Professional Documents
Culture Documents
2 1 CPRS DRS CGS Steel Pipeline PDF
2 1 CPRS DRS CGS Steel Pipeline PDF
Filteration
Pressure Reduction
Custody Transfer metering
Odorization
Preheating of NG if required
CGS – Design Criteria
• Upstream Pressure
• Downstream pressure requirement
• Downstream flow requirements including peak flow rates
• Future projections of volume growth / flow-rate
• Future expansion
• Consider safety at all stages
• Reference Standards : IGE/TD/13
Major Elements of CGS
• Suitable Land
• Below facilities with a hot stand by mode :
– Filtration (Knockout drum, Filter Cum Separator)
– Let Down Skid (PCV or PRV, SSV, CRV/SRV, Pressure Gauges)
– Metering (Turbine / Ultrasonic / Orifice)
– Odorization
• Pre-heating
• Ball Valves
• Station Piping & Supports
• Electrical Work
• Instrumentation work (SCADA / Control Panels)
Typical City Gate Station
Typical City Gate Station
Pipeline
• Type of Pipelines:
– Steel Pipeline
PNGRB T4S Technical Standards and Specifications including Safety Standards - CGD
ASME B 31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and other Liquids
OISD-226 Natural Gas Transmission Pipelines and City Gas Distribution Networks
Other References Applicable Standards / Specs of ASME, API, NACE, MSS, BS and DIN
Stages of Steel Pipeline Project
• Conceptualization
– Market surveys for deriving basic assumptions on demand
– Study Alternatives
– Initiation of Feasibility Study for Commercial / Technical viability
• Feasibility Report
– Route Selection & Surveys
– Hydraulics / Simulations
– Estimation of Project Cost
– Market Demand Assessment
– Project Approval
• Engineering & Planning
– Design & Sizing
– Specifications & Tender Document preparation
– Material Procurement / Release of Word Orders & Contracts
– Acquire RoU / Permissions
– Project Execution & Commissioning
• Operation & Maintenance
– As per AOMP
Route Selection / Surveys
• Type of Surveys
– Topographical
– Geo-Technical
– Population Density Index (Location Class)
– Soil Resistivity
– Cadastral
Design / Hydraulics / Simulation
• Process
– Simulation for Network Hydraulics is done in the SYNERGEE software
– This is basically required to derive diameter of pipeline in such a way that
required pressure at all locations can be achieved and future load
projections can be ascertained
– Formulae used for hydraulics : Colebrook White / Fundamental pipe
equation with flow dependent friction factor
– Roughness:
• Process
– Efficiency factor: 0.85 – 1, factor shall be determined by duly
calibrating actual field data in the approved flow equation
– Velocity: Max. allowable velocity of the gas in the steel pipeline
section of CGD network shall be 30 m/s
– STP:
• Standard pressure : 1.01325 Bar (a)
• Standard Temperature : 15.5 Deg C
– Design Life:
• Steel pipeline : 30 Years
• PE Pipeline : 50 Years
Design / Hydraulics / Simulation
• Location Class:
Class I 10 or fewer buildings in 1mile section
Class II 10 – 46 buildings
Class III 46 or more buildings
Class IV areas where multistoried buildings and heavy
underground utilities
• Location Class:
Class I 10 or fewer buildings in 1mile section
Class II 10 – 46 buildings
Class III 46 or more buildings
Class IV areas where multistoried buildings and heavy underground
utilities
• Wall Thickness calculation for steel pipeline
P = 2St FET
D
where
P Design pressure
S Specified minimum yield strength
D Nominal OD of pipe
t Nominal wall thickness
F Design factor
E Longitudinal joint factor
T Temperature de-rating factor
Line Pipes – Selection / Specifications
• Type
– ERW
– Seamless
– LSAW
– HSAW
• Material Grade
• Nominal Diameter and Wall Thickness
• Length (single random / double random)
Coating
• Fittings:
– Elbows & Bends
– Flow Tees
ASTM A 234
– Insulating Joints ANSI B 16.5 & 16.11
– Weldolet / Sockolet
– Flanges
– Gaskets
– Fasteners
• Valves:
– Sectional Valves
– Tap Off Valves (future API 6D
provisions)
Construction Stages
• Pre-constructional Activities
• Construction Activities
• Handover to Operations
Construction Stages
• Pre-constructional Activities
Activity Description / Steps
• Construction Activities
• Execution by Contractor
• Inspection & Certification for quality by TPIA
• Project Management by PMC
• Overall monitoring by GSPC Gas
Photo : Steel pipeline site
CPRS/DRS : typical schematic
Photo : DRS/CPRS
Components
Land Requirement
• 30-36 Sq. Meter
• No overhead electric lines / min. Distance 6 mtrs from HT/LT
• Land should not be in a water logged area
• Safe distance from Garbage collection/storage point
Installation & Commissioning