Professional Documents
Culture Documents
Customer
Kay Jay Forging Ltd.
SH 5228 (N3020120)
Output Sheet Of PPAP
Part/Size: SH 5228 (WALUJ) Date: 25.05.17
Document/ Rev status
Sr.
Requirement Document Remark
No.
References
Design Records of saleable
1 SH 5228 NA
products
Engineering change
2 Not Applicable NA
documents,if any
CustomerEngineering
3 Not Applicable NA
Approval,if req..
4 Design FMEA Not Applicable NA
6
5 Process Flow Diagrams W/PF/26/01 Attached
25.03.16
65
6 Process FMEA N/FM/26/74 QC
10.05.17
7 Dimensional Results Attached Attached
Material performance test
8 Attached Attached
results
9 Initial process study Attached Attached
Measurement System
10 Attached Attached
Analysis studies
Qualified Laboratory
11 Lab Manual QC
Documentation
4
12 Control Plan W/CP/26/55 Attached
12.11.2016
13 Part Submission Warrant Attached Attached
Appearance Approval
14 Not Applicable NA
Report if applicable
Bulk material requirements
15 Not Applicable NA
checklist (for bulk material
PPAP only)
16 Sample Product Not Applicable NA
Stored at NRB
17 Master sample QC
Waluj
18 Checking Aids Attached Attached
Records of compliance
19 Not Applicable NA
with customer specific
requirements
S :The supplier shall submit to designated customer products approval activity and retain a copy of records or documentation items
at appropriate locations,including manufacturing.
R :The supplier shall retain at appropriate locations,including manufacturing and readily available to the customer representative
upon request.
. :The supplier shall retain at appropriate locations and submit to the customer upon request.
Authorized Signatory
Name K.S.Deore
Designation Manager QA
Page 3 of 21
Process Flow
Part Name:Crank Pin Process Responsibility : Crank Process Identification :W/PF/26/01 Rev. No.:- 6
Part family : SH5228 Pin Date ( Original ) : 28.01.2007 Date (Revised): 25.03.16
Customer part no: N3020120
Vendor)
120 Prefinal OD grinding OD oversize from Rough Grd 1) Outer Dimeter Size
4) Ovality
5) Taper
123
Cross hole chamfer buffing 1) Removed sharp edges
Raw material Crack 1) Machine should detect Crack (BP) Man - skilled operator
200 Heavy dirt on component 1) Free from dirt Man - skilled operator (1)
2.Dirt Content below Specified limit. For Limit Size wise Machine- Freq. Of Ultrasonic generator
refer spec sheet (1),
Ultrasonic Cleanning Method : filters (1),clean MTO (1), cycle
time as per spec(1),
4) Counter ID undersize
Angular relations are not ok 1) Relation of cross hole w.r.t. inclined should be ok(BP)
2) Depth of Inclined Hole 3) Depth of cross Hole Man - skilled operator (1,2,3)
from drilling operations
220
Method - Size of gauging pins (1,2,3)
Environment - Nil
1) Free from Grinding marks , Flat marks, rusty marks Man - skilled (1)
Dirty component 2) Free from Pitting, Free from Chamfer damage Machine- Lamp for visual inspection
Temp of component is high 1) Sorting in correct grade Man - skilled operator (1,)
Machine -
Environment -
350 Pre Dispatch Inspection As per spec Method - As per PDI plan
NA
Method: Move to FG
360 Move to stores - -
CONTROL PLAN
Control Plan No.:- W/CP/26/29 Rev. No. :-004
Prototype Prelaunch Production Key Contact / Phone :- Mr. Hemant Jog (0240) 6634501
Date ( Orig. ) :- 17.07..2013 Date ( Rev. ) :- 12.11.2016
Part Family / Drawing no. :- Crankpin-SH 5228 rev a NA3020120 (TVS) Core Team :- HJ, AAM,AKS,KSD,GKB,VDS,NBB Customer Engineering Approval Date (If Req'd) :-
Supplier Plant Approval :- Customer Quality Approval Date (If Req'd) :-
Supplier Plant :- NRB Bearings Ltd. Waluj
Other Approval Date (If Req'd) :- Other Approval Date (If Req'd) :-
Process Name Machine, Characteristics Methods
Part / Special Char.
