Professional Documents
Culture Documents
EXECUTIVE ENGINEER
TYPICAL CROSS-SECTION OF A FLEXIBLE
PAVEMENT
SECTION-1
Embankment/Sub-grade Construction
The construction of embankments including Sub-grades, earthen
shoulders etc. is governed by Clause 305 of MORT & H
Specification for Roads & Bridge Works (5th revision).
A) Physical Requirements of Materials:
The materials used for construction of embankments/sub-grades/
earthen shoulders/Backfills shall be soil/earth, moorum, fly ash or a
mixture of these or any other materials as approved by the Engineer.
The following types of materials shall be considered unsuitable:-
Materials from swamps, marshes etc.
Clay having Liquid Limit (LL) > 50 and Plasticity Index(PI) > 25.
Expansive Clay exhibiting marked swell & shrinkage properties with
Free Swelling Index > 50.
B) Other Requirements:
(i) The size of the coarse materials/particle in the earth shall
ordinarily not exceed 75mm, when placed in the embankment and
50mm, when placed in the sub-grade.
(ii) Ordinarily, only the materials satisfying the density requirements
given in Table 300-1 of MORT&H spec., 5th Revn shall be used for the
construction of the embankment/sub-grade/shoulders etc.
TABLE 300-1: Density Requirements of Embankment & Sub-
grade Materials
Type of Work Max. dry density (MDD) when tested
in lab as per IS: 2720 (Part-8)
Embankments up to 3m height, not Not less than 1.52gm/cc or
subjected to extensive flooding. 15.2 KN/cum
Embankments exceeding 3m height or Not less than 1.60gm/cc or
embankments of any height subject to 16.0KN/ cum
long periods of inundation.
Sub-grade/Earthen Shoulders/ Not less than 1.75gm/cc or 17.5KN/cum
Backfill
NOTE: 1) The above table is not applicable for lightweight fill materials. e.g.
Fly-ash, etc.
2) The material to be used in Sub- grade shall be non-expansive and
shall satisfy the design CBR.
iii) It shall be ensured prior to actual execution that the
material to be used in the Sub-grade satisfies the
requirements of design CBR.
Test Frequency(Minimum)
Gradation 1 test per 400 cum.
Atterberg Limits 1 test per 400 cum.
Moisture content prior to compaction 1 test per 400 cum.
Density of compacted Layer 1 test per 1000 sqm.
SECTION-3
CONSTRUCTION OF BASE (NON-BITUMINOUS)
1) WATER BOUND MACADAM(WBM) (Popularly known as
Metalling)
i) The construction of WBM is governed by Clause 404 of
MORT&H Specification, 5th Revision & consists of crushed/
broken aggregates (popularly known as ‘Metals’), mechanically
interlocked by rolling and bonding together with stone screening,
binding materials (wherever necessary) and water, laid on a
properly prepared Sub-grade/Sub-base/ base or existing pavement
as the case may be.
NOTE: - If the water absorption value is greater than 2%, Soundness test
shall be done as per IS: 2386 (Part-5).
Grading Requirements of Coarse Aggregates for WBM (Table 400-9)
Grading No. Size Range IS Sieve Cum %age passing
1 63 to 45mm 75mm 100
63mm 90-100
53mm 25-75
45mm 0-15
22.4mm 0-5
2 53 to 22.4mm 63mm 100
53mm 95-100
45mm 65-90
22.4mm 0-10
11.2mm 0-5
%age voids in Mineral Aggregates 12% for DBM Gr-II 12% for DBM Gr-II
(VMA) & &
11% FOR DBM Gr-I 11% for DBM Gr-I
Before execution of the DBM work, mix-design is to be done at
laboratory and a Job-Mix Formula (JMF) is to be found out/
proposed for use in the works. The JMF should be based on a correct
and truly representative sample of materials that will actually be used
in the work. The work should be executed strictly as per the laboratory
JMF.
Whenever there is a change in source of materials to be proposed, a
new JMF shall be worked out at Lab through a revised mix-design.
