DATE : FEBRUARY 1-28, 2015

PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2


LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY


% TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 24.31 2.07
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 8.93 3.21
D. ARCHITECTURAL WORKS 28.76 0.00 0.00
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 0.61 0.01
J. ELECTRICAL & AUXILIARY WORKS 7.38 0.34 0.03
K. PLUMBING WORKS 5.36 1.53 0.08
L. FIRE PROTECTION WORKS 1.77 0.9 0.01
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 40.00 0.12
P. TESTING AND COMMISSIONING
TOTAL 100.00 6.24

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : MARCH 1-31, 2015
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 26.99 2.30
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 11.83 4.25
D. ARCHITECTURAL WORKS 28.76 0.00 0.00
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 3.25 0.06
J. ELECTRICAL & AUXILIARY WORKS 7.38 1.36 0.10
K. PLUMBING WORKS 5.36 3.18 0.17
L. FIRE PROTECTION WORKS 1.77 1.71 0.03
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 40.00 0.12
P. TESTING AND COMMISSIONING
TOTAL 100.00 7.75

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : APRIL 1-30, 2015
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 29.58 2.52
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 15.58 5.60
D. ARCHITECTURAL WORKS 28.76 0.32 0.09
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 6.86 0.14
J. ELECTRICAL & AUXILIARY WORKS 7.38 1.73 0.13
K. PLUMBING WORKS 5.36 4.93 0.26
L. FIRE PROTECTION WORKS 1.77 2.04 0.04
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 40.00 0.12
P. TESTING AND COMMISSIONING
TOTAL 100.00 9.61

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : MAY 1-31, 2015
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 32.27 2.75
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 18.8 6.76
D. ARCHITECTURAL WORKS 28.76 1.30 0.37
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 8.93 0.18
J. ELECTRICAL & AUXILIARY WORKS 7.38 2.59 0.19
K. PLUMBING WORKS 5.36 7.59 0.41
L. FIRE PROTECTION WORKS 1.77 3.07 0.05
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 40.00 0.12
P. TESTING AND COMMISSIONING
TOTAL 100.00 11.54

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : JUNE 1-30, 2015
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 34.86 2.97
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 26.67 9.59
D. ARCHITECTURAL WORKS 28.76 1.89 0.54
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 9.04 0.18
J. ELECTRICAL & AUXILIARY WORKS 7.38 2.58 0.19
K. PLUMBING WORKS 5.36 11.09 0.59
L. FIRE PROTECTION WORKS 1.77 4.19 0.07
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 40.00 0.12
P. TESTING AND COMMISSIONING
TOTAL 100.00 14.97

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : JULY 1-31, 2015
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 37.54 3.20
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 35.90 12.90
D. ARCHITECTURAL WORKS 28.76 2.64 0.76
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 14.16 0.28
J. ELECTRICAL & AUXILIARY WORKS 7.38 4.62 0.34
K. PLUMBING WORKS 5.36 15.18 0.81
L. FIRE PROTECTION WORKS 1.77 5.28 0.09
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 40.00 0.12
P. TESTING AND COMMISSIONING
TOTAL 100.00 19.22

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : AUGUST 1-31, 2015
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF AUGUST


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 40.22 3.43
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 46.15 16.59
D. ARCHITECTURAL WORKS 28.76 2.83 0.81
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 25.42 0.5
J. ELECTRICAL & AUXILIARY WORKS 7.38 6.06 0.45
K. PLUMBING WORKS 5.36 17.27 0.93
L. FIRE PROTECTION WORKS 1.77 7.01 0.12
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 40.00 0.12
P. TESTING AND COMMISSIONING
TOTAL 100.00 23.66

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : SEPTEMBER 1-30, 2015
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF SEPTEMBER


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 42.82 3.65
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 56.50 20.31
D. ARCHITECTURAL WORKS 28.76 2.92 0.84
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 29.63 0.59
J. ELECTRICAL & AUXILIARY WORKS 7.38 7.63 0.56
K. PLUMBING WORKS 5.36 20.06 1.08
L. FIRE PROTECTION WORKS 1.77 8.59 0.15
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 85.00 0.25
P. TESTING AND COMMISSIONING
TOTAL 100.00 28.14

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : OCTOBER 1-31, 2015
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF OCTOBER


