The document provides project status updates for the Sunshine 100 City Plaza Phase-2 project from February to June 2015. It includes a table summarizing the percentage of work completed for each item (A-P) on a monthly basis, indicating that structural works (Item C) progressed the most each month, reaching 26.67% completion by June, while some items like cabinetry works (Item F) and elevator (Item N) had not yet begun. Overall project completion increased from 6.24% in February to 11.54% in May.
The document provides project status updates for the Sunshine 100 City Plaza Phase-2 project from February to June 2015. It includes a table summarizing the percentage of work completed for each item (A-P) on a monthly basis, indicating that structural works (Item C) progressed the most each month, reaching 26.67% completion by June, while some items like cabinetry works (Item F) and elevator (Item N) had not yet begun. Overall project completion increased from 6.24% in February to 11.54% in May.
The document provides project status updates for the Sunshine 100 City Plaza Phase-2 project from February to June 2015. It includes a table summarizing the percentage of work completed for each item (A-P) on a monthly basis, indicating that structural works (Item C) progressed the most each month, reaching 26.67% completion by June, while some items like cabinetry works (Item F) and elevator (Item N) had not yet begun. Overall project completion increased from 6.24% in February to 11.54% in May.
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY
% TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 24.31 2.07 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 8.93 3.21 D. ARCHITECTURAL WORKS 28.76 0.00 0.00 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 0.61 0.01 J. ELECTRICAL & AUXILIARY WORKS 7.38 0.34 0.03 K. PLUMBING WORKS 5.36 1.53 0.08 L. FIRE PROTECTION WORKS 1.77 0.9 0.01 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 40.00 0.12 P. TESTING AND COMMISSIONING TOTAL 100.00 6.24
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : MARCH 1-31, 2015 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 26.99 2.30 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 11.83 4.25 D. ARCHITECTURAL WORKS 28.76 0.00 0.00 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 3.25 0.06 J. ELECTRICAL & AUXILIARY WORKS 7.38 1.36 0.10 K. PLUMBING WORKS 5.36 3.18 0.17 L. FIRE PROTECTION WORKS 1.77 1.71 0.03 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 40.00 0.12 P. TESTING AND COMMISSIONING TOTAL 100.00 7.75
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : APRIL 1-30, 2015 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 29.58 2.52 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 15.58 5.60 D. ARCHITECTURAL WORKS 28.76 0.32 0.09 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 6.86 0.14 J. ELECTRICAL & AUXILIARY WORKS 7.38 1.73 0.13 K. PLUMBING WORKS 5.36 4.93 0.26 L. FIRE PROTECTION WORKS 1.77 2.04 0.04 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 40.00 0.12 P. TESTING AND COMMISSIONING TOTAL 100.00 9.61
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : MAY 1-31, 2015 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 32.27 2.75 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 18.8 6.76 D. ARCHITECTURAL WORKS 28.76 1.30 0.37 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 8.93 0.18 J. ELECTRICAL & AUXILIARY WORKS 7.38 2.59 0.19 K. PLUMBING WORKS 5.36 7.59 0.41 L. FIRE PROTECTION WORKS 1.77 3.07 0.05 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 40.00 0.12 P. TESTING AND COMMISSIONING TOTAL 100.00 11.54
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : JUNE 1-30, 2015 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 34.86 2.97 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 26.67 9.59 D. ARCHITECTURAL WORKS 28.76 1.89 0.54 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 9.04 0.18 J. ELECTRICAL & AUXILIARY WORKS 7.38 2.58 0.19 K. PLUMBING WORKS 5.36 11.09 0.59 L. FIRE PROTECTION WORKS 1.77 4.19 0.07 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 40.00 0.12 P. TESTING AND COMMISSIONING TOTAL 100.00 14.97
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : JULY 1-31, 2015 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 37.54 3.20 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 35.90 12.90 D. ARCHITECTURAL WORKS 28.76 2.64 0.76 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 14.16 0.28 J. ELECTRICAL & AUXILIARY WORKS 7.38 4.62 0.34 K. PLUMBING WORKS 5.36 15.18 0.81 L. FIRE PROTECTION WORKS 1.77 5.28 0.09 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 40.00 0.12 P. TESTING AND COMMISSIONING TOTAL 100.00 19.22
