Professional Documents
Culture Documents
Crude Oil Foundation PDF
Crude Oil Foundation PDF
1.0 Introduction………………………………………………………………………………………………………….......…….. 1
2.0 Objective………………………………………………………………………………………………………………….……….. 1
3.0 Methodology…………………………………………………………………………………………..…………………….….. 1
APPENDIX
Appendix D – Analysis and design of tank loadings, RC ring beam and raft slab
1.0 Introduction
A crude oil storage tank is to be constructed in a designated site where the subsoil condition is
described in a given borelog shown in Appendix A. The tank has an internal diameter of 76m with the
height of 21m. The tank is made of heavy duty steel structure with steel plate thickness of 30mm.
Typical configuration of the tank is shown in Appendix B. This write up will briefly presents the design
calculation of the foundation system adopted for the proposed tank.
2.0 Objective
The purpose of this report is to briefly present the basic design procedures adopted for the tank
foundation system and produce construction drawing for tank foundation.
3.0 Methodology
In order to obtain the most effective in terms of safety and economical design options, the following
design procedures must be followed;
1) Available subsurface information must be studied thoroughly in order to determine and predict
the behaviour of ground under imposed load of the proposed tank construction.
3) Several types of foundation system to support the tank is explored and compared the
suitability in terms on economical, construction wise and performance during service life.
4) Subsequently after the most effective foundation system is selected, predicted pile movement
(pile elastic shortening and settlement) is calculated in order to ensure the total and
differential settlement of the tank is within the acceptable limit.
5) Recommendation on method of installation is given such that the structural integrity of the
foundation is maintained and fully utilised the advantages of the ground.
The only subsurface information provided for the foundation design is only field borelogs. No
geological information was made available. Therefore, the design shall only based on this information
with necessary assumptions were made to supplement the analysis.
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
Based on the provided borelogs, the subsoil generally consists of silty CLAY to clayey SILTS material.
The SPT-N value of the subsoil is ranging from 6 to 17 up to 9m b.g.l. indicating that the stiffness of
the soils is ranging from very soft to medium soft.
However, after 9m b.g.l. the subsoil has encountered hard layer which shown by consecutively seven
times SPT-N 50 (i.e. termination depth at 18m b.g.l.).
The groundwater table on the other hand is considered not very high whereby the highest reading
recorded during the investigation is approximately about 5m b.g.l.
The SPT-N value has been generalised in order to simplify the determination of pile working capacity
as shown in Appendix C.
Normally for real world storage tank design, the load is classified into several types which are dead
load, live load, wind load and seismic load. Typical composition of the storage tank is shown in
Appendix B. Analysis of the load calculation is enclosed in Appendix D.
1) Selfweight of tank roof and tank shell acting as line load (LL) on the ring beam.
2) Selfweight of tank base, sand bedding, reinforced concrete slab acting as uniform distributed
load (UDL)
Either storage fluid (namely Naphtha & Middle Distillates or fuel oil) or water is applied as uniform
distributed load (UDL) over the inner diameter of the concrete raft. The adopted specific gravity (SG)
for the storage fluids are either 0.787 or 1.0. Meanwhile the specific gravity for water is taken as 1.0.
Since there is no information provided for the wind load and seismis load, therefore this type of loads
is ignored and only considers the dead and live load for the foundation system analysis and design.
Typically two types of foundation system are considered namely shallow foundation (i.e. raft
foundation) and deep foundation system (i.e. piled raft foundation). However, shallow foundation
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
option has been eliminated during the assessment in view of very soft subsoil condition which will
lead to excessive settlement of the storage tank. Even though in certain case study there has been
successful practice shows that floating foundation system is possible, such system in fact require
detail assessment of the ground settlement behaviour using representative consolidation parameters.
Since the information is not available, therefore the option is not considered.
Therefore, only deep foundation system is explored during the analysis and design works. There are
several option of deep foundation system depending on subsoil condition and proposed site as listed
below. Determination of allowable pile working capacity is shown in respective appendices.
After carried out the above exercise, the following conclusion has been made;
1) All driven pile (displacement) length is estimated to be terminated at 9m b.g.l. as it was found
that the hard layer is encountered in the subsequent depth. Therefore, all the driven pile (i.e.
reinforced concrete pile, spun pile and etc) shall be terminated at this depth.