Once the Lab JMF is approved, plant trials should be done at HMP site
so as to ensure that the plant can produce a uniform mix conforming to
the approved JMF with the permissible variations as per Table 500-13.
The temperatures to be maintained in bitumen, aggregates, mix and
the laying and compacting temperature etc. are same as in case of BM
and to be strictly ensured during execution of the DBM work.
Rolling shall continue until the desired density i.e. 92% of GMM
(Approximately 95-96% of Lab Density) is achieved at field. It is to
be checked by taking 150mm size cores from the compacted layer of
DBM through core cutter machine.
Rolling must be completed before the mat cools down to 900 C.
Routine Quality Control Tests for DBM during execution
Test Frequency (Minimum)
Grading/Sieve Analysis 1 set for individual constituents & mixed
And aggregate from dryer for each 400 tons of
Bitumen Content DBM mix subject to minimum of 2 tests
per day per plant.
AIV and FI & EI etc. 1 test per 350 cum of aggregates for each
source & whenever there is change in
source/ quality of aggregates.
Stability and voids analysis 3 tests for stability/ flow value, density
and air voids etc. for each 400 tons of mix
subject to minimum of 2 tests per day per
plant.
Temperature of DBM mix at the time of
laying & compacting & also in HMP. At regular intervals.
• In case it is found that there is appreciable variation in gradation & other properties
of aggregates being used from those tested during mix design at lab, the JMF is
suitably revised & a fresh mix design is done at lab and then the work is executed as
per the revised JMF.
• The detailed procedure of construction of DBM is given in Clause 505 of MORT&H
Specification, 5th Revision.
SECTION-5
CONSTRUCTION OF BITUMINOUS WEARING COURSE
The frequently used bituminous wearing courses are Semi- Dense
Bituminous Concrete (SDBC), Bituminous Concrete (BC), Open
graded premium surfacing [popularly known as Pre Mix Carpet
(PMC)] along with seal coat (SC), close - graded Premix Surfacing
[Mixed Seal Surfacing (MSS)].
1) Semi- Dense Bituminous Concrete (SDBC)
The construction of SDBC is governed by Clause 508 of MORT&H
Specification for Roads & Bridges, 4th Revision and IRC: 111-
2009.
SDBC is laid in single layer of 25mm to 40mm.
It generally consists of a mixture of crushed aggregates of various
sizes & bitumen, premixed in a Hot- Mix Plant (HMP) & laid with a
paver machine.
Materials for SDBC
Coarse aggregates, Fine aggregates, filler, etc.
Physical properties of Coarse Aggregates for SDBC are same as
that in case of DBM, except additional requirement of Polished
Stone Value, which should be minimum 55%.
Aggregate grading and binder Content for SDBC
(Table: 500-15 of MORT&H Specification, 4th Revision)
Grading Gr-I Gr-II
Nominal Max Aggregate 13.2mm 9.5mm
Size
Layer Thickness 40mm 25mm
IS Sieve Cum %age passing Cum %age passing
19.0mm 100 -
13.2mm 90-100 100
9.5mm 70-90 90-100
4.75mm 35-51 35-51
2.36mm 24-39 24-39
1.18mm 15-30 15-30
3oo mic 9-19 9-19
75 mic 3-8 3-8
Bitumen Content Minimum 4.5% Minimum 5%
Mix Requirements of SDBC
Same as that in case of DBM except the VMA which is 14% for SDBC Gr- I & 15%
for SDBC Gr-II.
Before execution of the SDBC works, mix design is to be done at lab and a Job-
Mix Formula (JMF) is to be found out/proposed for use in the works. The JMF
should be based on a correct and truly representative sample of materials that
will actually be used in the work. The work should be executed strictly as per
the lab JMF.
Whenever there is a change in source of materials, a new JMF shall be worked
out at lab through a revised Mix Design.
Once the lab JMF is approved, plant trials should be done at HMP site so as to
ensure that the plant can produce a uniform mix conforming to the approved
JMF with the permissible variation as per Table 500-13 of MORT&H
Specification, 4th Revision.
