You are on page 1of 6

ACTIVITY PART QTY RATE

EXCAVATION F-1 8.98 m3 8


F-2 14.34 m3 8
F-3 3.07 m3 8
F-4 2.57 m3 8
Tie Beams 4.77 m3 8
Wall Footings 9.06 m3 8

REBAR FABRICATION F-1 132.58 kg


F-2 227.28 kg
F-3 56.82 kg
F-4 37.88 kg
Tie Beams kg
Wall Footings kg
C-1 kg
C-2 kg
C-3 kg
C-4 kg
Slab On Grade kg
Stairs (SKIP THIS MUNA)
RC Wall

REBAR INSTALLATION F-1 kg


F-2 kg
F-3 kg
F-4 kg
Tie Beams kg
Wall Footings kg
C-1 kg
C-2 kg
C-3 kg
C-4 kg
Slab On Grade kg
Stairs (SKIP THIS MUNA) kg
RC Wall kg

CONCRETING F-1 m3
F-2 m3
F-3 m3
F-4 m3
Tie Beams m3
Wall Footings m3
C-1 (Below NGL to Ground Floor) m3
C-2 (Below NGL to Ground Floor) m3
C-3 (Below NGL to Ground Floor) m3
C-4 (Below NGL to Ground Floor) m3
Slab on Grade m3
C-1 (Ground Floor to Mezzanine) m3
C-2 (Ground Floor to Mezzanine) m3
C-3 (Ground Floor to Mezzanine) m3
C-4 (Ground Floor to Mezzanine) m3
Mezzanine Beams m3
Mezzanine Slab m3
C-1 (Mezzanine to 2nd floor) m3
C-2 (Mezzanine to 2nd floor) m3
C-3 (Mezzanine to 2nd floor) m3
C-4 (Mezzanine to 2nd floor) m3
2nd floor Beams m3
2nd floor Slab m3
C-1 (2nd floor to Roof Level) m3
C-2 (2nd floor to Roof Level) m3
C-3 (2nd floor to Roof Level) m3
C-4 (2nd floor to Roof Level) m3
Roof Slab (slab for water tank) m3
Roof Beams m3
Firewall Beams m3
Stairs (SKIP THIS MUNA) m3
RC Wall m3

FORMWORKS Tie Beams m2


C-1 (Below NGL to Ground Floor) m2
C-2 (Below NGL to Ground Floor) m2
C-3 (Below NGL to Ground Floor) m2
C-4 (Below NGL to Ground Floor) m2
Slab on Grade m2
C-1 (Ground Floor to Mezzanine) m2
C-2 (Ground Floor to Mezzanine) m2
C-3 (Ground Floor to Mezzanine) m2
C-4 (Ground Floor to Mezzanine) m2
Mezzanine Beams m2
Mezzanine Slab m2
C-1 (Mezzanine to 2nd floor) m2
C-2 (Mezzanine to 2nd floor) m2
C-3 (Mezzanine to 2nd floor) m2
C-4 (Mezzanine to 2nd floor) m2
2nd floor Beams m2
2nd floor Slab m2
C-1 (2nd floor to Roof Level) m2
C-2 (2nd floor to Roof Level) m2
C-3 (2nd floor to Roof Level) m2
C-4 (2nd floor to Roof Level) m2
Roof Slab (slab for water tank) m2
Roof Beams m2
Firewall Beams m2
Stairs (SKIP THIS MUNA) m2
RC Wall m2
RATE DURATION
mhr/m3 71.84 manhr
mhr/m3 114.72 manhr
mhr/m3 24.56 manhr
mhr/m3 20.56 manhr
38.16 manhr
72.48 manhr

manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr

manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr

manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr

manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr
manhr

You might also like