height up to 3.66 m
Rate for other Floors 7F
Rate as above 7258.59
Hire charges of centering and
scaffolding 355.00
Labour charges 3456.00
a) LINTELS :
Rate for other Floors GF FF SF TF 4F 5F
Rate as above 7258.59 7258.59 7258.59 7258.59 7258.59 7258.59
Hire charges of centering and
scaffolding 1180.00 1180.00 1180.00 1180.00 1180.00 1180.00
Labour charges 1538.00 1692.00 1846.00 1999.00 2153.00 2307.00
Add for MA @ 25% 384.50 423.00 461.50 499.75 538.25 576.75
Lift charges of materials(Winch
35HP- Electric) 0.00 341.70 455.49 501.03 546.58 592.13
Crew Charges 0.00 277.70 370.17 407.19 444.21 481.23
Add for MA @ 25% 0.00 69.43 92.54 101.80 111.05 120.31
Rate per 1 cum 10361.09 11242.42 11664.29 11947.4 12231.68 12516.01
Overheads&Contractors Profit 1410.66 1530.66 1588.09 1626.63 1665.34 1704.05
@13.615%
Rate per 1 cum 11771.75 12773.08 13252.38 13574.0 13897.02 14220.06
Say 11771.75 12773.08 13252.38 13574.00 13897.02 14220.06
(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 400.00 Kgs 4700.00 1000 Kgs 1880.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.067 Nos 470.00 1 Each 31.49
2nd class Mason 0.133 Nos 425.00 1 Each 56.53
Mazdoor (both men&women) 3.077 Nos 400.00 1 Each 1230.80
Add for MA @ 25% 0.25 1318.82 329.70
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 237.10 1 hour 73.03
Crew charges 0.308 hours 359.40 1 hour 110.70
Needle vibrator 40mm ( petrol ) 0.308 hours 25.10 1 hour 7.73
Crew charges 0.000 hours 166.60 1 hour 0.00
Add MA on crew charges 0.25 110.70 27.67
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 5224.50
A) BEAMS :
un supported height up to 3.66 m
Rate for other Floors GF FF SF TF 4F 5F
Rate as above 5224.50 5224.50 5224.50 5224.50 5224.50 5224.50
Hire charges of centering and
scaffolding 2085.00 2085.00 2085.00 2085.00 2085.00 2085.00
Labour , lift charges for scaffolding 1812.00 1993.00 2174.00 2356.00 2537.00 2718.00
Add for MA @ 25% 453.00 498.25 543.50 589.00 634.25 679.50
Lift charges of materials(Winch
35HP- Electric) 0.00 91.23 100.36 109.48 118.60 127.73
Crew charges 0.00 74.15 81.56 88.98 96.39 103.80
Add for MA @ 25% 0.00 18.54 20.39 22.24 24.10 25.95
Rate for 1 cum 9574.50 9984.67 10229.31 10475.20 10719.84 10964.48
Overheads&Contractors Profit 1303.57 1359.41 1392.72 1426.2 1459.51 1492.81
@13.615%
Rate per 1 cum 10878.07 11344.08 11622.03 11901.4 12179.35 12457.29
Say 10878.07 11344.08 11622.03 11901.40 12179.35 12457.29
Add T.P @ 1.98% Exess 215.39 224.61 230.12 235.65 241.15 246.65
B) RCC SLABS :
a) Roof Slabs 115mm thick :
un supported height up to 3.66 m
Rate for Design mix M30 0.115 Cum 5224.50 1 Cum 600.82
(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 400.00 Kgs 4700.00 1000 Kgs 1880.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.167 Nos 470.00 1 Each 78.49
2nd class Mason 0.167 Nos 425.00 1 Each 70.98
Mazdoor (both men&women) 5.60 Nos 400.00 1 Each 2240.00
Add for MA @ 25% 0.25 2389.47 597.37
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 237.10 1 hour 316.05
Crew charges 1.333 hours 359.40 1 hour 479.08
Add MA on crew charges 0.25 479.08 119.77
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 7258.59
a) COLUMNS :
un supported height up to 3.66 m
Rate for other Floors GF FF SF TF 4F 5F
Rate as above 7258.59 7258.59 7258.59 7258.59 7258.59 7258.59
(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 400.00 Kgs 4700.00 1000 Kgs 1880.00
20mm HBG graded metal 0.80 Cum 1259.86 1 Cum 1007.89
Sand 0.40 Cum 878.42 1 Cum 351.37
B.LABOUR :
1st class Mason 0.067 Nos 470.00 1 Each 31.49
2nd class Mason 0.133 Nos 425.00 1 Each 56.53
Mazdoor (both men&women) 3.077 Nos 400.00 1 Each 1230.80
Add for MA @ 25% 0.25 1318.82 329.70
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 237.10 1 hour 73.03
Crew charges 0.308 hours 359.40 1 hour 110.70
Needle vibrator 40mm ( petrol ) 0.308 hours 25.10 1 hour 7.73
Crew charges 0.308 hours 166.60 1 hour 51.31
Add MA on crew charges 0.25 110.70 27.67
Water(including for curing) 1.20 kl 103.00 1 kl 123.60
Rate per 1 cum 5281.81
A) BEAMS :
un supported height up to 3.66 m
Rate for other Floors FF SF TF 4F
Rate as above 5281.81 5281.81 5281.81 5281.81
Hire charges of centering and
scaffolding 2085.00 2085.00 2085.00 2085.00
Labour , lift charges for scaffolding 1812.00 1993.00 2174.00 2356.00
Add for MA @ 25% 453.00 498.25 543.50 589.00
Providing impervious coat to exposed RCC roof slab surfaces of sump , sump side wall,sump bottom
slab,in side of septic tank , in sunken slabs etc. to required slopes with CM (1:3) prop. using screened sand
12mm thick mixed with integral cement water proofing liquid confirming to IS: 2645-2003 manufactured by
reputed manufacturers as approved by Engineer-in-charge at 1 Kg per one bag of cement, laid over roof
slab when it is green, finished smooth with a floating coat of neat cement and thread lining at regular
intervals of 45cmx45cm where ever necessary including cost and conveyance of all materials like cement,
sand, water proofing compound, water etc., to site, including seignorge charges, sales & other taxes except
GST on all materials and operational, incidental, and labour charges for mixing mortar, laying, lift charges,
rendering smooth and thread lining, curing including rounding off junctions of wall and slab etc., and
overheads & contractors profit etc complete for finished item of work. (APSS No. 901 & 903).
(BLD-CSTN-10-25)
Unit : 10 sqm
A.MATERIALS :
Cost of CM(1:3) 0.15 Cum 3477.84 1 Cum 521.68
Impervious Water proof compound 0.29 Lts 191.00 1.00 Lts 55.39
B.LABOUR :
1st Class Mason 0.60 Nos. 470.00 1 Each 282.00
Mazdoor (Unskilled) 0.96 Nos. 400.00 1 Each 384.00
Add for MA @ 25% 0.25 666.00 166.50
Rate per 10 Sqm 1409.57
Say 718.94
Add T.P @ 1.98% Exess 14.23
733.17
17 Supplying & Laying of precast concrete blocks for paving of M-30 grade and thickness not less than 50
mm for Nontraffic areas conforming to IS 15658:2006 in all shapes and design as per manufactures
specification , laid over 50mm thick sand bed including cost of designer pavers , labour charges charges for
laying & fixing of precast concrete blocks for paving of all grades, any thickness, all sizes & shapes
including all labour charges for loading & unloading, laying to desired lines and levels complete
excluding GST , overheads & contractors profit etc., complte for finished item of work.
Unit : 1sqm
A.MATERIALS :
Cost of inter locking designer 1.00 sqm 304.00 1 sqm 304.00
tiles(TBSC-C.IX-01)
cost of sand for base 0.05 cum 878.42 1 cum 43.92
Labour charges for laying(TBSC- 1.00 sqm 181.00 1 sqm 181.00
C.IX-06
Add for MA @ 25% 0.25 181.00 45.25
574.17
Overheads&Contractors Profit 0.13615 574.17 78.17
@13.615%
Rate per 1 Sqm 652.34
Say 652.34
Add T.P @ 1.98% Exess 12.92
665.26
18 Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 prop. Masonry. Inspection chamber up
to 914.4 mm (3'0") and fitted with 100 thick perforated slab. including cost and conveyance of all materials
and all labour charges, overheads & contractors profit etc., all taxes, except GST, complete for finished
item of work for all floors for Catch basin.
Unit : 1 sqm
A. MATERIALS:
cost of 4mm thick Aluminium
composite panel cladding- TBSC-
R.I-19 1.00 Sqm 2868.00 1 Sqm 2868.00
Scffolding charges 1.00 Sqm 15.13 15.13
Add for MA @ 25% 0.25 14.10 3.53
Rate per 1Sqm 2886.66
Overheads&Contractors Profit @13. 0.13615 2886.66 393.02
Rate per 1 RM 3279.67
say 3279.67
Add T.P @ 1.98% Exess 64.94
3344.61
22 Earth Work Excavation by mechanical means for road work with hydraulic excavator of 0.9 cum bucket
capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross-sections, and transporting to the embankment location as directed
by the Engineer-in-Charge including setting out, removal of stumps and all other deleterious matter, all
operational & incidental charges, hire & operational charges of all T&P, etc., complete in all soils up to SDR
as per Technical Specification Clause 301 MORTH, excluding GST
Unit = Cum
Taking output = 240 Cum
A MACHINERY :
Hydraulic excavator (Sl.No.4 of R&B
Hire charges) 6.00 hour 2821.50 1 hour 16929.00
B LABOUR :
Mate 0.320 Nos 425.00 1 Each 136.00
Mazdoor (unskilled) 8.00 Nos 400.00 1 Each 3200.00
Add for MA @ 25% 0.25 3336.00 834.00
Unit = cum
Taking output = 300 cum
A) Labour
Mate 0.48 Nos. 425.00 1 No. 204.00
Mazdoor skilled 2.00 Nos. 438.50 1 No. 877.00
Mazdoor 10.00 Nos. 400.00 1 No. 4000.00
Add for MA @ 25% 0.25 5081.00 1270.25
B) Machinery
Motror Grader 110 HP @ 50 cum
(Sl.No.3 of Hire charges of R&B) 6.00 hours 3216.00 1 Hour 19296.00
Vibratory roller 8 - 10 tonne (Sl.No.7
of Hire charges of R&B) 6.00 hours 2638.90 1 Hour 15833.40
Tractor - Rotavator (Sl.No.12 of Hire
charges of R&B) 12.00 hours 422.00 1 Hour 5064.00
Water tanker 6 KL capacity 3.00 hours 624.00 1 Hour 1872.00
C)Material
Close graded Granular sub-base
Material as per table 400-1
9.5mm to 4.75mm @ 35%
(Av. rate of 9.5-11.2mm , 5-7mm &
2.36 - 5mm HBG M/C metal) 134.40 cum 860.43 1 cum 115642.24
4.75 mm to 2.36 mm @ 12.5 per
cent 48.00 cum 763.98 1 cum 36670.8
2.36 mm below @ 52.5 per cent 201.6 cum 663.60 1 cum 133781.76
334511.45
d) Rate for 300 Cum Total (a+b+c)
Overheads&Contractors Profit
@13.615% 0.13615 334511.45 45543.7339
Cost for 300 cum = a+b+c 380055.18
Rate per cum = (a+b+c)/300 1266.90
Add T.P @ 1.98% Exess 25.08
/1Cum 1291.98
24 Plain Cement Concrete(1:4:8) mix using 40mm size hard broken granite metal including cost and
conveyance of all materials to site, seigniorage, machine mixing charges, labour charges, placing in
position, levelling, vibrating, curing, etc. complete for finished item of work as directed by the Engineer-in-
charge, excluding GST and Seigniorage charges as per technical specification clause No.2100 of Morth.
Unit = cum
Taking output = 75 cum (172.50 t)
(100 x 3.75 x 0.200)
a) Labour
Mason 1st Class 5.00 day 470.00 1 day 2350.00
Mason (2nd class) 5.00 day 425.00 1 day 2125.00
Mazdoor (Skilled) 4.00 day 438.50 1 day 1754.00
Mazdoor (Semi Skilled) 6.00 day 400.00 1 day 2400.00
Mazdoor (Unskilled) 100.00 day 400.00 1 day 40000.00
Add for MA @ 25% 0.25 48629.00 12157.25
60786.25
b) Machinery
Concrete mixer (cap. 0.40/0.28 cum) 36.00 hour 1 hour 13197.60
(Sl.No. 16 of Common SoR) 366.60
Needle vibrator hire charges 9.00 hour 191.70 1 hour 1725.30
Screed vibrator hire charges 9.00 hour 297.00 1 hour 2673.00
(Sl.No.47 0f Common SoR Hire
charges)
Plate vibrator (Sl.No.45 0f Hire 9.00 hour 369.10 1 hour 3321.90
charges)
Water tanker 6 kl capacity) 5.00 hour 624.00 1 hour 3120.00
(Sl.No.10 of R & B Hire charges)
24037.80
c) Material
Aggregate 20mm well graded 60.38 cum 1259.86 1 cum 76070.35
Cement 26.25 t 4700.00 1 t 123375.00
Coarse sand 33.90 cum 878.42 1 cum 29778.44
Polythene sheet 125 micron 375.00 sqm 17.00 1 sqm 6375.00
235598.79
Total (a+b+c) Total 320422.84
UNIT=10 RMT
Cost of precast cement concrete kerbs of 16.67 Nos. 315.00 1 Each
size 600x150x450( LMR)
5250.00
Transportation charges from local 16.67 No 10 1 Each
handeling in Site
166.67
Labour charges for fixing (LMR) 16.67 No 25 1 Each 416.67
Jointing with CM (1:4) 12mm thick 0.0130 Cum 2913.84 1 Cum
(16.66x0.45x0.15x0.012=0.013Cum)
37.88
Rate per 10 RM 5871.21
587.12
Overheads&Contractors Profit 0.10000 587
@13.615% 58.71
12 Earth work in excavation for culverts & drains by using Hydraulic excavator and depositing the earth on
road side or as directed by the Engineer-in-Charge with an initial lead of 50mts in all soils upto SDR in all
conditions including all operational, incidental and labour charges such as dry, wet, slushy, setting out,
construction of shoring and bracing, removal of stumps and other deleterious material, dressing of sides
and bottom, sheeting, planking, strutting, etc., complete for finished item of work excluding dewatering
charges excluding GST & Seignoriage Chargesetc., complete as per MORTH (5th Revision) specification
304.
13 Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size
mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days,
including all charges, hire & operational charges, all taxes except GST & Seigniorage charges as MORT&H
specification 2100 (5th revision) and as directed by the Engineer-in-charge for Strom Water Drains
b) Material
II 40 mm Aggregate 13.50 cum 905.85 1 Cum 12228.98
Fine Sand 6.75 cum 878.42 1 Cum 5929.34
cement 3.450 tonne 4700.00 1 tonne 16215.00
III c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) 6.00 hour hour
(Sl.No. 16 of Common SoR) 366.60 1 2199.60
Generator 33 KVA (Sl.No. 23 of 6.00 hour hour
Common SoR) 875.30 1 5251.80
Total 50252.21
Overheads&Contractors Profit
@13.615% 0.13615 50252.21 6841.84
Rate per 15 Cum 57094.05
Rate per 1 Cum 3806.27
Rate per 1Cum 3806.27
Add T.P @ 1.98% Exess 75.36
3881.63
14 Providing and laying Reinforced Cement Concrete corresponding to M-20 grade Design mix using 20
mm &10mm sizewell graded machine crushed hard granite chips (coarse aggregate) fine aggregate
including cost and conveyance of all materials like cement, & fine aggregate , coarse aggregate, water
etc., to site but including all charges for machine mixing, laying concrete in foundations, complete for
finished item of work as per MORTH specification 1500, 1700 & 2100. For Drains
B.LABOUR :
Mate 0.860 Nos 425.00 1 Each 365.50
Mason 1.500 Nos 470.00 1 Each 705.00
Mazdoor 20.00 Nos 400.00 1 Each 8000.00
Add for MA @ 25% 0.25 9070.50 2267.63
11338.13
C.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity (Sl.No. 16 of Common
SoR) 6.00 hour 366.60 1 hour 2199.60
Generator 30 KVA (Sl.No. 23 of
Common SoR) 6.00 hour 842.20 5053.20
7252.80
16 Supplying fitting and placing HYSD (Fe 500 grade as per IS 1786-1979) using primary producers like
TATA, SAIL, VSP, Jindal, Shyam Steel etc., of bar reinforcements below 36mm dia.s for RCC works,
including labour charges for straightening, cutting, bending to required sizes and shapes, placing in position
with cover blocks of approved materials and size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs and drawings, including cost and conveyance
of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including cost and
conveyance of binding wire, cover blocks and all incidental, operational, labour charges such as cutting,
bending, placing in position, tying including sales and other taxes on all materials etc., and overheads &
contractors profit complete for finished item of work as per MORTH Specification No.1600 & 2200.Except
GST.
Taking Output = 1 Mt
a Non Labour
TMT/HYSD BARS FE-500 1.05 MT 46500.00 1 MT
48825.00
Binding Wire 6 Kgs 46.00 1 Kg
276.00
B.LABOUR :
Mate 0.340 Nos 425.00 1 Each 144.50
Blacksmith / Bar bender 2.000 Nos 470.00 1 Each 940.00
Mazdoor 6.50 Nos 400.00 1 Each 2600.00
Add for MA @ 25% 0.25 3684.50 921.13
53706.63
Overheads&Contractors Profit 0.13615 53706.63 7312.16
@13.615%
Rate per 1 MT 61018.78
Total for 1 Mt Say 61018.78
Add T.P @ 1.98% Exess 1208.17
62226.95
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked fixtures
of 6 Nos.stainless steel butt hinges (IS:12817) 150mm long, 2 Nos. Stainless Steel Tower (IS:15833) 250 mm
Long Bolt-10 mm 245 at top, 2Nos. of Godrej Mortise lock Elc 05 6 - Lever Zinc Alloy Door handle with body
and 2 Nos of Rubber door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc,
including overheads & contractors profit etc., all taxes but excluding GST complete for finished item of work as
per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less than
10 mm) (1500mm x 2430mm)
Cost analysis
Cost of medium TW frame 2 m to 3m
length 0.04691 cum 80689.00 1 cum 3785.12
Cost of medium TW frame up to 2 m
length 0.01448 cum 72620.00 1 cum 1051.54
Cost of 40 mm thick flush shutter- TBSC-
L.II- 07 2.76 sqm 1528.00 1 sqm 4217.28
9 S9 Supply and fixing doors as per drawings with medium teak wood frame of section 127mm x 76 mm and ISI
marked Flush door shutters of 40mm thick double shutters with bond wood solid block board type core
having cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde synthetic
resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all
sides , fixing 4mm thick teak veneer lamination with natural grains to full width and height of the flush
shutter both sides , Teak wood beading of size 2" X 1" alround the frame and Supplying and fixing 0.14m x
2.15m size view panel to door shutters including cutting the shutter to the required area , fixing 12mm thick
plain float glass using 12mmx12mm size teak wood beading including cost and conveyance to site of teak
wood frame, flush shutter including
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked fixtures
of 6 Nos.stainless steel butt hinges (IS:12817) 150mm long, 2 Nos. Stainless Steel Tower (IS:15833) 250
mm Long Bolt-10 mm 245 at top, 1No. of Godrej Mortise lock Elc 05 6 - Lever Zinc Alloy Door handle with
body and 2 Nos of Rubber door stop bushes including fixing the fixtures to door with required number of
screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame
etc, including overheads & contractors profit etc., all taxes but excluding GST complete for finished item of
work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not
less than 10 mm) (1500mm x 2430mm)
Cost analysis
Cost of medium TW frame 2 m to 3m
length 0.04691 cum 80689.00 1 cum 3785.12
Cost of medium TW frame up to 2 m
length 0.01448 cum 72620.00 1 cum 1051.54
Cost of 40 mm thick flush shutter- TBSC-
L.II- 07 2.78 sqm 1528.00 1 sqm 4253.95
10 S10 Supply and fixing doors as per drawings with medium teak wood frame of section 127mm x 76 mm ,
Providing and fixing 35mm thick solid wood polymer composite (WPC) single extruded door shutter (plain
finish and ivory colours) with 3mm top and bottom rigid layer with an overall density of 750 Kgs/cum and Teak
wood beading of size 2" X 1" alround the frame including cost and conveyance to site of teak wood frame,
WPC shutter including
Cost analysis
Cost of medium TW frame 2 m to 3m
length 0.04691 cum 80689.00 1 cum 3785.12
Cost of medium TW frame up to 2 m
length 0.00965 cum 72620.00 1 cum 700.78
Cost of 35 mm thick WPC shutter- BMT-
N.88 1.76 sqm 3030.00 1 sqm 5332.80
Teakwood beading of size 2"X1" alround
the frame 0.0073 cum 80689.00 1 cum 585.00
Cost of MS Z hold fasts (Non-SSR) 6 Nos. 32.00 Each 192.00
Cost of Stainless steel Butt hinges
(IS:205)- 150 mm Long - TBSC-P.II-22 3 Nos. 148.00 Each 444.00
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked fixtures
of 6 Nos.stainless steel butt hinges (IS:12817) 150mm long, 2 Nos. Stainless Steel Tower (IS:15833) 250
mm Long Bolt-10 mm 245 at top , 1 No. Godrej Kadi Tala 275mm and 2 Nos of Rubber door stop bushes
including fixing the fixtures to door with required number of screws, bolt and nuts including labour charges for
fixing the frame in position, fixing the shutter to the frame etc, including overheads & contractors profit etc., all
taxes but excluding GST complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of
door shall be embedded in flooring for a depth of not less than 10 mm) (1000mm x 2430mm)
Cost analysis
Cost of medium TW frame 2 m to 3m
length 0.04691 cum 80689.00 1 cum 3785.12
Cost of medium TW frame up to 2 m
length 0.00965 cum 72620.00 1 cum 700.78
Cost of 35 mm thick WPC shutter- BMT-
N.88 1.76 sqm 3030.00 1 sqm 5332.80
Teakwood beading of size 2"X1" alround
the frame 0.0073 cum 80689.00 1 cum 585.00
Cost of MS Z hold fasts (Non-SSR) 6 Nos. 32.00 Each 192.00
Cost of Stainless steel Butt hinges
(IS:205)- 150 mm Long - TBSC-P.II-22 6 Nos. 148.00 Each 888.00
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked fixtures
of 3 Nos.stainless steel butt hinges (IS:12817) 150mm long, 1 Nos. Stainless Steel Tower (IS:15833) 150
mm Long Bolt-10 mm 147 at top , 1 No. Godrej cylindrical lock (stainless steel) and 1 Nos of Rubber door
stop bushes including fixing the fixtures to door with required number of screws, bolt and nuts including
labour charges for fixing the frame in position, fixing the shutter to the frame etc, including overheads &
contractors profit etc., all taxes but excluding GST complete for finished item of work as per APSS 1001 &
1002 (The vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm) (760mm x
2130mm)
Cost analysis
Cost of medium TW frame 2 m to 3m
length 0.04112 cum 80689.00 1 cum 3317.93
Cost of medium TW frame up to 2 m
length 0.00734 cum 72620.00 1 cum 533.03
Cost of 35 mm thick WPC shutter- BMT-
N.88 1.28 sqm 3030.00 1 sqm 3878.40
Teakwood beading of size 2"X1" alround
the frame 0.0063 cum 80689.00 1 cum 506.32
Cost of MS Z hold fasts (Non-SSR) 6 Nos. 32.00 Each 192.00
Cost of Stainless steel Butt hinges
(IS:205)- 150 mm Long - TBSC-P.II-22 3 Nos. 148.00 Each 444.00
Rate as per per Lowest Quotation 1.00 SQM 3767.40 1.00 SQM 3767.40
Transporation charges @ 1.5% 56.51
Hire charges for Access Scaffolding 1.00 SQM 1.03 1.00 SQM 1.03
Labour charges for scaffolding 1.00 SQM 10.84 1.00 SQM 10.84
Add for screws etc., 12.00
Rate per 1 Sqm 3847.78
OH & CP 0.100 3847.78 384.78
4232.56
Say
4232.56
Add T.P @ 1.98% Exess 83.80
4316.36
14 S14 Supply and installation of Ital Mesh (Aluminium Mesh) on existing MS Frame work with necessary
hardware for all floors
Rate as per per Lowest Quotation 1.00 SQM 6996.60 1.00 SQM 6996.60
Transporation charges @ 1.5% 104.95
Hire charges for Access Scaffolding 1.00 SQM 1.03 1.00 SQM 1.03
Labour charges for scaffolding 1.00 SQM 10.84 1.00 SQM 10.84
Add for screws etc., 12.00
Rate per 1 Sqm 7125.42
OH & CP 0.1 7125.42 712.54
7837.96
Say 7837.96
Add T.P @ 1.98% Exess 155.19
7993.15
15 S15 Providing and fixing of frameless Single leaf glazed door as per architectural design of size approximately
1000 X 2400mm fabricated with 12mm thick toughened glass including providing of brass cast body Floor
Spring IS: 6315 sleek in size with the S.S. / Brass Cover plates of Length 320 mm x Breadth 130 mm size
along with the Top Patch, Bottom Patch, Door Lock and Pivot with Double Cylinder etc., complete as approved
by Engineer-in-charge including other accessories, labour charges for manufacuturing and fixing etc.,
including overheads &contractors profit complete for finished item of work
Labour Charges for Fixing of Glass 2.4 Sqm 1012.00 1.00 Sqm 2428.80
Designing (TBSC-T.I-22)
Add for MA @ 25% 0.25 2428.80 607.20
18579.60
Unit : 1 sqm
A. MATERIALS:
cost of 4mm thick Aluminium composite
panel cladding- TBSC-R.I-19
1.00 Sqm 2868.00 1 Sqm 2868.00
Scffolding charges 1.00 Sqm 15.13 15.13
Add for MA @ 25% 0.25 15.13 3.78
Rate per 1Sqm 2886.91
Overheads&Contractors Profit @13.615% 0.13615 2886.91 393.05
Rate per 1 RM 3279.97
say 3280.00
64.94
3344.94
20 S23 Supplying and fixing aluminium composite cladding 4mm thick with skin material 0.5 mm thick
aluminium sheet cover material natural polyethylene aluminium cladding panel fixed with extruded aluminium
basis frame (50x25x1.5mm) angle cleats, weather sealants, rivets, GI brackets all as approved, using suitable
bolts on structural steel work including necessary accessories complete in all respects including all labour
charges, overheads and contractors profit etc., complete for finished item of work including scaffolding
charges, cost of structural steel, structural steel fabrication etc., complete for finished item of work at all
heights
21 S29 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) sliding windows two track sliding duly
manufactured using UPVC reinforced profiles of (62 mm x 60 mm)/(60 mm x 45 mm)/ (60 mm x 52 mm) x 2.0
mm for outer frames, (66 mm x 38 mm)/(58 mm x 39 mm)/ (60 mm x 42 mm) x 2.0 mm for sliding shutter
frames capable of mounting single glazing system, structurally reinforced with hot dip galvanized up to 50
microns of minimum thickness of 1.2 mm prefabricated & welded through fusion welding the window sash shall
be fitted with 5 mm thick clear float glass of reputed make duly fixed with TPV Gaskets/ EPDM weathering seal
resistant accessories like locking system 1 No., per set of sashes and the system is to be installed at the site
using anchor fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc., including cost and
conveyance of all materials, accessories, labour charges for transportation, erection at site with templates for
casement sizing, overheads and contractors profit etc., complete for finished item of work
22 S30 &Supplying and fixing of MS Grill to windows using 25mm x 6mm MS flat alround and 10mm MS square bars
horizontally at 125mm centre to centre and vertically at 30cm centre to centre including fixing with 4 Nos of MS
Z holdfasts (2 on each side) duly making cutting brick masonry, fixing and making to original surface neatly
and painting grill with one coat of red oxide primer including cost all taxes and conveyance of all materials
including cutting, bending, welding including all operational charges and all labour charges etc., complete for
finished item of work.
