You are on page 1of 2

Table 1: Tarea, duración y recursos de trabajo

Código de Tarea/Actividad Duración Predecesor Recursos de trabajo


actividad (días) requerido
A Start-up planning 5 - Software planning,
and design Equipment design
B Equipment 8 A Software planning,
determination and Equipment design,
planning Software installation,
Equipment assembly
C Specific software 9 A Software planning,
determination Software development
D Production line 4 B Equipment design
planning and
determination
E Equipment planning 7 B Software planning,
Software development
F Software planning 17 C Software planning
G Equipment 10 E Software planning,
documentation Documentation
H Documentation of 13 F Software planning,
operational system Equipment development
I Detailed hardware 7 E Equipment development
blueprints
J Hardware 1 I Procurement
component orders
K Hardware 6 J -
component
delivery
L Integration of phase 12 D,G,H,K Software development,
1 Equipment development,
Software installation,
Equipment assembly
M Prototype 10 L Software development,
development Equipment development
N Prototype 6 M Software installation,
introduction Equipment assembly
O System evaluation 9 N Software installation,
and improvement Equipment assembly,
Equipment development
P Hardware assembly 18 N Equipment assembly

Q Computer system 7 P Software development,


installation Software installation
R Project 4 O,P Software development,
documentation Equipment development,
Documentation
S Integration of phase 12 Q,R Software development,
2 Equipment development,
Software installation,
Equipment assembly

You might also like