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 45.85 3.91
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 67.52 24.27
D. ARCHITECTURAL WORKS 28.76 3.97 1.14
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 33.27 0.66
J. ELECTRICAL & AUXILIARY WORKS 7.38 9.10 0.67
K. PLUMBING WORKS 5.36 21.10 1.13
L. FIRE PROTECTION WORKS 1.77 9.71 0.17
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 85.00 0.25
P. TESTING AND COMMISSIONING
TOTAL 100.00 32.91

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : NOVEMBER 1-30, 2015
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF NOVEMBER


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 48.53 4.14
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 70.09 25.19
D. ARCHITECTURAL WORKS 28.76 4.22 1.21
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 46.30 0.92
J. ELECTRICAL & AUXILIARY WORKS 7.38 10.72 0.79
K. PLUMBING WORKS 5.36 25.25 1.35
L. FIRE PROTECTION WORKS 1.77 10.64 0.19
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 85.00 0.25
P. TESTING AND COMMISSIONING
TOTAL 100.00 34.75

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : DECEMBER 1-31, 2015
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF DECEMBER


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 51.21 4.37
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 76.92 27.65
D. ARCHITECTURAL WORKS 28.76 4.22 1.21
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 49.65 0.98
J. ELECTRICAL & AUXILIARY WORKS 7.38 11.77 0.87
K. PLUMBING WORKS 5.36 25.69 1.38
L. FIRE PROTECTION WORKS 1.77 11.91 0.21
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 85.00 0.25
P. TESTING AND COMMISSIONING
TOTAL 100.00 37.63

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : JANUARY 1-31, 2016
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF JANUARY


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 53.89 4.60
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 82.99 29.83
D. ARCHITECTURAL WORKS 28.76 5.37 1.54
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 54.33 1.08
J. ELECTRICAL & AUXILIARY WORKS 7.38 16.50 1.22
K. PLUMBING WORKS 5.36 27.38 1.47
L. FIRE PROTECTION WORKS 1.77 13.38 0.24
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 85.00 0.25
P. TESTING AND COMMISSIONING
TOTAL 100.00 40.94

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : FEBRUARY 1-29, 2016
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 56.31 4.80
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 86.67 31.15
D. ARCHITECTURAL WORKS 28.76 7.10 2.04
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 58.05 1.15
J. ELECTRICAL & AUXILIARY WORKS 7.38 17.37 1.28
K. PLUMBING WORKS 5.36 28.41 1.52
L. FIRE PROTECTION WORKS 1.77 17.62 0.31
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 85.00 0.25
P. TESTING AND COMMISSIONING
TOTAL 100.00 43.21

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : MARCH 1-31, 2016
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF MARCH


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 59 5.03
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 91.28 32.81
D. ARCHITECTURAL WORKS 28.76 9.14 2.63
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 0.00 0.00
I. MECHANICAL WORKS 1.98 59.11 1.17
J. ELECTRICAL & AUXILIARY WORKS 7.38 18.39 1.36
K. PLUMBING WORKS 5.36 29.74 1.59
L. FIRE PROTECTION WORKS 1.77 18.47 0.33
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 85.00 0.25
P. TESTING AND COMMISSIONING
TOTAL 100.00 45.88

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : APRIL 1-30, 2016
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 2
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF APRIL


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 8.53 61.59 5.25
B. EARTHWORKS 0.71 100.00 0.71
C. STRUCTURAL WORKS 35.94 100.00 35.94
D. ARCHITECTURAL WORKS 28.76 11.79 3.39
E. DOOR INCLUDING FINISH HARDWARE 2.63 0.00 0.00
F. CABINETRY WORKS 0.60 0.00 0.00
G. METAL & ROOFING WORKS 0.38 0.00 0.00
H. PAINTING WORKS 3.38 2.05 0.07
I. MECHANICAL WORKS 1.98 60.28 1.19
J. ELECTRICAL & AUXILIARY WORKS 7.38 19.60 1.45
K. PLUMBING WORKS 5.36 31.28 1.68
L. FIRE PROTECTION WORKS 1.77 23.51 0.42
M. GENERATOR SET 0.40 0.00 0.00
N. ELEVATOR 1.88 0.00 0.00
O. STP EQUIPMENT 0.29 85.00 0.25
P. TESTING AND COMMISSIONING
TOTAL 100.00 50.35