2 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or equivalent UPVC Pipes and
Fittings SCH -80 Grade to meet the requirement of ncluding cost and conveyance of all
materials to site, labour charges for fixing, overheads & contractors profit complete for finished
item of work at all floor levels..
a) 80.00mm OD pipe
Rate as per market 1 RM 800.00 RM 800.00
Over head @ 13.615% 0.13615 800.00 108.92
Rate per 1 RM 908.92
say 908.92
Add T.P @ 1.98% Exess 18.00
926.92
GENERAL ABSTRACT
As per Working
Sl.No. Description of Item As per Sanctioned Estimate
Estimate
1 IT -Building (G+3 Floors) Amount Amount
`
As per Working
Sl.No. Description of Item As per Sanctioned Estimate
Estimate
Furniture and partitions (as per lowest
4
Quotation)
27472159.00
Provisions
Provision towards P.S. & Contingencies @
1 ` 2475454.00 ` 0.00
1.50%
Difference 44.01
Detailed Estimate for Sub station
S.No Description Nos L B D Quantity Unit
1 VRCC
a Columns
Qty executed vide P.No.55 of MB No. 13 1.91
e Lintel concrete
R/S 1 3.460 0.225 0.200 0.156
W 2 2.560 0.225 0.200 0.230
0.386
SAY 0.40 CUM
f Sun-Shade
R/S 1 3.600 0.600 2.160
W 2 2.700 0.600 3.240
5.400
SAY 6.00 Sqm
AE Cum 2708.50 99.83 270401.60 270401.60 0.00 This item is provided for
additional components such
as Panel Room, compound
wall, security room & gate
and sump executed. Hence
Qty exceeded
3 Plain Cement Concrete (1:4:8) (cement: fine Cum 384.00 Cum 3712.66 1425660.94 384.00 3712.66 1425660.9 0.00 0.00
aggregate: Coarse aggregate) for
foundations and under flooring bed using
coarse aggregate 40mm size hard ,
machine crushed granite metal from
approved quarry including cost and
conveyance of all materials like cement,
sand, coarse aggregate, water etc. to site,
including seigniorge charges,sales & all
other taxes,except GST on all materials and
including all charges for machine mixing,
laying concrete in foundations and under
flooring bed, ramming in 15 cm layers,
finishing top surface to the required level,
curing etc.,complete and overheads &
contractors profit, complete, , for finished
item of work. (APSS No. 402)
a) Vibrated Plain Cement Concrete (1:3:6) Cum 162.00 Cum 4656.01 754273.21 4656.01 0.00 0.00 754273.21
nominal mix using 40mm size machine
crushed hard granite metal and 20mm
graded machine crushed hard granite metal
(coarse aggregate) in (2:1) ratio from
approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand), coarse aggregate, water
etc. to site, seignorge charges,sales & other
taxes on all materials, all charges for mixing,
laying concrete in position, vibrating, curing,
centering charges, overheads & contractors
profit, all taxes except GST etc.,for finished
item of work for footings and basement .
a) Footings Cum 788.00 Cum 8897.18 7010978.89 788.00 8897.18 7010978.89 0.00 0.00
AE 154.15 8897.18 1371500.50 1371500.50 0.00 This item is provided for
additional components such
as Panel Room,compound
wall, security room & gate
and sump raft executed.
Hence Qty exceeded
c) Plinth beams Cum 110.00 Cum 11353.54 1248889.14 110.00 11353.54 1248889.14 0.00 0.00
AE 61.21 11353.54 694950.04 694950.04 0.00 This item is provided for
additional componets such
as Panel Room, Security
Room & Gate and compound
wall and also Tie beam is
executed for Main bldg.
Hence Qty exceeded.
a) Columns
un supported height up to 5.49 m
i Ground Floor Cum 196.00 Cum 13453.19 2636825.24 101.55 13453.19 1366171.44 0.00 1270653.80
un supported height up to 4.27 m
ii First Floor : Cum 85.00 Cum 13697.34 1164273.90 58.66 13697.34 803486.00 0.00 360787.90
iii Second Floor : Cum 85.00 Cum 14159.55 1203561.75 58.87 14159.55 833572.76 0.00 369988.99
iv Third Floor : Cum 85.00 Cum 14621.76 1242849.60 58.31 14621.76 852594.90 0.00 390254.70
vi Terrace Floor Cum 12.00 Cum 15083.97 181007.64 12.00 15083.97 181007.66 0.02 0.00
AE Cum 2.22 15083.97 33471.33 33471.33 0.00 The item is provided for
columns to a height of 4.66
mt head room for Lift -1 &
Lift-2 executed. Hece Qty
exceeded.
b) Lintels
i Ground Floor Cum 2.00 Cum 11771.75 23543.50 2.00 11771.75 23543.50 0.00 0.00
AE Cum 1.81 11771.75 21306.87 21306.87 0.00 This item is provided for
additional componets such
as panel room and Security
Room & Gate executed.
Hence Qty exceeded.
Terrace Floor : 28.00 Sqm 2386.81 66830.65 2386.81 0.00 0.00 66830.65
A) Roof beams
un supported height up to 5.49 m
i Ground Floor Cum 173.00 Cum 13349.09 2309392.80 117.18 13349.09 1564246.52 0.00 745146.28
i Ground Floor sqm 108.00 sqm 1612.23 174120.84 108.00 1612.23 174120.84 0.00 0.00
AE sqm 1045.84 1612.23 1686134.62 1686134.62 0.00 This item is executed as per
approved Structural
drawings. Hence Qty
exceeded
un supported height up to 4.27 m
ii First Floor : sqm 84.00 sqm 1463.74 122954.16 84.00 1463.74 122954.16 0.00 0.00
AE sqm 844.10 1463.74 1235542.93 1235542.93 0.00 This item is executed as per
approved Structural
drawings. Hence Qty
exceeded
iii Second Floor : sqm 84.00 sqm 1500.00 126000.00 84.00 1500.00 126000.00 0.00 0.00
AE 855.66 1500.00 1283490.00 1283490.00 0.00 This item is executed as per
approved Structural
drawings. Hence Qty
exceeded
iii Third Floor sqm 84.00 1537.93 129186.12 84.00 1537.93 129186.12 0.00 0.00
AE 923.50 1537.93 1420278.36 1420278.36 0.00 This item is executed as per
approved Structural
drawings. Hence Qty
exceeded
iv Terrace Floor Sqm 110.00 1574.19 173160.90 110.00 1574.19 173160.90 0.00 0.00
AE 19.54 1574.19 30754.95 30754.95 0.00 This item is executed as per
approved Structural
drawings. Hence Qty
exceeded
i Ground Floor sqm 909.00 1760.62 1600403.58 339.76 1760.62 598188.25 0.00 1002215.33
i Ground Floor sqm 467.00 sqm 1933.73 903051.91 1933.73 0.00 0.00 903051.91
i Ground Floor cum 2.00 cum 4897.33 9794.67 2.00 4897.33 9794.67 0.00 0.00
ii First Floor : cum 1.30 cum 5027.00 6535.10 1.30 5027.00 6535.10 0.00 0.00
iii Second Floor : cum 1.30 cum 5156.66 6703.66 1.30 5156.66 6703.66 0.00 0.00
vi Terrace Floor cum 1.00 cum 5415.98 5415.98 1.00 5415.98 5415.98 0.00 0.00
ii First Floor Sqm 8.00 Sqm 577.02 4616.18 577.02 0.00 0.00 4616.18
iii Second Floor Sqm 8.00 Sqm 600.94 4807.55 600.94 0.00 0.00 4807.55
iv Third Floor Sqm 8.00 Sqm 624.87 4998.93 624.87 0.00 0.00 4998.93
9 Filling with useful available excavated earth Cum 2864.00 Cum 29.35 84059.95 1960.70 29.35 57547.61 0.00 26512.34
(excluding rock) with a lead of 50 m in
trenches, sides of foundations and basement
with initial lead in layers not exceeding 15cm
thick, watering and ramming including cost
and conveyance of water to work site and all
operaitonal, incidental, labour charges, hire
charges of T&P etc., and overheads &
contractors profit, all taxes except GST
complete, , for fnished item of work (APSS
NO.309&310)
AE Cum 19013.81 380.88 7241979.95 7241979.95 0.00 This item gravel filling is
provided for entire site area
Phase-I & Phase-II due to
avoid of back water near by
pond and heavy flood occur
in rainy seasonfrom the city
because of low laying area
of site. Hence Qty exceeded.
i Ground Floor Cum 353.00 Cum 6259.62 2209647.15 353.00 6259.62 2209647.15 0.00 0.00
AE 346.63 6259.62 2169757.70 2169757.70 0.00 This item is provided for
additional componets such
as panel room ,compound
wall, security room & gate
and sump executed. Hence
Qty exceeded
ii First Floor : Cum 247.00 Cum 6708.51 1657002.88 188.84 6708.51 1266835.72 0.00 390167.15
iii Second Floor : Cum 225.00 Cum 7157.40 1610415.83 199.42 7157.40 1427329.44 0.00 183086.39
iv Third Floor : Cum 232.00 Cum 7606.32 1764665.35 196.14 7606.32 1491902.85 0.00 272762.50
vi Terrace Floor Cum 119.00 Cum 8055.21 958569.53 122.83 8055.21 989420.97 30851.44 0.00
i Ground Floor Sqm 33.00 Sqm 701.83 23160.39 33.00 701.83 23160.39 0.00 0.00
AE Sqm 62.71 701.83 44011.76 44011.76 0.00 This item is executed at
elevation in all sides .Hence
qty exceeded..
ii First Floor : Sqm 126.00 Sqm 771.49 97208.06 126.00 771.49 97208.06 0.00 0.00
AE Sqm 188.90 771.49 145734.93 145734.93 0.00 This item is executed at
elevation in all sides .Hence
qty exceeded..
iii Second Floor : Sqm 44.00 Sqm 841.16 37010.82 44.00 841.16 37010.82 0.00 0.00
AE Sqm 229.21 841.16 192801.14 192801.14 0.00 This item is executed at
elevation in all sides .Hence
qty exceeded..
iv Third Floor : Sqm 44.00 Sqm 910.82 40075.97 44.00 910.82 40075.97 0.00 0.00
AE 240.10 910.82 218687.28 218687.28 0.00 This item is executed at
elevation in all sides .Hence
qty exceeded..
i Ground Floor Cum 3.00 Cum 6173.01 18519.03 3.00 6173.01 18519.03 0.00 0.00
AE Cum 14.70 6173.01 90724.73 90724.73 0.00 This item is provided for
additional componets at
Pump Room. Hence qty
exceeded.
ii First Floor : Cum 3.00 Cum 6404.33 19213.00 3.00 6404.33 19213.00 0.00 0.00
AE Cum 1.55 6404.33 9926.72 9926.72 0.00 as per revised drawing width
of staircase increased from
1.4mt to 1.50mts. Hence qty
exceeded.
iii Second Floor : Cum 3.00 Cum 6635.65 19906.96 3.00 6635.65 19906.96 0.00 0.00
AE 1.55 6635.65 10285.27 10285.27 0.00 as per revised drawing width
of staircase increased from
1.4mt to 1.50mts. Hence qty
exceeded.
iv Third Floor : Cum 3.00 Cum 6866.98 20600.93 3.00 6866.98 20600.93 0.00 0.00
AE 1.55 6866.98 10643.81 10643.81 0.00 as per revised drawing width
of staircase increased from
1.4mt to 1.50mts. Hence qty
exceeded.
i Ground Floor M.T. 256.471 M.T. 68546.49 17580193.69 215.316 68546.49 14759156.0 0.00 2821037.65
ii First Floor : M.T. 93.687 M.T. 69822.53 6541461.50 57.109 69822.53 3987494.58 0.00 2553966.92
iii Second Floor : M.T. 93.707 M.T. 71098.56 6662462.77 53.918 71098.56 3833492.16 0.00 2828970.61
iv Third Floor : M.T. 93.719 M.T. 72374.61 6782911.07 59.354 72374.61 4295722.31 0.00 2487188.76
v Terrace Floor M.T. 18.79 M.T. 73650.64 1383895.53 15.186 73650.64 1118458.62 0.00 265436.91
i Ground Floor M.T. 0.20 M.T. 64371.13 12874.23 64371.13 0.00 0.00 12874.23
ii First Floor : M.T. 0.30 M.T. 65647.18 19694.15 65647.18 0.00 0.00 19694.15
iii Second Floor : M.T. 0.20 M.T. 66923.21 13384.64 66923.21 0.00 0.00 13384.64
iv Third Floor : M.T. 0.20 M.T. 68199.25 13639.85 68199.25 0.00 0.00 13639.85
i Basement Sqm 282.00 Sqm 205.42 57928.44 282.00 205.42 57928.44 0.00 0.00
AE 70.23 205.42 14426.65 14426.65 0.00 This item is executed for
additional componets such
as panel room and Security
Room . Hence qty
exceeded.
i Ground Floor Sqm 1225.00 Sqm 161.54 197886.50 279.736 161.54 45188.55 0.00 152697.95
ii First Floor : Sqm 923.00 Sqm 180.02 166158.46 180.02 0.00 0.00 166158.46
iii Second Floor : Sqm 923.00 Sqm 198.47 183187.81 198.47 0.00 0.00 183187.81
iv Third Floor : Sqm 883.00 Sqm 216.96 191575.68 216.96 0.00 0.00 191575.68
vi Terrace Floor Sqm 84.00 Sqm 235.43 19776.12 84.00 235.43 19776.12 0.00 0.00
AE 73.92 235.43 17402.99 17402.99 0.00 This item is exceuted for
additional area for Lift Head
Rooms
18 Plastering 12mm thick in two coats using
screened sand with base coat of 8mm thick
in CM (1:6) and top coat of 4mm thick in CM
(1:4) with dubara sponge finishing including
cost and conveyance of all materials like
cement, sand, water etc., to site, including
seigniorge charges,sales & other taxes
except GST on all materials, and all
operational & incidental charges including
cost and conveyance of all materials to site,
all labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing,
including cutting grooves as directed by
Engineer - in - charge etc., complete,
including overheads & contractors profit for
finished item of work. (SS 901,903 & 904)
i Ground Floor Sqm 2816.00 Sqm 404.24 1138339.84 2816.00 404.24 1138339.84 0.00 0.00
AE Sqm 3092.13 404.24 1249962.63 1249962.63 0.00 This item is executed for
additional componets such
as panel room, sump ,
security room & gate and
compound wall. Hence Qty
exceeded
ii First Floor : Sqm 1758.00 Sqm 444.12 780767.36 1420.45 444.12 630853.81 0.00 149913.55
iii Second Floor : Sqm 1839.00 Sqm 484.00 890066.81 1328.64 484.00 643055.12 0.00 247011.69
iv Third Floor : Sqm 1715.00 Sqm 523.87 898432.76 1370.11 523.87 717756.10 0.00 180676.66
i Ground Floor Sqm 861.00 Sqm 421.70 363083.70 861.00 421.70 363083.70 0.00 0.00
AE Sqm 1539.49 421.70 649202.93 649202.93 0.00 This item is executed for
additional componets such
as panel room , sump and
security room & gate and
also elevation in all sides of
main building . Hence Qty
exceeded.
ii First Floor : Sqm 1152.00 Sqm 461.58 531743.04 1152.00 461.58 531743.04 0.00 0.00
AE 461.58 336.65 461.58 155391.75 155391.75 0.00 The plastering 20mm thick
item is executed as per
necessity for the elevation
in all sides of main building .
Hence Qty exceeded.
iii Second Floor : Sqm 1152.00 Sqm 501.46 577676.16 1152.00 501.46 577676.16 0.00 0.00
AE 501.46 35813.92 35813.92 0.00 The plastering 20mm thick
item is executed as per
necessity for the elevation
in all sides of main building .
Hence Qty exceeded.
71.42
iv Third Floor : Sqm 1258.00 Sqm 541.33 680990.00 1258.00 541.33 680990.00 0.00 0.00
AE 541.33 11145.93 11145.93 0.00 The plastering 20mm thick
item is executed as per
necessity for the elevation
in all sides of main building .
Hence Qty exceeded.
20.59
v Terrace Floor Sqm 1012.00 Sqm 581.20 588171.87 1012.00 581.20 588171.87 0.00 0.00
i First Floor : Sqm 281.00 Sqm 473.57 133073.17 281.00 473.57 133073.17 0.00 0.00
AE Sqm 255.97 473.57 121217.63 121217.63 0.00 The impervious coat item is
necessary to execute as per
site condition for additional
componets such as Sump &
security room & gate inverted
slab. Hence Qty exceeded
ii Second Floor : Sqm 50.00 Sqm 508.29 25414.50 42.00 508.29 21348.18 0.00 4066.32
iii Third Floor : Sqm 109.00 Sqm 543.01 59188.09 88.00 543.01 47784.88 0.00 11403.21
iv Terrace Floor Sqm 1033.00 sqm 577.73 596795.09 1033.00 577.73 596795.09 0.00 0.00
AE 245.80 577.73 142006.03 142006.03 0.00 The impervious coat item is
provided for elevation
projection in all sides of the
building at terrace slab area.
Hence qty exceeded.
i Ground Floor Sqm 6.00 sqm 784.05 4704.28 4.00 784.05 3136.18 0.00 1568.09
i Ground Floor Sqm 31.00 sqm 364.97 11314.07 31.00 364.97 11314.07 0.00 0.00
AE sqm 129.00 364.97 47081.13 47081.13 0.00 This item is to be executed
for Panel Room
i Ground Floor sqm 682.00 Sqm 1048.62 715156.28 682.00 1048.62 715156.28 0.00 0.00
AE sqm 114.00 1048.62 119542.25 119542.25 0.00 This item is to be provided
for additional componets
such as security room &
gate. Hence qty exceeded
ii First Floor : sqm 649.00 Sqm 1087.29 705652.01 649.00 1087.29 705652.01 0.00 0.00
AE sqm 14.00 1087.29 15222.08 15222.08 0.00 As per flooring pattern in
approved drawing. Quantity
exceeded
iii Second Floor : sqm 649.00 Sqm 1125.97 730752.09 649.00 1125.97 730752.09 0.00 0.00
AE sqm 14.00 1125.97 15763.53 15763.53 0.00 As per flooring pattern in
approved drawing. Quantity
exceeded
iv Third Floor : sqm 609.00 Sqm 1164.64 709265.91 617.00 1164.64 718583.03 9317.12 0.00
i Ground Floor Sqm 492.00 Sqm 4284.48 2107965.88 476.00 4284.48 2039414.15 0.00 68551.74
ii First Floor Sqm 171.00 Sqm 4355.99 744874.29 171.00 4355.99 744874.29 0.00 0.00
AE Sqm 36.00 4355.99 156815.64 156815.64 0.00 As per flooring pattern in
approved drawing. Quantity
exceeded
i Ground Floor Rmt 384.00 Rmt 104.24 40026.53 384.00 104.24 40026.53 0.00 0.00
AE Rmt 31.00 104.24 3231.31 3231.31 0.00 This item is to be provided
for additional componets
such as security room &
building partitions as per
revised approved drawing .
Hence Qty exceeded.
ii First Floor : Rmt 295.00 Rmt 108.10 31890.46 295.00 108.10 31890.46 0.00 0.00
AE Rmt 194.00 108.10 20972.03 20972.03 0.00 This item is to be provided
building partitions as per
revised approved drawing .
Hence Qty exceeded.
iii Second Floor : Rmt 295.00 Rmt 111.97 33031.37 295.00 111.97 33031.37 0.00 0.00
AE Rmt 126.00 111.97 14108.31 14108.31 0.00 This item is to be provided
building partitions as per
revised approved drawing .
Hence Qty exceeded.
iv Third Floor : Rmt 264.00 Rmt 115.84 30581.27 264.00 115.84 30581.27 0.00 0.00
i Ground Floor Rmt 37.00 Rmt 386.24 14290.75 37.00 386.24 14290.75 0.00 0.00
ii First Floor : Rmt 113.00 Rmt 390.42 44117.65 113.00 390.42 44117.65 0.00 0.00
AE 22.00 390.42 8589.28 8589.28 0.00 As per flooring pattern in
approved drawing. Quantity
exceeded
iii Second Floor : Rmt 113.00 Rmt 394.61 44590.58 113.00 394.61 44590.58 0.00 0.00
AE 22.00 394.61 8681.35 8681.35 0.00 As per flooring pattern in
approved drawing. Quantity
exceeded
iv Third Floor : Rmt 113.00 Rmt 398.79 45063.53 113.00 398.79 45063.53 0.00 0.00
AE 22.00 398.79 8773.43 8773.43 0.00 As per flooring pattern in
approved drawing. Quantity
exceeded
i Ground Floor Sqm 374.00 Sqm 3733.59 1396362.66 175.00 3733.59 653378.25 0.00 742984.41
ii First Floor : Sqm 23.00 Sqm 3775.45 86835.35 23.00 3775.45 86835.35 0.00 0.00
AE Sqm 11.00 3775.45 41529.95 41529.95 0.00 As per flooring pattern in
revised approved drawing.
Quantity exceeded
iii Second floor Sqm 23.00 Sqm 3817.30 87797.90 23.00 3817.30 87797.90 0.00 0.00
AE Sqm 11.00 3817.30 41990.30 41990.30 0.00 As per flooring pattern in
revised approved drawing.
Quantity exceeded
iv Third floor Sqm 23.00 Sqm 3859.15 88760.45 23.00 3859.15 88760.45 0.00 0.00
AE 11.00 3859.15 42450.65 42450.65 0.00 As per flooring pattern in
revised approved drawing.
Quantity exceeded
i Ground Floor Sqm 14.00 Sqm 4033.40 56467.58 14.00 4033.40 56467.58 0.00 0.00
ii First Floor : Sqm 5.00 Sqm 4104.90 20524.52 5.00 4104.90 20524.52 0.00 0.00
iii Second Floor : Sqm 5.00 Sqm 4176.41 20882.06 5.00 4176.41 20882.06 0.00 0.00
iv Third Floor : Sqm 5.00 Sqm 4247.92 21239.59 5.00 4247.92 21239.59 0.00 0.00
i Ground Floor : Sqm 36.00 Sqm 4033.40 145202.34 36.00 4033.40 145202.34 0.00 0.00
ii First Floor : Sqm 29.00 Sqm 4104.90 119042.24 29.00 4104.90 119042.24 0.00 0.00
iii Second Floor : Sqm 29.00 Sqm 4176.41 121115.93 26.00 4176.41 108586.70 0.00 12529.23
iv Third Floor : Sqm 40.00 Sqm 4247.92 169916.72 40.00 4247.92 169916.72 0.00 0.00
i Ground Floor Sqm 51.00 Sqm 928.07 47331.63 46.00 928.07 42691.28 0.00 4640.36
ii First Floor : Sqm 50.00 Sqm 966.75 48337.31 45.00 966.75 43503.58 0.00 4833.73
iii Second Floor : Sqm 50.00 Sqm 1005.42 50271.01 45.00 1005.42 45243.91 0.00 5027.10
iv Third Floor : Sqm 50.00 Sqm 1044.10 52204.76 45.00 1044.10 46984.29 0.00 5220.48
i Ground Floor Sqm 217.00 Sqm 638.44 138540.87 217.00 638.44 138540.87 0.00 0.00
ii First Floor : Sqm 205.00 Sqm 650.54 133361.15 205.00 650.54 133361.15 0.00 0.00
AE 23.00 650.54 14962.47 14962.47 0.00 This item is to be provided
for dadooing heigtht is
increased from 2.10 mt to
2.40mts as per revised
approved drawing . Hence
Qty exceeded.
iii Second Floor : Sqm 205.00 Sqm 662.65 135842.88 205.00 662.65 135842.88 0.00 0.00
AE 23.00 662.65 15240.91 15240.91 0.00 This item is to be provided
for dadooing heigtht is
increased from 2.10 mt to
2.40mts as per revised
approved drawing . Hence
Qty exceeded.
iv Third Floor : Sqm 205.00 Sqm 674.75 138324.35 205.00 674.75 138324.35 0.00 0.00
AE 23.00 674.75 15519.32 15519.32 0.00 This item is to be provided
for dadooing heigtht is
increased from 2.10 mt to
2.40mts as per revised
approved drawing . Hence
Qty exceeded.
i Ground Floor sqm 35.10 sqm 9076.70 318592.25 9076.70 0.00 0.00 318592.25
ii First Floor : sqm 23.40 sqm 9076.70 212394.83 2.43 9076.70 22056.39 0.00 190338.45
iii Second Floor : sqm 23.40 sqm 9076.70 212394.83 9076.70 0.00 0.00 212394.83
iv Third Floor : sqm 19.50 sqm 9076.70 176995.70 9076.70 0.00 0.00 176995.70
i Ground Floor 13.00 sqm 9076.70 117997.13 9076.70 0.00 0.00 117997.13
ii First Floor : 7.80 sqm 9076.70 70798.28 9076.70 0.00 0.00 70798.28
iii Second Floor : 7.80 sqm 9076.70 70798.28 9076.70 0.00 0.00 70798.28
iv Third Floor : 7.80 sqm 9076.70 70798.28 9076.70 0.00 0.00 70798.28
35 Supply and fixing doors as per drawings with
medium teak wood frame of section 100mm
x 65 mm and ISI marked Flush door
shutters, solid bond wood block board type
with teak ply on both faces.: 35 mm thick
Single shutter conforming to IS:2202
including
i Ground Floor sqm 11.34 sqm 7647.07 86717.76 1.89 7647.07 14452.96 0.00 72264.80
ii First Floor : sqm 7.56 sqm 7647.07 57811.84 7647.07 0.00 0.00 57811.84
iii Second Floor : sqm 7.56 sqm 7647.07 57811.84 7647.07 0.00 0.00 57811.84
iv Third Floor : sqm 7.56 sqm 7647.07 57811.84 7647.07 0.00 0.00 57811.84
v Terrace Floor sqm 9.45 sqm 7647.07 72264.80 7647.07 0.00 0.00 72264.80
i Ground Floor sqm 11.03 sqm 7706.56 84964.82 1.58 7706.56 12137.83 0.00 72826.99
ii First Floor : sqm 9.45 sqm 7706.56 72826.99 7706.56 0.00 0.00 72826.99
iii Second Floor : sqm 9.45 sqm 7706.56 72826.99 7706.56 0.00 0.00 72826.99
iv Third Floor : sqm 9.45 sqm 7706.56 72826.99 7706.56 0.00 0.00 72826.99
i Ground Floor Sqm 68.00 Sqm 5079.25 345389.06 68.00 5079.25 345389.06 0.00 0.00
ii First Floor : Sqm 62.00 Sqm 5079.25 314913.55 37.00 5079.25 187932.28 0.00 126981.27
iii Second Floor : Sqm 62.00 Sqm 5079.25 314913.55 37.00 5079.25 187932.28 0.00 126981.27
iv Third Floor : Sqm 62.00 Sqm 5079.25 314913.55 37.00 5079.25 187932.28 0.00 126981.27
i Ground Floor Sqm 4041.00 Sqm 219.94 888791.80 4041.00 219.94 888791.80 0.00 0.00
ii First Floor : Sqm 2681.00 Sqm 219.94 589668.60 2174.00 219.94 478157.23 0.00 111511.37
iii Second Floor : Sqm 2762.00 Sqm 219.94 607484.03 2082.00 219.94 457922.43 0.00 149561.60
iv Third Floor : Sqm 2598.00 Sqm 219.94 571413.29 2077.00 219.94 456822.71 0.00 114590.58
v Terrace Floor Sqm 255.00 Sqm 219.94 56085.60 255.00 219.94 56085.60 0.00 0.00
i Ground Floor Sqm 2816.00 Sqm 159.39 448840.40 2816.00 159.39 448840.40 0.00 0.00
AE 4146.00 159.39 660828.23 660828.23 0.00 As per instructions of the VC
& MD and approved
drawings the additional
partition walls and
cabins/office rooms &
Gypbord false ceiling
( Cafeteria, Audio visual
ii First Floor : Sqm 1758.00 Sqm 159.39 280206.47 1758.00 159.39 280206.47 0.00 0.00 room, entrance lobby
AE 416.00 159.39 66305.97 66305.97 0.00 etc.,)qty increased of the VC
As per instructions
& MD and approved
drawings the additional
partition walls and
cabins/office rooms &
Gypbord false ceiling qty
increased
iii Second Floor : Sqm 1839.00 Sqm 159.39 293117.01 1839.00 159.39 293117.01 0.00 0.00
AE 243.00 159.39 38731.61 38731.61 0.00 As per instructions of the VC
& MD and approved
drawings the additional
partition walls and
cabins/office rooms &
Gypbord false ceiling qty
increased
iv Third Floor : Sqm 1715.00 Sqm 159.39 273352.73 1715.00 159.39 273352.73 0.00 0.00
v Terrace Floor Sqm 171.00 Sqm 159.39 27255.58 171.00 159.39 27255.58 0.00 0.00
AE 159.39 81288.57 81288.57 0.00 The internal painting item is
provided for Lift head Room ,
staircase head room &
central cut-out
510.00
40 Providing and applying Wall putty of White
Cement or Polymer or Cement based of
average 2 to 3 mm thickness over plastered
surface to prepare the surface even and
smooth after thoroughly brushing the surface
to remove all dirt and remains of loose
powdered materials, applying emery paper,
Sand the surface, clean & wipe off loose
dust, applying putty/ texture paint filler by
putty knife / muslin pad, air dry for 2 - 3 hrs
for the surface preparation including cost
and conveyance of all materials to work site
and all operational, incidental, labour
charges all taxes except GST, over heads
and contractors profit etc., etc. complete for
finished item of work for external walls
i Ground Floor : Sqm 913.00 Sqm 397.70 363102.79 850.00 397.70 338047.50 0.00 25055.29
ii First Floor : Sqm 1152.00 Sqm 397.70 458153.79 373.00 397.70 148343.20 0.00 309810.59
iii Second Floor : Sqm 1152.00 Sqm 397.70 458153.79 306.00 397.70 121697.10 0.00 336456.69
iv Third Floor : Sqm 1258.00 Sqm 397.70 500310.30 320.00 397.70 127264.94 0.00 373045.36
v Terrace Floor Sqm 1012.00 Sqm 397.70 402475.38 461.00 397.70 183341.06 0.00 219134.32
i Ground Floor : Sqm 913.00 Sqm 230.20 210173.23 913.00 230.20 210173.23 0.00 0.00
AE Sqm 1610.00 230.20 370623.11 370623.11 0.00 This item is to be provided
for additional componets
such as substation , Sump
and Compouund wall.
ii First Floor : Sqm 1152.00 Sqm 230.20 265191.20 1152.00 230.20 265191.20 0.00 0.00
AE 230.20 77577.63 77577.63 0.00 This item is to be provided
for external and elevation
projection in all sides of main
337.00 building.
iii Second Floor : Sqm 1152.00 Sqm 230.20 265191.20 1152.00 230.20 265191.20 0.00 0.00
AE 230.20 16574.45 16574.45 This item is to be provided
for external and elevation
projection in all sides of main
72.00 building.
iv Third Floor : Sqm 1258.00 Sqm 230.20 289592.47 1258.00 230.20 289592.47 0.00 0.00
AE 230.20 4834.21 4834.21 This item is to be provided
for external and elevation
projection in all sides of main
21.00 building.
v Terrace Floor Sqm 1012.00 Sqm 230.20 232963.10 1,012.00 230.20 232963.10 0.00 0.00
AE 230.20 32228.10 32228.10 0.00 This item is to be provided
for external and elevation
projection in all sides of main
140.00 building.
Sqm 1003.00 Sqm 159.78 160258.84 617.00 159.78 98583.95 0.00 61674.89
i Ground Floor Sqm 40.00 Sqm 1010.95 40438.03 40.00 1010.95 40438.03 0.00 0.00
AE 9.00 1010.95 9098.56 9098.56 0.00 This item is to be provided
for additional componets
such as security room .
ii First Floor : Sqm 29.00 Sqm 1010.95 29317.57 29.00 1010.95 29317.57 0.00 0.00
AE 2.00 1010.95 2021.90 2021.90 0.00 Quantity exceeded as per
approved drawings.
iii Second Floor : Sqm 29.00 Sqm 1010.95 29317.57 29.00 1010.95 29317.57 0.00 0.00
AE 5.00 1010.95 5054.75 5054.75 0.00 Quantity exceeded as per
approved drawings.
i Ground Floor Sqm 12.00 Sqm 186.93 2243.16 12.00 186.93 2243.16 0.00 0.00
ii First Floor : Sqm 10.00 Sqm 186.93 1869.30 10.00 186.93 1869.30 0.00 0.00
iii Second Floor : Sqm 10.00 Sqm 186.93 1869.30 10.00 186.93 1869.30 0.00 0.00
iv Third Floor : Sqm 10.00 Sqm 186.93 1869.30 10.00 186.93 1869.30 0.00 0.00
v Terrace Floor Sqm 22.00 Sqm 186.93 4112.45 22.00 186.93 4112.45 0.00 0.00
AE 12.00 186.93 2243.16 2243.16 0.00 Quantity exceeded as per
approved drawings.
45 Providing and supplying aluminium extruded
tubular and other aluminium sections as per
the architectural drawings and approved
shop drawings , the aluminium quality as per
grade 6063 T5 or T6 as per BS
1474,including super durable powder coating
of 60 to 80 microns conforming to AAMA
2604 of required colour and shade as
approved by the Engineer-in-Charge. ( The
item includes cost of material such as cleats,
sleeves, screws etc. necessary for
fabrication of extruded aluminium frame
work. Nothing extra shall be paid on this
account). including cost and conveyance of
all material to site, all labour charges, all
incidental charges, hire and operational
charges of all equipment, all taxes except
GST and overheads and contractor's profit
etc complete (Shop Drawings should be
prepared by agency at his own cost for
approved TSIIC based on the conceptual
drawing )
i Ground Floor Kgs 3810.00 Kgs 384.30 1464193.43 3480.00 384.30 1337373.53 0.00 126819.90
ii First Floor : Kgs 2214.00 Kgs 384.30 850846.26 2214.00 384.30 850846.26 0.00 0.00
iii Second Floor : Kgs 2220.00 Kgs 384.30 853152.08 2220.00 384.30 853152.08 0.00 0.00
AE 472.00 384.30 181390.89 181390.89 0.00 Earlier, the elevation part is
provided with UPVC
windows. Now as per
approved drawings the
elevation part is provided
with curtain glazing
iv Third Floor : Kgs 2094.00 Kgs 384.30 804729.93 2094.00 384.30 804729.93 0.00 0.00
AE 598.00 384.30 229813.04 229813.04 0.00 Earlier, the elevation part is
provided with UPVC
windows. Now as per
approved drawings the
elevation part is provided
with curtain glazing
i Ground Floor Sqm 32.00 Sqm 7508.82 240282.24 29.00 7508.82 217755.78 0.00 22526.46
ii First Floor : Sqm 19.00 Sqm 7508.82 142667.58 18.00 7508.82 135158.76 0.00 7508.82
iii Second Floor : Sqm 19.00 Sqm 7508.82 142667.58 6.00 7508.82 45052.92 0.00 97614.66
iv Third Floor : Sqm 18.00 Sqm 7508.82 135158.76 17.00 7508.82 127649.94 0.00 7508.82
i Ground Floor Sqm 568.00 Sqm 1165.02 661732.79 301.00 1165.02 350671.78 0.00 311061.01
ii First Floor : Sqm 425.00 Sqm 1165.02 495134.57 295.00 1165.02 343681.65 0.00 151452.93
iii Second Floor : Sqm 424.00 Sqm 1165.02 493969.55 295.00 1165.02 343681.65 0.00 150287.91
iv Third Floor : Sqm 404.00 Sqm 1165.02 470669.10 295.00 1165.02 343681.65 0.00 126987.46
i Ground Floor 568.00 Sqm 1028.75 584329.88 568.00 1028.75 584329.88 0.00 0.00
AE 710.00 1028.75 730412.36 730412.36 0.00 The Gypboard false ceiling
item quantity increased due
to hide the HVAC duct,
electrical panels and Fire
Fightiing pipes and also
gypboard bottom to
armstrong bottom (depth of
75mm )alround the room and
also the instructions of VC &
MD, partitions/cabins/Office
rooms increased. Hence
Qty exceeded.
ii First Floor : 425.00 Sqm 1028.75 437218.66 425.00 1028.75 437218.66 0.00 0.00
iv Third Floor : 404.00 Sqm 1028.75 415614.92 404.00 1028.75 415614.92 0.00 0.00
AE 365.00 1028.75 375493.68 375493.68 0.00 The Gypboard false ceiling
item quantity increased due
to hide the HVAC duct,
electrical panels and Fire
Fightiing pipes and also
gypboard bottom to
armstrong bottom (depth of
75mm )alround the room and
also the instructions of VC &
MD, partitions/cabins/Office
rooms increased. Hence
Qty exceeded.
i Ground Floor Sqm 53.00 Sqm 5074.05 268924.43 38.00 5074.05 192813.74 0.00 76110.69
ii First Floor : Sqm 130.00 Sqm 5074.05 659625.97 18.00 5074.05 91332.83 0.00 568293.14
iii Second Floor : Sqm 130.00 Sqm 5074.05 659625.97 29.00 5074.05 147147.33 0.00 512478.64
iv Third Floor : Sqm 130.00 Sqm 5074.05 659625.97 18.00 5074.05 91332.83 0.00 568293.14
i Ground Floor Sqm 81.00 Sqm 5786.41 468699.37 81.00 5786.41 468699.37 0.00 0.00
iii Second Floor : Sqm 104.00 Sqm 5786.41 601786.84 40.00 5786.41 231456.48 0.00 370330.36
iv Third Floor : Sqm 104.00 Sqm 5786.41 601786.84 29.00 5786.41 167805.95 0.00 433980.90
a For Elevation , Security Room & Gate MT 82.16 MT 127154.1 10447044.04 24.08 127154.12 3061871.21 0.00 7385172.83
vi Terrace Floor 1.86 MT 127154.1 236782.84 1.04 127154.12 132240.28 0.00 104542.56
i Ground Floor : 116.00 Sqm 3258.48 377983.47 116.00 3258.48 377983.47 0.00 0.00
AE 322.00 3258.48 1049229.98 1049229.98 0.00 The ACP Cladding item, the
additional areas all sides of
columns and elevation roof
beams is not covered in the
estimate and it is necessity
to execute the item. Hence
Qty exceeded.
i Ground Floor : 116.00 Sqm 921.17 106855.51 116.00 921.17 106855.51 0.00 0.00
ii First Floor : Sqm 930.85 0.00
iii Second Floor : Sqm 940.54 0.00
iv Third Floor : Sqm 950.22 0.00
Ground Floor 2417.44 0.00 2417.44 224822.21 224822.21 0.00 The Toughed glass item, the
additional area at Ground
floor is not covered at in the
estimate and it is necessity
to execute the item. Hence
Qty exceeded.
93.00
i First Floor : 78.00 Sqm 2417.44 188560.57 179.00 2417.44 432722.33 244161.76 0.00
Second Floor 2417.44 2417.44 403713.01 403713.01 0.00 The Toughed glass item, the
additional area at Second
floor is not covered at in the
estimate and it is necessity
to execute the item. Hence
Qty exceeded.
167.00
ii Third Floor : 9.00 Sqm 2417.44 21756.99 137.00 2417.44 331189.71 309432.72 0.00
i First Floor : 47.00 Sqm 3978.80 187003.47 47 3978.80 187003.47 0.00 0.00
ii Second Floor : 47.00 Sqm 3978.80 187003.47 47 3978.80 187003.47 0.00 0.00
iii Third Floor : 47.00 Sqm 3978.80 187003.47 47 3978.80 187003.47 0.00 0.00
Terrace Floor Sqm 173.00 Sqm 1605.56 277761.88 64 1605.56 102755.84 0.00 175006.04
i Ground Floor RM 36.00 RM 347.43 12507.48 5.00 347.43 1737.15 0.00 10770.33
iii Terrace Floor 622.00 RM 347.43 216101.46 622.00 347.43 216101.46 0.00 0.00
16585172.04
Internal and external Sanitary &
WaterSupply
101.60mm dia upto 914.40mm (3') depth Rmt 100.00 Rmt 480.59 48059.15 100.00 480.59 48059.15 0.00 0.00
152.40mm dia upto 914.40mm (3') depth Rmt 250.00 Rmt 715.77 178943.63 250.00 715.77 178943.63 0.00 0.00
203.20mm dia upto 1524mm (5') depth Rmt 300.00 Rmt 989.87 296961.21 300.00 989.87 296961.21 0.00 0.00
2 Supplying and fixing of SWG Gully traps Each 10 Each 676.01 6760.09 10.00 676.01 6760.09 0.00 0.00
150mm x 100mm of ISI make confirming to
IS 651 & 4127 with C.I grating & constructing
cement brick masonry in CM (1:6) prop.,
intermediate chamber and fitted with 304.8
mm X 288.6 mm (12"x9") C.I Frame with
hinged cover of standard make as approved
including cost and conveyance of all
materials to site, labour charges,, overheads
& contractors profit etc., all taxes, except
GST complete for finished item of work.
3 Constructing 457.2 mm x 457.2 mm Each 11 Each 4332.14 47653.54 11.00 4332.14 47653.54 0.00 0.00
(1'6"x1'6") brick in CM 1:6 prop. Masonry.
Inspection chamber upto 914.4 mm (3'0")
and fitted with light weight 457.2 mm x 457.2
mm (1'6"x1'6") C.I frame and cover of 20 Kg
including cost and conveyance of all
materials like cement, sand, bricks, water
etc., to site, cost of seigniorage charges on
all materials and all incidental and
operational, labour charges like mixing
cement mortar, constructing masonry, lift
charges, curing,, etc overheads &
contractors profit etc., all taxes, except GST
complete for finished item of work as per
Standard specification.
4 Constructing 904.0 mm (3’0”) dia brick Each 10 Each 8317.75 83177.54 10.00 8317.75 83177.54 0.00 0.00
masonry inspection chamber as per IS -
4111: Part-1:1986 with cement mortar (1:6)
prop using 2nd Class Clay Bricks of 225 mm
thick from approved source having a
minimum crushing strength of 5 N/sq.mm
including plastering with cement mortar 1:3
prop; ½” thick both inside and outside fitted
with 20” dia RCC manhole covers and
frames including excavating pits up to a
depth of 904 mm (3'-0") in all sorts of soils
(exculding rock) and laying cement conrete
(1:4:8) 150 mm thick using 40 mm HBG
Metal and P.C.C. 1:2:4 benching and
channel 100 mm thick as per Standard
specification and including cost and
conveyance of all materials like cement,
sand, bricks, water etc., to site, cost of
seigniorage charges on all materials and all
incidental and operational, labour charges
like mixing cement mortar, constructing
masonry, lift charges, curing etc., overheads
& contractors profit etc.,all taxes, except
GST, complete for finished item of work as
per Standard specification.
6 Supplying and fixing of 4" (101.6mm) multi Each 150 Each 162.47 24370.42 150.00 162.47 24370.42 0.00 0.00
floor trap with jali - UPVC/SWR pipe fittings
as per site requirements with standard
practice for all floors including cost and
conveyance of all materials to site, labour
charges, , overheads & contractors profit
etc., all taxes, except GST complete for
finished item of work.
9 Supplying and fixing of stainless steel sink of Each 35 Each 5053.60 176875.83 35.00 5053.60 176875.83 0.00 0.00
size 508.00mm x 457.2mm x 203.20mm,
1mm thick of Indian make fixed on cantilever
brackets including supply and fixing 32mm
dia nominal size C.P. waste coupling, 30 mm
nominal size dia PVC flexible waste pipe of
914.4 mm length of Ist quality including
chiselling brick masonry wall and making
good & restoring to original surfaces,
including cost and conveyance of all
materials to site, labour charges etc
overheads & contractors profit etc., all taxes,
except GST complete for finished item of
work in all floors
11 Supplying and fixing TV shape mirror with Each 35 Each 529.45 18530.61 35.00 529.45 18530.61 0.00 0.00
plastic frame of size 609.6mm x 457.2mm,
plywood back with NP screws 1st quality
including cost and conveyance of all
materials, labour charges, , overheads &
contractors profit all taxes except GST,
complete for finished item of work in all
floors.
12 Supplying and fixing of 25 mm nominal size Each 35 Each 169.29 5925.02 35.00 169.29 5925.02 0.00 0.00
dia and 609.6mm long aluminium anodized
towel rod with brackets and aluminium
screws including cost and conveyance of all
materials,labour charges, , overheads &
contractors profit all taxes, except GST,
complete for finished item of work.
13 S&F of Chromium plated finish stainless Each 35 Each 899.83 31494.08 35.00 899.83 31494.08 0.00 0.00
steel body Toilet paper holder with 10 years
warranty including cost and conveyance of
all materials,labour charges, , overheads &
contractors profit all taxes, except GST,
complete for finished item of work.
14 Supplying and fixing 15 mm brass body CP NO 85 NO 267.85 22767.03 85.00 267.85 22767.03 0.00 0.00
finish bib tap of not less than 300 grams
weight screw type (full turn) with internal /
external threaded connection conforming to
IS 8931 as approved by the Engineer-In-
Charge including cost and conveyance of all
materials, labour charges, overheads &
contractors profit etc, all taxes except GST,
complete for finished item of work in all
floors.