The temperature and compaction requirements are the same as in case of
DBM.
The routine quality control tests for SDBC to be done at field lab during
execution of the work are almost the same as in case of DBM.
In case, it is found that there is appreciable variation in gradation & other
properties of aggregates being used from those tested during mix design at lab,
the JMF is suitably revised & a fresh mix design is done at lab and then the
work is executed as per the revised JMF.
The detailed procedure of construction of SDBC is given in Clause 508 of
MORT&H Specification, 4th Revision.
2) Bituminous Concrete (BC)
The construction of BC is governed by Clause 507 of
MORT&H Specification of Roads & Bridges, 5th Revision.
BC is laid in single layer of 30mm / 40mm/ 50mm.
It generally consists of a mixture of crushed aggregate of
various sizes and bitumen, premixed in a HMP and laid
with a paver machine.
Materials for BC
Bitumen, Coarse aggregates, Fine aggregates, filler, etc. as
in case of DBM / SDBC.
The physical properties of Coarse Aggregates for BC
are same as in that in case of SDBC, except the LA & AIV
requirement. The maximum LA & AIV in case of BC is 30%
& 24% respectively.
Aggregate grading and Binder Content for BC (Table 500-17)
Grading 1 2
Nominal Max Aggregate Size 19mm 13.2mm
Layer Thickness 50mm 30-40mm
IS Sieve Cum %age passing Cum %age passing
26.5mm 100 -
19.0mm 90-100 100
13.2mm 59-79 90-100
9.5mm 52-72 70-88
4.75mm 35-55 53-71
2.36mm 28-44 42-58
1.18mm 20-34 34-48
6oo mic 15-27 26-38
300 mic 10-20 18-28
150 mic 5-13 12-20
75 mic 2-8 4-10
Bitumen Content Minimum 5.2% Minimum 5.4%
The mix requirements of BC such as stability, flow, air voids, etc.
are same as that in case of DBM/ SDBC except the VMA, which is
13% for BC Grade-I
The other requirements such as temperature, compaction &
routine quality control tests, etc. are almost same as in case of
DBM/SDBC.
Before execution of the BC works, mix design is to be done at
lab and a Job- Mix Formula (JMF) is to be found out for use in
the works. The JMF should be based on a correct and truly
representative sample of materials that will actually be used in
the work. The work should be executed strictly as per the lab
JMF.
Whenever there is a change in source of materials, a new JMF
shall be worked out at lab through a revised Mix Design.
Once the lab JMF is approved, plant trials should be done at
HMP site so as to ensure that the plant can produce a uniform
mix conforming to the approved JMF with the permissible
variation as per Table 500-13 of MORT&H Specification, 5th
Revision.
OPEN- GRADED PREMIX SURFACING (Popularly known as PMC)
It is an open-graded mix of 20mm thickness, composed of stone
aggregates of nominal size 13.2mm(passing 22.4mm and retained
on 11.2mm sieve) (67%) and 11.2mm (passing 13.2mm and retained
on 5.6mm sieve) (33%), premixed with bitumen (@1.46Kg/m2) and
prepared in a hot mix plant (HMP) and laid over a prepared base.
The construction of PMC is governed by Clause- 510 of MORT&H
Specification, 5th Revision.
The physical requirements of Aggregates are same as that in case of
BM except that the water absorption value shall not be more than
1% and stone polished value shall not be less than 55.
If the loose density/ specific gravity of the above 2 aggregates i.e.
13.2 and 11.2mm are almost same, then the above proportions of
67% and 33% by volume can also be taken as same proportion by
weight also. In that case, one tentative combined grading limits of
PMC mix has been developed empirically in lab, which is given in
the next slide:
IS Sieve Cum %age passing by weight of total
aggregates
22.4mm 100
11.2mm 25-35
5.6mm 0
• Routine Quality Control Tests to be done are same as in case of PMC work.
• Traffic may be allowed after completion of the final rolling when the mix has
cooled down to the surrounding temperature.
THANK YOU