Professional Documents
Culture Documents
, LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
PROJECT:
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
SUBMISSION
DOCUMENT PREPEARED APPROVED
DATE DESCRIPTION OF CHANGE
NO. BY BY
2019-T03-
25/09/2019 Method Statement – First Issue AG LZ
MS01
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
CONTENT
1. Introduction
2. Test Objectives
3. Load Test Principle
4. Equipment
5. Test procedure
6. Test Results
7. Safety at Work
8. QA/QC Procedure
9. Certificate of equipment and layout for test pile
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
1. Introduction
This document describes the methods and equipment used in static load compression testing of
foundation pile using equipment specifically developed for the purpose.
This Method Statement (MS) describes the procedures, standards and HSE rules in testing of bored
piles for Project PhnomPenh. The MS shall cover the following tests:
- Instrumented Static Pile Load Test;
The MS is prepared in accordance to the Technical Specification included in Design Document
and applicable standards – ASTM D1143/ D1143M – 07- “Standard Test Methods for Deep Fo
undations Under Static Axial Compressive Load”;
2. Test Objectives
Instrumented Static Pile Load Tests are carried out to determine:
- The Load-Settlement behaviour of tested pilot piles.
3. Load Test Principle
The test is carried out by applying static axial load to the pile head so that the pile penetrates into the
ground. The axial load is created by one or more hydraulic jacks setting on top of the pile and acting
against a reaction system.
The reaction system is a combination of Kent-ledge (dead weight of concrete blocks) and ground
anchor (screw piles).
4. Equipment
The test equipment consists of apparatus for applying load, reaction system and a system of
movement measurement.
a. Apparatus for applying load
The apparatus for applying load consists of hydraulic jack(s) powered by a hydraulic pump with
pressure gauge. The following apparatus for applying load will be used in the test:
• 7 Hydraulic jack(s): maximum load 8,000kN/Jack.
• 1 Hydraulic pump: Maximum Operation Pressure of 10,000psi.
• 1 Pressure gauge: Pressure range 0-60 Mpa
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
Note: All anchor pile was installed in same condition and will be controlled by dial gauge, m
ounted on screw machine so select 1 or 2 anchor pile for testing is reasonable. Testing company
will make sure and decide this issue, based on actual installation.
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
YES=Proceed the
TEST
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
d. Man-power Organization
Managing Director
Project Manager
Item
Title Quantity
No
1 Managing Director 1
2 Project Manager 1
3 Site engineer 2
4 Safety officer 1
5 Eqpt. Operator/mechanic 2
6 Labor utilities 2
Total→ 9
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
b. Loading procedure
The minimum leave time from the end of construction to the beginning of the testing is 21 days.
• Preloading
Preloading will be carried out before testing for checking operation of test equipment and for
making good connection between test beam and hydraulic jacks. The preloading will be perfo
rmed by application of about 5% of design load, maintaining for 10 minutes and then fully unloading.
• Standard loading procedure
The loading and unloading shall be carried out in stages as shown in below Table. Following each
application of an increment of load the load shall be held for not less than the period shown or until
the rate of settlement is less than 0.25 mm/hr and is slowing down. The rate of settlement shall be
calculated from the slope of the curve obtained by plotting values of
settlement versus time and drawing a smooth curve through the points. Each stage of unloa
ding shall proceed after the expiry of the period shown in the below Tables:
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
6. Test Results
The test results will be presented in two formats, tabular and graphical.
a. Tabular form
The data including readings of load, time and settlement taken and recorded during testing for
tested pile shall be presented in "Pile Load Test Record" and “Summarised Test Results”.
b. Graphical form
From the test data, the following curves shall be established:
• Load - Settlement Curve
• Settlement - Time Curve
• Load - Time Curve
• Load - Settlement - Time Curve
c. Text part
In the text part, the following contents should be mentioned:
• Introduction;
• Details of test pile;
• Test purpose;
• Test method;
• Test equipment;
• Loading procedure;
• Test results;
• Conclusions and recommendations.
d. Appendices
In the appendix part, the following contents should be mentioned:
• Recording sheets of test data;
• Layout of test piles;
• Documents of soil conditions;
• Certificates of test equipment.
