Professional Documents
Culture Documents
Constructio and QC in Rigid Pavements As Per IRC 15 and 58 201 PDF
Constructio and QC in Rigid Pavements As Per IRC 15 and 58 201 PDF
,
Retired R&B Chief Engineer
E-mail: bhavannarao@yahoo.co.in
Phone: +919494440202
Asphalt Section
Concrete Section
Asphalt Layer
Subbase Base
Subgrade Subbase
Subgrade
Asphalt Layer
pressure
2.0 MPa
Percent passing
IS Sieve
Designation Grading Grading Grading Grading
Zone-I Zone-II Zone-III Zone-IV
10mm 100 100 100 100
4.75mm 90 – 100 90 – 100 90 – 100 95 – 100
2.36mm 60 – 95 75 – 100 85 – 100 95 – 100
1.18mm 30 – 70 55 – 90 75 – 100 90 – 100
600microns 15 – 34 35 – 59 60 – 79 80 – 100
300microns 5 – 20 8 – 30 12 – 40 15 – 50
150microns 0 – 10 0 – 10 0 – 10 0 - 15
Zone-I sand Zone-II sand
FM=3.32 F M =3.08
Percent by Weight
IS Sieve Size
Passing the Sieve
26.5mm 100
19 mm 80-100
9.5 mm 55-75
4.75 mm 35-60
0.600mm 10-35
0.075mm 0-5
Table 3 of IRC:15-2011: Combined Gradation of Coarse and
fine aggregates for Pavement Quality Concrete
31.5mm 100
26.5mm 85-95
19 mm 68-88
9.5 mm 45-65
4.75 mm 30-55
600 micron 8-30
150 micron 5-15
75 micron 0-5
Mineral Admixtures as per IRC:15-2011
Mix design shall be done as per IRC:44-2008
Fly Ash as per IS:3812 (Part-I)-2003.
Maximum dosage 20 percent by mass of
cementitious materials.
Granulated blast furnace slag as per
IS:12089. (up to 50% as per IS 455 ). Good in
coastal region.
Silica Fume as per IS:15355 and IS:456, IRC
:SP:70, up to 10%. Use of silica fume is
generally advantageous for higher grades
of concrete i.e. M50 and above.
Fibers
Fibers may be used subject to the
provision in the design/approval by the
engineer to reduce shrinkage cracking and
post cracking. The fibers may be steel fibers
as per IRC:SP:46 or polymeric synthetic
fibers.
When fibers are used the mix shall be so
designed that the slump of concrete at paving
shall be in the range of 25±10mm and that in
manual construction the slump shall be in the
range of 40±10mm
Water for mixing and curing as per
IS:456
Potable water is generally considered
satisfactory for both mixing and curing.
In case of doubt, 28 days average
compressive strength of at least three 150mm
cubes prepared with water proposed to be used
shall not be less than 90% of the average
strength of 3 similar cubes prepared with
distilled water.
Initial setting time of test block made with
water proposed to be used shall not be less than
30 minutes and shall not differ by ± 30 minutes
from the initial setting time of test block
prepared with distilled water.
Permissible limits for solids in Water
Cl. 5.4 of IS: 456-2000
Permissible limt
Tested as per
maximum
Organic IS 3025 part 18 200 mg/l
Inorganic IS 3025 part 18 3000 mg/l
Sulphate as SO3 IS 3025 part 24 400 mg/l
Air Temperature
Fresh Concrete Temperature
Relative Humidity
Wind Velocity
Methods of Curing
a)Contraction joints
b) longitudinal joints
c) Expansion joints
d) Construction joints
Requirement of good joints
Note: Dowel bars shall not be provided for slabs of less than
200mm thick. For heavy traffic, more than 450 CVPD, dowel
bars shall be provided at contraction joints also,
Mild steel dowell rods with sheathing and
caps. Groove cutting in progress
Shuttering sheets for MS dowels just removed,
Removed bulkhead is also seen.
Groove cutting machine
Mohammadalipalem road in Guntur District. Joint cutting
Mohammadalipalem road in Guntur District. Joint cutting
Mohammadalipalem road in Guntur District.