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : AUGUST 1-31, 2015 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF AUGUST
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 40.22 3.43 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 46.15 16.59 D. ARCHITECTURAL WORKS 28.76 2.83 0.81 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 25.42 0.5 J. ELECTRICAL & AUXILIARY WORKS 7.38 6.06 0.45 K. PLUMBING WORKS 5.36 17.27 0.93 L. FIRE PROTECTION WORKS 1.77 7.01 0.12 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 40.00 0.12 P. TESTING AND COMMISSIONING TOTAL 100.00 23.66
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : SEPTEMBER 1-30, 2015 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF SEPTEMBER
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 42.82 3.65 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 56.50 20.31 D. ARCHITECTURAL WORKS 28.76 2.92 0.84 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 29.63 0.59 J. ELECTRICAL & AUXILIARY WORKS 7.38 7.63 0.56 K. PLUMBING WORKS 5.36 20.06 1.08 L. FIRE PROTECTION WORKS 1.77 8.59 0.15 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 85.00 0.25 P. TESTING AND COMMISSIONING TOTAL 100.00 28.14
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : OCTOBER 1-31, 2015 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF OCTOBER
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 45.85 3.91 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 67.52 24.27 D. ARCHITECTURAL WORKS 28.76 3.97 1.14 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 33.27 0.66 J. ELECTRICAL & AUXILIARY WORKS 7.38 9.10 0.67 K. PLUMBING WORKS 5.36 21.10 1.13 L. FIRE PROTECTION WORKS 1.77 9.71 0.17 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 85.00 0.25 P. TESTING AND COMMISSIONING TOTAL 100.00 32.91
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : NOVEMBER 1-30, 2015 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF NOVEMBER
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 48.53 4.14 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 70.09 25.19 D. ARCHITECTURAL WORKS 28.76 4.22 1.21 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 46.30 0.92 J. ELECTRICAL & AUXILIARY WORKS 7.38 10.72 0.79 K. PLUMBING WORKS 5.36 25.25 1.35 L. FIRE PROTECTION WORKS 1.77 10.64 0.19 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 85.00 0.25 P. TESTING AND COMMISSIONING TOTAL 100.00 34.75
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : DECEMBER 1-31, 2015 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF DECEMBER
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 51.21 4.37 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 76.92 27.65 D. ARCHITECTURAL WORKS 28.76 4.22 1.21 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 49.65 0.98 J. ELECTRICAL & AUXILIARY WORKS 7.38 11.77 0.87 K. PLUMBING WORKS 5.36 25.69 1.38 L. FIRE PROTECTION WORKS 1.77 11.91 0.21 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 85.00 0.25 P. TESTING AND COMMISSIONING TOTAL 100.00 37.63
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : JANUARY 1-31, 2016 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF JANUARY
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 53.89 4.60 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 82.99 29.83 D. ARCHITECTURAL WORKS 28.76 5.37 1.54 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 54.33 1.08 J. ELECTRICAL & AUXILIARY WORKS 7.38 16.50 1.22 K. PLUMBING WORKS 5.36 27.38 1.47 L. FIRE PROTECTION WORKS 1.77 13.38 0.24 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 85.00 0.25 P. TESTING AND COMMISSIONING TOTAL 100.00 40.94
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : FEBRUARY 1-29, 2016 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 56.31 4.80 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 86.67 31.15 D. ARCHITECTURAL WORKS 28.76 7.10 2.04 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 58.05 1.15 J. ELECTRICAL & AUXILIARY WORKS 7.38 17.37 1.28 K. PLUMBING WORKS 5.36 28.41 1.52 L. FIRE PROTECTION WORKS 1.77 17.62 0.31 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 85.00 0.25 P. TESTING AND COMMISSIONING TOTAL 100.00 43.21
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : MARCH 1-31, 2016 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF MARCH