16 Supplying and fixing white glazed flat back Each 50 Each 3372.95 168647.27 50.00 3372.95 168647.27 0.00 0.00
half stall urinals of size 590 mm x 375 mm x
390 mm 1st quality conforming to IS:2556-
1995 with standard C.P. Spreader fixed with
screws complete Indian make
(HSW/Parry/Neycer) as approved by
Engineer-in-charge, including supply and
fixing 15 mm nominal size PVC connection
with brass union nut C.P coated, 15 mm
brass body CP finish self closing tap push
type conforming to IS 1711, 30 mm nominal
size dia PVC flexible waste pipe of 914.4
mm length of Ist quality including cost and
conveyance of all materials to site, labour
charges overheads & contractors profit etc.,
all taxes, except GST complete for finished
item of work for all floors.
17 Supplying and fixing of 16mm to 20 mm thick Each 50 Each 2051.67 102583.61 50.00 2051.67 102583.61 0.00 0.00
polished marble slab partitioins of size 4' 0" x
2' 0" for urinals including full rounding the
edges, fixing in position, polishing, including
cost and conveyance of all materials and
labour charges,all taxes, except GST,
overheads & contractors profit etc., all taxes,
except GST complete for finished item of
work for all floors.
15.90mm OD pipe Rmt 124.00 Rmt 160.20 19864.45 124.00 160.20 19864.45 0.00 0.00
22.20mm OD pipe Rmt 525.00 Rmt 195.42 102594.35 525.00 195.42 102594.35 0.00 0.00
28.60mm OD pipe Rmt 256.00 Rmt 234.05 59916.01 256.00 234.05 59916.01 0.00 0.00
34.90mm OD pipe Rmt 42.00 Rmt 319.26 13408.84 42.00 319.26 13408.84 0.00 0.00
41.30mm OD pipe Rmt 97.00 Rmt 395.38 38351.88 97.00 395.38 38351.88 0.00 0.00
54.00mm OD pipe Rmt 312.00 Rmt 577.16 180075.23 312.00 577.16 180075.23 0.00 0.00
19 Supplying and fixing 65 mm Nominal Bore GI Rmt 250.00 Rmt 911.19 227798.08 250.00 911.19 227798.08 0.00 0.00
pipe Medium Grade properties & weight as
per IS 1239 in ground or on wall with GI
fittings such as elbows tees couplings,
nipples, plugs including excavation for
trenches and refilling the trenches ,chiselling
masonry walls and making good the walls &
floors to the original surface and fixing MS
clamps on TW blocks on walls including cost
and conveyance of all materials and labour
charges , overheads & contractors profit
complete for finished item of work except for
GI bends union and GI connectors with
checkout and socket Tata or Zenith make or
equivalent
25mm Nominal bore Each 3 Each 1271.35 3814.06 3.00 1271.35 3814.06 0.00 0.00
32mm Nominal bore Each 3 Each 1931.46 5794.37 3.00 1931.46 5794.37 0.00 0.00
40mm Nominal bore Each 3 Each 2609.74 7829.21 3.00 2609.74 7829.21 0.00 0.00
50mm Nominal bore Each 3 Each 3823.14 11469.43 3.00 3823.14 11469.43 0.00 0.00
65mm Nominal bore Each 1 Each 5903.44 5903.44 1.00 5903.44 5903.44 0.00 0.00
21 Supplying & fixing Bronze Horizontal Check Each 1 Each 2250.71 2250.71 1.00 2250.71 2250.71 0.00 0.00
(Non return) Valve as per IS-778 I-class
heavy duty - 40 mm NB S including cost and
conveyance of all materials, labour charges,
overheads & contractors profit etc., all taxes,
except GST, complete for finished item of
work.
75mmdia Rmt 259.00 Rmt 190.31 49289.03 259.00 190.31 49289.03 0.00 0.00
110mmdia Rmt 259.00 Rmt 277.98 71997.29 259.00 277.98 71997.29 0.00 0.00
23 Construction of Brick masonry support for Each 85 Each 86.35 7339.53 85.00 86.35 7339.53 0.00 0.00
CPVC pipe of size 304.80mm x 228.60mm x
228.60 mm with Brick in CM (1:6) prop
including plastering and finishing with 12mm
thick in CM (1:5) including cost and
conveyance of all materials and all labour
charges, overheads & contractors profit etc.,
all taxes, except GST, complete for finished
item of work for all floors.
ELECTRICAL ITEMS
1 Supply and Laying of ISI 25mm outer dia Rmt 52000.00 74.00 3848000.00 0.00 74.00 0.00 3848000.00
heavy grade(2.10mm thickness) IS:9537
part 3 regid PVC pipe concealed in Roof
Slabs with all required Metallic Deep Boxes
including labour charges etc., complete.
Makes : Sudhakar / Modi / VIP / Precision
2 Supply and laying of ISI 25mm outer dia Rmt 34750.00 63.00 2189250.00 20000.00 63.00 1260000.00 929250.00
medium (1.80mm thickness) grade with
IS:9537 part 3 regid PVC pipe consealed in
wall with Metallic junction boxes and all
required accessories including masonary
work for light, fan and separate plug point
with including all labour charges etc.,
complete.
Makes : Sudhakar / Modi / VIP / Precision
3 Wiring with run of 2 of 22/0.3mm (1.5 Sqmm) Each 1339.00 597.00 799383.00 0.00 0.00 799383.00
/ HFFR PVC insulated flexible ISI mark
copper cable in existing PVC conduit pipe
including Supply and fixing of Jumbo Ceiling
rose and 6A/10A ISI Mark 1way Modular
switch with required modular box and cover
frame in existing Surface or Concealed pipe
wiring,ferrules including cost and
conveyance of all material and all labour
charges etc., complete for light, Fan,
Exhaust fan and bell points in N.R.B .
Makes : Finolex / RR kabel / Havells / APAR
EBXL
Accessories Makes : Legrand Myrius /
Cabtree Verona / Gold Medal Curve / Anchor
Roma viola / GM Four-Five / L&T / Salzar
5 Supply and fixing of ISI marked 6A/10A Each 256.00 383.00 98048.00 104.00 383.00 39832.00 58216.00
3/2pin Modular socket, 6 Amps Modular
switch on 3 modular box with suitable cover
frame on a common switch board
including cost and conveyance of all material
and all labour charges etc., complete in
N.R.B.
Accessories Makes : Legrand Myrius /
Cabtree Verona / Gold Medal Curve / Anchor
Roma viola / GM Four-Five / L&T / Salzar
6 Wiring with run of 3 of 22/0.3mm (1.5 Each 248.00 627.00 155496.00 50.00 627.00 31350.00 124146.00
Sqmm) FRLS / HFFR PVC insulated flexible
ISI marked copper cable including Supply
and fixing of ISI Marked 6A/10A- 3/2 pin
Modular socket, 6A/10A 1way Modular
switch with required cover frame including
connections, cost and conveyance of all
material and all labour charges etc.,
complete for seperate plug points in N.R.B.
/ R.B.
Makes : Finolex / RR kabel / Havells / APAR
EBXL
Accessories Makes : Legrand Myrius /
Cabtree Verona / Gold Medal Curve / Anchor
Roma viola / GM Four-Five / L&T / Salzar
9 Supply and Run of 3 of 22/0.3mm (1.50 Rmt 11700.00 65.00 760500.00 1000.00 65.00 65000.00 695500.00
Sq.mm) FRLS / HFFR PVC insulated flexible
ISI mark copper cable in existing pipe for run
of mains, ferrules inlcuding all labour
charges etc., complete.
Makes : Finolex / RR kabel / Havells / APAR
EBXL
10 Supply and Run of 3 of 36/0.3mm (2.50 Rmt 5200.00 94.00 488800.00 5200.00 94.00 488800.00 0.00
Sq.mm) FRLS / HFFR PVC insulated flexible
ISI mark copper cable in existing pipe for run
of mains, ferrules inlcuding all labour
charges etc., complete.
11 Supply and Run of 3 of 56/0.3mm (4.00 Rmt 4100.00 144.00 590400.00 4100.00 144.00 590400.00 0.00
Sq.mm) FRLS / HFFR PVC insulated flexible
ISI mark copper cable in existing pipe for run
of mains,ferrules inlcuding all labour charges
etc., complete.
Makes : Finolex / RR kabel / Havells / APAR
EBXL
17 Supply,transportation and fixing of 15W LED Each 900.00 1211.50 1090350.00 124.00 1211.50 150226.00 940124.00
slimline panel light Housing made of Powder
coated, round / Square with Protruded high
efficiency diffuser, IP20, with wide operating
voltage range, Power factor > 0.9, Surge
protection: > 2KV, System efficacy of >100
lumens/watt, CCT: 3000K - 6500K as
desired by the department and as per IS,
CRI >80, and THD is less than 15%
etc., complete with 5 years warranty.
LUMINAIRE MAKE : Phillips / OSRAM / GE /
Crompton / VIN / Bajaj / Havells / Halonix /
HPL / Syska / Surya.
LED MAKE : PHILIPS LUMILEDS / CREE /
NICHIA / OSRAM / SAMSUNG / LG LEDs.
SOR 17-18.ELEC-3.9.10
19 Supply and transportation and fixing of 18W Each 55.00 2422.00 133210.00 0.00 2422.00 0.00 133210.00
LED Down Light round/ square with housing
made of Powder coated Pressure die cast
aluminium housing with extended heat sink,
with Protruded high efficiency diffuser, IP20,
with wide operating voltage range, Power
factor > 0.9, Surge protection: > 2KV,
System efficacy of >100 lumens/watt, CCT:
4000K as desired by the department and as
per IS, CRI >80, and THD is less than
15% etc., complete with 5 years warranty.
LUMINAIRE MAKE : Phillips / OSRAM / GE /
Crompton / VIN / Bajaj / Havells / Halonix /
HPL / Syska / Surya.
LED MAKE : PHILIPS LUMILEDS / CREE /
NICHIA / OSRAM / SAMSUNG / LG LEDs.
SOR 17-18.ELEC-3.9.7
23 Supply, Transportation and Fixing of 48" Each 26.00 1990.00 51740.00 4.00 1990.00 7960.00 43780.00
(1200mm) Sweep 5 star rated ISI mark
Ceiling Fan as per IS 374 - 1979 but
without regulator including all standard
accessories with twin core flat copper wire
of Finolex / RR kabel / Havells / Polycab /
GM / Million / V-Guard / Gold Medal / HPL /
RPG / Payal ,connections and all labour
charges etc., complete.
Makes : Crompton / Bajaj / Orient
25 Supply, Transportation and Fixing of light Each 2.00 1610.00 3220.00 2.00 1610.00 3220.00 0.00
duty 9" (225mm) ISI, Fresh Air fan with
metallic body and blades and masonary
work and all labour charges etc., complete.
Makes: Crompton / Bajaj Bahar WG /
Havells Ventil Air-DS / Orient hill air
Twin Core Wire Makes: Finolex / RR kabel /
Havells / APAR EBXL
26 Supply, Transportation and Fixing of 12" Each 16.00 3360.00 53760.00 16.00 3360.00 53760.00 0.00
(300mm) ISI, 900 RPM Heavy duty exhaust
fan with metallic blades with Mark and
masonary work and all labour charges etc.,
complete.
Makes: Crompton / Almonard / Havells
Turbo Force.
Twin Core Wire Makes: Finolex / RR kabel /
Havells / APAR EBXL
27 Supply and fixing of 8Way SPN DB Each 34.00 3940.00 133960.00 15.00 3940.00 59100.00 74860.00
Horizontal with IP 43 Protection as per
IS:13032 with 1 No 40A DP Isolator and 8
Nos 6-32 A 10kA ISI Marked C/D curveSP
MCBs including alll connections and labour
charges for Flush Mounting etc., complete.
DB Makes: Legrand / Schneider
Isolator Makes: Legrand / Schneider
SP, MCBs Makes: Legrand / Schneider
32 Supply and laying of 150mm x 38mm G I Rmt 720.00 538.00 387360.00 720.00 538.00 387360.00 0.00
Raceways of 2mm thick with top cover and
required hard ware etc complete.
33 Supply and laying of 100mm x 38mm G I Rmt 240.00 409.00 98160.00 240.00 409.00 98160.00 0.00
Raceways of 2mm thick with top cover and
required hard ware etc complete.
34 Supply and fixing of 172mm x 52mm G.I. Each 256.00 303.00 77568.00 256.00 303.00 77568.00 0.00
Junction box of 2mm thick for direct acces to
cables at the inter section of Raceways.
i Ground Floor : Sqm 0.00 Sqm 280.60 0.00 763.00 280.60 214098.58 214098.58 0.00 The texture paint item is to
ii First Floor : Sqm 0.00 Sqm 285.34 0.00 745.00 285.34 212580.60 212580.60 0.00 be provided for elevation
iii Second Floor : Sqm 0.00 Sqm 290.07 0.00 612.00 290.07 177525.88 177525.88 0.00 purpose with comination of
glass and texture for
iv Third Floor : Sqm 0.00 Sqm 294.80 0.00 640.00 294.80 188669.85 188669.85 0.00 aesthetic point of view.
v Terrace Floor Sqm 0.00 Sqm 299.54 0.00 576.00 299.54 172534.29 172534.29 0.00 Hence supplemented for all
floors
23 Supply and fixing of spider glazing with
12mm clear toughened glass for façade area
and fin considered 21.52 laminated glass.
Hardware considered Dorma series with
necessary hardware and silicon sealent
including cost and conveyance of all
materials to work site and all operational,
incidental, labour charges, scaffolding
charges, overheads and contractors profit
etc., complete for finished item of work
i Ground Floor : Sqm 0.00 Sqm 17696.92 0.00 17696.92 2566053.20 2566053.20 0.00 The spider glazing item is to
be provided for south side
front elevation & North side
elevation. Hence
supplemented
145.00
Ground Floor : Sqm 22.00 4243.33 93353.21 93353.21 0.00 The Alco panel cladding with
First Floor : Sqm 22.00 4243.33 93353.21 93353.21 0.00 MS frame item is to be
Second Floor : Sqm 22.00 4243.33 93353.21 93353.21 0.00 provided for elevation in all
floors. Hence supplemented
Third Floor : Sqm 21.00 4243.33 89109.89 89109.89 0.00
Panel Room
a Roof beams
un supported height up to 4.27 m
for Panel Room cum 0.00 11933.44 0.00 11933.44 42005.72 42005.72 0.00
RCCM30 grade item for roof
beam is executed for panel
room as per approved
drawings. Hence
3.52 supplemented
for Panel Room Sqm 0.00 1563.85 0.00 1563.85 6255.38 6255.38 0.00
RCM facia for Rolling
shutter is to be for panel
4.00 room . Hence supplemented
for Panel Room & Pump room Sqm 0.00 4096.97 0.00 4096.97 46459.66 46459.66 0.00 Rolling shutter is to be
provided for panel room &
Pump Room . Hence
11.34 supplemented
for Panel Room Kgs 0.00 102.89 0.00 102.89 116366.04 116366.04 0.00 Chequered plate is to be
provided over cable trench
top in panel room . Hence
1131.00 supplemented
300 mm thick side walls Sqm 0.00 0.00 1343664.90 1343664.90 0.00
RCCM30 grade item 300mm
thick side walls is executed
for sump as per approved
drawings. Hence
6200.00 216.72 6200.00 supplemented
Sump Roof beams upto 3.66 mts level cum 0.00 11093.46 0.00 2.15 11093.46 23850.93 23850.93 0.00
RCCM30 grade Sump Roof
beams and security roof
beams at 3.60mts height is
executed as per approved
drawings. Hence
supplemented
Pump Roof beams upto 6.15 mts level cum 0.00 14453.4 0.00 2.7 14453.4 39457.75 39457.75 0.00
RCCM30 grade Pump Room
Roof beams at 6.15mts
height is executed as per
approved drawings. Hence
supplemented
Pump Roof slabs 125mm thick upto 6.15 mts Sqm 0.00 1739.20 0.00 56.77 1739.20 98734.24 98734.24 0.00
level
RCCM30 grade Pump Room
Roof slab of 125mm thick at
6.15mts height is executed
as per approved drawings.
Hence supplemented
Sump Roof Slab 150 mm thick upto an Sqm 0.00 1478.35 0.00 58.74 1478.35 86838.17 86838.17 0.00
unsupported height of 3.66 mts level
RCCM30 grade Sump Roof
slab of 150mm thick at
3.66mts height is executed
as per approved drawings.
Hence supplemented
Compound wall
34 Plain Cement Concrete M 20 nominal mix cum 0.00 5183.64 0.00 7.00 5183.64 36285.50 36285.50 0.00 The item coping is executed
using WEIGH BATCHER / MIXER, 20mm on top of compound wall.
size hard granite machine crushed graded Hence supplemented
metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from
approved quarry, using a minimum quantity
of 350 kgs. of cement per 1 cum of concrete
including cost and conveyance of all
materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site
including steel centering, shuttering,
machine mixing, lift charges, laying
concrete,vibrating, curing, overheads &
contrctors profit etc., complete for finished
item of work for coping on top of compound
wall (APSS No. 402 & 403).
b) Roof Slabs
Slabs 125 mm thick
i) un supported height up to 3.66 m Sqm 0.00 1327.01 0.00 13.40 1327.01 17781.90 17781.90 0.00
RCCM30 grade Secuirty
Room Roof slab of 125mm
thick at 3.66mts height is
executed as per approved
drawings. Hence
supplemented
INERNAL CC ROAD
Cum 0.00 101.86 0.00 101.86 1629.75 1629.75 0.00 The earth work item is to be
provided for kerb stone.
16.00 Hence supplemented
RM 0.00 245.68 0.00 245.68 160427.04 160427.04 0.00 The expansion joint item is
to be provided for internal
CC path way. Hence
653.00 supplemented
5 Plain Cement Concrete(1:4:8) mix using cum 0.00 3105.67 0.00 15.00 3105.67 46584.99 46584.99 0.00
40mm size hard broken granite metal
including cost and conveyance of all
materials to site, seigniorage, machine
mixing charges, labour charges, placing in
position, levelling, vibrating, curing, etc.
complete for finished item of work as
directed by the Engineer-in-charge,
excluding GST and Seigniorage charges as
per technical specification clause No.2100 of
Morth.
RM 0.00 658.62 0.00 658.62 439300.18 439300.18 0.00 The Kerbstone item is to be
provided for CC Pathway
both sides. Hence
667.00 supplemented
7 Painting two coats after filling the surface
with synthetic enamel paint in all shades on
new plastered concrete surface as per
Technical Specification 800 of MORT&H (5th
Revision) and as directed by the Engineer-
in-Charge.
Sqm 0.00 665.26 0.00 665.26 392503.87 392503.87 0.00 The CC Pavement blocks
item is to be provided for
Parking areas. Hence
590.00 supplemented
For drain slabs cum 0.00 5604.27 0.00 5604.27 140106.63 140106.63 0.00 The RCC(M20 grade item is
to be provided for storm
water drain slab. Hence
25.00 supplemented
SQM 0.00 733.17 0.00 733.17 143701.81 143701.81 0.00 The Plinth protection item is
to be provided alround the
building. Hence
196.00 supplememnted
8 Constructing 457.2 mm x 457.2 mm Each 0.00 5064.86 0.00 25.00 5064.86 126621.53 126621.53 0.00
(1'6"x1'6") brick in CM 1:6 prop. Masonry.
Inspection chamber up to 914.4 mm (3'0")
and fitted with 100 thick perforated slab.
including cost and conveyance of all
materials and all labour charges, overheads
& contractors profit etc., all taxes, except
GST, complete for finished item of work for
all floors for Catch basin. The inspection chamber item
is to be provided for regular
maintenance of UGD .
Hence supplememnted
Rmt 0.00 1470.61 0.00 92.00 1470.61 135296.23 135296.23 0.00 The 250mm SWG item is to
be provided for municipal
drainage line. Hence
b) 254mm dia upto 1524.0mm (5') depth supplememnted
80 mm Dia Rmt 0.00 926.92 0.00 926.92 76007.16 76007.16 0.00 For raising main from sump
to terrace water tank is to be
provided. Hence
82.00 supplemental
3 Supplying and fixing Gunmetal Gate (GM)
Bronze Gate/ Globe valves as per IS-778
Class - I , Indian make heavy type including
cost and conveyance of all materials, labour
charges, overheads & contractors profit etc.,
all taxes, except GST, complete for finished
item of work.
80 mm Dia NO 0.00 8923.89 0.00 8923.89 17847.78 17847.78 0.00 80mm dia gun metal valve
for raising mainis to be
provided. Hence
2.00 supplemental
Subtotal (Water Supply& Sanitary _Suppl) 229151.17 229151.17
1 Supply and Fixing of 25mm dia 1.5mm thick Rmt 18000.00 70.88 1275821.93 1275821.93 0.00 Surface conduit is proposed
surface P.V.C. pipe (ISI MARK) with all in place of Slab conduit since
accessories fixing on chromium plated all the area is poposed with
metallic base saddles including all labour false ceiling
charges etc.
Makes : Sudhakar / Modi / VIP / Precision
(Data-1)
2 Wiring with run of 3 of 22/0.3mm (1.5 Sqmm) Each 1100.00 745.11 819616.36 819616.36 0.00 As per Agreement Intem No
/ HFFR PVC insulated flexible ISI mark 3, 2Runs was provided which
copper cable in existing PVC conduit pipe can accomadate Phase and
including Supply and fixing of Jumbo Ceiling Neutral, where as earth wire
rose and 6A/10A ISI Mark 1way Modular is mandatory, Hence the
switch with required modular box and cover supplemantal item is
frame in existing Surface or Concealed pipe proposed wiith 3 Runs ,
wiring,ferrules including cost and
conveyance of all material and all labour
charges etc., complete for light, Fan,
Exhaust fan and bell points in N.R.B .
Makes : Finolex / RR kabel / Havells / APAR
EBXL
Accessories Makes : Legrand Myrius /
Cabtree Verona / Gold Medal Curve / Anchor
Roma viola / GM Four-Five / L&T / Salzar
(Data-2)
3 Wiring with run of 3 of 22/0.3mm (1.5 Sqmm) Each 20.00 1117.66 22353.17 22353.17 0.00 As per Agreement Intem No
/ HFFR PVC insulated flexible ISI mark 3, 2Runs was provided which
copper cable in existing PVC conduit pipe can accomadate Phase and
including Supply and fixing of Jumbo Ceiling Neutral, where as earth wire
rose and 6A/10A ISI Mark 1way Modular is mandatory, Hence the
switch with required modular box and cover supplemantal item is
frame in existing Surface or Concealed pipe proposed wiith 3 Runs ,
wiring,ferrules including cost and
conveyance of all material and all labour
charges etc., complete for stair case light
points / Double Height Light points in
N.R.B .
Makes : Finolex / RR kabel / Havells / APAR
EBXL
Accessories Makes : Legrand Myrius /
Cabtree Verona / Gold Medal Curve / Anchor
Roma viola / GM Four-Five / L&T / Salzar
(Data-3)
5 Supply and fixing of 18W LED Down Light Each 650.00 2469.72 1605319.94 1605319.94 0.00 As per Agreement Intem No
Recessed mounting round/ square with 19, was proposed with
housing made of Powder coated Pressure surface lights, since all the
die cast aluminium housing with extended areas are having false ceiling
heat sink, with Protruded high efficiency , Recessed mounted fixtures
diffuser, IP20, with wide operating voltage are proposed. Hence the
range, Power factor > 0.9, Surge protection: item is supplemantal.
> 2KV, System efficacy of >100 lumens/watt,
CCT: 3000K - 6500K as desired by the
department and as per IS, CRI >80, and
THD is less than 15% etc., complete
with 5 years warranty.
LUMINAIRE MAKE : Phillips / OSRAM / GE /
Crompton / VIN / Bajaj / Havells / Halonix /
HPL / Syska / Surya.
LED MAKE : PHILIPS LUMILEDS / CREE /
NICHIA / OSRAM / SAMSUNG / LG LEDs.
(Data-5)
LAN SYSTEM
7 Supply, Transportation and Run of 1 of LAN Rmt 27500.00 32.34 889417.05 889417.05 0.00 CAT-6 wire for Networking
Cable cat - 6 UTP cable in the existing cable (LAN) (750x35 mtrs) is
tray/ conduit pipe and labour charges etc., mandatory, Hence the item
complete.Makes : D Link / AMP / Molex / is supplemantal.
Legrand / Krone (Data-7)
8 Supply, Transportation and Fixing of Cat 6 Each 781.00 504.80 394247.85 394247.85 0.00 LAN outlet (RJ-45) for
RJ-45 information outlets including duel face conneting Network to
plate including all accessories and labour Computer is mandatory,
charges etc., complete.Makes : D Link / AMP Hence the item is
/ Molex / Legrand / Krone (Data-8) supplemantal.
9 Supply of 7 feet length moulded patch cord Each 781.00 227.09 177360.86 177360.86 0.00 Path cords from RJ-45 Port
Makes : D Link / AMP / Molex / Legrand / to Computer are mandatory l,
Krone.(Data-9) Hence the item is
supplemantal.