Contraction joint 3 to 5 mm wide
1/3 to 1/4 in depth
Tie rods at
longitudinal joint
Table6 of IRC:58-2011,Details of tie bars for
longitudinal joint IRC: 58-2011
Slab
Dia Max. spacing mm Max. length mm
thickness
mm Plain Plain
mm deformed deformed
bars bars
8 330 530 440 480
150
10 520 830 510 560
10 390 620 510 560
200
12 560 900 580 640
250 12 450 720 580 640
12 370 600 580 640
300
16 660 1060 720 800
12 320 510 580 640
350
16 570 910 720 800
Requirements of joint sealants
Elastic even at low temperatures
Should not flow in summer
Should not become sticky resulting in loss of
sealant
Should not undergo permanent deformation
Should have resistance to intrusion of solids
Should have high resistance to hardening with
age
Should have high bonding property with
adjoining concrete
Should not shrink after they have been poured
Types of sealants
PQC Paver
EXECUTION METHODOLOGY
Pavement Quality Concrete (PQC)
Unloading of Concrete
EXECUTION METHODOLOGY
Pavement Quality Concrete (PQC)
Band Saw for Dowel Bar Cutting & Stock of Dowel Bars
EXECUTION METHODOLOGY
Pavement Quality Concrete (PQC)
Primer Application after fixing Masking Tape & before Sealant filling
EXECUTION METHODOLOGY
Pavement Quality Concrete (PQC)
Finishing of Sealant
EXECUTION METHODOLOGY
Pavement Quality Concrete (PQC)
Longitudinal cracking
may also result from
inadequate placement
of longitudinal joints,
over-reinforcing of
longitudinal joints, or
too-shallow joint saw
cuts.
Shattered slabs are divided into three or more pieces by
intersecting cracks. These working cracks allow for
differential settlement of the slab sections at a rapid rate.
This type of distress can be attributed to numerous factors,
the most important being too-heavy loads, inadequate slab
thickness, and poor support.
Deviation in Longitudinal Joint
Damaged Edges due to early initial cut
Crack development at the location Contraction Joint
An eroded base can lead to
high tensile stresses,
resulting in cracking
Shrinkage cracking probably due to late sawing (left)
Joint raveling due to early sawing (right)
4 to 12 after compaction is good for joint cutting
Timing the Sawing Window: Joints are usually
constructed by saw-cutting the concrete a few hours
after placing. The optimum period of time to saw
contraction joints is known as the sawing window.
The sawing window for conventional saws generally
begins when concrete is strong enough not to
ravel excessively along the saw cut. The window
ends when significant shrinkage occurs that induces
uncontrolled crackin
Crack caused by late joint sawing
Crack developed on CC road laid at Annamayya
statue in Tallapaka
Misalignment of dowels
Burlap dragging
Finished PQC Surface showing Texturing
Table 600 -2, Texture requirement
The texture depth shall be measured by
Sand Patch method.
Required texture depth
Number of mm
Time of test
measurements Specified
tolerance
value
1. Between 24
hours and 7 days
after construction of
1.0 mm +0.25mm
the slab or until the
slab is first used by
users
2. Not later than 6
weeks before the An average of 5 +0.25
1.0 mm
road is opened to measurements - 0.35
public traffic
Joints sealed with hot-pour liquid sealants. Normally
these joints should coincide with lane divisions
our practice of sealing joints
Preparation for slump test, casting cubes (150 mm)
and beams(70 х 15 х 15 cm)
12.8 of IRC:15-2011 Accepting Criteria of
Strength
Flexural Strength:
Core Strength on
As per the requirement of
hardened Concrete as
Engineer or 2 cores/km
per IS:516
1 test per dumper load at both
Workability of fresh batching plant site and paving
concrete as per site initially when work starts.
IS:1199 Subsequently sampling may be
done from alternate dumper
Tests on concrete 2
From the level data of concrete
pavement surface and sub base
Thickness
at grid points of 5m×3.5m or
Determination
6.25m×3.5m. Cores may be cut
in case the Engineer desires.
Thickness measured
3 cores per trial length
for trial length
String line or steel forms shall be
Verification of level of checked for level at an interval of
string line in the case 5m or 6.25m. The level tolerance
of slip form paving allowed shall be ± 2mm. These
and steel form in case shall be got approved 1-2 hours
of fixed form paving before the commencement of
concrete activity.
Sub base for Rural Roads as per IRC:SP:62-
2004
IRC:SP:76-2008: Tentative
Guidelines for Conventional, Thin
and Ultra-Thin White Topping
Types of White-topping
Used on
200mm or
Conventional Heavily Trafficked
more
Corridors
More than
100mm and Used for
Thin
less than Collector Streets
200 mm
Used for
Up to 100
Ultra Thin Collector And Local
mm
Streets
Thin White-topping
Thickness 100-200 mm
Mumbai
Pune
Nasik
Nagpur
Aligarh
Wazirabad Bridge Approaches
A View of Ultra-Thin White Topping in Pune
A View of Ultra-Thin White Topping in Mumbai
Mumbai City Road
Mumbai City Road
Mumbai City Road
Mumbai City Road