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 59 5.03 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 91.28 32.81 D. ARCHITECTURAL WORKS 28.76 9.14 2.63 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 0.00 0.00 I. MECHANICAL WORKS 1.98 59.11 1.17 J. ELECTRICAL & AUXILIARY WORKS 7.38 18.39 1.36 K. PLUMBING WORKS 5.36 29.74 1.59 L. FIRE PROTECTION WORKS 1.77 18.47 0.33 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 85.00 0.25 P. TESTING AND COMMISSIONING TOTAL 100.00 45.88
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : APRIL 1-30, 2016 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF APRIL
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 8.53 61.59 5.25 B. EARTHWORKS 0.71 100.00 0.71 C. STRUCTURAL WORKS 35.94 100.00 35.94 D. ARCHITECTURAL WORKS 28.76 11.79 3.39 E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00 F. CABINETRY WORKS 0.60 0.00 0.00 G. METAL & ROOFING WORKS 0.38 0.00 0.00 H. PAINTING WORKS 3.38 2.05 0.07 I. MECHANICAL WORKS 1.98 60.28 1.19 J. ELECTRICAL & AUXILIARY WORKS 7.38 19.60 1.45 K. PLUMBING WORKS 5.36 31.28 1.68 L. FIRE PROTECTION WORKS 1.77 23.51 0.42 M. GENERATOR SET 0.40 0.00 0.00 N. ELEVATOR 1.88 0.00 0.00 O. STP EQUIPMENT 0.29 85.00 0.25 P. TESTING AND COMMISSIONING TOTAL 100.00 50.35
Prepared by: Noted by:
Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : JUNE 1-30, 2018 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF JUNE 2018
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 6.08 5.27 0.32 B. EARTHWORKS 0.85 71.67 0.61 C. STRUCTURAL WORKS 32.33 2.00 0.65 D. ARCHITECTURAL WORKS 35.03 0.00 0.00 E. MECHANICAL WORKS 1.4 0.00 0.00 F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00 G. PLUMBING WORKS 4.22 0.00 0.00 H. FIRE PROTECTION WORKS 1.96 0.00 0.00 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 0.00 0.00 K. CONTINGENCIES 3.60 0.00 0.00 L. PROFIT 6.31 0.0 0.00 TOTAL 100.00 1.58
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : JULY 1-31, 2018 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF JULY 2018
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 7.95 0.48 B. EARTHWORKS 0.85 74.17 0.63 C. STRUCTURAL WORKS 32.33 17.22 5.57 D. ARCHITECTURAL WORKS 35.03 0.00 0.00 E. MECHANICAL WORKS 1.4 0.00 0.00 F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00 G. PLUMBING WORKS 4.22 0.00 0.00 H. FIRE PROTECTION WORKS 1.96 0.00 0.00 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 0.00 0.00 K. CONTINGENCIES L. PROFIT TOTAL 100.00 6.68
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : AUGUST 1-31, 2018 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF AUGUST 2018
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 10.63 1.70 B. EARTHWORKS 0.85 100.00 0.85 C. STRUCTURAL WORKS 32.33 24.40 7.89 D. ARCHITECTURAL WORKS 35.03 0.00 0.00 E. MECHANICAL WORKS 1.4 0.00 0.00 F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00 G. PLUMBING WORKS 4.22 0.00 0.00 H. FIRE PROTECTION WORKS 1.96 0.00 0.00 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 0.00 0.00 K. CONTINGENCIES L. PROFIT TOTAL 100.00 10.44
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : SEPTEMEBR 1-30, 2018 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF SEPTEMBER 2018
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 13.22 2.11 B. EARTHWORKS 0.85 100.00 0.85 C. STRUCTURAL WORKS 32.33 28.55 9.23 D. ARCHITECTURAL WORKS 35.03 0.00 0.00 E. MECHANICAL WORKS 1.4 0.00 0.00 F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00 G. PLUMBING WORKS 4.22 0.00 0.00 H. FIRE PROTECTION WORKS 1.96 0.00 0.00 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 0.00 0.00 K. CONTINGENCIES L. PROFIT TOTAL 100.00 12.19
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : NOVEMBER 1-30, 2018 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF NOVEMBER 2018
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 18.5 2.96 B. EARTHWORKS 0.85 100.00 0.85 C. STRUCTURAL WORKS 32.33 40.88 13.22 D. ARCHITECTURAL WORKS 35.03 0.00 0.00 E. MECHANICAL WORKS 1.4 0.00 0.00 F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00 G. PLUMBING WORKS 4.22 0.00 0.00 H. FIRE PROTECTION WORKS 1.96 0.00 0.00 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 0.00 0.00 K. CONTINGENCIES L. PROFIT TOTAL 100.00 17.03
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : DECEMBER 1-31, 2018 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF DECEMBER 2018
