Cladding
NO INSULATION
Line replacement
Classification: Internal Use #
06/14/2019
1.Localized insulation cladding and rust bleeding/stains
was observed throught the entire line.
2.CUI was observed on insulation removal areas.
06/18/19
06/18/2019
1.Line was not insulated .Localized surface rust and scales
was observed over the entire line where coating has
failed.
2. UT thickness measurement was carried out and
revealed no significant thickness reduction.
(LOCATION : top platform of TE-1403A)
06/19/2019
1.Minor CUI was observed throughout the insulation
removal areas ,most of the coating on these locations has
failed.
2.Gland leak was observed on valve (FV4101) and
insulation termination points on these locations are
unproperly sealed which is susceptible for ingress of
moisture.
3.UT thickness measurement revealed without significant
thickness reduction.
(LOCATION : CONNECTED to Z-0175 condensate pot)
Classification: Internal Use #
6/18/2019
1.CUI in the form of loose flaky scales was observed throughout
the insulation removal areas.
Contact point corossion at the crevice between the pipe and
hanger support was also evident.
2.UT thickness measurement was carried out and revealed an
actual min. thick of 2.5mm against the nominal thikness of
2.9mm, with CA of 1.2mm.
(LOCATION : near TE-1201S)
06/14/2019
1.Insulation was found with isolated cladding damage and
rust bleeding/stains.
06/17/2019
2.CUI was observed throughout the insulation removal
areas and entire coating on these locations has failed which
corossion and scales are evident.
3.UT thickness measurement revealed an actual min. thick
of 2.2mm against the nominal thick of 2.9mm .Thickness
reduction are located on the pipe bends.
(LOCATION : TE-1205A Connected to Z-0173)
Classification: Internal Use #
06/14/2019
1.100 % insulation removal to extend visual and thickness survey.