METHOD STATEMENT FOR STATIC LOAD TEST

PROJECT:

PHNOM PENH, CAMBODIA

PREPARED BY : ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD


DOCUMENT NO : 2019-T03-MS01
DATE : 25 SEPTEMBER 2019
REVISION : 00

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

SUBMISSION
DOCUMENT PREPEARED APPROVED
DATE DESCRIPTION OF CHANGE
NO. BY BY
2019-T03-
25/09/2019 Method Statement – First Issue AG LZ
MS01

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

CONTENT
1. Introduction
2. Test Objectives
3. Load Test Principle
4. Equipment
5. Test procedure
6. Test Results
7. Safety at Work
8. QA/QC Procedure
9. Certificate of equipment and layout for test pile

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

1. Introduction
This document describes the methods and equipment used in static load compression testing of
foundation pile using equipment specifically developed for the purpose.
This Method Statement (MS) describes the procedures, standards and HSE rules in testing of bored
piles for Project PhnomPenh. The MS shall cover the following tests:
- Instrumented Static Pile Load Test;
The MS is prepared in accordance to the Technical Specification included in Design Document
and applicable standards – ASTM D1143/ D1143M – 07- “Standard Test Methods for Deep Fo
undations Under Static Axial Compressive Load”;
2. Test Objectives
Instrumented Static Pile Load Tests are carried out to determine:
- The Load-Settlement behaviour of tested pilot piles.
3. Load Test Principle
The test is carried out by applying static axial load to the pile head so that the pile penetrates into the
ground. The axial load is created by one or more hydraulic jacks setting on top of the pile and acting
against a reaction system.
The reaction system is a combination of Kent-ledge (dead weight of concrete blocks) and ground
anchor (screw piles).
4. Equipment
The test equipment consists of apparatus for applying load, reaction system and a system of
movement measurement.
a. Apparatus for applying load
The apparatus for applying load consists of hydraulic jack(s) powered by a hydraulic pump with
pressure gauge. The following apparatus for applying load will be used in the test:
• 7 Hydraulic jack(s): maximum load 8,000kN/Jack.
• 1 Hydraulic pump: Maximum Operation Pressure of 10,000psi.
• 1 Pressure gauge: Pressure range 0-60 Mpa

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

Installation of hydraulic Jacks and dial gages


b. Reaction system (Anchor pile method)
The reaction system contains test beam (main beam), cross beam, Kent ledge (deadweight of
concrete blocks) and ground anchorage (screw piles).
Appendix I- “Test Layout and Setup” present a detailed calculation and testing arrangement of each
pile size:
• Appendix I-1 –
Reaction System Capacity - Anchor pile details and capacity
(compression and tension) are estimated from the Geotechnical data
made available by Clients. Also included is the field load test for
verification of anchor pile capacity
• Appendix I-2 – Example of Testing Arrangement is illustrated including the
details dimension and number of each member

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

The loading frame is constructed by a system of cross beams. The Kent-


ledge included concrete blocks & steel anchor pile (screw pile) is placed safely on the loading
frame; the test

Installation of anchor piles


The ground anchor consists of steel tube segment of 4m with screwing blades of 400mm. The screw
piles are installed into the ground by using a torque converter mounted on a excavator and powered
by the hydraulic system of the excavator. Each screw pile is installed to a pre-determined depth with
the applying torque being monitored and recorded to ensure it has sufficient capacity. The screw
piles serve the two purposes:
• Before the test while building up the Kent ledge (stacking the concrete
blocks), the screw piles will support all the weight of the Kent ledge
and eliminate the possibility of excessive settlement and instability
(Kent ledge collapsing). During this stage, the screw piles support the
Kent ledge by mobilizing the compressive capacity.
• During the load test, the uplifting force from the hydraulic jacks will be
balanced by first the Kent ledge (weight of concrete blocks); once, the
uplifting force reaches the capacity of the Kent ledge, the further
reaction is provided by the pull-out (tension) capacity of the screw piles.
During the load test, movement of the ground anchor system was closely monitored by using
precision levels. The upward movement of the anchor piles shall be within the allowable limit of 10%
anchor pile diameter (i.e., 40mm). If reached, the load test will be cancelled.