10 Supply of 3 feet length moulded patch cord Each 781.00 202.23 157945.30 157945.30 0.00 Path cords from SWitch Port
Makes : D Link / AMP / Molex / Legrand / to Patch panel are
Krone. (Data-10) mandatory, Hence the item
is supplemantal.
12 Supply, Transportation and Fixing of 24 port Each 59.00 6694.66 394984.66 394984.66 0.00 Networking Patch panel for
patch panels including all accessories and all offices are mandatory,
labour charges etc., complete.Makes : D Hence the item is
Link / AMP / Molex / Legrand / Krone (Data- supplemantal.
12)
13 Supply, Transportation and Fixing of 19" 6U Each 8.00 4840.82 38726.58 38726.58 0.00 Networking Racks are
floor / Wall mounting net work rack Makes : mandatory for accomadating
HCL / Vall with power spike including all the LAN switches, Hence
accessories and labour charges etc., the item is supplemantal.
complete. (Data-13)
14 Supply, Transportation and Fixing of 19" 9U Each 30.00 5746.88 172406.49 172406.49 0.00 Networking Racks are
floor / Wall mounting net work rack Makes : mandatory for accomadating
HCL / Vall with power spike including all the LAN switches, Hence
accessories and labour charges etc., the item is supplemantal.
complete. (Data-14)
15 Supply, Transportation and Fixing of 19" 12U 6.00 7421.33 44527.99 44527.99 0.00 Networking Racks are
floor / Wall mounting net work rack Makes : mandatory for accomadating
HCL / Vall with power spike including all the LAN switches, Hence
accessories and labour charges etc., the item is supplemantal.
complete.(Data-15)
Each
16 Supply, Transportation and Fixing of 19" 42U 3.00 36252.87 108758.60 108758.60 0.00 Networking Racks are
floor / Wall mounting net work rack Makes : mandatory for accomadating
HCL / Vall with power spike including all the LAN switches, Hence
accessories and labour charges etc., the item is supplemantal.
complete.(Data-16)
Each
EXTERNAL ELECTRIFICATION
630 KVA Transformer
17 Supply, Transportation, Installation, Testing Each 1.00 2218120.7 2218120.73 2218120.73 0.00 It is proposed to serve the
and Commissioning of 630 KVA total Connected Electrical
TRANSFORMER with all test reports. The load (interl, External,
Transformer shall be designed and Pumps , Street lights etc).
manufactured as per IS:1180 OCTC with OLTC is proposed for
level-II with initial filling of oil as per IS 335- stebilizing the incoming
1993. The basic details of the Transformer power. As per TSNPDCL
are as under. norms , and it is
Makes: Kirloskar / PETE / Esennar / Voltamp mandatory ,Hence the item is
/ Crompton / ABB / Schneider.(Data-17) supplemantal.
27. Standrad Fittings & Accessories.
19 Supply,transpotation,installation,testing and Each 1.00 616863.01 616863.01 616863.01 0.00 This item is proposed for
commissioning of HT INDOOR type single Insolation / Breaker/
panel switchgear with VCB of floor mounted, protection for 11KV (HT side
metal clad 11KV, 630A, not less than 18.4KA ) Mandatory for Garding the
(350MVA) VCB Panel, with 1No VCBs totally Transformer. As per CEIG
enclosed and horizantal drawout type, norms , and mandatory.
horizontal isolation type breaker as per IS Heance the item is
13118 as amended upto date and additional supplemantal.
specifications having capacities as
mentioned below , single break trip free
mechanism, motorised/manually charged
and auto manually closing breaker suitable
for use on 12KV,3phase,50HZ AC supply
with self contained fully interlocked rackin
and
rackout mechanism air insulated allumium.
(Data-19)
INCOMING
Supply of 1000A 4 Pole, 50kA Air Circuit
Breaker electrically drawout Confirms to IS
13947-2, IEC 60947-2 and BS-EN 60947
with Micro processer based having over
load, shot circuit and earth fault protection. -
1No
MAKE : KAPPA
Out Going feeders:
Supply of 800A 4 Pole MCCB / Confirms to
IS/IEC 60947-2 having Breaking Capacity 50
KA with thermal magnetic release Panel
Mounted.. - 1 No
INCOMING
Supply of 1000A 4 Pole, 50kA Air Circuit
Breaker electrically drawout Confirms to IS
13947-2, IEC 60947-2 and BS-EN 60947
with Micro processer based having over
load, shot circuit and earth fault protection. -
12No
MAKE : KAPPA
Out Going feeders:
Supply of 400A 4 Pole MCCB / Confirms to
IS/IEC 60947-2 having Breaking Capacity 50
KA with thermal magnetic release Panel
Mounted.. - 4 No
INCOMER
Supply of 250A 4 Pole MCCB, Adjustable,
Confirms to IS/IEC 60947-2 having Breaking
Capacity 35/36 KA with thermal magnetic
release Panel Mounted - 1 No
MAKE : KAPPA
32A Bakelite fuse units with HRC fuse links
(A.R.) - 3Nos
Supply and fixing of 8 Stage APFC Relay
with connections suitable CTs sensing from
main bus bar of main panel. - 1No
Metering Panel
24 Supply, installation, testing and Each 4.00 305615.54 1222462.16 1222462.16 0.00 This item is proposed for
commissioning of floor mounting type panel measuring / recording the
board with Alluminium bus bars fabricated consumption of power
with 16 Gauge CRCA Sheet comprising of useage by the tenents/
TPN bus bars with bus bars of equal size in offices Heance the item is
all phases and neutral equipped with bus supplemantal
bar chambers and cable chambers. The bus
bars fault level shall be 50 KA and shall be
as per the requirement of local CEIG, fire
regulations, CPRI norms and other
authorities etc. The painting of the complete
system shall be powder coated duly
processing the panel in 7 tank process . The
panel shall be suitable for accomdating the
following switch gear including supply of all
components, hard wares etc including all
necessary civil works, adequate
reinforcement foundation bolts, suitable G.I
earth strip 40 x 6 mm, door loop earthings ,
bus bars should be colour sleeved with heat
shrinkable sleeves for phase and neutral
duly supported at regular intervels by SMC
supports and all cables shall have proper
cable entry, danger board, feeder
identification marks, rigid inter connections,
cadmium plated bolts and nuts and shall be
installed and consisting of the following as
required and as per IS standards for
Lighting panel.
(Panel shall be manufacture only from
CPRI approval fabricators.).(Data-24)
INCOMER
Supply of 250A 4 Pole MCCB, Adjustable,
Confirms to IS/IEC 60947-2 having Breaking
Capacity 35/36 KA with thermal magnetic
release Panel Mounted - 1 No
MAKE : KAPPA
Labour charges etc complete with
connections for Finished item of work.
INCOMER
Supply of 400A 4 Pole MCCB / Confirms to
IS/IEC 60947-2 having Breaking Capacity 50
KA with thermal magnetic release Panel
Mounted.
MAKE : KAPPA
Labour charges etc complete with
connections for Finished item of work.
INCOMER
Supply of 125A 4 Pole MCCB, Adjustable,
Confirms to IS/IEC 60947-2 having Breaking
Capacity 25 KA with thermal magnetic
release Panel Mounted -1 No
MAKE : KAPPA
Labour charges etc complete with
connections for Finished item of work.
27 Supply & run of 3 Core 11 KV 95 Sqmm HT Rmt 100.00 1043.71 104370.81 104370.81 0.00 This item is proposed ,11KV
XLPE (E) armoured Cable, as per IS (HT) cable connecting the
specification confirming to IS 7098/II/85 with transformer , HT panel,
latest ammendments of makes Makes : Electricity Board etc. is
Torrent / Universal / Unicab / Polycab / mandatory, hence the item is
Havells / KEI / RPG / Gloster. (Data-27) supplemantal.
28 Providing and errecting heat shrinkable Each 2.00 12825.05 25650.10 25650.10 0.00 This item is proposed for HT
outdoor termination kit for 11 KV XLPE HT termination kits outdoor
cable 3 core 70-95 Sqmm with necessary type , hence the item is
materials etc., complete with anti tracking Supplemantal
red colour material as per IEC / IS specs
only.(Data-33)
Makes : Transeal - Hong shang / Raychem /
M Seal / Multy. (Data-28)
29 Providing and errecting heat shrinkable Each 2.00 164.20 328.39 328.39 0.00 This item is proposed for HT
indoor termination kit for 11 KV XLPE HT termination kits Indoor type ,
cable 3 core 70-95 Sqmm with necessary Hence the item is
materials etc., complete.(Data-34) supplemantal
Makes : Transeal - Hong shang / Raychem /
M Seal / Multy. (Data-29)
30 Supply and run of 16 Sqmm 3.5 Core XLPE Rmt 500.00 203.50 101752.27 101752.27 0.00 This item is proposed for
insulated, 1100V grade armoured aluminium cabaling Street Lights etc ,
cable PVC XLPE armoured cable 1100 V Hence the item is
Grade with ISI mark stranded / solid, supplemantal
aluminium conductor complete (Data-35)
Makes : Torrent / Universal / Unicab /
Polycab / Havells / Gloster / KEI. (Data-30)
32 Supply and run of 50 Sqmm 3.5 Core XLPE Rmt 1500.00 413.86 620797.39 620797.39 0.00 This item is proposed for
insulated, 1100V grade armoured aluminium cabeling utility panels etc ,
cable PVC XLPE armoured cable 1100 V Hence the item is
Grade with ISI mark stranded / solid, supplemantal
aluminium conductor complete.(Data-37)
Makes : Torrent / Universal / Unicab /
Polycab / Havells / Gloster / KEI.(Data-32)
33 Supply and run of 95 Sqmm 3.5 Core XLPE Rmt 500.00 643.99 321995.80 321995.80 0.00 This item is proposed for
insulated, 1100V grade armoured aluminium cabeling Meter, HVAC
cable PVC XLPE armoured cable 1100 V panels etc , Hence the item
Grade with ISI mark stranded / solid, is supplemantal
aluminium conductor complete.(Data-38)
Makes : Torrent / Universal / Unicab /
Polycab / Havells / Gloster / KEI.(Data-33)
34 Supply and run of 240 Sqmm 3.5 Core Rmt 1200.00 1313.14 1575771.66 1575771.66 0.00 This item is proposed for
XLPE insulated, 1100V grade armoured cabeling MPCC, APFCR,
aluminium cable PVC XLPE armoured panels etc , Hence the item
cable 1100 V Grade with ISI mark stranded / is supplemantal
solid, aluminium conductor complete.(Data-
39)
Makes : Torrent / Universal / Unicab /
Polycab / Havells / Gloster / KEI.(Data-34)
35 Termination of UG cables of size 16 Sqmm 4 Each 25.00 234.09 5852.32 5852.32 0.00 This item is proposed for
Core XLPE insulated, 1100V grade termination of 16Sqmm ug
armoured aluminium cable including with cable , Hence the item is
required cable glands, Lugs complete with all supplemantal
required accessories as directed by the
department including cost and conveyance
of all materials and labour charges etc.,
complete..(Data-35)
37 Termination of UG cables of size 50 Sqmm Each 25.00 315.94 7898.49 7898.49 0.00 This item is proposed for
3.5 Core XLPE insulated, 1100V grade termination of 50Sqmm ug
armoured aluminium cable including with cable , Hence the item is
required cable glands, Lugs complete with all supplemantal
required accessories as directed by the
department including cost and conveyance
of all materials and labour charges etc.,
complete..(Data-37)
38 Termination of UG cables of size 95 Sqmm Each 4.00 517.82 2071.29 2071.29 0.00 This item is proposed for
3.5 Core XLPE insulated, 1100V grade termination of 95Sqmm ug
armoured aluminium cable including with cable , Hence the item is
required cable glands, Lugs complete with all supplemantal
required accessories as directed by the
department including cost and conveyance
of all materials and labour charges etc.,
complete..(Data-38)
39 Termination of UG cables of size 240 Sqmm Each 12.00 986.10 11833.20 11833.20 0.00 This item is proposed for
3.5 Core XLPE insulated, 1100V grade termination of 240Sqmm ug
armoured aluminium cable including with cable , Hence the item is
required cable glands, Lugs complete with all supplemantal
required accessories as directed by the
department including cost and conveyance
of all materials and labour charges etc.,
complete..(Data-39)
40 Supply and Installation of 450mm x 50mm x Rmt 200.00 939.60 187920.00 187920.00 0.00 This item is proposed for
2mm thick GI perforated cable tray along suporting ug cable , Hence
with required angle supports, with coupler the item is supplemantal
plates, Anchor bolts and nuts etc complete
and the tray should be fitted on the wall /
Ceiling etc. complete..(Data-40)
42 Supply and Installation of 150mm x 50mm x Rmt 700.00 445.37 311759.00 311759.00 0.00 This item is proposed for
2mm thick GI perforated cable tray along suporting LAN / DATA
with required angle supports, with coupler cable , Hence the item is
plates, Anchor bolts and nuts etc complete supplemantal
and the tray should be fitted on the wall /
Ceiling etc. complete..(Data-42)
43 Supply , fabrication and transportation of Kg 100.00 91.53 9153.30 9153.30 0.00 Item used for Suports ,
MS channel iron/ angle iron /flats including suspension etc
two coats of alluminium paint and one coat
of red oxide paint including all labour
charges etc complete..(Data-43)
44 Supply of Rubber hand gloves suitable for 11 Each 2.00 206.24 412.48 412.48 0.00 This item is proposed for
KV..(Data-44) Safety items /As per CEIG
Norms ,Hence the item is
supplemantal
45 Supply and fixing of PVC synthetic elastomer Sqmt 100.00 4326.38 432638.33 432638.33 0.00 This item is proposed for
electrically insulated mat with Class B Safety items /As per CEIG
insulation conforming to IS: 15652-2006 Norms ,Hence the item is
having 2.5mm thickness upto 11KV.(Data- supplemantal
45)
46 Providing & Fixing of Shock instrution chart Each 4.00 515.60 2062.39 2062.39 0.00 This item is proposed for
in English / Hindi / Telugu duly framed with Safety items /As per CEIG
front glass.(Data-46) Norms ,Hence the item is
supplemantal
47 Providing & Fixing of Danger Notice Plates Each 8.00 258.38 2067.02 2067.02 0.00 This item is proposed for
of size 250x200mm, shall comply with Safety items /As per CEIG
IS:2551-1982. .(Data-47) Norms ,Hence the item is
supplemantal
48 Providing floor mounting stand for keeping Each 6.00 1236.28 7417.65 7417.65 0.00 This item is proposed for
4No of fire bucket 1500mm length, 900mm Safety items /As per CEIG
height made out of 40x40x6mm angle iron Norms ,Hence the item is
welded with 4 hooks and duly painted with supplemantal
one coat of red lead and two coats of enamel
paint. (Data-48)
50 First Aid box 18" x 12" x 8" containing Each 4.00 1133.16 4532.62 4532.62 0.00 This item is proposed for
material as prescribed by St. John Safety items /As per CEIG
Ambulance brigade OR Indian Red Cross Norms ,Hence the item is
complete as required.(Data-50) supplemantal
51 Preparation of Drawings of existing or new Job 1.00 40000.00 40000.00 40000.00 0.00 This item is proposed for
installations and obtaining approval from the Safety items /As per CEIG
CEIG complete as per the requirement at Norms ,Hence the item is
site.(Data-51) supplemantal
52 Earthings: Providing independent earthing Each 18.00 4685.20 84333.57 84333.57 0.00 This item is proposed for
by exacavating a pit to a depth of 2.25Mtr in Body earthing for safety/
all soils as per size specified in the data for allow leakage current to
Important equipment with 2.5Mtr length ground etc.Hence the item is
40mm dia 'B' class G.I pipe and 18" dia 3" supplemantal
thick hume pipe ring with R.C.C. Slab cover
duly providing staggered holes filling with
20Kg Salt and 40Kg Charcoal or 40Kg
bentonite powder from the bottom of the pipe
giving earth connection from electrode
through G.I strip of 25 x 6mm x 200mm
length to be bolted with nut bolts including
supply and termination of No.8 G.I.wire from
bottm of the pipe with all accessories and
labour charges complete, as per IS
specifications 732/1982 (Part II)(Data-52)
54 Supply and Run of 25mm x 6mm G.I Strip Rmt 1800.00 105.55 189994.73 189994.73 0.00 This item is proposed for
including cost of all accessories and labour Earth Bus / Conductor Hence
charges etc., complete.(Data-54) the item is supplemantal
55 Supply and Run of 50mm x 6mm G.I Strip Rmt 400.00 188.98 75590.05 75590.05 0.00 This item is proposed for
including cost of all accessories and labour Earth Bus / Conductor Hence
charges etc., complete.(Data-55) the item is supplemantal
56 Supply and Run of 25mm x 6mm copper Rmt 600.00 857.51 514508.24 514508.24 0.00 This item is proposed for
strip (Cuurrent Carrying Capacity 270A) Earth Bus / Conductor Hence
including cost of all accessories and labour the item is supplemantal
charges etc., complete.(Data-56)
57 Supply and Run of No.8 SWG G.I wire Rmt 500.00 17.73 8863.64 8863.64 0.00 This item is proposed for
including cost of all accessories and labour Earth Bus / Conductor Hence
charges etc., complete. (0.104Kgs/1Mtr) the item is supplemantal
(Data-57)
58 Supply and installation of 3.0KVA, 72VDC Each 6.00 40689.32 244135.93 244135.93 0.00 This item is proposed for
true on line UPS system IGBT technology Unintruption of power supply
pure sine wave out put, double conversion while power cutoff, To
with auto and manual static by pass switch maintain the power quality,
single phase input / Single phase output. etc .Hence the item is
(Data-72) supplemantal
Makes: Makes: Consul / Power one /
Numeric / Fuji Electrical / Emerson. (Data-
58)
60 Supply and installation of 7.5KVA, Each 16.00 97326.24 1557219.91 1557219.91 0.00 This item is proposed for
180/192VDC true on line UPS system IGBT Unintruption of power supply
technology pure sine wave out put, double while power cutoff, To
conversion with auto and manual static by maintain the power quality,
pass switch single phase input / Single etc .Hence the item is
phase output. (Data-74) supplemantal
Makes: Consul / Power one / Numeric Fuji
Electrical / / Emerson. (Data-60)
61 Supply and fixing of 12V 65 AH SMF battery Each 492.00 8209.01 4038830.60 4038830.60 0.00 This item is proposed for
including wire leads of Makes : Quanta / storage of DC power for
Racket / Fuji / Exide.(Data-61) supporting the UPS .Hence
the item is supplemantal
62 Supply and providing of UPS cum battery Each 18.00 2961.50 53306.97 53306.97 0.00 This item is proposed for
rack up to 5 to 10 batteries.(Data-62) Staking of UPS
batteries.Hence the item is
supplemantal
63 Supply and providing of UPS cum battery Each 24.00 5329.77 127914.49 127914.49 0.00 This item is proposed for
rack up to 11 to 20 batteries.(Data-63) Staking of UPS
batteries.Hence the item is
supplemantal
CC SURVEILLANCE SYSTEMS
68 Supply and fixing of 1080P FHD 2.0 Each 18.00 6198.75 111577.59 111577.59 0.00 This item is proposed for
megapixel IR Dome Cameras with out motor Dome type Camera
Verifocal & pixel zoom and as per detailed Surveillance which is
specification in the annexure. mandatory as per safety
Make:CP Plus/Octavision (Data-68) norms.Hence the item is
supplemantal
69 Supply and fixing of 1080P FHD 2.0 Each 6.00 6665.69 39994.13 39994.13 0.00 This item is proposed for
megapixel IR Bullet Cameras with out motor Bullet type Surveillance
Verifocal & pixel zoom and as per detailed which is mandatory as per
specification in the annexure safety norms.Hence the item
Make: CP plus/Octavision. (Data-69) is supplemantal
70 Supply and fixing of 32 Channel NVR 1080P Each 1.00 48518.29 48518.29 48518.29 0.00 This item is proposed for
HDCVI/Analog/IP Video inputs; H.264 dual- stoaring and retriving
stream Video Compression Version, Support of.Hence the item is
1 SATA HDD up to 6TB, 2 USB2.0 amd RJ- supplemantal
45 port (10/100M),as per detailed
specification in the annexure. Make:CP
Plus/Octavision. (Data-71)
71 Supply and fixing of 4-TB Surveillance Disk Each 1.00 21782.54 21782.54 21782.54 0.00 This item is proposed for
as per detailed specification in the annexure. Surveillance which is
Make: Toshiba/Seagate (Data-72) mandatory as per safety
norms.Hence the item is
supplemantal
73 Supply and fixing of 8 PoE 10/100/1000 Each 4.00 11146.17 44584.69 44584.69 0.00
ports Switch-
Make-D-Link/ Cisco/Netgear/HP (Data-74)
Lightning Arrestor
74 Supply , testing , errection and commisioning 1.00 856833.16 856833.16 856833.16 0.00 This item is proposed As per
of the - Early Streamer Emission Lightning CEIG norms Lightning
protection Airterminal with Aviation light and arrestor is mandatory, hence
it'sattachments, Mounting support, Down- the item is supplemantal.
conductor and Maintenance-free earthing
system.
a) ESE Active
Lightning Rod ( T = 60 µs) manufactured
as per NFC 17-102:2011, is made of high
quality, non corrosive and weather resistant
XL-304 Stainless Steel Having Protection
Radius of 107 Meters at Level-IV
b)
G.I mast of 5 Meters length, 50 mm Dia, with
FRP Collar (Insulating Bush) Base Plate, &
Complete Fitting Accessories.
c) Supporting Guy Wire: Supporting Guy
Wire(Stay Wires) with all fitting
d)
Supply of 95mm² insulated copper cable.
Total Electrical Items(B) 33569458.32 33569458.32 0.00
HVAC
75 Supply, Lifting, Installation , Testing and 0.00 This item is proposed as per
Commissioningof Variable Refrigerent Approves Drawings. Air
Volume/Flow outdoor units comprising condition Out door units /
multiple scroll invertor compressors with VRF units witch controls the
100% invertors per Module with high COP, Refrigerent flow.
low noise inverter type propellor type aero
spiral fan,Condenser coil with special acrylic
pretreatment for improved resistance to salt
corrosion,refrigerant shut off valves,safety
devices, lead free PC boards suitable for
operation on R410a.and on 380 - 415 V, 50
Hz, 3 phase A/C supply. as per standards
along with top up gas charging as per site
conditions (Data AC-76)
82 Supply and laying of 2core 1.5Sqmm PVC Rmt 925.00 55.96 51765.40 51765.40 0.00 This item is proposed as per
Insulated and FRLS Round Sheathed Multi Approves Drawings.Control
Core Bright Annealed Bare Copper cable for VRF units
Conductor Heavy Duty Industrial Cables for
Voltage Grade upto 1100 Volts as per IS:
694:1990 including all transportation charges
etc complete in existing Conduit as per
requiremetns
86 Supply and Fixing of Canvas connection Each 33.00 3018.61 99614.06 99614.06 0.00 This item is proposed as per
butween indoor and duct (Data AC-87) Approves Drawings.Canvas
for connecting indoor unit
and duct
90 Supply and fixing of 19mm thickness closed Sqmtr 640.00 1204.99 771194.62 771194.62 0.00 This item is proposed as per
cell nitrile rubber (Class O) insulation on Approves
existing duct after applying 2 coats of cold Drawings.Insulation
setting adhesive (CPRX Compound). The
joints shall be sealed with 50mm wide and
3mm thick self adhesive nitrile rubber tape
insulation complete with star bond coating
and covered with 24 guage alluminium
cladding as per specifications for out door
applications. (Data AC-91)
91 SupplyInstallation Testing of R410 A Gas Hp 346.00 2156.88 746279.44 746279.44 0.00 This item is proposed as per
Charging (Data AC-91) Approves Drawings.Coolent
Gas
92 SupplyInstallation Testing of Ms stands Each 14.00 21543.28 301605.85 301605.85 0.00 This item is proposed as per
(Data AC-93) Approves Drawings.Steel
93 SupplyInstallation Testing of Uv protected Rmt 110.00 769.95 84694.39 84694.39 0.00 This item is proposed as per
layer for copper pipe(Data AC-94) Approves
Drawings.Insulation
94 Supply Installation Testing and Nos 4.00 199559.56 798238.25 798238.25 0.00 This item is proposed as per
commissioning of 2000CFM, 40mm Static Approves Drawings.Exhaust
presure , Double skin cabinet Type fan for system
toilet exhaust. Make: Kruger/ carrier.(Data
AC-95)
95 Supply and fixing of 6" circular disc valve for Nos 60.00 1988.61 119316.60 119316.60 0.00 This item is proposed as per
toilet exhaust. Make: Srisai/Padmavathi Approves Drawings.exhaust
(Data AC-96) system
96 Supply and laying of 6" circular PVC Flexible Rmts 30.00 530.30 15908.88 15908.88 0.00 This item is proposed as per
pipe. Make: Twiga (Data AC-97) Approves Drawings.exhaust
system
98 Termination of UG cables of size 16 Sqmm 4 Each 28.00 275.80 7722.51 7722.51 0.00 This item is proposed as per
Core PVC insulated, 1100V grade armoured Approves
Copper cable including with required cable Drawings.Termination of the
glands, CU Lugs complete with all required above cable at both ends
accessories as directed by the department
including cost and conveyance of all
materials and labour charges etc., complete.