Process Product/process Evaluation / Measurement Control Method
Operation Tools for Mfg. No. Product Process Recording Sample Frequency Responsibility Reaction Plan Corective Action
Number Class Specification/Tolerance Technique Error Proffing Detection
As per
Inward Inspection As per Inspection plan no. As per Inspection
30 material Manual 1 plan of N/OT/12/5177 T & plan Y As per Inspection plan Each Lot Inspection Report Inspector Reject
inspection Turned N/OT/12/51777 D
blanks of size
As per
Inward Inspection As per Inspection
50 material Manual 1 plan of As per Inspection plan. plan Y As per Inspection plan Each Lot Inspection Report Inspector Reject
inspection drilled blanks
of size
Inward
As per
material As per Inspection plan no. As per Inspection
55 Manual 1 Inspection Y As per Inspection plan Each Lot Inspection Report Inspector Reject
inspection N/OT/12/112 plan
plan
Plug
70 Heat Furnace As per HT control plan As per HT control As per HT control plan As per Heat treatment
1 As per HT control plan Inspector Rework/Reject
Treatment plan controlplan
3 Taper 5.0 µ Comparator LC 1.0 µ Y 5 nos. New setting/per shift First-off Operator
Rework/Reject
Reset the m/c
Y 2 nos. per hour In process Inspection Operator
4 Circularity 5.0 µ on plain OD MMQ30 Y 5 nos. New setting/per shift MMQ30 Graph Operator
New V belt
Y 5 nos. per hour In process Inspection Operator
conveyor provided
Interlinking of
New setting/per First-off
2 Ovality 3.0 µ /comparator LC 1µ Y 5 nos. Operator Prefinal & Buffing
shift Rework/Reject
Reset the m/c .
Comparator LC 1 µ Y 2 nos. per hour In process Inspection Operator
3.0 µ,
Circularity New setting/per First-off/ roundness
3 No regular waviness , chatter Roundness Tester Y 5 nos. Operator
Naer centre shift graph
form
4 Taper 2.0 µ comparator LC 1µ Y 2 nos. New setting/per First-off/ cylindricity Operator
shift graph
Free from damage, burns, dash
New setting/per First-off
5 Visual marks, deep grd marks ,surface Visual Inspection Y 5 nos. Operator
shift
crack
N 2 nos. After every 0.5 hour In process Inspection Operator
A Grinding wheel & At every wheel
As per setup chart Verify wheel sticker Y 1 Nos. First off Inspection Operator Reject the wheel
Regulating wheel change
B spec/
Reg & size (For
grd Wheel
Manual counting/signal Redress the wheel if
dressing As defined in W.I./Set up plan N ---- After defined freq. Inprocess Inspection Operator
on screen rqurired
(for 1,2,3,4)
C Tilt angle of Reg.
As per setup chart Match the marking Y One Each setting First off inspection Operator Reset the m/c
Wheel (for 1,4)
D RPM of Regulating
As per set up plan RPM indicator Y One Each setting First off inspection Operator Reset the m/c
wheel
E (for 1,2,4)
Center height
As per set up plan Vernier Height gauge Y One Each setting First off inspection Operator Reset the m/c
( for 2,4)
F Spindle runout Regualting wheel :- <15µ Adjust the play from
Dial gauge Y 1 Nos. Every wheel change Machine log book Operator
(for 2,4,5) Grinding wheel :- < 20µ maint
G Cut setting Visual & feeling( On
As per work instrucion N Every new setting Every new setting --- Operator Reset /dress the wheel
( for 3,5) slide setting dial)
H Lower track
Free from over wear Visual N One Each setting --- Operator Change the track
(for 1,2,4,5)
I Entry and exit guides Should not overwear, align the Visual, hand feel N One Each setting ---- Operator Change the guides
J (for 3,5) entry of should
Coolant pin from
notguides with reg
over dirt
MIN :50 LPM Rework/Reject
Coolant ( for 1,2,5) ,changing freq 4 month Y Every shift First Off Operator
3~4% Reset the m/c
Coolant Flow , Coolant %
K Dressers ( Reg & grd one Operator
Dresser point should be sharp Visual/ Finger feeling N Every week Record in log book Change the diamond
wheel) (for 1,2,4,5)
L