Prepared by: Noted by:

Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : JUNE 1-30, 2018
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF JUNE 2018


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 6.08 5.27 0.32
B. EARTHWORKS 0.85 71.67 0.61
C. STRUCTURAL WORKS 32.33 2.00 0.65
D. ARCHITECTURAL WORKS 35.03 0.00 0.00
E. MECHANICAL WORKS 1.4 0.00 0.00
F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00
G. PLUMBING WORKS 4.22 0.00 0.00
H. FIRE PROTECTION WORKS 1.96 0.00 0.00
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 0.00 0.00
K. CONTINGENCIES 3.60 0.00 0.00
L. PROFIT 6.31 0.0 0.00
TOTAL 100.00 1.58

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : JULY 1-31, 2018
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF JULY 2018


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 7.95 0.48
B. EARTHWORKS 0.85 74.17 0.63
C. STRUCTURAL WORKS 32.33 17.22 5.57
D. ARCHITECTURAL WORKS 35.03 0.00 0.00
E. MECHANICAL WORKS 1.4 0.00 0.00
F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00
G. PLUMBING WORKS 4.22 0.00 0.00
H. FIRE PROTECTION WORKS 1.96 0.00 0.00
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 0.00 0.00
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 6.68

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : AUGUST 1-31, 2018
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF AUGUST 2018


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 10.63 1.70
B. EARTHWORKS 0.85 100.00 0.85
C. STRUCTURAL WORKS 32.33 24.40 7.89
D. ARCHITECTURAL WORKS 35.03 0.00 0.00
E. MECHANICAL WORKS 1.4 0.00 0.00
F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00
G. PLUMBING WORKS 4.22 0.00 0.00
H. FIRE PROTECTION WORKS 1.96 0.00 0.00
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 0.00 0.00
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 10.44

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : SEPTEMEBR 1-30, 2018
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF SEPTEMBER 2018


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 13.22 2.11
B. EARTHWORKS 0.85 100.00 0.85
C. STRUCTURAL WORKS 32.33 28.55 9.23
D. ARCHITECTURAL WORKS 35.03 0.00 0.00
E. MECHANICAL WORKS 1.4 0.00 0.00
F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00
G. PLUMBING WORKS 4.22 0.00 0.00
H. FIRE PROTECTION WORKS 1.96 0.00 0.00
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 0.00 0.00
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 12.19

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : NOVEMBER 1-30, 2018
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF NOVEMBER 2018


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 18.5 2.96
B. EARTHWORKS 0.85 100.00 0.85
C. STRUCTURAL WORKS 32.33 40.88 13.22
D. ARCHITECTURAL WORKS 35.03 0.00 0.00
E. MECHANICAL WORKS 1.4 0.00 0.00
F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00
G. PLUMBING WORKS 4.22 0.00 0.00
H. FIRE PROTECTION WORKS 1.96 0.00 0.00
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 0.00 0.00
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 17.03

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : DECEMBER 1-31, 2018
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF DECEMBER 2018


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 21.18 3.39
B. EARTHWORKS 0.85 100.00 0.85
C. STRUCTURAL WORKS 32.33 44.46 14.37
D. ARCHITECTURAL WORKS 35.03 0.00 0.00
E. MECHANICAL WORKS 1.4 0.00 0.00
F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00
G. PLUMBING WORKS 4.22 0.00 0.00
H. FIRE PROTECTION WORKS 1.96 0.00 0.00
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 0.00 0.00
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 18.61

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : JANUARY 1-31, 2019
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF JANUARY 2019


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 21.18 3.39
B. EARTHWORKS 0.85 100.00 0.85
C. STRUCTURAL WORKS 32.33 47.27 15.28
D. ARCHITECTURAL WORKS 35.03 0.00 0.00
E. MECHANICAL WORKS 1.4 0.00 0.00
F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00
G. PLUMBING WORKS 4.22 0.00 0.00
H. FIRE PROTECTION WORKS 1.96 0.00 0.00
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 0.00 0.00
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 19.52

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : FEBRUARY 1-28, 2019
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF FEBRUARY 2019