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

Anchor Pile Testing


Using the combined system of ground anchor and Kent ledge has some major advantages ov
er the pure Kent ledge:
• Using less deadweight as reaction, this leads to the safer testing pro
gram with significant improvement in term of accident prevention and
Kent ledge collapse. The deadweight is firmly supported by ground anchors
thus reducing the ground movement during testing – improving the quality
of settlement readings.
• The reaction comes from both deadweight and ground anchors hence
allowing a much higher test load.
• Minimize the ground preparation (ground strengthening – such as co
mpacted crushed stone, steel plates and in some cases steel or concrete
piles) to support the Kent ledge system.
• Cost effective since a sizeable portion of test expense comes from
transportation and handling of deadweight.
On each test site, prior to setting up the reaction system, one or two anchor pile will be tested
for compression and tension to verify the capacity. These anchor pile will be selected
during anchor pile installation, based on the actual value were recorded at dial gauge mount
ed on screw pile machine or will be selected by Client randomly. The testing procedure is shown as
blow:

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

Note: All anchor pile was installed in same condition and will be controlled by dial gauge, m
ounted on screw machine so select 1 or 2 anchor pile for testing is reasonable. Testing company
will make sure and decide this issue, based on actual installation.

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

Installation of loading frame

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

Installation of beams and blocks

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

c. Work flow and procedure:

Pile head treatment

Anchor pile installation (56 points)


+ Testing

Set up cover hat & 4 sleep beam

Set up steel plate on pile head

Set up Hydraulic jack eccentric to test


pile resting on level steel plate

Set up 32 base concrete block and 2


sleeper beam

Set up the Load carrying beam system


(Main beam)

Set up connection parts, 16


cross beam and the kenledge load on
load Beams
NO= Clarify
Set up 2 reference beam for the 4 dial Objection
settlement gauges

Install the 4 dial settlement gauges


and load gauge for the hydraulic jack

Check the efficiency of jack, gauges Get the Approval of the


and the loads, beams and Girders for Engineer at site before
their proper position commencing the test

YES=Proceed the
TEST

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

d. Man-power Organization

Managing Director

Project Manager

Site Engineer Safety Engineer Survey/Site


Engineer

Item
Title Quantity
No
1 Managing Director 1
2 Project Manager 1
3 Site engineer 2
4 Safety officer 1
5 Eqpt. Operator/mechanic 2
6 Labor utilities 2
Total→ 9

e. System of Movement Measurement


The system of settlement measurement consists of by 4 dial gauges placed firmly on the two
stable reference beams. The reference beams should be stably installed to ensure no influenc
e of soil movement or deformation of equipment. The 4 dial gauges with maximum stroke 100 mm
accuracy 0.01 mm will be used for measuring settlement of pile head.
Furthermore, observations of any movements of the reference frame will be made by levellin
g or other method consented by the Employer’s Representative and a check shall be made of the
movement of the pile head relative to an external datum during the progress of the test.
Before testing, the inspection and calibration certificates of the dial gauges will be submitted to the
Owner and Consultant. These certificates are attached hereinafter.
5. Test Procedure
a. Preparation Test
Before testing, the following works should be prepared:
• Test site preparation: clearing, levelling and draining of the ground;
• Preparation for test pile head:
1. Checking the top of bore pile. If there have some tube for sonic test,
grouting them by cement or sika. (this is done by piling contractor)
2. Checking the quality concrete of head pile. If having bad concr
ete, cutting and moving them. (this is done by piling contractor
3. Covering around the head pile by steel plate (thickness 2mm) to pro
tect head pile. (this is done by piling contractor)
4. Grouting and making smooth surface by sika grout 214-11.
• Mobilization of test equipment to test site;
• Installation of test equipment;

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

b. Loading procedure
The minimum leave time from the end of construction to the beginning of the testing is 21 days.
• Preloading
Preloading will be carried out before testing for checking operation of test equipment and for
making good connection between test beam and hydraulic jacks. The preloading will be perfo
rmed by application of about 5% of design load, maintaining for 10 minutes and then fully unloading.
• Standard loading procedure
The loading and unloading shall be carried out in stages as shown in below Table. Following each
application of an increment of load the load shall be held for not less than the period shown or until
the rate of settlement is less than 0.25 mm/hr and is slowing down. The rate of settlement shall be
calculated from the slope of the curve obtained by plotting values of
settlement versus time and drawing a smooth curve through the points. Each stage of unloa
ding shall proceed after the expiry of the period shown in the below Tables:

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

• Procedure of data recording


The reading frequency is shown in the below Table as stipulated in the Specifications.
Intrument Frequency of Monitoring
Dial Gage - After 5 min, 10 min,
15 min and every
15 min thereafter
during the first 2h
- Every 1hr for the
next 10h.
- Every 2h for the
next 12h.
Hydraulic Pressure Gage - After 5min, 10 min,
15 min and every 15
minutes thereafter.
Optical Level Every 60 minutes
1. Abandonment of load test
Test shall be discontinued if any of the following occurs:
a. Pre-jacking or pre-
loading before the commencement of the test
Improper setting of datum
b. Disturbed or unstable bench marks or scales
c. Faulty of pile cap or instability of the Kent-ledge
d. Failure of concrete to reach the design compressive strength

e. Faulty jack, equipment or gauge.