Setting of OD Master Correct size OD Master as per pass Calibration identification Change the master if
N --- After every setting Operator
(for 1) on BR Gauge opn master required inform to QC
Safety Instruction :-1.Use handgloves , goggle while doing coolant change/ dust cleaning 2.While operating machine use air muff & if reqd nose masks
Safety Instruction :-1. Use air muff 2. While changing stansol 60 apply KERODEX CREAM to the hands , Use handgloves while handling stansol 60
124 Crack Crack
detection Detector Reject the cracked pins As
1 Surface Cracks Free from surface cracks Visual Y 100% Each Lot On line/MPI status Record Shift Engineer / operator per Reaction plan WI of
Crack Detection
First-off/ roundness
2 Circularity 2.0 µ, Roundness Tester Y 5 nos. New setting/per shift Operator
graph
2µ First-off
3 Cylindricity Roundness Tester Y 2 nos. New setting/per shift Operator
Rework/Reject
4 Ovality 2.0 µ Air gauge LC 0.2 µ / Y 5 nos. New setting/per shift First-off Operator
Reset the m/c
5 Surface finish .1 Ra Roughness Tester Y 5 nos. New setting/per shift First-off Operator
6 Taper 1.5 µ Air gauge LC 0.2 µ / Y 5 nos. New setting/per shift First-off Operator
F RPM of Regulating
wheel As per set up plan RPM indicator Y One Each setting First off inspection Operator Reset the m/c
(for 1,2,4)
G
Center height (for
As per set up plan Vernier Height gauge Y One Each setting First off inspection Operator Reset the m/c
2,4)
I
entry and exit guides should align with regulating wheel Change the
Visual N One Each setting --- Operator
(for 5,3) axis, should not overwear guides/reset
K
Master should be in running coolant at gauge setting &
Master temp. Temp gauge N online ---- Operator Inform to mainteance
of machine & clean check
Safety Instruction :-1.Use handgloves , goggle while doing coolant change/ dust cleaning 2.While operating machine use air muff & if reqd nose masks
Safety Instruction :-1. Use air muff 2. While changing STANSOL 60 aaply KERODEX CREAM to the hands , Use handgloves while handling STANSOL60
Cap fitting after
Cap fitting Dial gauge L C 0.01 + Rework/Reject Modifided Punch
ultrasonic Cap Depth Min 5.0 mm Y 5 nos Each lot at Start First off operator
Press Comparato Reset the m/c to be use for cap
washing work instruction fitting
presence of
Cap should be present N Each Piece --- operator Reset the m/c
cap
Air Pressure
5 ~ 6 bar Pressure Gauge N
1
Temperature Soaking for 45 min. in A/C Room of
stabilized Temperature Y 100% Each Lot Operator Set room temterature
material 18 to 22º C
Soaking for
216 Temperature A/C Room In Time Register
Stabilization Temp of surrounding 18 to 22 deg Temp gauge N 100% On line Operator Rest the machine
soaking time as per spec. 45 min Wall clock Y 100% On line Operator Re soak the pins
Safety Instruction :-1. Use air muff 2. While changing stansol 60 apply KERODEX CREAM to the hands , Use handgloves while handling stansol 60
Manual Manual
310 Colur Code Colur Code. Work Instruction Colur coding is leagible 100% Each Piece On line Operator Rework/Reject
1 n
Packing Manual Ensure the VCI
Paper Sizes 100
1 Quantity 50 nos per Box Visual N 100% Each Piece On line Operator Recount/ Repack x130 for Specific
As per grading / Customer
340 colour coding chart, HMSI/TVS
Packing standard
Crank Pin Name, WO No, Grade,
2 Labling Packing Date, customer part Visual N 100% EACH BOX On line Operator Re Lable
name :-N3020120
350 Pre-dispatch Manual 1 Refer PDI Plan NA NA NA NA NA NA NA NA NA NA NA
inspection
2 03.05.2016 Magnetic saparator provided on T-4 ,New V belt conveyor on T4 , Interlinking. /soaking temp 18 to 22°C
3 28.09.16 Modifided Punch used & / Ensure the VCI Paper Sizes 100 x130 for Specific Customer HMSI/TVS
4 12.11.2016 Lower group produc in Batch & Don’t produce excess against plan.
