REINFORCEMENT STEEL RECONCILIATION

RECONCILIATION STATEMENT AS ON Dt :…………….. -

SL NO. PARTICULAR QTY UNIT

1 Total steel received @ Project Site as on Date 640.00 MT

2 Stock at Project Site as per Stores Stock Statement 40.00 MT

3 Total actual consumption (1-2) 600.00 MT

4 Stock at Project Site with sub contractor 15.00 MT

5 Transfer to other Project Sites 0.00 MT

6 Issued on chargable basis 0.00 MT

7 Net actual consumption (3-4-5-6) 585.00 MT

8 Invoiced & Certified Quantity by Client 250.00 MT

9 Invoiced but Not Certified Quantity by Client 300.00 MT

10 Work In Progress (Not Invoiced but Executed at Site) 45.00 MT


Total Quantity executed as on Dt. as per drawing (Theoretical
11 595.00 MT
consumption) (8+9+10)
12 Gross Wastage / Savings quantity (11-7) 10.00 MT

13 Wastage / Savings % (12/11) 1.68%

14 Average Rate in Rs 0.00

15 Wastage/Profit amount in Rs 0

NOTE: This format can be used seperately for different sizes of Steel & for Structural Steel as well.