f. Pile head crack or broken.
g. Initial readings are incorrect.
2. Failure of test pile
The test pile shall be deemed to have failed if any one of the following criterions is reached:
a. Pile material is broken;
b. A working test pile shall be deemed to have failed if is maxi
mum settlement under the test load exceeds the following :

c. A working test pile , loaded to 2 times working load , shall


also be deemed to have failed if the residual
settlement exceeds 40% of the settlement under test
load or
10mm whichever is less, even if the settlement under t
est load is satisfactory. For working test pile that is
loaded to less than 2 times working load, the test pile shall
also be deemed to have failed if the residual settlement
exceeds 40% of the settlement under test, even if the
settlement under test load is satisfactory.
d. The rate of settlement continues undiminished without furt
her increment of load.

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

6. Test Results
The test results will be presented in two formats, tabular and graphical.
a. Tabular form
The data including readings of load, time and settlement taken and recorded during testing for
tested pile shall be presented in "Pile Load Test Record" and “Summarised Test Results”.
b. Graphical form
From the test data, the following curves shall be established:
• Load - Settlement Curve
• Settlement - Time Curve
• Load - Time Curve
• Load - Settlement - Time Curve
c. Text part
In the text part, the following contents should be mentioned:
• Introduction;
• Details of test pile;
• Test purpose;
• Test method;
• Test equipment;
• Loading procedure;
• Test results;
• Conclusions and recommendations.
d. Appendices
In the appendix part, the following contents should be mentioned:
• Recording sheets of test data;
• Layout of test piles;
• Documents of soil conditions;
• Certificates of test equipment.
7. Safety at Work
During testing, besides obeying regulations of safety at work in construction, the following rul
es should be observed:
a. No entry to test site for unauthorized people;
b. All building waste, mud, oil… on test area should be cleaned;
c. It is necessary to have protection method for test equipment from rain, sun shine;
d. Hydraulic jacks, pump, system of hydraulic hoses, valves and connectors
should periodically have checked and cleaned. Replace timely the damaged parts;
e. The mobilisation and de-mobilisation of Kent-
ledge and test equipment should safety, do not block public traffic;
f. Should have safety method for installation of Kent-
ledge. People stay under crane and in operation area of crane
At each site, a dedicated safety officer will be assigned full-
time. This employee will be in charge of all HSE regulations and has the authority to stop work if
necessary until corrective action and prevention in-place.

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

8. QA/QC Procedure
This inspection procedure is used for the combined Kent-ledge and ground anchor method. It also
applicable for testing with Kent-ledge only by removing unrelated sections. Each step of inspection
will be accomplished by forms and certifications signed by related parties.

Internal machines & equipment inspection by ANXIN 

Machines & equipment inspection by all parties 

Screw piles installation (observed by Owner/Consultant/Engineer) 

Screw pile compression/tension test (observed by Owner/Consultant/Engineer) 

Final Inspection of screw pile system by all Parties 

Installation of the loading frame (kentledge) and other equipment (jack, pump, measuring 
devices) 

Final inspection before testing by all Parties 

Load testing (observed by Owner/Consultant/Engineer) 

Certification of raw data by all parties 

Reporting and Revising 

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

APPENDIX I – TEST EQUIPMENT CERTIFICATE 

NEW PROJECT
25th September 2019
VI t;:N HA'\ LAl\1 Kl-fOA IIQC \'A CO:\G �Gllf, \'I f,T NA \1 Van pht'111g 291 rnrJ\i
RIFN PHU - Q3
V!PTNAMES[ ACADEMY A'\JI) TECH OLOGY Oflicc. TP H6 Chi Minh Vi¢t Nam
VlE'.N CO HQC ,it TIN H()C USG Dl)NG Tel: 3930 8483 Fax: 3930 8300