2) RC pile allowable working capacity only utilise 26% to 40% of the pile structural capacity. The
percentage of utilisation decrease with the increment of pile size.
3) Therefore, RC pile option is becoming more ineffective with bigger pile size. On the other
hand, smaller pile size provides smaller pile working capacity and hence requires more piles
to be installed. With the limited space under the tank, sufficient pile nos unable to be
provided.
4) In addition, RC pile is known to have more problems during installation in soft soil such as pile
deviation, rotation and tilt due to small confining effect of the soft soil.
5) As for boredpile, design approach normally heading to the direction of trying to fully utilise the
structural capacity. Minimum bored pile size in practice is approximately about 500mm as
smaller size than this is not more economical.
6) Bored pile only considers the contribution of shaft resistance and ignores resistance of the
pile base due to uncertainty of pile base cleaning during construction.
7) The assessment has shown that in order to fully utilise the structural capacity, the pile length
need to be extended from 27m to 73m deep in the ground. As this is not practical for
construction, therefore the option is not preferable.
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
8) Analysis on spun pile shown that full structural capacity can be achieve in practical range of
pile length. Even though driven spun pile shall also terminated at 9m b.g.l., but with the usage
of pre bore method the issue can be resolve. Furthermore, the method is quite common being
adopted in construction practice in this country.
9) Therefore, it has been decided that spun pile foundation system to be adopted. This pile shall
be pre bored after 9m b.g.l. and driven to set.
11) Expected pile settlement and elastic shortening shall be discussed in subsequent section.
In order to estimate pile settlement during the service life of the tank, elastic settlement method based
on Vesic, 1977 recommendation was adopted. Total settlement of the pile has been divided into three
components which are pile elastic settlement of pile, settlement of pile at pile base and settlement of
pile at shaft.
Analysis of the estimation of the total pile settlement is compiled in Appendix H. The estimation
involves several assumptions that have been made to assist the calculation. Based on the calculation,
it has indicated that the total pile settlement is 15.3mm which contributed by pile elastic settlement
(4.15mm), base pile settlement (10.19mm) and pile shaft settlement (0.95mm).
However the estimation is only a guideline and shall not be taken for crucial design purposes. The
actual pile settlement behaviour shall only be determined using pile testing (i.e. static / maintain load
test). The test not only gives pile settlement curve (load vs settlement) but also assist the designer to
determine the total settlement at working load and test load which later on used to verify the earlier
design assumptions during design stage.
It is also recommended to carry out the static load test coupled with sonic logging to determine stress-
strain of the pile at different pile depths respectively.
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
Reinforced concrete ring beam and raft/slab is constructed below the tank structure to provide rigid
foundation for the tank prior the load is transferred to the piles. Ring beam is designated specifically to
take line load from the tank which also carrying the load from the tank roof.
Sand bedding was introduced to cater for possible differential settlement that might occur during the
service life. This is crucial as excessive deformation might lead to crack of tank body and causing
leakage which is very hazardous. With the sand bed below the tank, it helps the tank to ‘readjust’ the
tank base with the ground deformation.
Ring beam is designed as continuous beam with the pile act like a column supporting the line load
from the ring beam. On the other hand, raft is designed as slab which bending capacity and punching
shear checking is carried out to ensure safety of the tank base. Summary of the analysis and design
of the concrete structure is shown in Appendix D.
Normally spun pile is installed using driven or displacement method. However, since the given
borelogs has indicated hard layer is located 9m b.g.l., then the deepest pile length that can be
achieved is 9m. Based on Appendix G, 9m spun pile length only able to provide and utilise 28% to
38% structural capacity which is economically ineffective.
In order to optimise structural capacity of the spun pile, the pile length need to be increased as
tabulated in the same appendix. This is when pre bore method come into the picture, this method
enable designer to have longer pile length. For example, 250mm dia spun pile only gives 190kN
allowable geotechnical capacity which is only 37% of structural pile capacity. However, by pre boring
to subsequent 8m depth, make up total depth of 17m would enable the pile to fully utilise the
structural capacity.