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 21.18 3.39 B. EARTHWORKS 0.85 100.00 0.85 C. STRUCTURAL WORKS 32.33 44.46 14.37 D. ARCHITECTURAL WORKS 35.03 0.00 0.00 E. MECHANICAL WORKS 1.4 0.00 0.00 F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00 G. PLUMBING WORKS 4.22 0.00 0.00 H. FIRE PROTECTION WORKS 1.96 0.00 0.00 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 0.00 0.00 K. CONTINGENCIES L. PROFIT TOTAL 100.00 18.61
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : JANUARY 1-31, 2019 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF JANUARY 2019
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 21.18 3.39 B. EARTHWORKS 0.85 100.00 0.85 C. STRUCTURAL WORKS 32.33 47.27 15.28 D. ARCHITECTURAL WORKS 35.03 0.00 0.00 E. MECHANICAL WORKS 1.4 0.00 0.00 F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00 G. PLUMBING WORKS 4.22 0.00 0.00 H. FIRE PROTECTION WORKS 1.96 0.00 0.00 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 0.00 0.00 K. CONTINGENCIES L. PROFIT TOTAL 100.00 19.52
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : FEBRUARY 1-28, 2019 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY 2019
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 26.27 4.20 B. EARTHWORKS 0.85 100.00 0.85 C. STRUCTURAL WORKS 32.33 49.49 16.00 D. ARCHITECTURAL WORKS 35.03 0.00 0.00 E. MECHANICAL WORKS 1.4 0.00 0.00 F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00 G. PLUMBING WORKS 4.22 0.00 0.00 H. FIRE PROTECTION WORKS 1.96 0.00 0.00 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 0.00 0.00 K. CONTINGENCIES L. PROFIT TOTAL 100.00 21.05
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : APRIL 1-30, 2019 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF APRIL 2019
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 31.55 5.04 B. EARTHWORKS 0.85 100.00 0.85 C. STRUCTURAL WORKS 32.33 56.72 18.34 D. ARCHITECTURAL WORKS 35.03 0.08 0.03 E. MECHANICAL WORKS 1.4 1.90 0.03 F. ELECTRICAL & AUXILIARY WORKS 6.22 4.03 0.25 G. PLUMBING WORKS 4.22 3.45 0.15 H. FIRE PROTECTION WORKS 1.96 4.55 0.09 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 30.00 0.10 K. CONTINGENCIES L. PROFIT TOTAL 100.00 24.88
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : JUNE 1-30, 2019 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF JUNE 2019
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 36.82 5.89 B. EARTHWORKS 0.85 100.00 0.85 C. STRUCTURAL WORKS 32.33 61.25 19.80 D. ARCHITECTURAL WORKS 35.03 0.90 0.32 E. MECHANICAL WORKS 1.4 4.88 0.07 F. ELECTRICAL & AUXILIARY WORKS 6.22 7.28 0.45 G. PLUMBING WORKS 4.22 5.21 0.22 H. FIRE PROTECTION WORKS 1.96 7.94 0.16 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 30.00 0.10 K. CONTINGENCIES L. PROFIT TOTAL 100.00 27.86
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : JULY 1-31, 2019 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF JULY 2019
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 39.5 6.32 B. EARTHWORKS 0.85 100.00 0.85 C. STRUCTURAL WORKS 32.33 63.94 20.67 D. ARCHITECTURAL WORKS 35.03 0.90 0.32 E. MECHANICAL WORKS 1.4 7.44 0.10 F. ELECTRICAL & AUXILIARY WORKS 6.22 7.99 0.50 G. PLUMBING WORKS 4.22 6.36 0.27 H. FIRE PROTECTION WORKS 1.96 8.80 0.17 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 30.00 0.10 K. CONTINGENCIES L. PROFIT TOTAL 100.00 29.30
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : AUGUST 1-31, 2019 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF AUGUST 2019
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 42.18 6.74 B. EARTHWORKS 0.85 100.00 0.85 C. STRUCTURAL WORKS 32.33 67.35 21.77 D. ARCHITECTURAL WORKS 35.03 1.70 0.60 E. MECHANICAL WORKS 1.4 8.41 0.12 F. ELECTRICAL & AUXILIARY WORKS 6.22 9.78 0.61 G. PLUMBING WORKS 4.22 6.88 0.29 H. FIRE PROTECTION WORKS 1.96 10.29 0.20 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 30.00 0.10 K. CONTINGENCIES L. PROFIT TOTAL 100.00 31.29
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo
JMB-Project Architect JMB-Project Manager DATE : SEPTEMBER 1-30, 2019 PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3 LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY
SUMMARY OF ACCOMPLISHMENT AS OF SEPTEMBER 2019
TO DATE % ACTUAL % WEIGHT ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT A. PRELIMINARIES 15.99 44.77 7.16 B. EARTHWORKS 0.85 100.00 0.85 C. STRUCTURAL WORKS 32.33 70.72 22.86 D. ARCHITECTURAL WORKS 35.03 1.87 0.66 E. MECHANICAL WORKS 1.4 15.92 0.22 F. ELECTRICAL & AUXILIARY WORKS 6.22 11.52 0.72 G. PLUMBING WORKS 4.22 8.48 0.36 H. FIRE PROTECTION WORKS 1.96 12.70 0.25 I. ELEVATOR 1.62 0.00 0.00 J. STP EQUIPMENT 0.34 30.00 0.10 K. CONTINGENCIES L. PROFIT TOTAL 100.00 33.18
Prepared by: Noted by:
Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo