You are on page 1of 3

Attention:

Project:
Site:
Owner:
Date:

SCOPE OF WORKS AND BID FORM


DAYS OF SKILLED LABOR COST MATERIAL COST TOTAL AMOUNT
ITEM BID ITEM WORKS
C F S L
1.0 GENERAL REQUIREMENTS
Mobilization/Demobilization/temporary facilities /Tools
and Equipment/General Cleaning Prior to Turn
over/Supervision
2.0 DEMOLITION OF EXISTED BUILDING
Demolition/site clearing/hauling
3.0 SUPPLY AND INSTALLATION OF MATERIALS
STRUCTURAL WORKS
a. Lay out / excavation of footing and tie beam
b. footing and tie beam form / rebars/ concrete
c. septic tank excavation / hollow blocks laying / flooring
d. Plumbing pipes embedded / fitting / fixture
e. earthfill / hauling / trucking
f. ground flooring tamper / rebars / concrete
g. hollow blocks laying 1st floor
h. post 1st floor form / rebars / concrete
i. slab, beam form / rebars / concrete
j. electrical pipes, boxes embedded/ wiring / fixture
k. stairs form / rebars/ concrete
l. hollow blocks laying 2nd floor
m. post 2nd floor form / rebars / concrete
n. truss,beam form / rebars / concrete
o. structural / trusses / roofing

4.0 FINISHING WORKS


p. hollow blocks plastering 1st floor interior / exterior
q. hollow blocks plastering 2nd floor interior / exterior
r. ceiling works 1st floor
s. ceiling works 2nd floor
t. tile works 1st floor
u. tile works 2nd floor
v. welding works / railing / grills
w. doors / jamb
x. windows / frame
y. carpentry works drawer / cabinet
z. painting works interior/ exterior
TOTAL CONTRACT COST LABOR AND MATERIALS

TERMS AND CONDITION:


Payment: Fifty Percent(50%) Downpayment
Balance: Through progress billing as per work accomplishment
Full and final payment upon completion of the project
Duration:

Excluded: 1. Electric and water supply / storage of construction materials to be


provided by the owner

2. building permit , as built plans and occupancy permit and other


government permits - to be provided by the owner
3. Perimeter fence

Prepared By:
CONFORME:
DATE:
ROMMEL P. LORENZO
09202417320 (Smart)
09159999602 (Globe)