7. Safety at Work
During testing, besides obeying regulations of safety at work in construction, the following rul
es should be observed:
a. No entry to test site for unauthorized people;
b. All building waste, mud, oil… on test area should be cleaned;
c. It is necessary to have protection method for test equipment from rain, sun shine;
d. Hydraulic jacks, pump, system of hydraulic hoses, valves and connectors
should periodically have checked and cleaned. Replace timely the damaged parts;
e. The mobilisation and de-mobilisation of Kent-
ledge and test equipment should safety, do not block public traffic;
f. Should have safety method for installation of Kent-
ledge. People stay under crane and in operation area of crane
At each site, a dedicated safety officer will be assigned full-
time. This employee will be in charge of all HSE regulations and has the authority to stop work if
necessary until corrective action and prevention in-place.
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
8. QA/QC Procedure
This inspection procedure is used for the combined Kent-ledge and ground anchor method. It also
applicable for testing with Kent-ledge only by removing unrelated sections. Each step of inspection
will be accomplished by forms and certifications signed by related parties.
Internal machines & equipment inspection by ANXIN
Machines & equipment inspection by all parties
Screw piles installation (observed by Owner/Consultant/Engineer)
Screw pile compression/tension test (observed by Owner/Consultant/Engineer)
Final Inspection of screw pile system by all Parties
Installation of the loading frame (kentledge) and other equipment (jack, pump, measuring
devices)
Final inspection before testing by all Parties
Load testing (observed by Owner/Consultant/Engineer)
Certification of raw data by all parties
Reporting and Revising
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
APPENDIX I – TEST EQUIPMENT CERTIFICATE
NEW PROJECT
25th September 2019
VI t;:N HA'\ LAl\1 Kl-fOA IIQC \'A CO:\G �Gllf, \'I f,T NA \1 Van pht'111g 291 rnrJ\i
RIFN PHU - Q3
V!PTNAMES[ ACADEMY A'\JI) TECH OLOGY Oflicc. TP H6 Chi Minh Vi¢t Nam
VlE'.N CO HQC ,it TIN H()C USG Dl)NG Tel: 3930 8483 Fax: 3930 8300
Le Tram
I. Cac kct qua thu nghi¢m chi Jung voi m5u do khach hang goi clen The test results are based on tested sample only.
2. Ten m�u. ten kha..:h luing gh1 thco yeu du cua nai gai mfiu Name of sample and client arc wnllcn as client's request
l Khong dtrQ'C tich. sao lllQI phfin ket qua 1lm nghi�m nJu khong c6 SlJ d6ng y cua Vi�n Ccr I IQC vii Tin HQC (fog D\Jng/ TlllS te�t
report shall 1101 be reproduced except in full. without the approval IA \11
Vlf,'1 HA'i LAM KIIO/\ HQC \'A CO:'.G \IGII�� \'If,T N/\'\1 Van phbng 291 1)11:N RIFN PHU - Q3
VIETNAMESE ACAl)E\4Y A�I) TECIINOLOGY Office· TP H6 Chi Minh Vi9t Nam
Vlf,N CO HOC ,a
TIN H()C (J'NG D{)NG Tel 3930 8483 Fax: 3930 8300
INSTITUTE OF APPLIED MECI IAN!CS an<l lNFOMA TICS
utram
I. Cac kct qua thtr ngh1�n1 ch, dung voi mfiu do kh:ich h,ing gl'Ji den The te�t results arc based on tested sample only.
2. Tcn m�u. ten kh:ich hang gh, theo yeu du cua no1 gl11 mfiu Name of sample and client are wrillen as client's request.
3. Khong cltrqc tich. sao 11191 phfin k�t qua thtr nghi�m n�u khong c6 SI! d6ng y cua Vi�n Co H<;>c va Tin I l<;>c (fog D\mg This test
report shall not be reproduced except 111 fttll, without the approval !AMI.
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
APPENDIX II – LAYOUT OF WORKING PILE – 1587.0 TONNES
NEW PROJECT
25th September 2019
SCREW PILE PLAN SUPPORT BEAM ON PILE TOP PLAN (A-A)
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
APPENDIX III – LAYOUT OF WORKING PILE – 1745.0 TONNES
NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993
APPENDIX III – LAYOUT OF WORKING PILE – 2313.0 TONNES
NEW PROJECT
25th September 2019