(1) Select required instruments.
(2) Conduct a Field reconnaissance.
(3) Sketch a Reconnaissance diagram.
(4) Set up the instrument.
(5) Run the compass survey round the figure.
(6) Read and book bearings.
(7) Measure the distances and book.
(8) Reduce and compute the data
(9) Adjust the compass traverse by graphical method
(10) Plot the data on the drawing paper (using scale 1:500).
N 5
1
Start
4
and end
station.
2 3
CONCLUSION:
Draw the final network on the paper and check a diagonal using suitable scale.
PRACTICAL WORK FOR WEEK FOUR - SIX.
TITLE :
Tertiary Leveling.
AIM :
To carry out tertiary leveling, reduction to produce elevations of all permanent stations along
a circuit of about 1km.
EQUIPMENT:
Level, tripod, leveling staves, steel tape, linen tape, ranging pole, arrows, leveling field book,
foot plate, pegs, nails and bottle cork, pen, etc.
Procedure:
(1) Select instruments.
(2) Conduct a Field reconnaissance
(3) Sketch a Reconnaissance diagram of the area.
(4) Set the level instrument and check the back sight and fore sight are approximately the
same length.
(5) Place a staff on the starting point and a staff where the interval terminates.
(6) Observe the back staff, read and note the readings.
(7) Observe the forward staff, read and note the readings.
(8) Reduce the readings.
CONCLUSION:
Summarize the final reduced levels in tabular from and comment on the closing error.
PRACTICAL WORK FOR WEEK SEVEN – NINE.
TITLE :
Tacheometric Surveying
AIM :
To Use theodolite along with staff to obtain distances and heights.
EQUIPMENT:
Theodolite, tripod, leveling staff, steel tape, linen tape, ranging pole, arrows, traverse survey
field book, pegs, nails and bottle cork, pen, protractor, set squares, drawing paper, scale rule,
eraser etc.
Stadia lines
M
RLx V
hi
P
D
Where;
PROCEDURE:
(1) Select instrument
(2) Conduct a Field reconnaissance
(3) Sketch the Reconnaissance diagram
(4) Set up the instrument at the instrument station
(5) Perform temporary adjustment
(6) Measure the height of instrument (hi)
(7) Set the telescope and the staff so that all the three stadia hairs intersect the staff
(8) Book the vertical circle reading and horizontal circle readings
(9) Read and book the three stadia hair readings
(10) Reduction of angles
(11) Compute the distances and reduced levels using the following formula;
Horizontal distance P x = D = KS cos2 Ø + C cos Ø (i)
Where;
K = the multiplying constant of instrument, usually 100
CONCLUSION:
PROCEDURE :
B D
A
C
CONCLUSION:
Draw the traverse network on the drawing paper and ink.
PRACTICAL WORK FOR WEEK THIRTEEN - FIFTEEN.
TITLE :
Sstting Out.
AIM : To set out a simple building plan (four corner) on the ground.
EQUIPMENT:
Theodolite, tripod, levelling staff, steel tape, ranging pole, arrows , pegs, nails and pen, scale
rule,building plan,profile board, etc.
5000mm
D C
90⁰ 90⁰
DIAGONALS
5000mm
90⁰ 90⁰
A B
BASE LINE
PROCEDURE:
(1) Read and understand the drawings thoroughly.
(2) Determine the base line/building by direct measurement.
(3) Establish the two corners on the building Line (A and B).
(4) Set up the Theodolite at the one corner (A) on the building line.
(5) Perform temporary adjustment of the Theodolite.
(6) Turn the instrument to sight a ranging pole at point (B).
(7) Adjust the horizontal circle bearing to read 00⁰ 00’ 00’’.
(8) Turn the instrument anticlockwise until angle 90⁰ 00’ 00’’ is obtained.
(9) Align a ranging pole to the line of sight and place a ranging pole.
(10) Measure out the horizontal line AD from the plan and peg.
(11) Transfer the equipment from A to point D and sight back to A.
(12) Adjust the horizontal circle bearing to read 00⁰ 00’ 00’’.
(13) Turn the instrument anticlockwise until angle 90⁰ 00’ 00’’ is obtained.
(14) Align a ranging pole to the line of sight and place a ranging pole.
(15) Measure out the horizontal line DC from the plan and peg.
(16) Transfer the equipment from D to point C and sight back to D.
(17) Repeat steps (7-9) to give line CB.
(18) Join line AB and check the distance from the plan.
(19) Check the diagonals; AC and BD, if the same in lengths, the exercise is accurate
otherwise check work over for necessary corrections.
(20) Set up profile boards at each corner of the building.