An issue may need to be considered is the stability of the bored hole prior to pile installation due to
soft 9m thick overburden silty and clayey material. However, this issue can be addressed by realising
that undrained shear strength, s u of the soil is greater than drained or effective strength and therefore
stabilised the bored hole in short term condition. Therefore, it must be noted and put into compulsory
to the engaged contractor to immediately install the spun after pre boring the pile point. No pre boring
is allowed at any time should the contractor is not ready to install the spun pile.
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
Construction drawing is the language to communicate between engineer and contractor. All
necessary information must be included in the drawing to ensure all the requirements are fulfilled
(Appendix I). The following are some example but not limited to;
1) Pile Layout
4) Installation method
APPENDIX A
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
APPENDIX B
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
APPENDIX C
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
APPENDIX D
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
Tank Dimension
Unit Weight
Vo = ( /4 ) x 76 x 76 x 21
= 95265.7 m3
Additional Loads
Weight of Raft/Slab, Wr = c x Vr
Wrs = 24 x 2726.18
= 65428.2 kN
Loading imposed on the Tank footing (not including along ring beam), La
La = Wo + Wb + Wsd + Wrs
= 934556 + 10493.3 + 61242.2 + 65428.2
= 1071720 kN
k = M/bd2fcu
fcu = 35 N/mm2
bar dia
= 20 mm
cover = 40 mm
steel tensile strength, fy = 460 N/mm2
effective depth, d = 1300 mm
As req = M / 0.95fyz
0.95d = 1235 mm
z = d [ 0.5 + √ (0.25 - k/0.9)]
= 1116.47 mm
As req = M / 0.95fyz
/ 0.95
= 3872.66 x 460 x 1116.47
= 7937.43 mm2
As min = 0.13%bh
= 0.13% x 600 x 1350
= 1053 mm2
Bar dia
= 20 mm
Nos of bars = 16
As prov
= 5026.55 mm2 Insufficient reinforcement
Pt = 1071720 / 4536.46
= 236.246 kN/m2
Bottom reinforcement
k = M/bd2fcu
fcu = 35 N/mm2
bar dia
= 20 mm
cover = 40 mm
steel tensile strength, fy = 460 N/mm2
effective depth, d = 550 mm
As req = M / 0.95fyz
0.95d = 522.5 mm
z = d [ 0.5 + √ (0.25 - k/0.9)]
= 544.27 mm
As req = M / 0.95fyz
/ 0.95
= 98.231 x 460 x 522.5
= 430.21 mm2
As min = 0.13%bh
= 0.13% x 1000 x 600
= 780 mm2
Bar dia
= 20 mm
Bar Spacing = 300 mm
Top reinforcement
k = M/bd2fcu
fcu = 35 N/mm2
bar dia
= 20 mm
cover = 40 mm
steel tensile strength, fy = 460 N/mm2
effective depth, d = 550 mm
As req = M / 0.95fyz
0.95d = 522.5 mm
z = d [ 0.5 + √ (0.25 - k/0.9)]
= 542.156 mm
As req = M / 0.95fyz
/ 0.95
= 133.951 x 460 x 522.5
= 586.651 mm2
As min = 0.13%bh
= 0.13% x 1000 x 600
= 780 mm2
Bar dia
= 20 mm
Bar Spacing = 300 mm
APPENDIX E
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
APPENDIX E
Qult = Qs + Qp
= 118.8kPa + 225kPa
= 343.8kPa
2) Allowable Capacity
Qall = Qsu / S.F + Qbu /S.F or Qall = Qult/2
= 118.8 + 225 = 343.8
2 3 2
= 134.4kN = 171.9kN
Table Below Shows The Geotechnical Capacity And Structural Capacity Of R.C Square Pile With
APPENDIX F
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
APPENDIX F
Structural capacity
Q sc = 0.25 x f cu x Ac
= [0.25 x 35 x (πx5002/4)]/1000
= 1718.06 Kn
Geotechnical Capacity
Qu=Qb+Qs
=Abq+Asf
= A b x 200N + As x 2N
= 65.97 + 245.04
= 311.02 kN
The base contribution was ignored due to uncertainty of base cleaning. Take factor of safety, F.O.S,
friction = 3, by considering disturbance during installation of the bored pile as a displacement pile.