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 26.27 4.20
B. EARTHWORKS 0.85 100.00 0.85
C. STRUCTURAL WORKS 32.33 49.49 16.00
D. ARCHITECTURAL WORKS 35.03 0.00 0.00
E. MECHANICAL WORKS 1.4 0.00 0.00
F. ELECTRICAL & AUXILIARY WORKS 6.22 0.00 0.00
G. PLUMBING WORKS 4.22 0.00 0.00
H. FIRE PROTECTION WORKS 1.96 0.00 0.00
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 0.00 0.00
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 21.05

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : APRIL 1-30, 2019
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF APRIL 2019


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 31.55 5.04
B. EARTHWORKS 0.85 100.00 0.85
C. STRUCTURAL WORKS 32.33 56.72 18.34
D. ARCHITECTURAL WORKS 35.03 0.08 0.03
E. MECHANICAL WORKS 1.4 1.90 0.03
F. ELECTRICAL & AUXILIARY WORKS 6.22 4.03 0.25
G. PLUMBING WORKS 4.22 3.45 0.15
H. FIRE PROTECTION WORKS 1.96 4.55 0.09
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 30.00 0.10
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 24.88

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : JUNE 1-30, 2019
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF JUNE 2019


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 36.82 5.89
B. EARTHWORKS 0.85 100.00 0.85
C. STRUCTURAL WORKS 32.33 61.25 19.80
D. ARCHITECTURAL WORKS 35.03 0.90 0.32
E. MECHANICAL WORKS 1.4 4.88 0.07
F. ELECTRICAL & AUXILIARY WORKS 6.22 7.28 0.45
G. PLUMBING WORKS 4.22 5.21 0.22
H. FIRE PROTECTION WORKS 1.96 7.94 0.16
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 30.00 0.10
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 27.86

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : JULY 1-31, 2019
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF JULY 2019


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 39.5 6.32
B. EARTHWORKS 0.85 100.00 0.85
C. STRUCTURAL WORKS 32.33 63.94 20.67
D. ARCHITECTURAL WORKS 35.03 0.90 0.32
E. MECHANICAL WORKS 1.4 7.44 0.10
F. ELECTRICAL & AUXILIARY WORKS 6.22 7.99 0.50
G. PLUMBING WORKS 4.22 6.36 0.27
H. FIRE PROTECTION WORKS 1.96 8.80 0.17
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 30.00 0.10
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 29.30

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : AUGUST 1-31, 2019
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF AUGUST 2019


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 42.18 6.74
B. EARTHWORKS 0.85 100.00 0.85
C. STRUCTURAL WORKS 32.33 67.35 21.77
D. ARCHITECTURAL WORKS 35.03 1.70 0.60
E. MECHANICAL WORKS 1.4 8.41 0.12
F. ELECTRICAL & AUXILIARY WORKS 6.22 9.78 0.61
G. PLUMBING WORKS 4.22 6.88 0.29
H. FIRE PROTECTION WORKS 1.96 10.29 0.20
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 30.00 0.10
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 31.29

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager
DATE : SEPTEMBER 1-30, 2019
PROJECT : SUNSHINE 100 CITY PLAZA PHASE - 3
LOCATION : PIONEER ST. COR. SHERIDAN ST., MANDALUYONG CITY

SUMMARY OF ACCOMPLISHMENT AS OF SEPTEMBER 2019


TO DATE % ACTUAL % WEIGHT
ITEM PARTICULARS % WEIGHT ACCOMPLISHMENT ACCOMPLISHMENT
A. PRELIMINARIES 15.99 44.77 7.16
B. EARTHWORKS 0.85 100.00 0.85
C. STRUCTURAL WORKS 32.33 70.72 22.86
D. ARCHITECTURAL WORKS 35.03 1.87 0.66
E. MECHANICAL WORKS 1.4 15.92 0.22
F. ELECTRICAL & AUXILIARY WORKS 6.22 11.52 0.72
G. PLUMBING WORKS 4.22 8.48 0.36
H. FIRE PROTECTION WORKS 1.96 12.70 0.25
I. ELEVATOR 1.62 0.00 0.00
J. STP EQUIPMENT 0.34 30.00 0.10
K. CONTINGENCIES
L. PROFIT
TOTAL 100.00 33.18

Prepared by: Noted by:

Jr. Arch't. Byron Punzalan Arch't. Jessie Bernardo


JMB-Project Architect JMB-Project Manager