(Data AC-99)
FIRE FIGHTING
99 Supplying and fixing single headed Internal / Each 10 9414.00 94139.97 94139.97 0.00 This item is proposed As Per
External hydrant valve with instantaneous NBC , Local Fire Fighting
Gun metal couplings of 63mm dia with Cast Requirements, and
iron wheel ISI marked conforming to IS mandatory, hence the item is
5290 (Type -A) with blank Gun Metal cap supplemetal.
and chain as required.(Make: Mini Max /
Safex / Newage / Winco / Padmini) (DATA -
F100)
101 Supply ,fixing and testing 63mm dia, 15 mtr 20 6384.14 127682.76 127682.76 0.00 This item is proposed As Per
long CP hose pipe with 63mm dia Male and NBC , Local Fire Fighting
Female Gun metal / SS couplings duly Requirements, and
binded with GI wire, rivets etc conforming to mandatory, hence the item is
IS 636 (Type -A) as required etc complete supplemetal.
for finished item of work (Make: Mini Max /
Safex / Newage / Winco / Padmini)(DATA -
F102)
102 Supply ,fixingand testing 63mm dia Gun Each 10 2931.37 29313.74 29313.74 0.00 This item is proposed As Per
metal branch pipe with 20mm (Nominal NBC , Local Fire Fighting
internal diameter) size Gun metal / SS Requirements, and
nozzle conforming to IS 903, suitable for mandatory, hence the item is
instantaneous connection to interconnect supplemetal.
hose pipe coupling as required.(Make: Mini
Max / Safex / Newage / Winco / Padmini)
(DATA -F103)
104 Supplying , installation,testing and Each 10 753.12 7531.20 7531.20 0.00 This item is proposed As Per
commissioning of 25MM dia ball valve NBC , Local Fire Fighting
Makes : Zoloto / Leader / Approved makes. Requirements, and
(DATA -F105) mandatory, hence the item is
supplemetal.
105 Supplying, installation testing and
commissioning of the following (Class 'B')
MS pipes and fittings confirming to IS 1239
PI & II, with flanges welded /welded joints)
as required including pipe of shorter lengths,
tapering connecting pieces, short or long
bends, specials like sockets, union nuts,
elbows, reducers, plugs, Tees etc.Complete
to make the system operative as required by
local fire authorities. including welding,
cutting, fixing in / on walls, under ground
etc., the pipes will have to be laid and fixed
in trenches on walls, ceilings, into brick walls
or RCC with lead anchor fastners and
painting two coats of approved shade of
enamel paint over a coat of approved
primer.Makes : Jindal / Hissar / Tata pipes
(DATA -F106)
a) 100mm dia RM 42 1477.27 62045.48 62045.48 0.00 This item is proposed As Per
NBC , Local Fire Fighting
Requirements, and
mandatory, hence the item is
supplemetal.
a) 100mm dia Each 20 3939.40 78787.91 78787.91 0.00 This item is proposed As Per
NBC , Local Fire Fighting
Requirements, and
mandatory, hence the item is
supplemetal.
107 Supply, installation, testing & commissioning Each 2 1448.31 2896.61 2896.61 0.00 This item is proposed As Per
of 25/20mm dia Air release valve etc NBC , Local Fire Fighting
complete for finished item of work and work Requirements, and
is to be carried out as per the all mandatory, hence the item is
specifications, requirement of site conditions supplemetal.
and as per the directions of department
officials only.(DATA -F108)
110 Supplying and fixing 63mm dia, 15 mtr long Each 16 7114.09 113825.36 113825.36 0.00 This item is proposed As Per
RRL hose pipe with 63mm dia Male and NBC , Local Fire Fighting
Female Gun metal / SS couplings duly Requirements, and
binded with GI wire, rivets etc conforming to mandatory, hence the item is
IS 636 (Type -A) as required. and work is to supplemetal.
be carried out as per the directions of
department officials only(Make: Mini Max /
Safex / Newage / Winco / Padmini)
(DATA -F111)
111 Supply and fixing 63mm dia Gun metal Each 8 2931.37 23450.99 23450.99 0.00 This item is proposed As Per
branch pipe with 20mm (Nominal internal NBC , Local Fire Fighting
diameter) size Gun metal / SS nozzle Requirements, and
conforming to IS 903, suitable for mandatory, hence the item is
instantaneous connection to interconnect supplemetal.
hose pipe coupling as required and work is
to be carried out as per the directions of
department officials only(Make: Mini Max /
Safex / Newage / Winco / Padmini)
(DATA -F112)
a) 150mm dia RM 80.00 2242.43 179394.75 179394.75 0.00 This item is proposed As Per
NBC , Local Fire Fighting
Requirements, and
mandatory, hence the item is
supplemetal.
115 Supplying, installing and commissioning of Each 0.00 2 10543.68 21087.35 21087.35 0.00 This item is proposed As Per
4way fire brigade inlet connection NBC , Local Fire Fighting
conforming to IS 5290 comprising of 4nos. Requirements, and
63mm dia instantaneous couplings complete mandatory, hence the item is
with CI non-return valve, CI butterfly valve, supplemetal.
connected to 150 mm dia for tank filling.
(DATA -F116)
116 Supplying, fixing, testing and commissioning Each 8 5040.11 40320.87 40320.87 0.00 This item is proposed As Per
of butterfly valve PN 1.6, with Bronze / Gun NBC , Local Fire Fighting
metal seat duly ISI marked complete with Requirements, and
Nuts, Bolts, Washers, gaskets, conforming to mandatory, hence the item is
IS 13095 of size 150mm dia supplemetal.
makes:Audco/Kirloskar/BDK/H-Shanker/Lea
der/Zolotto/Intervalve)(DATA -F117)
120 ELECTRCAL PANEL: Each 2 290405.67 580811.34 580811.34 0.00 This item is proposed As Per
Fabrication, Supplying, .installation, Testing NBC , Local Fire Fighting
& Commissioning of electrical control panel Requirements, and
of cubical construction, floor mounted MV mandatory, hence the item is
panel type, fabricated out of 2mm. thick supplemetal.
CRCA sheet compartmented with hinged
lockable doors, dust and vermin proof,
powder coated of approved shade after 7
tank treatment process, cable alley, Inter-
connection, having switchgears and
accessories mounting and internal wiring,
earth terminals. numbering etc. complete in
all respect suitable for operation on 415 V, 3
phase, 50 HZ. AC supply with endosura
protection class IP 42 as required. (DATA -
F121)
INCOMER:
400A TPN MCCB- 1NO
Voltmeter (0-500 Volts) with selector switch.
125 Supplying, installation testing and Each 6 2847.11 17082.69 17082.69 0.00 This item is proposed As Per
commissioning of 25mm dia G.M. Non- NBC , Local Fire Fighting
return valves conforming to IS 778 etc Requirements, and
complete for finished item of work and work mandatory, hence the item is
is to be carried out as per the directions of supplemetal.
department officials only (Makes:) (DATA -
F126)
126 Supply and fixing air vessel made of 250mm Each 2 1853.83 3707.67 3707.67 0.00 This item is proposed As Per
dia, 8 mm thick MS sheet, 1200mm in height NBC , Local Fire Fighting
with air release valve on top and flanged Requirements, and
connection to riser, drain arrangement with mandatory, hence the item is
25mm dia Gun metal wheel valve, with supplemetal.
required cessories,pressure gauge and
painting with synthetic enamel paint of
approved shade as required.(DATA -F127)
127 Supply, installation, testing and Each 12 782.09 9385.03 9385.03 0.00 This item is proposed As Per
commissioning of Bourden type, stainless NBC , Local Fire Fighting
steel dial type pressure gauge with isolation Requirements, and
valve and pipe having calibration of 0-16 mandatory, hence the item is
kg/cm2 with required fittings and accessories supplemetal.
etc complete. (DATA -F128)
128 Supplying, installation testing and Each 6 6.74 40.44 40.44 0.00 This item is proposed As Per
commissioning of Pressure switch (0-15 NBC , Local Fire Fighting
Kg./sqcm) with required fittings and Requirements, and
accessories etc complete and work is to be mandatory, hence the item is
carried out as per the directions of supplemetal.
department officials only
(Danfoss/Indfoss/Approved makes) (DATA -
F129)
131 Supply, fixing, testing and commissioning of Each 280 567.74 158966.20 158966.20 0.00 This item is proposed As Per
15mm size quartzoid bulb type sprinklers of NBC , Local Fire Fighting
rating 68ºC. pendent / side wall with required Requirements, and
accessories etc complete and work is to be mandatory, hence the item is
carried out as per the directions of supplemetal.
department officials only ( Makes: SAFEX /
HD / TYCO / VIKING / NEWAGE / SHARP)
(DATA -F132)
132 Supply and installation, Providing and fixing Each 280 608.29 170320.93 170320.93 0.00 This item is proposed As Per
approved make 15mm orifice quartzoid bulb NBC , Local Fire Fighting
type sprinklers, 68°C rating, recessed Requirements, and
upright type with rossset plate (adjustable) mandatory, hence the item is
off white finish wherever required and all supplemetal.
accessories, supports and painting etc
complete and work is to be carried out as per
the directions of department officials only
(DATA -F133)
133 Supply, fixing, testing and commissioning of Each 280 1390.37 389304.98 389304.98 0.00 This item is proposed As Per
UL approved flexible dropper of 1.5 Mtrs NBC , Local Fire Fighting
length with required accessoriesincluding Requirements, and
angles and supports.(DATA -F134) mandatory, hence the item is
supplemetal.
with MPCB-1No
Contactor for controlling butterfly valve – 1No
143 Supply, Installation, testing and Each 1 237892.35 237892.35 237892.35 0.00 This item is proposed As Per
commissioning of wall mounting 2 loop micro NBC , Local Fire Fighting
processor based analog addressable fire Requirements, and
control panel expandable by minimum 2 mandatory, hence the item is
additional loops with minimum 80 character supplemetal.
LCD display 4 access levels 1000 events,
historical logging, flash E-PROM, 240 volts A
C Power supply, automatic battery charger,
24V SLA batteries suitable for operating the
entire system including tack back units and
the hooters/strobes for a minimum of 4 hours
in battery condition the panel shall have
suitable power amplifiers for hooter / strobes
the panel shall be capable beeing integrated
with the BMS system and shall include cost
of supply, installation of any additional
modules or interfaces required for the same.
The panel shall be completed as per the
specification and as required fixing of 2 loop
Micro processor based Fire Alarm control
panel with zonal indictions and battery back
up as per detailed specifications.(DATA -
F144)
144 Supply and laying of 2C X1.5 sq.mm 650V RM 600 48.55 29128.35 29128.35 0.00 This item is proposed As Per
grade shielded PVC insulated copper NBC , Local Fire Fighting
conductor flexible wires through existing Requirements, and
PVC conduit.(DATA -F145) mandatory, hence the item is
supplemetal.
145 Supply installation testing and Each 70 7154.64 500824.63 500824.63 0.00 This item is proposed As Per
commissioning of analogue addressable NBC , Local Fire Fighting
type Multi (smoke& Heat ) photo electric Requirements, and
detectors with LED indication lamp and with mandatory, hence the item is
in built fault isolator.(Below false ceiling) with supplemetal.
complete fixing accessories.(DATA -F146)
147 Supply installation testing and Each 70 452.97 31707.90 31707.90 0.00 This item is proposed As Per
commissioning of response indicators with all NBC , Local Fire Fighting
fixing accessories etc complete (DATA - Requirements, and
F148) mandatory, hence the item is
supplemetal.
148 Supply and fixing of addressable wall Each 10 6685.39 66853.86 66853.86 0.00 This item is proposed As Per
mounting strobes cum hooters including the NBC , Local Fire Fighting
cost of mounting accessories complete as Requirements, and
per specifications and as required including mandatory, hence the item is
testing and commissioning. (Makes: Notifier / supplemetal.
Edwards) (DATA -F149)
149 Supply and installation of addressable Each 10 6836.01 68360.10 68360.10 0.00 This item is proposed As Per
analogue manual call point with resetable NBC , Local Fire Fighting
flexible element to initiate alaram including Requirements, and
the cost of mounting accessories etc. mandatory, hence the item is
complete(Makes: Notifier / Edwards) (DATA - supplemetal.
F150)
150 Supply and fixing of Exit Light fixtures with Each 10 4589.10 45891.00 45891.00 0.00 This item is proposed As Per
1.5hrs battery backup etc complete for NBC , Local Fire Fighting
finshed item of work (DATA -F151) Requirements, and
mandatory, hence the item is
supplemetal.
151 Supply,installation, testing and Each 10 4953.21 49532.11 49532.11 0.00 This item is proposed As Per
commissioning of Intalligent analogue NBC , Local Fire Fighting
addressable fault isolator modules including Requirements, and
the cost of mounting accessories complete mandatory, hence the item is
as per specifications and complete as supplemetal.
requiredm for finished item of work (Makes:
Notifier / Edwards) (DATA -F152)
152 Supply,installation, testing and Each 20 6053.92 121078.48 121078.48 0.00 This item is proposed As Per
commissioning of Intalligent analogue NBC , Local Fire Fighting
addressable Control Modules including the Requirements, and
cost of mounting accessories complete as mandatory, hence the item is
per specifications and as required.(Makes: supplemetal.
Notifier / Edwards) (DATA -F153)
155 Supply, installation, testing and Each 2 137589.19 275178.37 275178.37 0.00 This item is proposed As Per
commissioning of Repeater panel on FACP NBC , Local Fire Fighting
network configuration to monitor and control Requirements, and
all local fire alarm control panels with RS 485 mandatory, hence the item is
port on CPU board with optional network supplemetal.
software connectivity, fire/ fault indicators,
audio visual signals, battery, battery charger,
central processing unit 80 character display
unit complete in all respects(Makes: Notifier /
Edwards) (DATA -F156)
156 Supply and run of 3 Core x 1.5Sqmm FRLS RM 300 110.07 33021.40 33021.40 0.00 This item is proposed As Per
armoured copper cable as per IS. 7098 / NBC , Local Fire Fighting
Part-I / 1988 including all taxes etc., Requirements, and
complete in existing PVC conduit etc mandatory, hence the item is
complete for finished item of work (Makes: supplemetal.
Universal / Unicab / Polycab / Finolex
/Havells) (DATA -F157)
FIRE EXTINGUISHERS
157 Supply installation testing and Each 20 6488.42 129768.33 129768.33 0.00 This item is proposed As Per
commissioning of ABC type Fire Extinguisher NBC , Local Fire Fighting
of 5.0 Kgs, fitted with discharge control valve Requirements, and
( squeeze grip type ) , inside STORED mandatory, hence the item is
PRESSURE with ISI mark, with discharge supplemetal.
hase and open nozzel overall conforming to
IS: 15683 with ISI mark along with wall
bracket and initial refilling at site . Fire Rating
2A.(DATA -F158)
159 Supply of following size PVC Insulated and This item is proposed As Per
FRLS Round Sheathed Multi Core Bright NBC , Local Fire Fighting
Annealed Bare Copper Conductor Heavy Requirements, and
Duty Industrial Cables for Voltage Grade mandatory, hence the item is
upto 1100 Volts as per IS: 694:1990 supplemetal.
including all transportation charges etc
complete. (DATA -F160)
LIFT 10 Passenger/680Kg
Difference 82003911.81
48.73 %
2 Antitermite treatment
as per execution quantity vide
P.No.23 of MB No.03 1636.00
942.15
b Pedestals
as per execution quantity vide
P.No.24 of MB No.03 195.580
171.21
5 a Columns
as per execution quantity vide
P.No.25 of MB No.03 101.55
101.55
b Lintels
as per execution quantity vide
P.No.25 of MB No.03 3.81
B) Roof Slab
i Roof Slab 125mm thick
as per execution quantity vide
P.No.27 of MB No.03 1153.840
1960.70
10 Filling with carted gravel
as per execution quantity vide
P.No.29 of MB No.03 4647.75
To be done
Site development
Phase-I area as per drawing 7063.99 Sqm
Deductions
Bldg -1511.00 Sqm
Electrical room -67.570 Sqm
Pump Room -41.730 Sqm
Security Room -13.400 Sqm
Sump room -58.740 Sqm
5371.550 1.200 6445.86
19880.81
To be done
Front side compound wall 1 74.000 0.225 1.350 22.478
699.628
95.710
14 HYSD STEEL
as per execution quantity vide
P.No.33 of MB No.03 215.3160
17 Ceiling Plastering
as per execution quantity vide
P.No.35 of MB No.03 279.736
279.736
18 Internal plastering - 12 mm thick
as per execution quantity vide
P.No.35 of MB No.03 Say 5908.13
5908.13
19 External Plastering (12mm thick)
as per execution quantity vide
P.No.36 of MB No.03 2400.490
ii Panel Room
Panel Room 1 10.00 6.000 60.000
Ramp 1 10.00 1.350 13.500
Steps 1 1.25 1.200 1.500
159.46
Say 160.00
b Risers
Stair cases - 1,2,3 3 34 1.410 0.15 21.57
Entrance steps 1 5 5.670 0.15 4.25
before innovation hall 1 5 8.500 0.15 6.38
External staircase lobby 1 5 9.720 0.15 7.29
Out door glass (covered) 1 4 12.860 0.15 7.72
47.21
Say 48.00
31 Non-Skid Flooring
Gents toilets 1 4.3 3.7 15.91
janitor room 1 2.4 2 4.80
ladies toilets 1 4.5 2.4 10.80
ladies toilets 1 3 1.7 5.10
ph toilets 1 3 2.5 7.50
Sump
Ist Flight 1 2.040 1.000 2.04
IInd Flight 1 4.080 1.000 4.08
Midlanding 1 2.500 1.000 2.50
60.36
Say 61.00
38 Wall putty for Internal Walls &
ceiling
i Same as ceiling 1318.00
ii same as internal plastering
as per execution quantity vide
P.No.35 of MB No.03 Say 5908.13
ii Substation
ceiling plastering 1 10.000 6.000 60.00
iv Security Room & Gate
ceiling plastering 20.02
2522.18
Say 2523.00
43 Melamine Polish to Wood work
D1a 0.75 2 1.500 2.430 5.47
D1 0.75 6 1.500 2.430 16.40
D2 0.75 8 1.000 2.430 14.58
D3 0.75 3 1.000 2.430 5.47
46 Curtain glazing
East side Elevation
Innovative Hall -vertical 1 8.665 4.1 35.527
Innovative Hall -Horizontal 1 13.865 4.1 56.847
Faculty Room 1 1.145 3.745 4.288
Skill Development Class-02 1 2.162 3.745 8.097
Skill Development Class-02 1 2.265 3.745 8.482
OutDoor Class 1 3.63 4.1 14.883
OutDoor Class 1 8.96 4.1 36.736
North Side Elevation
Leftside of Staircase 1 9.76 4.1 40.016
Leftside of Staircase 1 3.63 4.1 14.883
Rightside of Staircase 1 4.009 3.3 13.230
Rightside of Staircase 1 4.665 3.3 15.395
Staircase 1 1.91 2.5 4.775
Innovation Group - vertical (Open to 15.180
sky area) 1 4.6 3.3
Spider Glazing
North Entry 1 4.865 4.3 20.920
North Entry 1 4.67 4.3 20.081
South entry 1 17.57 4.3 75.551
Left side (Lobby) 1 4.368 4.3 18.782
Left side (Lobby) 1 2.037 4.3 8.759
144.09
Say 145.00
False Ceiling
49 Armstrong false ceiling
Audio visualroom/lecture hall 1 12 6.92 83.04
Innovatives of skill Training 1 6.6 10.2 67.32
Innovatives Hall 1 14.4 6.6 95.04
Innovatives Group activities 1 8.4 6.6 55.44
300.84
Say 301.00
51 Fixed Partitions
Innovation Hall
class room Room-1 & 2 1.00 2 2.215 4.495 19.91
Toilet block 1.00 5 1.500 2.400 18.00
37.91
Say 38.00
53 Trapezoidal Dome
100 X 75 - Box section
or
122 X 61 x 4.5mm @ 11.88 Kg/Rm-
Box section
Section-A
Main Rafter 4 6.083 24.332
Section-B
Main Rafter 2 4.194 8.388
Verticals
4 0.85 3.4
2 1.2 2.4
3 1.05 3.15
41.67
or 495.0396
50 X 50 x 3.60 mm @ 4.98 Kg/RM
Box section
Purlins 3 8.3 24.9
1 7.98 7.98
1 7.39 7.39
1 6.73 6.73
1 6.04 6.04
alround 1 21.62 21.62
74.66
or 371.8068
13 Aluminium louvers
1 10.69 3.4 36.346
Say 37.00
15 Glass Door
Glass Room-1,2,3 & 4 1.00 4 1.000 2.400 9.60
9.60
Say 10.00
23 External cladding
S-W Right
Entry
Alco panel
verticals sides 2 3.750 3.000 22.500
verticals face 1 0.300 3.000 0.900
Ceiling 2 5.660 3.750 42.450
ceiling -face 1 5.660 0.300 1.698
ceiling -sides 1 3.750 0.300 1.125
Ampithere sides 1 5.870 5.000 29.350
Ampithere sides 1 6.630 5.000 33.150
Ampithere sides 1 6.630 5.000 33.150
Ampitheatre back 1 3.970 0.600 2.382
Ampitheatre side 1 6.590 0.600 3.954
innovation hall 1 8.960 0.600 5.376
innovation hall 2 2.510 0.600 3.012
Skill development Class-1 1 4.780 0.600 2.868
Skill development Class-2 1 4.780 0.600 2.868
Faculty Room 1 1.180 0.600 0.708
learning centre 1 7.000 0.600 4.200
Columns
as per execution quantity vide
P.No.51 of MB No.03 1.51
Rolling shutter
for panel room 1 3.00 2.100 6.300
Cum
Sqm
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Sqm
Sqm
Cum
Cum
Cum
Cum
Cum
Cum
Sqm
Sqm
Cum
Cum
MT
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Rmt
Rmt
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Kgs
Sqm
Sqm
Sqm
Sqm
Sqm
Kgs
Kgs
Sqm
Sqm
Sqm
Sqm
Sqm
RM
RM
RM
RM
RM
RM
Kgs
RM
RM
RM
RM
RM
RM
RM
Kgs
Kgs
Kgs
Sqm
Sqm
cum
cum
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
SQM
Sqm
Sqm
Sqm
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Sqm
Cum
Sqm
cum
cum
Sqm
Sqm
cum
Sqm
6 A) Roof beams
as per execution quantity vide
P.No.26 of MB No.03 84.110 Cum
B) Roof Slab
i Roof Slab 125mm thick
as per execution quantity vide
P.No.27 of MB No.03 928.10 Sqm
14 HYSD STEEL
as per execution quantity vide
P.No.33 of MB No.03 57.1090 MT
19 12 mm thick plastering in CM
(1:6) external
as per execution quantity vide 1488.650
P.No.36 of MB No.03 Sqm
1488.65
Say 1488.65 Sqm
ii Sump
Sump top slab 1 8.60 6.60 56.76
Pump Room 1 7.500 7.500 56.25
b Risers
Stair cases - 1,2,3 3 28 1.410 0.15 17.77
Say 18.00 Sqm
31 Non-Skid Flooring
Gents toilets 1 4.3 3.7 15.91
janitor room 1 2.4 2 4.80
ladies toilets 1 4.5 2.4 10.80
ladies toilets 1 3 1.7 5.10
ph toilets 1 3 2.5 7.50
44.11
Say 45.00 Sqm
32 Dadooing
Gents Toilet
W.C 2 5.400 2.400 25.92
Infront of W.C 1 9.490 2.400 22.78
At Hand Wash 1 10.800 2.400 25.92
Janitor Room 1 8.800 2.400 21.12
L. Toilet
2173.14
Say 2174.00 Sqm
Ceiling plastering
Qty. same Vitrified tile flooring 663.00
Qty. same Waist slab area
Qty. same Non- Skid flooring 45.00
Qty. same polished granite flooring 207.00
915.00
Say 915.00 Sqm
2174.00
Say 2174.00 Sqm
40 Wall putty for external paint
Same as 25% of external
plastering 372.16
372.16
Say 373.00 Sqm
46 Glazings
East side Elevation
From First Floor to Terrace
Left side 1 4.311 10.63 45.82593
Right side 1 3.568 10.63 37.92784
Staircase 1 1.95 13.1 25.545
North Side Elevation
From First Floor to Terrace
Staircase 1 1.91 13.1 25.021
Staircase left side
1 4.76 3.1 14.756
1 4.6 3.1 14.26
1 3.93 3.1 12.183
3 4.7 3.4 47.94
1 4.76 3.4 16.184
1 4.6 3.4 15.64
1 3.93 3.4 13.362
1 4.76 3.4 16.184
1 4.6 3.4 15.64
1 3.93 3.4 13.362
Staircase Right side
3 4.06 3.35 40.803
3 4.715 3.35 47.38575
West Side Elevation
From First Floor to Terrace
Left side 1 4.311 10.63 45.82593
Right side 1 3.568 10.63 37.92784
South Side Elevation
From First Floor to Terrace
Left side & Right side
First Floor 2 15.09 3.195 96.4251
Second Floor 2 15.09 3.495 105.4791
Third Floor 2 15.09 3.495 105.4791
Central Portion
First Floor 1 8.096 2.25 18.216
Second Floor 1 8.096 3.25 26.312
13 Aluminium louvers
b Lintels
as per execution quantity vide
P.No.26 of MB No.03 Say 2.13 Cum
6 A) Roof beams
as per execution quantity vide
P.No.26 of MB No.03 84.190 Cum
B) Roof Slab
i Roof Slab 125mm thick
as per execution quantity vide
P.No.27 of MB No.03 939.66 Sqm
14 HYSD STEEL
as per execution quantity vide
P.No.33 of MB No.03 53.918
53.918 MT
19 12 mm thick plastering in CM
(1:6) external
as per execution quantity vide 1223.420
P.No.36 of MB No.03
1223.42
Say 1223.42 Sqm
20 Impervious coat for Toilets
Gents Toilet
W.C 2 1.500 1.200 3.60
Infront of W.C 1 2.115 2.630 5.56
At Hand Wash 1 3.730 1.670 6.23
Janitor Room 1 2.000 2.400 4.80
L. Toilet
W.C 4 1.500 1.200 7.20
Infront of W.C 1 1.383 2.630 3.64
At Hand Wash 1 3.010 1.700 5.12
PH Toilet 1 2.000 2.720 5.44
41.59
Say 42.00 Sqm
23 Vitrified tile flooring
Office 1 & 2 1 16 8.5 136.00
Office 3 & 4 1 16 8.5 136.00
Office 5 & 6 1 16 8.5 136.00
Office 7 & 8 1 16 8.5 136.00
Office 9 1 3.5 3 10.50
Office 10 1 7 4 28.00
Office 11 1 9 6.2 55.80
AHU 1 5.47 3 16.41
PH Toilet 1 3 2.5 7.50
662.21
Say 663.00 Sqm
24 Polished Granite flooring
Staircase midLanding 3 3.000 1.500 13.50
Staircase Rooflevel Landing 1 3.000 2.000 6.00
Lobby 1 131.500 131.50
Deduct Cut out -1 19.630 -19.63
Lobby before PH Toilet and AHU
Room 1 2.000 5.950 11.90
Passage from Fire duct to
staircase 1 7.460 2.000 14.92
Passage in front of Janitors 1 3.490 1.575 5.50
Room
Passage Near cut out 1 2.000 6.000 12.00
Waiting Near cutout 1 6.600 4.600 30.36
206.05
Say 207.00 Sqm
25 Skirting with Vitrified tiles
Office 1 1 38.000 38.00
Office 2 1 23.600 23.60
44
Aluminium tubular @ 6 kg /Sqm 2692.00 Kgs
46 Glazing
East side Elevation
From First Floor to Terrace
Left side 1 4.311 10.63 45.82593
Right side 1 3.568 10.63 37.92784
Staircase 1 1.95 13.1 25.545
North Side Elevation
From First Floor to Terrace
Staircase 1 1.91 13.1 25.021
Staircase left side
1 4.76 3.1 14.756
1 4.6 3.1 14.26
1 3.93 3.1 12.183
3 4.7 3.4 47.94
1 4.76 3.4 16.184
1 4.6 3.4 15.64
1 3.93 3.4 13.362
1 4.76 3.4 16.184
1 4.6 3.4 15.64
1 3.93 3.4 13.362
Staircase Right side
3 4.06 3.35 40.803
3 4.715 3.35 47.38575
West Side Elevation
From First Floor to Terrace
Left side 1 4.311 10.63 45.82593
Right side 1 3.568 10.63 37.92784
South Side Elevation
From First Floor to Terrace
Left side & Right side
First Floor 2 15.09 3.195 96.4251
Second Floor 2 15.09 3.495 105.4791
Third Floor 2 15.09 3.495 105.4791
Central Portion
First Floor 1 8.096 2.25 18.216
Second Floor 1 8.096 3.25 26.312
East side Elevation
Office -8 (verticals) in First Floor 1 4.720 3.1 14.632
Office -7 (verticals) in First Floor 1 4.710 3.1 14.601
Drop
office 1 1 30 0.075 2.25
office 2 1 18.1 0.075 1.36
office1 & 2 northside sides 1 14.63 0.895 13.09
office1 & 2 west gyp sides 1 4.3 0.675 2.90
office1 & 2 south side sides 1 15.88 0.895 14.21
office 3 1 22.9 0.075 1.72
office 4 1 26.4 0.075 1.98
office3& 4 south side sides 1 15.9 0.895 14.23
office3& 4 north side sides 1 10.04 0.895 8.99
office3& 4 east side sides 1 4.31 0.675 2.91
18 SS railing
circular portion (All Round) 1 1 16.600 1.025 17.02
Box Portion (All Round) 1 1 16.760 1.025 17.18
34.19
Say 35.00 Sqm
19 UPVC Windows
W 3 0.900 1.200 3.24
3.24
Say 4.00 Sqm
20 UPVC Ventilators
V 4 0.600 0.600 1.44
V1 1 5.885 0.600 3.53
4.97
Say 5.00 Sqm
21 Texture paint for external
Same as 50% of external
plastering 611.71
611.71
Say 612.00 Sqm
6 A) Roof beams
as per execution quantity vide
P.No.27 of MB No.03 83.13 Cum
B) Roof Slab
i Roof Slab 125mm thick
as per execution quantity vide 688.79
P.No.27 of MB No.03 Sqm
14 HYSD STEEL
as per execution quantity vide
P.No.33 of MB No.03 59.3540
59.354 MT
18 Internal plastering 12 & 20 mm
thick
as per execution quantity vide
P.No.36 of MB No.03 Say 1370.11 Sqm
20 Impervious coat
i Open terrace 1 45.960 45.96
45.96
Say 46.00 Sqm
Impervious coat for Toilets
ii Gents Toilet
W.C 2 1.500 1.200 3.60
Infront of W.C 1 2.115 2.630 5.56
At Hand Wash 1 3.730 1.670 6.23
Janitor Room 1 2.000 2.400 4.80
L. Toilet
W.C 4 1.500 1.200 7.20
Infront of W.C 1 1.383 2.630 3.64
At Hand Wash 1 3.010 1.700 5.12
PH Toilet 1 2.000 2.720 5.44
41.59
Say 42.00 Sqm
46 Glazing
East side Elevation
From First Floor to Terrace
Left side 1 4.311 10.6 45.83
Right side 1 3.568 10.6 37.93
Staircase 1 1.950 13.1 25.55
North Side Elevation
From First Floor to Terrace
Staircase 1 1.910 13.1 25.02
Staircase left side
1 4.760 3.1 14.76
1 4.600 3.1 14.26
1 3.930 3.1 12.18
3 4.700 3.4 47.94
1 4.760 3.4 16.18
1 4.600 3.4 15.64
1 3.930 3.4 13.36
1 4.760 3.4 16.18
1 4.600 3.4 15.64
1 3.930 3.4 13.36
Staircase Right side
3 4.060 3.4 40.80
3 4.715 3.4 47.39
West Side Elevation
From First Floor to Terrace
Left side 1 4.311 10.6 45.83
Right side 1 3.568 10.6 37.93
South Side Elevation
From First Floor to Terrace
Left side & Right side
First Floor 2 15.090 3.2 96.43
Second Floor 2 15.090 3.5 105.48
Third Floor 2 15.090 3.5 105.48
Central Portion
First Floor 1 8.096 2.3 18.22
Second Floor 1 8.096 3.3 26.31
East side Elevation
Office -8 (verticals) in First Floor 1 4.720 3.1 14.63
Office -7 (verticals) in First Floor 1 4.710 3.1 14.60
Office -6(verticals) in First Floor 1 4.760 3.1 14.76
Office -5 (verticals) in First Floor 1 4.600 3.1 14.26
51 Fixed Partitions
Toilet block 1.00 5 1.500 2.4 18.00
18.00
Say 18.00 Sqm
52 Fixed Partitions with Door
Meeting Room 1 1 2.860 3.5 9.92
Toilet block 1.00 3 2.630 2.4 18.94
28.86
Say 29.00 Sqm
South west
100 X 150 Box Section
(172x92X4.80 @ 18.71 Kg/RM
wall 1 8.6 8.58 RM
Arc portion 1 9.8 9.77 RM
18.35 RM
or 343.35 Kgs
Say 344.00 Kgs
54 ACP Cladding
Portico - Top & Bottom 2 6.763 3.8 51.30 Sqm
Portico - Face 1 21.112 0.3 6.33 Sqm
Shear wall
alround 1 8.180 2.8 23.17 Sqm
Central portion
verticals 8 2.000 0.200 7.7 24.64 Sqm
verticals 8 2.000 0.200 0.3 0.80 Sqm
verticals 8 1.000 0.200 0.5 0.72 Sqm
Horizontals 8 6.000 0.200 0.8 8.05 Sqm
Supporting clamps 8 3.000 0.200 0.9 4.32 Sqm
8 3.000 0.200 0.4 1.68 Sqm
277.66 Sqm
Say 278.00 Sqm
South west
100 X 150 Box Section
(172x92X4.80 @ 18.71 Kg/RM
wall 1 0.500 8.6 4.29 Sqm
Arc portion 1 0.500 9.8 4.88 Sqm
9.18 Sqm
Say 10.00 Sqm
b Lintels
D1 3 1.960 0.225 0.175 0.23
D3 3 1.460 0.225 0.175 0.17
D4 1 1.220 0.225 0.175 0.05
For Terrace Dome 1 16.100 0.230 0.150 0.56
For cut-out Dome 1 16.100 0.230 0.150 0.56
1.56
Say 1.60 Cum
6 A) Roof beams
as per execution quantity vide
P.No.27 of MB No.03 15.497 Cum
B) Roof Slab
i Roof Slab 125 mm thick
as per execution quantity vide
P.No.27 of MB No.03 129.537 Sqm
12 HYSD STEEL
as per execution quantity vide
P.No.33 of MB No.03 Say 15.186 MT
17 Ceiling plastering
as per execution quantity vide
P.No.35 of MB No.03 Say 157.92 Sqm
680.80
Say 681.00 Sqm
39 Plastic emulsion Paint for Internal
Wall
Same as wall putty area 680.80
680.80
Say 681.00 Sqm
40 Wall putty for external paint
Same as 40% of external plastering
460.52
Say 461.00 Sqm
Acrylic emulsion paint for external
41
Same as of external plastering 1,151.31
Say 1,152.00 Sqm
42 Painting to wood work
D1 2.25 3 1.500 2.430 24.60
D3 1.00 3 1.000 2.430 7.29
D4 1.00 1 0.760 2.130 1.62
33.51
Say 34.00 Sqm
53 Dome
i Circular Dome
75 X 75X4.8 mm @ 9.66 Kg/RM-
MS Box section
Radial members 8 2.457 19.656 RM
circumferential 1 17.15532 17.155 RM
36.81 RM
Say 355.60 Kgs
75mmx75mmx3mm MS Plate @
23.55Kg/Sqm 8 0.075 0.075 0.045 Sqm
or 1.05975 Kgs
ii Rectangular Dome
50 X 50 x 3.60 mm @ 4.98 Kg/RM
Box section
Main Rafters 11 2.8 30.800 RM
Purlins 5 6.6 33.000 RM
verticals 4 0.49 1.960 RM
verticals 2 0.75 1.500 RM
67.26 RM
Say 334.95 Kgs
75mmx75mmx3mm MS Plate @
23.55Kg/Sqm 16 0.075 0.075 0.09 Sqm
or 2.1195 Kgs
Wooden Doors
8 i D1a 3 1.500 2.430 10.94
Say 11.00 Sqm
1 Earth work excavation for foundations (Mechanical 39.00 One CUM 99.83 3894
Means) for buildings in ordinary soils and depositing on
bank for all lifts and with an initial lead of 10m and up to
3m depth including all operational,incidental, labour
charges such as shoring, sheeting, planking, strutting etc.,
and overheads & contractors profit, all taxes except GST
complete,for finished item of work excluding dewatering
charges etc., as per SS 20 B(APSS 308)
2 Plain Cement Concrete (1:4:8) (cement: fine aggregate: 3.00 One CUM 3712.66 11138
Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine
crushed granite metal from approved quarry including
cost and conveyance of all materials like cement, sand,
coarse aggregate, water etc. to site, including seigniorge
charges,sales & all other taxes,except GST on all
materials and including all charges for machine mixing,
laying concrete in foundations and under flooring bed,
ramming in 15 cm layers, finishing top surface to the
required level, curing etc.,complete and overheads &
contractors profit, complete, , for finished item of work.
(APSS No. 402)
3 Plain Cement Concrete (1:5:10) (cement: fine aggregate: 6.00 One CUM 3539.65 21238
Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine
crushed granite metal from approved quarry including
cost and conveyance of all materials like cement, sand,
coarse aggregate, water etc. to site, including seigniorge
charges,sales & all other taxes,except GST on all
materials and including all charges for machine mixing,
laying concrete in foundations and under flooring bed,
ramming in 15 cm layers, finishing top surface to the
required level, curing etc.,complete and overheads &
contractors profit, complete, , for finished item of work.
(APSS No. 402)
4 Filling with useful available excavated earth (excluding 31.00 One CUM 29.35 910
rock) with a lead of 50 m in trenches, sides of foundations
and basement with initial lead in layers not exceeding
15cm thick, watering and ramming including cost and
conveyance of water to work site and all operaitonal,
incidental, labour charges, hire charges of T&P etc., and
overheads & contractors profit, all taxes except GST
complete, , for fnished item of work (APSS NO.309&310)
5 Supply and placing of the Design Mix Concrete M 30
grade corresponding to IS 456 with minimum cement
content of 400 kgs per 1 cum of concrete using WEIGH
BATCHER / MIXER with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS
383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water
etc., to site and seignorge charges,sales & other taxes on
all materials , centering using Steel scaffolding pipes ,
jack props , wallers , Foot plates , brackets , steel
centering plates etc., including all operational, incidental
and labour charges such as weigh batching, machine
mixing, laying concrete, curing etc., and overheads &
contractors profit,all taxes except GST complete but
excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402)
3 PCC (1:5:10)
Granolithic flooring 1 6.600 9.000 0.100 5.94 ###
Deductions
C1 -6 0.900 0.450 0.100 -0.24
For 1 Shed 5.70
For 1 Sheds Say 6.00 Cum
4
Earth filling with available earth
Qty as per excavation 38.61 38.61
Deductions
a Qty as per PCC (1:4:8) -2.9
b Qty as per PCC (1:5:10) -5.70
c Qty as per footing -4.86
d Qty as per Pedestals upto Ground
level -3.77
21.39075 -17.22
For 1 Shed 21.39
Say 21.00 Cum
5 Basement Filling
Qty Same as Granolithic flooring 59.40 0.230 13.66
For 1 Shed 13.66
For 1 Sheds Say 14.00 Cum
9 TMT STEEL
Columns Footings 4.9 60.000 Kgs/Cum 291.60
Pedestals 5.4 125.000 Kgs/Cum 677.36
For 1 Shed 969.0
For 1 Sheds Say 1.00 MT
10 Granolithic flooring
For 1 Shed 1 6.600 9.000 59.40 Sqm
For 1 Sheds Say 59.00 Sqm
Truss
12 MS Tubular pipes
Length Weight - Total
Particulars Nos
in mts Kg/RM weight
For Vertical Post
48.3 (OD) (M) vertical members -
12 2.85
(6x2=12) 3.610 123.46
48.3 (OD) (M) Horizontal members
30 0.45
for vertical Posts - (6x5=30) 3.610 48.74
48.3 (OD) (M) inclined members for
30 0.60
vertical Posts - (6x5=30) 3.610 65.20
For Truss
48.30 (OD) (M) Top curved member
6 4.257
- (6x1=6) 3.610 92.21
48.30 (OD) (M) vertical member -
12 0.15
(6x2=12) 3.610 6.50
48.30 (OD) (M) inclined member -
12 0.35
(6x2=12) 3.610 15.03
48.30 (OD) (M) inclined member -
12 0.44
(6x2=12) 3.610 18.89
48.30 (OD) (M) inclined member -
(6x2=12) 12 0.44
3.610 18.84
48.30 (OD) (M) inclined member -
(6x2=12) 12 0.53
3.610 22.74
48.30 (OD) (M) inclined member -
12 0.51
(6x2=12) 3.610 22.14
48.30 (OD) (M) inclined member -
12 0.50
(6x2=12) 3.610 21.75
48.30 (OD) (M) bottom member -
6 4.20
(6x1=6) 3.610 90.97
Purlins- 40x40x3.2mm 8 9.00 3.490 251.28
For 6 Trusses 797.74 Kgs
For 1 Shed 0.80 MT
For 1 Sheds 1.00 MT
13 Structural steel
For Columns
16mm thick Base plate 6 0.41 125.6 305.21 ###
16mm thick Cap plate 6 0.41 125.6 305.21 ###
16mm thick Gusset plate 48 0.0061 125.6 36.47 ###
Purlin connecting plate
(270x130x10mm) 48 0.04
78.5 132.26
20 mm dia bolts 60 0.60 2.470 88.92
16 mm dia bolts 96 0.10 1.580 15.17
883.24 Kgs
For 6 Trusses 0.88 MT
For 1 Shed 0.88 MT
For 1 Sheds 1.00 MT
14 Roofing
Parking shed 1 5.210 9.00 46.89 Sqm
For 1 Shed 46.89 Sqm
For 1 Sheds Say 47.00 Sqm
2 Plain Cement Concrete (1:4:8) (cement: fine 6.80 One CUM 3712.66 25246
aggregate: Coarse aggregate) for foundations and
under flooring bed using coarse aggregate 40mm size
hard , machine crushed granite metal from approved
quarry including cost and conveyance of all materials
like cement, sand, coarse aggregate, water etc. to site,
including seigniorge charges,sales & all other
taxes,except GST on all materials and including all
charges for machine mixing, laying concrete in
foundations and under flooring bed, ramming in 15 cm
layers, finishing top surface to the required level,
curing etc.,complete and overheads & contractors
profit, complete, , for finished item of work. (APSS No.
402)
3 Plain Cement Concrete (1:5:10) (cement: fine 32.00 One CUM 3539.65 113269
aggregate: Coarse aggregate) for foundations and
under flooring bed using coarse aggregate 40mm size
hard , machine crushed granite metal from approved
quarry including cost and conveyance of all materials
like cement, sand, coarse aggregate, water etc. to site,
including seigniorge charges,sales & all other
taxes,except GST on all materials and including all
charges for machine mixing, laying concrete in
foundations and under flooring bed, ramming in 15 cm
layers, finishing top surface to the required level,
curing etc.,complete and overheads & contractors
profit, complete, , for finished item of work. (APSS No.
402)
4 Filling with useful available excavated earth (excluding 72.00 One CUM 29.35 2113
rock) with a lead of 50 m in trenches, sides of
foundations and basement with initial lead in layers not
exceeding 15cm thick, watering and ramming including
cost and conveyance of water to work site and all
operaitonal, incidental, labour charges, hire charges of
T&P etc., and overheads & contractors profit, all taxes
except GST complete, , for fnished item of work (APSS
NO.309&310)
Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
5 Supply and placing of the Design Mix Concrete M 30
grade corresponding to IS 456 with minimum cement
content of 400 kgs per 1 cum of concrete using
WEIGH BATCHER / MIXER with 20mm size graded
machine crushed hard granite metal (coarse aggregate
- as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry including cost and conveyance
of all materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and seignorge
charges,sales & other taxes on all materials , centering
using Steel scaffolding pipes , jack props , wallers ,
Foot plates , brackets , steel centering plates etc.,
including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying
concrete, curing etc., and overheads & contractors
profit,all taxes except GST complete but excluding cost
of steel and its fabrication charges for finished item of
work (APSS No. 402)
8 Plastering 20mm thick single coat in CM(1:5) using 30.00 One SQM. 205.42 6163
screened sand including cost and conveyance of all
materials like cement, sand, water etc., to site,
including sales & other taxes on all materials, and all
operational, incidental charges on materials and
including cost of all labour charges for mixing mortar,
finishing, curing as directed by Engineer-in-charge etc.,
and overheads & contractors profit complete for
finished item of work .(SS 901,903 & 904)
3 PCC (1:5:10)
Granolithic flooring 1 8.900 18.000 0.100 16.02 ###
Deductions
C1 -7 1.050 0.450 0.100 -0.33
For 1 Shed 15.69
For 2 Sheds Say 32.00 Cum
4
Earth filling with available earth
Qty as per excavation 45.05 45.05
Deductions
a Qty as per PCC (1:4:8) -3.4
b Qty as per PCC (1:5:10) -15.69
c Qty as per footing -5.70
d Qty as per Pedestals upto Ground
level -5.13
15.15075 -29.89
For 1 Shed 15.15
Say 15.00 Cum
5 Basement Filling
Qty Same as Granolithic flooring 160.20 0.230 36.85
For 1 Shed 36.85
For 2 Sheds 37.00
Say 74.00 Cum
9 TMT STEEL
Columns Footings 5.7 60.000 Kgs/Cum 340.20
Pedestals 7.4 125.000 Kgs/Cum 921.97
For 1 Shed 1262.2
For 2 Sheds Say 2.60 MT
10 Granolithic flooring
For 1 Shed 1 8.900 18.000 160.20 Sqm
For 2 Sheds Say 322.00 Sqm
Truss
12 MS Tubular pipes
Length Weight - Total
Particulars Nos
in mts Kg/RM weight
For Vertical Post
88.9 (OD) (M) vertical members -
(7x2=14) 14 5.81
8.480 690.00
48.3 (OD) (M) Horizontal members
for vertical Posts - (7x4=28) 28 0.60
3.610 60.65
48.3 (OD) (M) Horizontal members
for vertical Posts - (7x1=7) 7 1.16
3.610 29.31
48.3 (OD) (M) inclined members for
21 0.74
vertical Posts - (7x3=21) 3.610 55.72
For Truss
48.30 (OD) (M) Top curved member
7 8.99
- (7x1=7) 3.610 227.10
48.30 (OD) (M) inclined member -
14 0.34
(7x2=14) 3.610 17.13
48.30 (OD) (M) inclined member -
14 0.39
(7x2=14) 3.610 19.91
48.30 (OD) (M) inclined member -
14 0.47
(7x2=14) 3.610 23.80
48.30 (OD) (M) inclined member -
(7x2=14) 14 0.55
3.610 27.65
48.30 (OD) (M) inclined member -
14 0.62
(7x2=14) 3.610 31.39
48.30 (OD) (M) inclined member -
14 0.70
(7x2=14) 3.610 35.58
48.30 (OD) (M) inclined member -
14 0.77
(7x2=14) 3.610 38.71
48.30 (OD) (M) inclined member -
14 0.85
(7x2=14) 3.610 43.06
48.30 (OD) (M) inclined member -
14 0.90
(7x2=14) 3.610 45.38
48.30 (OD) (M) inclined member -
14 1.02
(7x2=14) 3.610 51.40
48.30 (OD) (M) inclined member -
14 1.05
(7x2=14) 3.610 52.81
48.30 (OD) (M) inclined member -
(7x2=14) 14 1.22
3.610 61.86
48.30 (OD) (M) inclined member -
14 1.36
(7x2=14) 3.610 68.89
48.30 (OD) (M) Horizontal member
1.7mts above baseplate - (6x2=12) 12 2.92
3.610 126.58
Tie Runners
48.30 (OD) (M) Tie Runners -
6 18.38
(6x1=6) 3.610 398.11
26.70 (OD) (M) Wind bracings for
24 3.41
Tie Runners - (6x4=24) 1.580 129.42
Purlins- 63x63x3.6mm 15 18.38 6.710 1849.95
26.70 (OD) (M) Wind bracings for
48 3.14
Purlins - (6x1=6) 1.580 238.29
For 7 Trusses 4322.71 Kgs
For 1 Shed 4.32 MT
For 2 Sheds 8.65 MT
13 Structural steel
For Columns
16mm thick Base plate 7 0.47 125.6 415.42 ###
16mm thick Cap plate 7 0.41 125.6 356.08 ###
8mm thick Gusset plate 56 0.0061 62.8 21.28 ###
Tie Runner connecting plate
42 0.02
(150x100x10mm) 78.5 49.46
Purlin connecting plate
105 0.04
(270x130x10mm) 78.5 289.31
20 mm dia bolts 70 0.60 2.470 103.74
16 mm dia bolts 84 0.10 1.580 13.27
16 mm dia bolts 210 0.10 1.580 33.18
For 7 Trusses 1281.73 Kgs
For 1 Shed 1.28 MT
For 2 Sheds 2.56 MT
14 Roofing
Parking shed 1 9.000 18.38 165.42 Sqm
For 1 Shed 165.42 Sqm
For 2 Sheds Say 332.00 Sqm
15 Aluminium glazing
Parking shed 15 18.380 275.70 RM
For 1 Shed 275.70 RM
For 2 Sheds Say 552.00 RM
2 Providing Plain Cement Concrete (1:3:6) mix using 20mm size 73.00 ONE CUM 3692.38 269544
HBG crushed stone aggregate and fine aggregate conforming
to table 1000-2 of MoRT&H including cost, conveyance of all
materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other
incidental and operational charges of all T&P etc., complete
for finished item of work as per MoRT&H specification
1500,1700, 2100 (5th Revision) and as directed by the
Engineer-in-Charge for base coarse below CC Pavement
excluding GST.
