1 BANGUNAN PENGELAK LAU SIMEME

TIPE A : 100 m TIPE B : 200 m TIPE A : 140 m TIPE B : 120 m TIPE C : 160 m

ZONA 1 : 440 m ZONA 2 : 280m

Keterangan : 100 240 100 120 160


1. Tipe A Medium Rock 440 280
2. Tipe B Soft Rock
3. Tipe C Medium - Soft Rock

a. Diameter 8.8 m
b. Luas Area 69.1152 m2
c. Shotcrete t = 15 cm 22.616 m2
d. Wiremesh 22.616 m2
e. Steel Rib
- Jenis H125 @ 3 m
- Panjang 22.616 m
f. Rock Bolt
- Jenis L= 4,@2m
- Nos/penampang 9 Nos

* Tebal shotcrete pada gambar 15 cm, pada BoQ 10 cm

TUNNEL EXCAVATION WITH DRILLING BLASTING METHOD - CYCLE TIME

D:\Doni\D\teknik sipil\PBKL\BENDUNGAN LAUSIMEME\DATA


Page 1 LAUSIMEME\DOKUMEN TEKNIS LAU SIMEME PAKET 2\DOKUMEN TEKNIS LAU SIMEME PAKET 2\171102 (BS) TUNNEL Excavation Cycle Time Drill Blasting (1).xlsx
10/17/20188:25 PM

Description unit Medium Rock Soft Rock

Excavation Data
- Diameter m 8.80 'D' - Shape 8.80 'D' - Shape
- Face Area m2 69.12 69.12
- Drilling Holes bh 164 226 Add Periphere
- Drilling Depth m 1.50 1.20
- Advance Excavation m 1.50 1.20
- Mucking Vol m3 134.77 107.82
- Working Time hr 24.00 3.00 3 Shift 24.00 3.00 Shift
- Main Equipment ns 1.00 2.00 2B Jumbo Driller 3.00 3.00 Leg Drills
- Dynamite kg/m3 2.00 Soft-Medium Rock 1.30 Soft Rock
2 2
- Shotcrete m2 22.62 0.10 m thickness 22.62 0.10 m thickness
2 2
- Wire Mesh m2 22.62 4 x 10 x 10 m 22.62 4 x 10 x 10 m
- Steel Ribs @ 1.0m Ns 1.00 538.26 Kg/set (H125=23.8Kg/m) 1.00 538.26 Kg/set (H125=23.8Kg/m)
- Rock Bolts @ 4.0m Ns 6.00 6.00
- Oprating Factor # 0.85 0.75

Cycle Time - Excavation


- Survey & Marking mnt 15.00 20.00
- Jumbo In mnt 15.00 20.00
- Drilling mnt 208.57 0.90 m'/mnt Drill speed 271.71 1.50 m'/mnt Drill speed
- Charging mnt 49.08 0.30 mnt/hole 113.21 0.50 mnt/hole
- Jumbo Out mnt 15.00 15.00
- Blasting & Fume out mnt 20.00 20.00
- Mucking mnt 120.00 DT + Schaff/SideD.Loader 150.00 distance to dispossal ?

Supports:
- Shotcrete mnt 30.00 2 x 5cm 50.00 2 x 5cm
2 2
- Wire Mesh mnt 20.00 4 x 10 x 10 m 30.00 4 x 10 x 10 m
- Rock Bolt mnt 30.00 dia 22mm 60.00 dia 22mm
- Steel Ribs mnt 120.00 150.00 Steel Ribs I-300
Services (Utility) mnt 30.00 blower, drainage, utility 40.00 drainage
Others mnt 30.00 60.00

Total Cycle Time mnt 702.65 999.92

Number of Blasting / Day # 1.74 1.08

Production / day m 2.61 1.30