SR SAMPLE OBSERVATION
PARAMETER SPECIFICATION REMARKS
NO. QTY 1 2 3 4 5
3 Drill Diameter 12.00 12.00 ( ± 0.10 ) mm 5 12.02 12.01 12.03 11.98 11.99 OK
4 Drill Diameter 16.00 16.00 ( - 0.05 ~ - 0.15 ) mm 5 15.88 15.87 15.88 15.87 15.87 OK
10 Cross hole Distance 21 mm 21.00 ( ± 0.25 ) mm 5 21.13 21.15 21.14 21.16 21.16 OK
15 Face hole Distance 8.00 mm 8.00 ( ± 0.1 ) mm 5 7.92 7.96 7.98 7.96 7.92 OK
17 Face hole Chamfer & Angle 0.5 ( 0 / +0.2 ) X 45º 1 0.52 X 45°29'38" OK
19 Inclined hole angle 39° ( ±1° ) 5 39°23'38" 39°57'32" 39°26'17" 38°26'38" 39°20'39" OK
22 Dimple distance from face 6.5 ( ± 0.15 ) mm 5 6.53 6.58 6.54 6.53 6.48 OK
End Profile
SAMPLE SUBMISSION
INVESTIGATION
SAMPLE APPROVAL
SAMPLE STUDY
LOT ACCEPTANCE
40 Plug material CRCA 'D' with Zn plated 5 CRCA 'D' with Zn plated OK
42 Face hole to inclined hole angle 180° +/-2° 5 178°05'01" 178°23'23" 178°04'53" 178°35'33" 179°12'06" OK
Heat treatment- Pin
Carburising,Quenching,
43 Heat treatment 5 Carburising,Quenching, tempering all over. OK
tempering all over.
44 Surface Hardness 60 to 64 HRC 1 63 63 62 63 63 OK
REMARKS:- OK PURPOSE
Grade Dia. Qty PRE-DESP INSP.
SAMPLE STUDY
28 21 12
43 11
35 5
9
44
8
45 6 10
42 9
46 4
1
3
47
7
20
16
48
41
40
39 38
36
37
40
NRB BEARINGS LIMITED ( SPC -variable_Bi-Lateral Tolerance) ( Rbar/d2)
PLANT SHIFT DEPT. MACH. NO. PART NAME / NO. OPERATION CHARACTERISTIC SAMPLE SIZE FREQUENCY UNITS OPERATOR DATE
Waluj 1 Crank Pin Modler-1 SH 5228 final Grinding OD Reading 125 Intervel µm MBN 21.04.17
DATA
USL 4.000 LSL -2.000 35
Goal
S.No. 1 2 3 4 5 Actual
1 1.2 1.6 1.2 1.4 1.6 30
-1
23 1.8 1.4 1.2 1 1.2 0.4
27
28 X = Avg x USL = X+A2R LSL = X-A2R R = Avg r USL = D4R LSL = D3R
29 Mean
Proc. Capability s= 0.295 6s = 1.772 Cp = 3.39 Cpk = 2.75 1.000 Mean Actual 1.563
Spec.
30
Remarks :ok
YAP KSD
Checked By Approved By
Part Submission Warrant
Are polymetric parts identified with appropriate ISO marking codes ? Yes No N/A
REASON FOR SUBMISSION
P Initial Submission Change to Optional Construction or Material
Engineering Change (s) Sub-Suplier or Material Source Change
Toolings : Transfer ,Replacement,Refurbishment, or additional Change in Part Processing
Correction of Discrepancy Parts Produced at Additional Location
Tooling inactive > than 1 Year Other - Please specify
Level 2 - Warrant with product samples and limited supporting data submitted to customer
P Level 3 - Warrant with product samples and complete supporting data submitted to customer
Level 5 - Warrant with product samples and complete supporting data reviewed at supplier's manufacturing location
SUBMISSION RESULTS
The results for P dimensional measurements, P material and functional tests, appearance criteria P
statistical process package
These results meet all design record requirements: Yes No (If "No" - Explanation Required)
Mold / Cavity / Production Process
DECLARATION
I affirm that the samples represented by this warrant are representative of our parts, which have made by a process that meets all Production Part
Approval Process Manual 4 th Edition Requirements. I further affirm that these samples were produced as the rate of 100 No. / hours.
I also certify that documented evidence of such compliance is on file and available for review. I have noted any deviations from this declaration below.
EXPLANATION / COMMENTS:
Is each Customer Tool properly tagged and numbered ? Yes No N/A
Organization Authorised Signature Date 27.05.17
Print Name K.S.Deore Phone No. 240- 6634517 Fax No.
Title Manager QA Email