Q all = [π 0.5) (3) (2x7)]/3 + [π (0.5) (6) (2x13)]/3
= 21.99 + 81.68
= 103.67 kN
Table 1 below shows the geotechnical and structural capacity of bored pile with different size of
diameter up to 9m length.
Table 1
Structural Ultimate Geotechnical Allowable Geotechnical
Diameter(mm) capacity (kN) capacity(kN) capacity(kN)
300 618.50 186.61 62.20
400 1099.56 248.81 82.94
500 1718.06 311.02 103.67
600 2474.00 373.22 124.41
700 3367.39 435.42 145.14
800 4398.23 497.63 165.88
900 5566.51 559.83 186.61
1000 6872.23 622.04 207.35
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
0.25 x f cu x Ac = As x 2N
[0.25 x 35 x (πx5002/4)]/1000 = [π 0.5) (3) (2x7)]/3 + [π (0.5) (6) (2x13)]/3 + [π x 0.5 x (2x50)]/3
x = 30.8 m
Figure 2
Table 2 below shows the shaft length of Bored pile required in hard layer and total length of the pile
with different size of diameter.
Table 2
pile shaft
Structural length in hard Total length of
Diameter(mm) Area (m2) capacity (kN) layer, x(m) bored pile
300 0.0707 618.50 17.7 27
400 0.1257 1099.56 24.3 34
500 0.1963 1718.06 30.8 40
600 0.2827 2474.00 37.4 47
700 0.3848 3367.39 44.0 53
800 0.5027 4398.23 50.5 60
900 0.6362 5566.51 57.1 67
1000 0.7854 6872.23 63.7 73
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
APPENDIX G
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
APPENDIX G
Outer diameter = 250 mm, inner diameter = 140 mm, wall thickness = 55, f cu = 60N/mm2
Pile length = 9m
Structural capacity
Q sc = 0.25 x f cu x Ac
= 505.4 kN
Geotechnical Capacity
Qu=Qb+Qs
=Abq+Asf
= A b x 200N + As x 2N
By assuming that the skin resistance is contributed by outer diameter, hence the ultimate load:
= 492.44 kN
= 190.07 kN
= 246.22 kN
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
Table 3 below shows the capacity of spun pile with different size of diameter.
Table 3
In order to fully utilize the structural capacity, pre-boring method can be carried out to have longer
pile length. For example:
0.25 x f cu x Ac = As x 2N
x = 8.03 m
Table 4 below shows the shaft length of spun pile required in hard layer and total length of the pile with
different size of diameter.
Table 4
total length
Outer inner wall structural pile shaft length of spun
diameter(mm) diameter(mm) thickness(mm) capacity(kN) in hard layer, x(m) pile(m)
250 140 55 505.40 8 17
300 180 60 678.58 9 18
350 210 70 923.63 11 20
400 240 80 1206.37 13 22
450 290 80 1394.87 13 22
500 320 90 1738.87 15 24
600 400 100 2356.19 17 26
700 480 110 3058.34 20 29
800 560 120 3845.31 22 31
900 640 130 4717.10 24 33
1000 720 140 5673.72 26 35
Figure 3
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
Say 20% downgrade is adopted due to soil disturbance during pre boring
Qall = 1200 (20%)
= 1000 kN (adopted for design)
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
APPENDIX H
Estimation of Pile Total Settlement, se
In summary, the adopted pile design is spun pile with 500mm outer diameter and 90mm wall thickness (320mm inner diameter) and is
installed until 17.5m into the soil to achieve 1200kN allowable geotechnical capacity. 823kN of the loading is taken by the pile shaft
and the balance of 386kN is taken by the pile base. Soil modulus is taken by empirical correlation of 2000N which the SPTN value is 50.
= 0.0042 m
= 4.15 mm
2
se (2) = qwp . D . (1 - µs ) I wp
Es
2
= 3329.7 x 0.3842 x (1 - 0.25 ) x 0.85
100000
= 0.0102 m
= 10.19 mm
2
se (3) = Qws . D . (1 - µs ) . I ws
p . L . Es
2
= 823 x 0.5 (1 - 0.25 ) . 4.07
1.57 x 17.5 x 60000
= 0.001 m
= 0.95 mm
= 15.30 mm
ECG 714 Foundation Engineering
Report on Analysis and Design of Crude Oil Storage Tank Foundation
APPENDIX I