•�nn• fNSTITUTE OF APPLIED MECIIANlCS and I FOMATICS

S6 hi¢u I N" · 01032019, KTTB


BAO CAO THU' NGHIJ;:M
TEST REPORT

I. Ten thi�t bi/ Name of equipment: D6ng h6 so I Dial Indicator.


2. Hang san xu�t/ Manufactory: MfTUTOYO- Japan I Nh�t ban.
3. Ki�u thi<3t bi/ Model: 3062S-19
4. Thong s6 ky thu�t /specifications: IOOmm
5. Gia tri v�ch chia I Division value: O.Ol mm
6. S6 ch� t�o/ Serial number: PUZ 656
7. Noi gui m�u/ Customer:
No 2734, Street 598, Sangkat Kilometer No 6. Khan Russey,
Phnom Penh, Cambodia
8. Ngay ki6m tra I Test date: 02/03/2019
9. Ngay h�t h�n I Expiration date: 01/03/2020
I 0. K�t qua I Result: D�t yeu du v� ky thu�t do luc'rng theo DLVN 75:200 I I
Satisfactory measurement techniques in DLVN 7 5: 200 I
Sai s6 nho hon ±0,081 mm tren toan khoang ho�t dc)ng I
Enor less than ±0.081 mm over about activities

Le Tram

I. Cac kct qua thu nghi¢m chi Jung voi m5u do khach hang goi clen The test results are based on tested sample only.
2. Ten m�u. ten kha..:h luing gh1 thco yeu du cua nai gai mfiu Name of sample and client arc wnllcn as client's request
l Khong dtrQ'C tich. sao lllQI phfin ket qua 1lm nghi�m nJu khong c6 SlJ d6ng y cua Vi�n Ccr I IQC vii Tin HQC (fog D\Jng/ TlllS te�t
report shall 1101 be reproduced except in full. without the approval IA \11
Vlf,'1 HA'i LAM KIIO/\ HQC \'A CO:'.G \IGII�� \'If,T N/\'\1 Van phbng 291 1)11:N RIFN PHU - Q3
VIETNAMESE ACAl)E\4Y A�I) TECIINOLOGY Office· TP H6 Chi Minh Vi9t Nam
Vlf,N CO HOC ,a
TIN H()C (J'NG D{)NG Tel 3930 8483 Fax: 3930 8300
INSTITUTE OF APPLIED MECI IAN!CS an<l lNFOMA TICS

° So hi9u IN": 0-1032019/KTTB


BAO CAO THlJ NGHIF;M
TEST REPORT

l. Ten thi�t bi/ Name of equipment: B6ng hf> so I Dial Indicator.


2. Hang san xufit/ Manufactory: MTTUTOYO - Japan I Nh�t ban.
3. Ki�u thi6t bi/ Model: 3062S-19
4. Thong s6 ky thu�t /specifications: IOOrnm
5. Gia tri v�ch chia I Division value: O.Olrnm
6. S6 ch� t�o/ Serial number: PUZ 660
7. Noi gui m�u/ Customer: Khmer D&C Technical Consultant Co., Ltd
No 2734, Street 598, Sangkat Kilometer No 6, Khan Russey.
Phnom Penh, Cambodia
8. Ngay kicm tra I Test date: 02/03/2019
9. Ngay h�t hi;m I Expiration date: 01/03/2020
I 0. K�t qua I Result: B;,1t yeu du v� ky thu�t do ltrong theo BLVN 75:200 l I
Satisfacto1y measurement techniques in DL VN 75: 200 I
Sai s6 nh6 hon ±0.081mm tren toan khoang ho;,1t d(>ng I
Error less than ±0.081mm over about activities

Phong thi nghi?m chin doan ky thu�t


Technical Diagnusf ·s Laboratory
Ng iri th

utram
I. Cac kct qua thtr ngh1�n1 ch, dung voi mfiu do kh:ich h,ing gl'Ji den The te�t results arc based on tested sample only.
2. Tcn m�u. ten kh:ich hang gh, theo yeu du cua no1 gl11 mfiu Name of sample and client are wrillen as client's request.
3. Khong cltrqc tich. sao 11191 phfin k�t qua thtr nghi�m n�u khong c6 SI! d6ng y cua Vi�n Co H<;>c va Tin I l<;>c (fog D\mg This test
report shall not be reproduced except 111 fttll, without the approval !AMI.
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

APPENDIX II – LAYOUT OF WORKING PILE – 1587.0 TONNES 

NEW PROJECT
25th September 2019
SCREW PILE PLAN SUPPORT BEAM ON PILE TOP PLAN (A-A)
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

APPENDIX III – LAYOUT OF WORKING PILE – 1745.0 TONNES 

NEW PROJECT
25th September 2019
ANXIN CONSTRUCTION ENGINEERING (CAMBODIA) CO., LTD
Street 598, Sangkat Kilometer VI, Khan Russey Keo,
Phnom Penh, Cambodia.
+855 979602993

APPENDIX III – LAYOUT OF WORKING PILE – 2313.0 TONNES 