3 Construction of un-reinforced, dowel jointed at expansion and 145.00 ONE CUM 4999.59 724941
construction joint only, plain cement concrete pavement,
thickness as per design, over a prepared sub base, with 43
grade cement or any other type as per Clause 1501.2.2 M30
(Grade), coarse and fine aggregates conforming to IS : 383,
maximum in a concrete mixer of not less than 0.2 cum
capacity and appropeiate weigh batcher using approved mix
design, laid in approved fixed side formwork (steel channel,
laying and fixing of 125 mictron thick polythene film, wedges,
steel plates including levelling the formwork as per drawing),
spreading the concrete with sholvels, rakes, compacted using
needle, scareed and plate vibrators and finished in continuous
operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant,
dowel bars, near approaches to bridge / culvert and
construction joints, admixtures as approved, curing of
concrete slabs for 14- days, curing compound (where
specified) and water finishing to lines and grade as per
drawing and Technical Specification Clause 1501 MORD
excluding GST.
2 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse 13.20 Cum 3712.66 49007
aggregate) for foundations and under flooring bed using coarse
aggregate 40mm size hard , machine crushed granite metal
from approved quarry including cost and conveyance of all
materials like cement, sand, coarse aggregate, water etc. to site,
including seigniorge charges,sales & all other taxes,except GST
on all materials and including all charges for machine mixing,
laying concrete in foundations and under flooring bed, ramming
in 15 cm layers, finishing top surface to the required level, curing
etc.,complete and overheads & contractors profit, complete, ,
for finished item of work. (APSS No. 402)
a Sump Roof beams upto 3.66 mts level 1.40 CUM 10878.07 15229
b Pump Roof beams upto 3.66 mts level 2.40 CUM 10878.07 26107
c Sump Roof Slab 125 mm thick upto an unsupported height of 60.00 Sqm 1301.24 78075
3.66 mts level
d Pump Room Roof Slab 125 mm thick upto an unsupported 47.00 Sqm 1301.24 61158
height of 3.66 mts level
e 150 mm thick Roof Slab upto an unsupported height of 3.66 14.00 Sqm 1449.65 20295
mts level
f 175mm thick Roof Slab upto an unsupported height of 3.66 mts 10.00 Sqm 1614.51 16145
level
7 Plain Cement Concrete M 20 design mix using WEIGH 0.50 CUM 6173.01 3087
BATCHER / MIXER, 20mm size hard granite machine crushed
graded metal (coarse aggregate - as per IS 383 - 1970 and IS
2386 Part 1 to Part 8) from approved quarry, using a minimum
quantity of 350 kgs. of cement per 1 cum of concrete including
cost and conveyance of all materials like cement, fine
aggregate (Sand), coarse aggregate, water etc., to site
including steel centering, shuttering, machine mixing, lift
charges, laying concrete,vibrating, curing, overheads &
contrctors profit etc.,all taxes except GST complete for finished
item of work (APSS No. 402 & 403) for steps
9 Providing impervious coat to exposed RCC roof slab 334.00 Sqm 160.15 53489
surfaces of sump , sump side wall,sump bottom slab,in
side of septic tank , in sunken slabs etc. to required slopes
with CM (1:3) prop. using screened sand 12mm thick mixed
with integral cement water proofing liquid confirming to IS: 2645-
2003 manufactured by reputed manufacturers as approved by
Engineer-in-charge at 1 Kg per one bag of cement, laid over roof
slab when it is green, finished smooth with a floating coat of neat
cement and thread lining at regular intervals of 45cmx45cm
where ever necessary including cost and conveyance of all
materials like cement, sand, water proofing compound, water
etc., to site, including seignorge charges, sales & other taxes
except GST on all materials and operational, incidental, and
labour charges for mixing mortar, laying, lift charges, rendering
smooth and thread lining, curing including rounding off junctions
of wall and slab etc., and overheads & contractors profit etc
complete for finished item of work. (APSS No. 901 & 903).
10 Providing impervious coat to exposed RCC roof slab surfaces to 105.00 Sqm 473.57 49725
required slopes with CM (1:3) prop. using screened sand 20mm
thick (average) mixed with integral cement water proofing liquid
confirming to IS: 2645-2003 manufactured by reputed
manufacturers as approved by Engineer-in-charge at 0.40 litres
per 10.00sqm of roof area, laid over roof slab when it is green,
finished smooth with a floating coat of neat cement slurry and
thread lining at regular intervals of 45cmx45cm including cost
and conveyance of all materials like cement, sand, water
proofing compound, water etc., to site, including seigniorge
charges, sales & all other taxes except GSTon all materials and
operational, incidental, and labour charges for mixing mortar,
laying, lift charges, rendering smooth and thread lining, curing
including rounding off junctions of wall and slab etc., and
overheads & contractors profit complete for finished item of
work. (APSS No. 901 & 903).
12 Ornamental ceiling plastering 12mm thick single coat in CM (1:5) 42.00 SQM 161.54 6785
using screened sand including cost and conveyance of all
materials like cement, sand, water etc., to site, including sales &
other taxes on all materials, and all operational, incidental
charges on materials and including all taxes except GST, cost of
all labour charges for mixing mortar, finishing, curing as directed
by Engineer-in-charge etc., and overheads & contractors profit
complete for finished item of work.(SS 901,903 & 904)
13 Plastering 12mm thick in two coats using screened sand with 57.00 SQM 404.24 23042
base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in
CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site,
including seigniorge charges,sales & other taxes except GST on
all materials, and all operational & incidental charges including
cost and conveyance of all materials to site, all labour charges
for mixing mortar, finishing, scaffolding, lift charges, curing,
including cutting grooves as directed by Engineer - in - charge
etc., complete, including overheads & contractors profit for
finished item of work. (SS 901,903 & 904)
14 Plastering 20mm thick in two coats using screened sand with 61.00 SQM 421.70 25724
base coat of 16mm thick in CM(1:6) and top coat of 4mm thick in
CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site,
including seigniorge charges,sales & all other taxes except GST
on all materials, and all operational, incidental charges including
cost and conveyance of all materials to site, all labour charges
for mixing mortar, finishing, scaffolding, lift charges, curing,
including cutting grooves as directed by Engineer-in-charge etc.,
and overheads & contractors profit complete for finished item of
work .(SS 901,903 & 904) External faces of Walls
16 Supply & fixing of Rolling shutter made of 80 x 1.25 mm 5.10 SQM 4017.43 20489
machine rolled CRCA laths, interlocked together through their
entire length and jointed together at the ends by end-locks,
mounted on specially designed pipe shaft of 50mm dia nominal
bore MS B class pipe with brackets, plates, guide channels,
stoppers, bottom locking plates and arrangements for inside &
outside locking with push-pull operations including cost of hood
cover and springs complete, painted with one coat of approved
steel primer, locks, ball bearings, all accessories etc., overheads
& contractors profit complete for finished item of work as per
special spn: 1108
17 Painting two coats with synthetic enamel paint Grade-II VOC 11.00 SQM 159.78 1758
(Volatile Organic Compound) content less than 50 grams/litre
over primer coat of red oxide to new iron work including cost and
conveyance of all materials to site, sales & other taxes,
incidental, operational and all labour charges etc., and
overheads & contractors profit ,all taxes except GST complete
for finished item of work in all floors. (SS No. 1201, 1212 &
1207).
18 White washing two coats with white cement to ceiling to give an 42.00 SQM 20.39 856
even shade after thouroughly brushing the surface to remove all
dirt and remains of loose powdered materials including cost of
all materials , labour charges and incidental such as scaffolding ,
lift charges all taxes except GST, overheads & contractors profit
etc., complete for finished item of work.
19 Supply & application of one coat water based Cement Primer of 57.00 SQM 159.39 9085
Interior Grade-1 and two coats of acrylic emulsion paint interior
grade having VOC (Volatile Organic Compound) content less
than 50 grams/ liter for internal walls including cost and
conveyance of all materials to site, sales & other taxes except
GST, incidental, operational and all labour charges etc.,and
overheads & contractors profit etc.,complete for finished item of
work in all floors.
21 Supplying and fixing stainless steel hand railing, balustrade etc 21.00 SQM 5079.25 106664
using 304 grade stainless steel pipes of 50 mm dia nominal bore
for hand railing at 3'0" high from base leveland 40mm dia
nominal bore for vertical supports placed at 5'0"c/c and two
numbers 25mm dia nominal bore for horizontal pipes placed
below hand railing pipe as per the approved drawing including
cost and conveyance of all materials to site, buffing charges,
polishing charges all taxes except GST, over heads &
contractors profit etc complete using pipes with minimum weight
of 4.57kg/Rmt for 50mm dia, 3.61kg /Rmt for 40mm dia and
2.46kg/Rmt for 25mmdia, complete for finished item of work.
22 Supply and placing in postion water stopper 8 - 10 mm thick 310 163.00 RM 460.14 75003
mm wide including cost and conveyance of all materials to site
and sales and other taxes except GST on all materials to site
etc., complete for finished item of work
23 Filling with useful available excavated earth (excluding rock) 97.00 CUM 29.35 2847
with a lead of 50 m in trenches, sides of foundations and
basement with initial lead in layers not exceeding 15cm thick,
watering and ramming including cost and conveyance of water
to work site and all operaitonal, incidental, labour charges, hire
charges of T&P etc., and overheads & contractors profit, all
taxes except GST complete, , for fnished item of work (APSS
NO.309&310)
3633141.00
b PCC Steps
Staircase steps 0.50 19 1.00 0.30 0.150 0.43
0.428
SAY 0.500 CUM
c 375 mm thick side walls
Sump long walls 2 9.975 3.600 71.82
Sump short walls 1 5.000 3.600 18.00
Pump Room long walls 2 6.750 4.100 55.35
Pump Room short walls 1 5.000 4.100 20.50
165.670
SAY 166.000 Sqm
125 mm thick Pump Room Roof Slab 0.125 46.81 70.0 Kg/cum 409.58
150 mm thick Ramp Slab 0.15 13.20 70.0 Kg/cum 138.55
175mm thick Staircase slab 0.175 9.880 80.0 Kg/cum 138.32
16436.89
Say 16.50 MT
10 External Plastering
Pump Room alround 1 23.840 2.525 60.196
SAY 61.000 Sqm
11 Basement Plastering
Sump alround 1 46.800 0.600 28.080
SAY 29.000 Sqm
18 SS Railing
Ist Flight 1 2.040 1.000 2.04
IInd Flight 1 4.080 1.000 4.08
Midlanding 1 2.500 1.000 2.50
Ramp 1 10.150 1.000 10.15
Ramp 1 1.300 1.300 1.69
20.46
Say 21.000 SQM
2 Plain Cement Concrete (1:5:10) (cement: fine aggregate: 3.80 Cum 3539.65 13451.0
Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine crushed
granite metal from approved quarry including cost and
conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including seigniorge
charges,sales & all other taxes,except GST on all materials
and including all charges for machine mixing, laying concrete
in foundations and under flooring bed, ramming in 15 cm
layers, finishing top surface to the required level, curing
etc.,complete and overheads & contractors profit, complete, ,
for finished item of work. (APSS No. 402)
115 mm thick Septic Tank Roof Slab 27.00 Sqm 1241.89 33531.0
6 Supplying fitting and placing Thermo Mechanically Treated 3.00 MT 68546.49 205639.0
(TMT) (Fe 500 grade as per IS 1786-1979) using primary
producers like TATA, SAIL, VSP, Jindal, Shyam Steel etc., of
bar reinforcements below 36mm diameter for RCC works,
including labour charges for straightening, cutting, bending to
required sizes and shapes, placing in position with cover
blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks
and all incidental, operational, labour charges such as cutting,
bending, placing in position, tying including sales and all other
taxes except GST on all materials etc. ,and overheads &
contractors profit complete for finished item of work.( APSS
No.126)
8 RCM facia 50mm thick using screened sand for drop walls, 3.00 Sqm 1533.48 4600.0
fins with rabbit wire mesh & nomianl reinforcement as
directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to site,
seigniorge charges,sales & other taxes except GST on all
materials,operational & incidental, cost and conveyance of
cement,wire mesh,water to work site,centering,scaffolding and
form work,lift charges etc., and overheads & contractors profit
complete for finished item of work but excluding cost of steel
and its fabrication charges for finished item of work(APSS
NO.403&903)
9 Supply and delivery of encapsulated plastic steps 36.00 Each 197.69 7117.0
Manufactured as per company’s standard specification for
man holes anywhere in T.G. including cost of materials
packing as per company’s standards, loading, transportation,
unloading and stacking at site of work , overheads &
contractors profit etc, complete but excluding taxes and others
etc., as applicable including labour charges for fixing etc.
complete for finished item of work..
10 Plain Cement Concrete (1:3:6) nominal mix using 20mm size 0.10 Cum 4897.33 490.0
graded machine crushed hard granite metal (coarse aggregate
- as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and conveyance of all
materials like cement, fine aggregate(sand), coarse aggregate,
water etc. to site, including seigniorge charges,sales & all
other taxes except GST on all materials including all labour
and machinery charges such as mixing, laying concrete in
position, curing ,vibrating, all lift charges etc.,, and overheads
& contractors profit for Bed Blocks & Hold Fasts for finished
item of work. (APSS No. 402).
368 833673.0
a Bottom
Compartment-1 1 5.70 2.10 11.97
Compartment-2 1 2.85 2.10 5.99
Inlet chamber 1 1.000 1.00 1.00
Outlet chamber 1 1.000 1.00 1.00
b Internal walls
Compartment-1 1 15.600 3.235 50.47
Compartment-2 1 9.900 2.950 29.21
Inlet chamber 1 4.000 1.00 4.00
Outlet chamber 1 4.000 1.00 4.00
c ceiling
Compartment-1 1 5.70 2.10 11.97
Compartment-2 1 2.85 2.10 5.99
Inlet chamber 1 1.000 1.00 1.00
Outlet chamber 1 1.000 1.00 1.00
127.58
SAY 128.000 SQM
6 Baffle walls
1 2.100 0.675 1.42
1 2.100 0.600 1.26
2.68
SAY 3.000 Sqm
7 Refilling with excavated earth
Qty same as per excavation 74.00
Deductions
Qty same as PCC (1:4:8) -3.749
Qty same as Raft concrete -8.800
Septic tank internal (compartment-1) -23.760
Septic tank internal (compartment-2) -10.175
Compartment-1
Qty same as Side walls
1*(2.1+5.93)=13.96 -6.235
shorter Side walls -0.536
Qty same as Side walls
1*(3.225+2.1*2)=8.55 -3.270
-56.52 -56.525
17.475
Say 18.000 Cum
2 Plain Cement Concrete (1:5:10) (cement: fine aggregate: 11.00 Cum 3539.65
Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine crushed
granite metal from approved quarry including cost and
conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including seigniorge
charges,sales & all other taxes,except GST on all materials
and including all charges for machine mixing, laying concrete
in foundations and under flooring bed, ramming in 15 cm
layers, finishing top surface to the required level, curing
etc.,complete and overheads & contractors profit, complete, ,
for finished item of work. (APSS No. 402)
8 Providing impervious coat to exposed RCC roof slab 44.00 Sqm 438.85
surfaces to required slopes with CM (1:3) prop. using
screened sand 20mm thick (average) mixed with integral
cement water proofing liquid confirming to IS: 2645-2003
manufactured by reputed manufacturers as approved by
Engineer-in-charge at 1 Kg per one bag of cement, laid over
roof slab when it is green, finished smooth with a floating coat
of neat cement and thread lining at regular intervals of
45cmx45cm including cost and conveyance of all materials like
cement, sand, water proofing compound, water etc., to site,
including seignorge charges,sales & other taxes on all
materials and operational, incidental, and labour charges for
mixing mortar, laying, lift charges, rendering smooth and
thread lining, curing including rounding off junctions of wall and
slab etc., and overheads & contractors profit complete all
taxes except GST for finished item of work. (APSS No. 901 &
903).
10 Ornamental ceiling plastering 12mm thick single coat in CM 25.00 Sqm 161.54
(1:5) using screened sand including cost and conveyance of
all materials like cement, sand, water etc., to site, including
sales & other taxes on all materials, and all operational,
incidental charges on materials and including all taxes except
GST, cost of all labour charges for mixing mortar, finishing,
curing as directed by Engineer-in-charge etc., and overheads
& contractors profit complete for finished item of work.(SS
901,903 & 904)
11 Plastering 12mm thick in two coats using screened sand with 65.00 Sqm 404.24
base coat of 8mm thick in CM (1:6) and top coat of 4mm thick
in CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to
site, including seigniorge charges,sales & other taxes except
GST on all materials, and all operational & incidental charges
including cost and conveyance of all materials to site, all
labour charges for mixing mortar, finishing, scaffolding, lift
charges, curing, including cutting grooves as directed by
Engineer - in - charge etc., complete, including overheads &
contractors profit for finished item of work. (SS 901,903 &
904)
12 Plastering 20mm thick in two coats using screened sand with 108.00 Sqm 421.70
base coat of 16mm thick in CM(1:6) and top coat of 4mm thick
in CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to
site, including seigniorge charges,sales & all other taxes
except GST on all materials, and all operational, incidental
charges including cost and conveyance of all materials to site,
all labour charges for mixing mortar, finishing, scaffolding, lift
charges, curing, including cutting grooves as directed by
Engineer-in-charge etc., and overheads & contractors profit
complete for finished item of work .(SS 901,903 & 904)
External faces of Walls
10 Supply & fixing of Rolling shutter made of 80 x 1.25 mm 5.00 SQM 4017.43
machine rolled CRCA laths, interlocked together through their
entire length and jointed together at the ends by end-locks,
mounted on specially designed pipe shaft of 50mm dia
nominal bore MS B class pipe with brackets, plates, guide
channels, stoppers, bottom locking plates and arrangements
for inside & outside locking with push-pull operations including
cost of hood cover and springs complete, painted with one
coat of approved steel primer, locks, ball bearings, all
accessories etc., overheads & contractors profit complete for
finished item of work as per special spn: 1108
11 Painting two coats with synthetic enamel paint Grade-II VOC 15.00 SQM 159.78
(Volatile Organic Compound) content less than 50 grams/litre
over primer coat of red oxide to new iron work including cost
and conveyance of all materials to site, sales & other taxes,
incidental, operational and all labour charges etc., and
overheads & contractors profit ,all taxes except GST complete
for finished item of work in all floors. (SS No. 1201, 1212 &
1207).
12 White washing two coats with white cement to ceiling, 198.00 SQM 20.39
internal and external walls to give an even shade after
thouroughly brushing the surface to remove all dirt and
remains of loose powdered materials including cost of all
materials , labour charges and incidental such as scaffolding ,
lift charges, all taxes except GST on materials and overheads
& contractors profit etc., complete for finished item of work in
all floors.
12 Plain Cement Concrete (1:3:6) nominal mix using 20mm size 2.00 Cum 4897.33
graded machine crushed hard granite metal (coarse aggregate
- as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and conveyance of all
materials like cement, fine aggregate(sand), coarse aggregate,
water etc. to site, including seigniorge charges,sales & all
other taxes except GST on all materials including all labour
and machinery charges such as mixing, laying concrete in
position, curing ,vibrating, all lift charges etc.,, and overheads
& contractors profit for Bed Blocks & Hold Fasts for finished
item of work. (APSS No. 402).
1267
Amount
60237.0
38936.0
226309.0
21092.0
31530.0
1392235.0
18493.0
53351.0
65234.0
52368.0
19309.0
4039.0
26276.0
45544.0
20087.0
2397.0
4037.0
9795.0
3016671.0
Staircase
Flights 2 1.500 0.75 2.25
Mid landing 1 1.500 1.00 1.50
44.970
SAY 45.000 Sqm
e Columns
f Roof beams
Pump Room & Panel Room- long beams
2 8.200 0.23 0.300 1.132
Ded for col -6 0.230 0.23 0.300 -0.095
Pump Room & Panel Room- short beams
3 3.000 0.23 0.300 0.621
1.657
SAY 1.700 cum
g 125mm thick Roof Slab
above Pump Room 1 8.200 3.60 29.52
Platform before Treated water to Rube 1 7.814 1.20 9.38
settler (as per Arch Drg)
Tube settler 1 3.000 0.425 1.28
40.172
SAY 41.000 Sqm
a Bottom
Treated water Tank 1 2.65 3.00 7.95
Filter Feed 1 1.80 1.20 2.16
Filter Feed 1 1.80 1.50 2.70
Tube settler 1 2.000 3.00 6.00
M.B.B.R -1 & 2 2 2.500 3.00 15.00
Equalisation Tanks 1 2.000 3.00 6.00
Bar screen 1 0.750 0.70 0.53
b Internal walls
Treated water Tank 1 11.300 4.200 47.46
Filter Feed 1 6.600 4.350 28.71
Filter Feed 1 6.000 4.350 26.10
Tube settler 1 10.000 4.350 43.50
M.B.B.R -1 & 2 2 11.000 4.200 92.40
Equalisation Tanks 1 10.000 4.200 42.00
Bar screen 1 2.900 2.050 5.95
326.45
SAY 327.000 SQM
6 Impervious coat Plastering 20mm thick
over roof slab with CM(1:4) prop.
8 Ceiling plaster
Pump Room 1 7.740 3.140 24.304
SAY 25.000 SQM
9 Internal Plastering
Alround Pump Room 1.00 21.760 3.175 69.09
Deductions
R/S -1.00 2.000 2.400 -4.80
64.288
SAY 65.000 SQM
10 External Plastering
Alround Pump Room 1.00 24.200 3.300 79.86
Alround the STP 1.00 38.300 0.850 32.56
Deductions
R/S -1.00 2.000 2.400 -4.80
107.615
SAY 108.000 SQM
11 RCM Facia
Staircase Flights 2 1.500 0.900 2.70
1 3.500 0.900 3.15
Tube settler 1 3.000 0.150 0.45
Platform before Treated water to Rube 1 7.814 7.03
settler (as per Arch Drg) 0.900
13.33
SAY 14.000 Sqm
12 Rolling shutter
1 2.000 2.400 4.80
4.80
SAY 5.000 Sqm
13 Painting to iron work
3.00 1 2.000 2.400 14.40
14.40
SAY 15.000 Sqm
14 White cement paint
Qty same as external plastering 108.000
Qty same as internal plastering 65.000
Qty same as ceiling plastering 25.000
198.000 Sqm
14 PCC(1:3:6)
Staircase steps 1 6 0.750 0.15 0.300 0.10125 cum
M.B.B.R- 1 &2 24 0.150 0.15 0.200 0.108 cum
Tube settler 1 0.600 0.60 0.400 0.144 cum
Tube settler 1 1.300 1.800 0.600 1.404 cum
1.75725 cum
Say 2.000 cum